IDEAL – NM Innovative Digital Education and Learning in New Mexico December 19, 2007
description
Transcript of IDEAL – NM Innovative Digital Education and Learning in New Mexico December 19, 2007
© 2006 NMLN1
IDEAL – NMInnovative Digital Education and Learning in New Mexico
December 19, 2007
Presented to: Project Oversight Committee
Presented by: IDEAL-NM Steering Committee Members:
Susie Bussman (RETA), Veronica Chavez-Neuman (HED), Jim Holloway (PED), Brian Ormand (NMLN), Tom Ryan (CTE), Tim Snyder (IDEAL)
It is anticipated that IDEAL-NM will have a major impact and within 5 years, all students graduating from a New Mexico high school will have experience with at least one on-line course
Governor’s Press Release October 27, 2006
© 2006 NMLN2
Project Management Status
Project Management Plan – Last Revised (December, 2007)
Project Schedule – Last Revised (December, 2007)
IV&V Contract – In Progress (Reference contractor proposal)
Project Team Meetings – Every Monday @ 8:00am
Project Status Report – Submitted to DoIT (December 10, 2007)
© 2006 NMLN3
Phase I Status $2,370,000 Certified on October 1, 2007
Cyber Academy:Staffing
IDEAL-NM Executive Director – Interviews in progress IDEAL-NM Academy Principal – Hired (Dr. Tim Snyder)IDEAL-NM Administrative Assistant – Hired (Sharron Purcell)
© 2006 NMLN4
Phase I Status $2,370,000 Certified on October 1, 2007
Cyber Academy Continued: Course Offerings
Aventa Course Offerings – Enrolling Students for Spring Semester
NM History on APS Platform – Ready for Spring Semester
Semester I, Algebra I – Ready for Spring Semester
Teacher Training26 Teachers trained to teach online courses
Ongoing training planned
© 2006 NMLN5
Phase I Status $2,370,000 Certified on October 1, 2007
IDEAL-NM Service Center IDEAL-NM eServices Director – Selection made
HelpdeskHelpdesk Staff not hired yet
Helpdesk Software RFP complete, ready for procurement
Office SpaceFacility Established in Rio Rancho (10 offices)Staff Computer Equipment ProcuredOffice Furniture Secured
© 2006 NMLN6
Phase I Status $2,370,000 Certified on October 1, 2007
Learning Management System (LMS) Data Center Preparation
Pre-Implementation Strategy – Started
Data Center Preparation – Waiting on LMS selection and State determination to implement a Vendor-Hosted or Agency-Hosted model.
Data Center Equipment Procurement – Waiting on LMS selection.
© 2006 NMLN7
Phase II Planning $5,200,000 Certification Request, December 19, 2007
Procure LMS RFP Process is complete and a recommendation has been made to the State.
Awaiting confirmation from State Purchasing to begin contract negotiations
Determine most advantageous solution for the state in a Vendor-Hosted or Agency-Hosted solution
Higher Education Department will Establish Contract with LMS Vendor
© 2006 NMLN8
Phase II Planning $5,200,000 Certification Request, December 19, 2007
Procure Web Conferencing System Finalize RFP after LMS Solution has been determined
Begin State Procurement Process to select a Web Conferencing Solution
Higher Education Department will Establish Contract with Web Conferencing System Vendor
© 2006 NMLN9
Phase II Planning $5,200,000 Certification Request, December 19, 2007
Implementation of LMS and Web Conferencing System Establish Implementation Team in Accordance with Pre-Implementation Strategy Results – Build Implementation Plan
Determine Hardware/Software Requirements Needed to establish a complete Statewide supported Data Center(s)
Procure Hardware/Software Required for Data Center(s)
© 2006 NMLN10
© 2006 NMLN11
IDEAL-NM Technology Timeline
3/31/2008Revision 2 Web Portal
12/19/07
Software Delivery Timeline
7/2/2007 8/29/2008
8/1/2007 9/1/2007 10/1/2007 11/1/2007 12/1/2007 1/1/2008 2/1/2008 3/1/2008 4/1/2008 5/1/2008 6/1/2008 7/1/2008 8/1/2008
Communicate to:- Schools- Institutions- State Agencies
7/2/2007Project Start
6/30/2008Functioning
Data Center(s)
5/30/2008 - 8/29/2008Implement Communications Plan
2/29/2008Procure Web Conferencing
8/20/2007 - 7/31/2008Implement Cyber Academy Plan (temporary hosting at APS)
8/1/2008Cyber Academy
OPEN12/31/2007
Procure LMS
5/16/2008Revision 3 Web Portal
© 2006 NMLN
Questions?
Thank you!
12