Identifying software project
stages, tasks and deliverables
José Onofre Montesa AndrésUniversidad Politécnica de
ValenciaEscuela Superior de Informática
Aplicada2003-2004
GpiI-2C Identifying software project stages, tasks and deliverables 2
Aim
• Breakdown the estimated effort into tasks.
• To do that, we shall identify:– project deliverables,– project stages and– project tasks.
GpiI-2C Identifying software project stages, tasks and deliverables 3
Breakdown Methods:
• By Processes– Different conceptual stages
• What?, How?, Development, Test ...
• by Products– We identify different products that will
make up the required system.– Example: Sales, Stock Control, ...
GpiI-2C Identifying software project stages, tasks and deliverables 4
It will be focused to an only product.
• Reasons:– Project Size - failure risk.– Coordination costs.– Incremental development.– It is logic that the “strategic direction” is
the one in charge to identify the needed products for the enterprise.
GpiI-2C Identifying software project stages, tasks and deliverables 5
Work Breakdown Structure (WBS)
• method of representing, in hierarchical manner the components of a process or product.
GpiI-2C Identifying software project stages, tasks and deliverables 6
Graphic representation of WBS.
1.1. S t udy
pr esent syst em.
1.2 . A dd N ew
char act er ist ics.
1. S pecif y
needs
2 .1. S t udy
Pr ocesses.
2 .2 . S t udy
Dat a
2 .0. A nalyze
A ccount ing
3 .1. Dat a Base
Design
3 .2. Pr ogr ams
Design
3 .0 . S yst em
Design
4 .1. S cheme
development
4 .2. Pr ogr ams
code
4 .0 . Coding
5 .1. U nit
T est
5 .2 . S yst em
T est
5 .0 . T est
0 . A ccount ing
pr oj ect .
GpiI-2C Identifying software project stages, tasks and deliverables 7
List representation of WBS.
0. Accounting project.1. Specify needs1.1. Study present
system.1.2. Add New
characteristics.2. Analyze Accounting.2.1. Study Processes.2.2. Study Data
3. System Design.3.1. Data Base Design.3.2. Programs Design.4. Coding4.1. Scheme
development.4.2. Programs code.5. Test.5.1. Unit test.5.2. System test.
GpiI-2C Identifying software project stages, tasks and deliverables 8
WBS
• Numbers help to locate tasks in the WBS.• Nodes are read as:
– “is contained in”
• Developing a WBS.– Identify the top of the WBS.– Partition each component into 72– The lowest level are the task in a project
GpiI-2C Identifying software project stages, tasks and deliverables 9
TASK CARD
Task specificationNumber: 3.1.Name: Data Base Design.Description: Designing the data
base as proposed in the analysis by entity-relation model, and with the aim to get a system functioning with DB2 .
Estimated Effort : 2 weeks/personDeliverables: D.B. implementation
structure…: …
GpiI-2C Identifying software project stages, tasks and deliverables 10
Software project Deliverables.
• Concept:– "Products interchanged among clients
and developers during the software project development".
• Relatives:– To the object.– To the project management.
GpiI-2C Identifying software project stages, tasks and deliverables 11
It has to be defined a minimum set of
deliverables.• They provide:
– the component set that will make the product once the development ended.
– The means to measure the progress and quality of the product development.
– The needed materials for the following stage.
– Usually the enterprises have their own deliverables check list.
GpiI-2C Identifying software project stages, tasks and deliverables 12
Breakdown in stages of a system development.
• Since time ago, many enterprises classify the kind of tasks achieved in a project and analyze the effort dedicated to each of them.
• We will see same examples provided by Martyn A. Ould, and one an other from HP.
GpiI-2C Identifying software project stages, tasks and deliverables 13
Effort distribution about middle of the ´70
24
46
5
5
20
0 10 20 30 40 50
System integration
System design
Project management
GpiI-2C Identifying software project stages, tasks and deliverables 14
Effort distribution at beginning of the ´80
19
35
13
14
19
0 10 20 30 40
System integration
System design
Project management
GpiI-2C Identifying software project stages, tasks and deliverables 15
Effort distribution at the end of the ´80
11
25
15
28
21
0 5 10 15 20
25 30
System integration
System production
System design
System definition
Project management
GpiI-2C Identifying software project stages, tasks and deliverables 16
Effort distribution in HP (´96)
5
7
8
11
19
2
209
0 5 10 15 20
Support
Quality asurance
System production
System definition
GpiI-2C Identifying software project stages, tasks and deliverables 17
Activity-Based software costing Caper Jones, Computer May 96
Activities performed usr cpd Out com Sys Mil
1 Requirements X X X X X
2 Prototyping X X X X X X
3 Architecture X X X X X
4 Project plans X X X X X
5 Initial design X X X X X
6 Detailed design X X X X X
7 Design Reviews X X X X
8 Coding X X X X X X
9 Reuse acquisition X X X X X
GpiI-2C Identifying software project stages, tasks and deliverables 18
Activity-Based software costing Caper Jones, Computer May 96
Activities performed usr cpd Out com Sys Mil
10 Package purchase X X X X
11 Code inspection X X X
12 Independent V & V X
13 Configuration mgt. X X X X X
14 Formal integration X X X X X
15 User documentation X X X X X X
16 Unit testing X X X X X X
17 Function testing X X X X X
GpiI-2C Identifying software project stages, tasks and deliverables 19
Activity-Based software costing
Caper Jones, Computer May 96Activities performed usr cpd Out com Sys Mil
18 Integration testing X X X X X
19 System testing X X X X X
20 Field testing X X X
21 Acceptance testing X X X X
22 Independent testing X
23 Quality assurance X X X X
24 Installation/Training X X X X
25 Project management X X X X X
Total……………... 5 16 20 21 22 25
GpiI-2C Identifying software project stages, tasks and deliverables 20
Breakdown the software project into tasks.
• By deliverables (More than a week?)• Two horizon levels.
– Immediately– Half term
GpiI-2C Identifying software project stages, tasks and deliverables 21
Equipment focusing to identify tasks by activities.
• Implying to developers.– Use their knowledge and experience.
• The worker perception.– Submission to the goals– Responsibility
GpiI-2C Identifying software project stages, tasks and deliverables 22
Usual ways to identify tasks to a deliverable.
• To document, to find out or research,• To Organize, to write documents,• To check, to verify, to review• To Revise, to update documents,• To deliver, to finalize• Other ways:
• Breakdown provided by employed technician
GpiI-2C Identifying software project stages, tasks and deliverables 23
Usual tasks in a software project.
• Same enterprises have their own check list with a tasks list, were you can find the more important tasks to be considered.
GpiI-2C Identifying software project stages, tasks and deliverables 24
Some ideas on the software project breakdown.
• Make the tasks in order to be done by one or two persons in one or to weeks.
• Try to have independent tasks, don´t cut natural process.
• Worry about people communications.• Reuse code, but it cost time to.