0 CHARI/LOGONE RURAL INTEGRATED DEVELOPPEMENT PROJECT (PDRI-CL) PROJECT COMPLETION REPORT (PCR) January 2016 Coopération Cameroun Banque Islamique de Développement (BID) Fonds de l’OPEP pour le développement International (OFID) Ministère de l’Economie, de la Planification et de l’Aménagement du Territoire (MINEPAT) Projet de Développement Rural Intégré Chari-Logone (PDRI-CL) BP 295 Kousseri Tel : (00237) 222 41 44 50 Email: [email protected]

Transcript of IDB PROJECT COMPLETION REPORT (PCR) - pdri …pdri-cl.org/fichier PDF/RAPPORTS/Char-Logone_...

IDB PROJECT COMPLETION REPORT (PCR)

0

V

Le Coordonnateur,

CHARI/LOGONE RURAL INTEGRATED DEVELOPPEMENT PROJECT

(PDRI-CL)

PROJECT COMPLETION REPORT

(PCR)

January 2016

Coopération Cameroun Banque Islamique de Développement (BID)

Fonds de l’OPEP pour le développement International (OFID)

Ministère de l’Economie, de la Planification et de l’Aménagement du Territoire (MINEPAT)

Projet de Développement Rural Intégré Chari-Logone (PDRI-CL) BP 295 Kousseri Tel : (00237) 222 41 44 50

Email: [email protected]

IDB PROJECT COMPLETION REPORT (PCR)

1

COUNTRY : CAMEROON PROJECT NUMBER : 2CM0053 PCR NUMBER : 01 PROJECT TITLE : CHARI/LOGONE INTEGRATED RURAL DEVELOPMENT PROJECT DEPARTMENT : AGR/IRD DIVISION : INTEGRATED RURAL DEVELOPEMENT OFFICER : SEYDOU KANE DATE : 2015

IDB PROJECT COMPLETION REPORT (PCR)

2

TABLE OF CONTENTS

1.1 ECUTIVE SUMMARY ........................................................................................ 6 1.1.1 Objective ....................................................................................................... 6

1.1.2 Project outcomes ........................................................................................... 6 1.1.3 Scope (planned vs. actual) ............................................................................. 6

PART -1: BASIC PROJECT DATA .......................................................................... 9 I.1. PROJECT KEYS................................................................................................... 9

I.2 MODES & TERMS OF FINANCING AT APPRAISAL...................................... 10 i.3. KEY DATES ....................................................................................................... 10

I.4. PROJECT COST AT APPRAISAL ..................................................................... 11 I.5. FINANCING PLAN AT APPRAISAL ................................................................ 11

I.6. IMPLEMENTATION PLAN AT APPRAISAL .................................................. 12 I.7. DISBURSEMENT PLAN AT APPRAISAL (IDB FUNDS)................................ 12

III. KEY DATES ........................................................................................................... 13 IV. SCOPE .................................................................................................................... 13

CIVIL WORK ........................................................................................................... 13 SUPPORT TO COMMUNITY DEVELOPMENT .................................................... 14

SUSTAINABLE CROP, LIVESTOCK AND FISHING PRODUCTION .................. 14 NATURAL RESOURCE MANAGEMENT .............................................................. 15

Major changes in project scope and reasons thereof ................................................... 15 V. PROJECT COSTS: Expressed in US$ Equivalent ..................................................... 21

Major changes in project cost and reasons thereof...................................................... 21 PROJECT COSTS (in Local Currency) ..................................................................... 22

Major changes in project cost and reasons thereof...................................................... 22 VI. FINANCING PLAN................................................................................................ 23

Major changes in project'S financing plan and reasons thereof ................................... 23 VII. IMPLEMENTATION SCHEDULE ....................................................................... 24

VIII. DISBURSEMENT AMOUNTS AND DATES ..................................................... 26 IX. MAJOR CHANGES EXPERIENCED DURING IMPLEMENTATION ................. 26

summary of the major changes experienced during project implementation covering

key areas ................................................................................................................... 26

X. COMPLIANCE WITH LOAN COVENENTS.......................................................... 30 XI. PERFORMANCE RATING SUMMARY (scores and ratings are auto-generated

based on assessments made in other sections ................................................................. 31 XII. RESPONSIBLE BANK STAFF ............................................................................. 31

PART-2: PROJECT IN CONTEXT ........................................................................ 32 A. PROJECT CONTEXT AND RATIONALE .......................................................... 32

SummarY OF the context and rational for the Bank assistance.................................. 32 Substantial changes in the above during implementation............................................ 32

B. PROJECT OBJECTIVES AND COMPONENTS ................................................. 32

the Project Development Objectives ........................................................... 32 C. SUMMARY OF PROJECT LOG FRAME ........................................................... 33

Major Changes Experienced During Implementation ..................................................... 41 1. Civil work ............................................................................................................. 41

IDB PROJECT COMPLETION REPORT (PCR)

3

2. Support on community development ...................................................................... 41 3. Sustainable crop, fish and livestock production ...................................................... 41 4. Biodiversity conservation action through waza and kalamaloué national

parks ........................................................................................................................ 41

5. PMU ...................................................................................................................... 42 6. ADMINISTRATIVE AND TRADITIONAL AUTHORITIES .............................. 42

D. PROJECT DESIGN AND READINESS FOR IMPLEMENTATION ................... 45 Design and readiness for implementation for each dimension of project ................... 46

E. PROJECT IMPLEMENTATION ......................................................................... 48 F. ACHIEVEMENT OF PROJECT OUTPUTS AND (PRELIMINARY)

OUTCOMES AND IMPACTS............................................................................................ 55 Achievement of Outputs ............................................................................................ 55 Achievement of Outcomes .............................................................................. 61

Preliminary Impacts ........................................................................................ 62

Overall Financial and Economic Performance ................................................ 64

G. SUSTAINABILITY ................................................................................................. 65 H. LESSONS LEARNED AND RECOMMENDATIONS ............................................ 66

1. Lessons Learned .................................................................................................... 66 3. Recommendations ................................................................................................. 66

I. OVERALL ASSESSMENT ....................................................................................... 67 J. PROCESSING ........................................................................................................... 71

APPENDIX -1: Map and Details of Various Items/project outputs ................................ 72 Map of the project location ........................................................................................ 73

Some outputs ............................................................................................................. 74 Actual achievement at pcr .......................................................................................... 79

Disbursements and sources of funds 80Llist of missions carried out (with dates, number

of persons, composed of mission, staff days............................................................... 81 List of project's reports .............................................................................................. 82

Summary of financial and economic analyses ............................................................ 87 Planned vs. Actual procurement plan ......................................................................... 89

Sources of information .............................................................................................. 98 OTHER DETAILS .................................................................................................. 100

APPENDIX -2 ......................................................................................................... 102 PERFORMANCE RATING SCALE ....................................................................... 102

IDB PROJECT COMPLETION REPORT (PCR)

4

CURRENCY EQUIVALENTES: US$ 20, 5 MILLION

ABBREVIATIONS

APD

AVANT PROJET DÉTAILLÉ

BID

BANQUE ISLAMIQUE DE DÉVELOPPEMENT

FCFA FRANC DE LA COMMINAUTE FINANCIERE D'AFRIQUE

CBLT COMMISSION DU BASSIN DU LAC TCHAD

CDS

CRÉDIT DU SAHEL

COPIL

COMITÉ DE PILOTAGE

CSPM COMMISSION SPECIALE DE PASSATION DES MARCHES

DSCE DOCUMENT DE STRATEGIE POUR LA CROISSANCE ET

L’EMPLOI

FAO FOOD ALIMENTATION ORGANISATION

FED FONDS EUROPÉEN DE DÉVELOPPEMENT

FEPROLOC FEDERATION DES PRODUCTEURS DU LOGONE ET CHARI

GIC ID IDB

GROUPEMENT D’INITIATIVE COMMUNE

ISLAMIC DINAR

ISLAMIC DEVELOPMENT BANK

MINADER

MINISTERE DE L’AGRICULTURE ET DU DEVELOPPEMENT RURAL

MINEPAT MINISTERE DE L’ECONOMIE, DE LA PLANIFICATION ET

DE L’AMENAGEMENT DE TERRITOIRE

MINEPIA MINISTERE DE L’ELEVAGE, DES PECHES ET DES

INDUSTRIES ANIMALES

OAD ORGANISATION D’APPUI AU DÉVELOPPEMENT

OFID OPEP FUNDS FOR INTERNATIONAL DEVELOPMENT

OHADA ORAGANISATION POUR L'HARMONISATION DES DROITS DES AFFAIRES EN AFRIQUE

OPEP ORGANISATION DES PAYS EXPORTATEURS DE

PETROLE

PDRI-CL CHARI/LOGONE INTEGRATED RURAL DEVELOPMENT

PROJECT

IDB PROJECT COMPLETION REPORT (PCR)

5

PIB PRODUIT INTERIEUR BRUT

PNDP PROGRAMME NATIONAL DE DEVELOPPEMENT PARTIPATIF

PNK KALAMALOUE NATIONAL PARK

SEMRY SOCIETE D’EXPANSION ET DE MODERNISATION DE LA

RIZICULTURE DE YAGOUA

TDR TERMES DE RÉFÉRENCE

IDB PROJECT COMPLETION REPORT (PCR)

6

1.1 ECUTIVE SUMMARY

1.1.1 OBJECTIVE The objective of the project is to contribute to poverty reduction, to improve food security and living conditions of the population in the project area. The specific objectives are to:

(i) Increase crop, livestock and fisheries production.

(ii) Diversify income generating activities.

(iii) Increase number of classrooms, health centers and potable water points.

(iv) Strengthen self-management and production capacities of the beneficiary

population.

(v) Protect river banks and degraded areas as well as identifying measures to

preserve biodiversity through the natural reserve parks of Waza and

Kalamaloue.

1.1.2 PROJECT OUTCOMES To achieve these objectives, the main outcomes are:

1. Crop, livestock and fishing production increased. 2. Income generating activities diversified. 3. Number of classrooms, health centres and potable water points increased. 4. Self-management and production capacities of the beneficiary population

strengthened. 5. River banks and degraded areas protected as well as measures to preserve

biodiversity through the natural reserve parks of Waza and Kalamaloue identified.

1.1.3 SCOPE (PLANNED VS. ACTUAL) The scope of the project is sub-divided into components based on the sub-sectors concerned and the consequences action to be conducted to achieve objectives and reach the main outcomes and impacts of the project. So the planned scope includes: (I) civil work, (ii) community development, (iii) sustainable crop production, (iv) sustainable animal and fish production and (v) natural resource management and biodiversity conservation. The scope of the project is maintained its main orientations. Nevertheless, within the components some changes were made to take into consideration the needs expressed by producers in their production systems. So the civil work component and the number of infrastructures were highly increased and some of them like water points for animals use are modified by innovative approach of using solar energy to pump water on a permanent basis for animals and even for the villagers. One animal water point is used by more than 10,000 cattle and about 15,000 small ruminants per year. Additional water points were constructed for irrigation purpose of vegetables, and other crops with high added value in the area particularly for women and youth. The actual challenge of the Cameroonian economy and specifically for the northern part is the poverty alleviation of this particular group of people. 1.3.4. Cost (planned vs. actual) The cost of the project at the appraisal stage has been overestimated for some components of the Project. In the implementation, internal adjustments within the components have been made to allow perform actions, not programmed or strengthen those programmed in term of quantities and scale. However, the overall cost of the project implementation was established with a remaining balance of nearly more than CFA + 1, 3 billion. This is mainly due to a reduction in the cost of some important infrastructures

IDB PROJECT COMPLETION REPORT (PCR)

7

programmed, fair mobilization of contingencies and the exchange rate of US dollar. More than 95% of programmed infrastructures are carried out but some disbursements are still awaited. 1.3.5. Implementation schedule (planned vs. actual) The implementation schedule at the beginning of the project was organized in a way that the civil work, community development and sustainable production, will be engaged in January 2012 and be accomplished in December 2014. As regards to the PMU, it will start in January 2010 and will end in December 2014; the services of a consultant would begin in January 2012 up to December 2014 (thus 36 months). The auditor should be mobilized in December 2011 and would wrap-up a month before the end of each year and it services are spread for 5 years. In the actual implementation of the project, taking into account the contingencies surrounding the operation of the project and part of the work, that is once concerning the socioeconomic infrastructures for small scale, a tiny part of the action of community development and sustainable production had been initiated in 2011 but all of those action have been suspended for managerial problems. It was only from July 2013 that all of the shares and infrastructures have resumed and finalized in 22 months. The PMU stated in February 2010, the services of the consultant in December 2012 (for 36 months) and the auditor have operated in accordance with the original schedule. 1.3.6. Outputs (planned vs. actual) The activities undertaken in the framework of this project are within the components identified at appraisal. That is civil works (infrastructures) to increase production and ameliorate productivity in agriculture, livestock and fish production, strengthening capacities of producers', building capacity to ensure the sustainable use of infrastructures and common used natural resources The implementation of the programme in term of civil works had resulted with the rehabilitation of more than 1,300 hectares of irrigated perimeters, the construction of two sluice dams, construction of 68 water points for human use (55 boreholes and 13 well rehabilitated at the beginning of the project), 32 classrooms constructed/rehabilitated and equipped, 07 open air slaughterhouses constructed in each head quarter of councils (two head quarters are not concerned because the characteristics of the localities), 02 cattle markets constructed instead of one, a fish market with a cold room and a landing stage constructed, 13 vaccination parks, 19 boreholes for agricultural use, 08 boreholes equipped with solar energy pumping system for both livestock and human use, 04 health centres constructed/rehabilitated and equipped with basic materials avec modern water distribution system. A modern slaughterhouse constructed in Kousseri. The civil works done are more important than planned (in number and quality). With regard to the community development, an important number of producers' organizations are putted in place to manage the entire infrastructures in a sustainable way as well as to handle the input acquisitions and products sell for a better price. The CVCA in six sub-divisions have been rehabilitated or created, micro-projects are elaborated with producers for credit through loan line. A specific monitoring system has been organized to be sure that the money borrowed was used for the production purpose. The project area, a total amount of CFA 880 million was distributed with an adequate follow-up by the Project. Nevertheless, the Credit de Sahel is not well organized to tackle the issue due to lack of human resource and adequate procedure according the agreement signed between the Bank, the Governor and the microfinance structure. In the area of agriculture, livestock and fishering, the main actions were base on the improvement of production techniques, amelioration of productivity and diversification of the income sources with a sustainably way. As estimation of the gross income indicated

IDB PROJECT COMPLETION REPORT (PCR)

8

that more than CFA 16 billion (around US$ 32 million) has been created in less than three years (mostly in é years). The sustainable natural resource management was focused on the restoration of nearly 1,000 hectares of degraded land, the establishment of 40,000 seedlings (forestry plants) in the public places and some private areas, the implementation of a "platform" of dialog and conflict management was organized in the Logone floodplain where transhumance is developed. The action relating to the conservation of biodiversity was focused on the definition of new boundaries of the Kalamaloue National Park. A map of the park has been established through the geographical information system (GIS). The surroundings population has been sensitized. As regards to the Waza National Park, the biodiversity conservation actions have been determined for the second phase as planned on appraisal stage. The sustainability of all the actions was be taken into consideration for any specific activity (or infrastructure), that is a participatory approach and the management committees. 1.3.7. Impacts, sustainability (prospects), and project ratings The delay in the implementation of the various actions of the project and the report period (just at the end of the project) don't allow indentifying clearly the real impacts of the project. However the results obtained and preliminary impacts on gross revenue estimated augur of significant impacts for the coming years. The estimation made on the agricultural production (cereals, vegetable and cowpea), the meat equivalent of cattle and small ruminant product, the additional quantity of milk induced, the revenue from fish farming are the real indication of the future impacts of the Project. In various discussions within different forums on development issues in the Farnorth region. 1.3.8. Other significant issues, recommendations and follow-up action In the framework of the implementation of this project, in accordance with the needs clearly indicated by the producers, the aspects to be strengthened are those related to the availability of inputs in relevant timescale and quantities. The pane strengthening technical capacities of producers seem to be fundamental because it had never been taken into account by the various projects and programs and even by the local representatives of ministries in charge of training farmers. This capacity building is the key action for the rural development that has to be considered by existing projects or future programs/projects. Producers in the project area are poorly trained. Char-Logone project has organized a large number of training sessions (innovative production techniques, using of new varieties and materials, etc...). The new important challenge for the area is the practicability of roads in rising season. The second phase most has as part of objective to tackle this issue. The other crucial issue is the employment of youth and the marginal people.

IDB PROJECT COMPLETION REPORT (PCR)

9

PART -1: BASIC PROJECT DATA (BASIC PROJECT INFORMATION INPUTTED INTO THE SYSTEM SOON AFTER APPRAISAL – REMAINS CONSTANT.)

I.1. PROJECT KEYS

Country: Cameroon

Project Identification Number/Code: 2CM0053

Project Title: Chari/Logone Integrated Rural Development Project

Project Location(s): Northern Part of Cameroon (Logone and Chari Division)

Main Sector(s): Rural Development

Sub Sector(s): - Community Development - Agriculture, - Husbandry, - Fish production - Natural Resource Management

Beneficiary: Population of the Northern Part of the Far North Province, particularly those of the Logone and Chari Division (around 590,000 inhabitants)

Executing Agency: Ministry of Economy, Planning and Regional Development

CO-FINANCIERS AND EXTERNAL PARTNERS

Financing plan at appraisal US$ 20 million IDB: ID 7 million (eq.US$ 10.5 million) OFID: US$ 7.00 million Cameroon: US$ 2.5 million Implementation stage IDB : ID 7 m or (eq.US$ 10.5 million) OFID : US$ 6 million Cameroon: US$ 3.5 million

Address of the Executing Agency Ministry of Economy, Planning and Regional Development P.O. Box 13750 Yaoundé Republic of Cameroon Facsimile (+237)222 23 37 17

IDB PROJECT COMPLETION REPORT (PCR)

10

I.2 MODES & TERMS OF FINANCING AT APPRAISAL

Item/Mode Estimated at Appraisal

Mode -11

Loan

Mode-2 Mode-3

Amount ID 7.00 million

(eq.US$ 10.5

million)

Service Fee/Mark-up <2.5 perce

Repayment Period 25 years

Grace Period/Gestation

Period

7 years

Guarantee Sovereign

Guarantee

I.3. KEY DATES

Key Dates Mode-1 : LOAN

Identification Date 25/10/2005 (date of

official request)

Loan Appraisal Date 17/5 – 6/6/2007

Loan Approval Date 7/7/2007

Loan Signature Date 4/6/2008

Effective Date 16/12/2008

Project (physical) Commencement Date 20/4/2010

Last Date for First Disbursement: 16/6/2009

Last Date of Last Disbursement: 31/12/2012

Projected Closing Date 31/12/2012

Actual Date of First Disbursement 20/4/2010

Number of Extensions One

Actual Date of First Disbursement 20/4/2010

Actual Date of Last Disbursement 07.07.2015

Project (Physical) Completion Date 30.06.2015

1 Usually the loan processing dates are the same for different modes of financing.

IDB PROJECT COMPLETION REPORT (PCR)

11

I.4. PROJECT COST AT APPRAISAL

Components Cost

US$ equivalent, million

Foreign

currency

Local

currency

TOTAL

Civil Work 3.20 6.50 9.69

Support to Community Development 0 0.72 0.72

Sustainable Crop, Livestock and Fishing

Production

0.83 4.10 4.93

Project Management Unit 0.37 1.24 1.62

Consultancy Services 0.85 0.21 1.07

Audit 0 0.18 0.18

Base Cost 5.26 12.95 18.21

Contingencies (5% physical + 5%

financing)

0.53 1.29 1.82

Total 5.8 14.2 20.00

I.5. FINANCING PLAN AT APPRAISAL

Parties

Financing Plan

US$ equivalent, million

Amount Terms

Service Fee/Mark, Up Repayment

period

Grace

Period Guarantee

IDB 10.5 <=2.5 percent 25 years 7 years Sovereign

Guarantee

Government 2.5 - - - NA

OFID 7.00 2 percent 20 years 5 years Sovereign

Guarantee

Total 20.00

IDB PROJECT COMPLETION REPORT (PCR)

12

I.6. IMPLEMENTATION PLAN AT APPRAISAL

Components

Implementation Plan

Start Date Completion Date Period (Years/

Months)

Civil Work Jan 2012 December 2014 3 years

Support to Community

Development

Jan 2012 December 2014 3 years

Sustainable Crop, Livestock and

Fishing Production

Jan 2012 December 2014 3 years

Project Management Unit Jan 2010 December 2014 5 years

Consultancy Services Jan 2012 December 2014 3 years

Audit December 2011 1 month at the end

of every year

5 years

Overall 5 years

I.7. DISBURSEMENT PLAN AT APPRAISAL (IDB FUNDS)

Item LOAN

(US$ million)

Total

(Cumulative)

Year 1 1.512 1.512

Year 2 4.121 5.633

Year 3 1.860 7.493

Year 4 0.826 8.319

Year 5 1.222 9.540

Total 9.54

IDB PROJECT COMPLETION REPORT (PCR)

13

II. MODES & TERMS OF FINANCING

Item/Mode Estimated at Appraisal Actual

Mode -12 Mode-2 Mode-3 Mode-1 Mode-2 Mode-3

Amount (ID, $, € etc) 20 US$ 20 US$

Service Fee/Mark-up 2,5% IDB and 2% OFID

2,5%

Repayment period IDB 25 years OFID 20 years

IDB 25 years OFID 20 years

Grace Period/Gestation Period

7 years 7 years

Guarantee Sovereign Sovereign

III. KEY DATES

Key Dates Modes

Mode -1 Mode-2 Mode-3

Identification Date 25/10/2005

Concept Clearance Date -

Preparation Mission Date -

Appraisal Date 17/5-6/6/2007 7/07/2007

Board Approval Date 16/12/2008

Loan Signing Date 4/06/2008

Effective Date 01/01/2010

Project (physical) Commencement Date 17/02/2010

Last Date for First Disbursement: Number of Extensions:

20/4/2010

One

Last Date of Last Disbursement: Number of Extensions:

24/12/ 2014 One

Actual Date of First Disbursement 20/04/2010

Actual Date of Last Disbursement 30/06/2015

Project (Physical) Completion Date 13/072015

Project (Financial) Closing Date 30/06/2015

IV. SCOPE The major intervention sector of the project is focused on civil work, community development and sustainable crop, livestock and fisheries production.

CIVIL WORK Irrigated perimeters In this Subsector the action and activities are oriented to hydro-agricultural infrastructures prior to the rehabilitation of some irrigated perimeters, mainly the Zimado and Ndou perimeters of the total area of 570 ha (170 for Ndou and 400 for Zimado).

2 Usually the loan processing dates are the same for different modes of financing.

IDB PROJECT COMPLETION REPORT (PCR)

14

Sluice dams in the Lake Chad area At appraisal stage one dam was programmed for Chouara's distributaries in Blangpua subdivision. Socioeconomic infrastructures The infrastructures concerned are those to support agriculture and livestock production, others to ameliorate livelihood conditions in the rural area (water points, health centres, classrooms and slaughterhouses.) In total, the civil work programme at appraisal is:

Rehabilitation and /construction of classroom; Construction of health centres; 25 waters points for human use (16 boreholes with hand pumps and 9 wells

covered with large diameter); 01 modern slaughterhouse. 07 slaughter areas with water sources, drying and possibility of hides and skins. 20 Vaccination Park; Rehabilitation of 3 pools and 1 artesian well for livestock water supply. 1 fish market stalls with the wind. 1 landing site at Blangoua. 1 cattle market. 10 community grain store. 1 water storage dam and sluice protection distributaries at Chouara. Rehabilitation of perimeters at Zimado (400 ha) and Ndou (170 ha). Construction/rehabilitation of 21 offices for support services.

SUPPORT TO COMMUNITY DEVELOPMENT At appraisal, the action related to community development that has highlighted concerns with the:

Support for basic economic organizations (micro finance institutions, cooperative

associations of producers, women, youths, artisans etc.),

Development and updating of local plans of development,

Strengthening of producer organizations, their professionalism and their self-

management capabilities,

Creating and strengthening of Village Savings and Credit Self-managed (CVECA)

Financing awareness raising, information, communication with communities,

leadership development groups, seminars and exchange of experience,

Due to the institutional changes and the decentralization process, the Government with World Bank support have developed a national program, "Programme National de Développement Participatif (PNDP)" to prepare the local development plans for all the councils and financed the priorities through subsidies.

SUSTAINABLE CROP, LIVESTOCK AND FISHING PRODUCTION Crop production

Introduces techniques to improve crop productivity; Diversification of income generating activities (market gardening, Marketing,

packaging and processing of products); Access to microcredit by the establishment of a credit line.

IDB PROJECT COMPLETION REPORT (PCR)

15

Livestock and Fishing Production Diversified of income generating activities (fish farming, intensification of

livestock production in the short cycle (poultry, small livestock); Rational Management pasture; Animal health care; Support, consulting and training for the fishermen toward using of proper

equipment, i.e. fishing equipment. Strengthening of fish harvesting control; Acquisition of 15 motorized canoes and 15 life-jackets. Code of Conduct for Responsible Fisheries, Extension developed by FAO.

NATURAL RESOURCE MANAGEMENT The activities planned are:

Concerted delimitation growing areas, paths and community forests. Management of concerted cross-border transhumance (vaccination and

determination of transhumance animals, spatial occupation, date of departure and return).

Realization of forest and fruit tree nurseries. Setting defense mechanisms and land restoration (DRS) such as erosion control

bounds filter.

MAJOR CHANGES IN PROJECT SCOPE AND REASONS THEREOF

Components At Appraisal Actual Major Changes

Civil Work Rehabilitation and /construction of classroom.

Construction of health centres (includes 1 car, 3 motorized canoe, 2 generator groups, and essential drugs).

25 points for drinking water, 16 boreholes with hand pumps and 9 wells covered with large diameter.

1 state-of-the-art slaughterhouse.

7 slaughter areas with water sources, drying and possibility of hides and skins.

20 Vaccination Park. Rehabilitation of 3

pools and 1 artesian wells for livestock water supply.

1 fish market stalls with the wind.

1 landing site at Blangoua.

1 cattle market. 10 community grain

store.

32 classrooms constructed/rehabilitated and equipped with tables and latrines.

4 integrated health centres constructed and equipped with water points, main necessaries materials (laboratory materials and beds).

55 boreholes drilled with pumps and 13 wells rehabilitated.

1 modern slaughterhouse in kousseri;

7 open air slaughter areas with water points constructed.

13 vaccination parks. 8 pastoral boreholes with a

solar energy pump system for livestock water supply (with a permanent capacity of 6,000 litres) and human use;

1 fish market and a landing site at Blangoua;

2 cattle markets; 2 big stores for commodities,

with a storage capacity of 12,000 m3 each;

2 sluice dams to secure maize area;

Rehabilitation of Ndou and Zimado perimeters (580 ha) abandoned for more than 23

Civil work The main changes are: the number of infrastructures programmed and executed. At the appraisal most of the component is overestimated for most of the important infrastructure. So for some of them, the executed number is doubled (thus, the infrastructures such as: dams, rehabilitation of irrigated perimeters or livestock markets). On the other hand, the construction of offices and buying cars for civil servants was left to ministries responsibilities (especially for the ministry in charge of livestock. In total, the major changes were positive and are in the interest of rural people (producers) for whom action and activities have been oriented. The rural electrification was introduced to ameliorate the living

IDB PROJECT COMPLETION REPORT (PCR)

16

Components At Appraisal Actual Major Changes

1 water storage dam and sluice protection distributaries at Chouara.

Rehabilitation of perimeters at Zimado (400 ha) and Ndou (170 ha).

Construction/rehabilit

ation of 21 offices for

support services.

years, 04 FED perimeters (668 hectares) left for 09 years and Dole and Biamo traditional perimeters (120 ha) or total of more than 1,300 ha;

Construction of Zilim dam for the regulation of water in Maga dam downstream.

19 water points for irrigation of trees/crop integrated production systems.

02 villages electrified through solar energy (Government's decision).

conditions of the rural populations, knowing that none of the villages in the area was electrified.

Support for Community Development

Support to Community Development Support of Basic

economic

organizations (micro

finance institutions,

cooperative

associations of

producers, women,

youths, artisans etc.).

Development and

updating of local plans

of development.

Strengthening of

producer

organizations, their

professionalism and

their self-management

capabilities.

Creating and

strengthening of

Village Savings and

Credit Self-managed

(CVECA).

Financing Awareness

raising, information,

communication with

communities,

leadership

development groups,

seminars and

exchange of

experience.

Support to Community Development Diagnosis and organization of

community based associations

for the management of

rehabilitated perimeters and

other common infrastructures

More than 600 basic economic

organizations are supported for

a total amount of CFA 880

million to reinforce their

production systems by

acquisition of inputs mainly

Produces Management

Committees were organized all

over the area to ensure the

sustainability of using

infrastructures and common

use natural resource.

Strengthening seed growers’

capacities

Diagnosis of the only divisional

level producer structure,

Federation of Farmers of

Logone and Chari (FEPROLOC)

and other existing umbrella, in

order to strengthening the

managing capacity.

Capacity Building of market

gardeners, the use of organic

manure and compost

fabrication.

Training of producers on

microfinance system

Changing of status of more than

400 small producer

organizations according to

OHADA regulations.

Creation and/or strengthening

of Village Savings and Credit

Self-managed (CVECA) for 200.

There are no major changes in the domain of Community Development. During the implementation process, the action and activities are more coherent than programmed and the results are well appreciated by producers.

IDB PROJECT COMPLETION REPORT (PCR)

17

Components At Appraisal Actual Major Changes

Sustainable Crop, Livestock and Fishing Production

Sustainable Crop . Introduce Techniques to improve crop productivity. Diversification of

income generating

activities

(marketing,

gardening).

Marketing,

packaging and

processing

products.

Access to

microcredit by the

establishment of a

credit line.

Livestock and Fishing Production Diversification of

income generating

activities (fish

farming,

intensification of

livestock

production in the

short cycle (poultry,

small livestock).

Management

Rational pasture.

Animal health care.

Power additional

Sustainable Crop Amelioration of techniques

and introduction of improved

varieties of crops.

Sensitizing producers’

organizations and

individuals for the

establishment of loan line (a

total amount of CFA 880

million is settled up to date in

term of microcredit with an

average rate of

disbursement of 60%.

More than 2,000 ha of

cowpea covered in terms of

crop protection are treated.

Introduction of improved

techniques of transformation

of vegetable to create an

added value to crops.

Establishment of prize

information system for the

area.

Capacity building for organic

fertilizing techniques to

reduce chemical fertilizers

and improve environmental

conditions of production.

Support for producers with

some materials.

Livestock and Fishing Production Strengthening the capacities

of farmers (cattle fattening

and ovine).

Fight against epizooties.

Acquisition of 05 canoes for

control of fishing activities.

Support for the development

of village poultry.

Support for the development

of fish farming (creation of

the fish nursery centre);

Capacity building (fish

conservation techniques; the

technical route of fodder

crops; conservation

Sustainable Crop There are no major changes for sustainable crop production apart the lack of pertinent human resources in this domain at the beginning of the project. Things are changed with modification on PMU staff members. The estimation of the gross added revenue for crop production for the last years of implementation was about CFA 10 527,200,000 (around US$ 20 million). Livestock and Fishing Production As indicated for the crop productions there are no major changes even if the implication of the state civil servant was fair according to the fishing control. The global results obtained are relevant, the gross revenue created in the animal and fish productions is estimated at CFA 5 331 782 600 (around US$ 10 million).

IDB PROJECT COMPLETION REPORT (PCR)

18

Components At Appraisal Actual Major Changes

livestock.

Support, Consulting

and training

towards the

fishermen for the

use of proper

equipment, fishing

equipment.

Strengthening of

fisheries control.

Provision of

management,

technical services

15 motorized

canoes.

15 Lifejackets.

Natural resource management Concerted

delimitation

growing areas,

paths and

community forests.

Management of

concerted cross-

border

transhumance

(vaccination and

determination of

transhumance

animals, spatial

occupation, date of

departure and

return).

Realization of forest

and fruit tree

nurseries.

Setting up defence

mechanisms and

land restoration

(DRS) such as

erosion control

bounds filter.

techniques of fodder crops;

village poultry breeding).

Organizing and Structuring

of fishermen.

Strengthening fishing

capacity.

Support in veterinary

medicines.

Natural resource management Action accomplished during the implementation of the project concerned the following points: DEFENSE MECHANISMS AND LAND RESTORATION Information and

sensitisation of local actors

on the issues.

Identification of different

area concerned.

Inventory by identifying a

forest area.

Physical demarcation of

zones.

Organization of local

monitoring committee.

Elaboration and execution of

simplified management plan.

Distribution of more than

40,000 forest plants.

Organization of plantation

campaigns in schools and

public spaces

Training and equipment for

tree nursery producers (19).

PLANNING OF AGROPASTORAL COMMON USE TERRITORIES Explanation of the process to

the main actors.

Elaboration of main

diagnoses.

Organization of local actors

(development of community

For natural resource management, all the action programmed at the appraisal has been executed and others like firewood strategies are integrated to take into consideration the main environmental problems of the area.

IDB PROJECT COMPLETION REPORT (PCR)

19

Components At Appraisal Actual Major Changes

organizations).

Identification and

organization of different

zones:

Determination of crop

production and other

activities calendar.

Arrival and departure dates

for animal holders.

Beginning of raining season

production (up to harvesting

period).

Semi-irrigated production

period.

Identification main actors

and their strategies.

Identification of different

type of conflicts.

Determination of rules and

regulations for conflict

resolution.

Participatory determination

of different actors’ forums to

manage common use spaces

and related conflicts.

BIODIVERSITY CONSERVATION ACTION THROUGH WAZA AND KALAMALOUÉ NATIONAL PARKS Determination of the new

limits of Kamaloue national

park and map.

Identification of all the

surrounding villages and

people.

Sensitization campaigns in

biodiversity conservation.

Building capacities for

technicians

Identification of the main

action for the conservation

of biodiversity within the

Waza National Park.

Project Management Unit

Construction of

offices.

Recruitment of main

All the planning actions were executed. Management of the project with adequate standards.

Better coordination within procedures. Respect of agreement and Cameroonian rules

IDB PROJECT COMPLETION REPORT (PCR)

20

Components At Appraisal Actual Major Changes

staff.

Acquisition of

vehicles and other

office materials.

Organization of

procurement

procedures

according to the

agreement and

rules and

regulations.

Management of the

project as a whole.

Anticipation on future action by finalizing feasibility study for second phase with pertinent domains of intervention.

and regulations. The finalization of log, frame and all needed documents according to the Agreement and Execution Agency. Proactive approach. Anticipation attitude.

Consultancy

Services

Conduct the

technical studies

for civil work.

Prepare all the

tender documents.

Monitoring and

supervision of

infrastructures.

Support from experts and

other civil servant with

relevant competence for the

elaboration of all the studies.

Tender documents prepared

were mostly prepared with a

strong support of the PMU

staff.

Support of other technicians

for the supervision of civil

work.

Number of staff

mobilized in lower

than the planned.

Fair experiences

and expertise in the

fields concerned

with the project.

Fair motivation and

engagement of the

different staff.

Lack of necessary

working materials.

Audit Auditing and

certification of

payments.

Work well done and at the time needed by the Bank and other actors.

Any changes

IDB PROJECT COMPLETION REPORT (PCR)

21

V. PROJECT COSTS: EXPRESSED IN US$ EQUIVALENT

MAJOR CHANGES IN PROJECT COST AND REASONS THEREOF.

Cost Item

Estimated at the Appraisal (expressed in

US$)

Actual (expressed in US$)

% age Change Main Reasons

FC LC TOTAL FC LC TOTAL FC LC TOTAL

Civil Work 3.20 6.50 9.69 3.20 6.5 9.46 4.73 0 -54.3% Delay o, disbursements for OFID funds mainly oriented for civil work (payments are still awaited)

Support to Community Development

0 0.72 0.72 0 0.94 0.94 0.24 0 +30% Support by government due to the importance of the component

Sustainable Crop, Livestock and Fishing Production

0.83 4.10 4.93 0.83 4.10 2.59 2.59 0 -47.5% Fair capacity of agricultural expert at the beginning of project

Project Management Unit

0.37 1.24 1.62 0.37 1.22 1.22 0 0 -25% Education in the PMU staff members for about 6 months

Consultancy Services

0.85 0.21 1.07 0.85 0.21 0.71 0 0 -43.7% Low amount for the consultant due to low financial proposition

Audit 0 0.18 0.18 0 0.18 0.18 0 0 0% Any change

Base Cost 5.26 12.95 18.21 5.26 12.95 17.56

-39.1% Rate change of dollar vs. CFA Non-payment of about 60% of OFID funds due to the clearance problems

Contingencies (5%

physical + 5%

financing)

0.53 1.29 1.82 0.53 1.29 0 Fair mobilization of contingency and t the rate of dollars

Total Cost 5.8 14.2 20.00 5.8 14.2 17.56 -22.2% Important remaining payments of OFID funds and fair mobilization of contingencies

NB: the payments are ongoing for part of the work due to the important delay for OFID funds disbursements so the exact amount will be known soon, at the end of this process of disbursements

IDB PROJECT COMPLETION REPORT (PCR)

22

PROJECT COSTS (IN LOCAL CURRENCY)

MAJOR CHANGES IN PROJECT COST AND REASONS THEREOF.

Cost Item

Estimated at the Appraisal (expressed in Local

Currency)

Actual (expressed in Local Currency)

% age Change Main Reasons

FC LC Total FC LC Total FC LC Total

Civil Work 1600

3200 4845 4444 -9% Application of adequate cost for best quality infrastructures

Support to Community Development

0 360 360 335 -7% Actions are engaged in 2013 but oriented mostly to planned actions

Sustainable Crop, Livestock and Fishing Production

415 2050 2465 2352 -5% Actions are still ongoing for the counterpart financing part

Project Management Unit

185

620 805 1124 The PMU is still in place that is to assure the closing procedure and preparation of second phase mostly financed by Government The loan line was integrated in the PMU for a better control and monitoring In the other hand the during years (from 2010 to beginning 2013) the expenditures for PMU were abnormally high, for example in the 2012 for total amount mobilized of CFA 413 million, the expenditures for PMU are CFA 270 million (around 67% of the total expenditures)

Consultancy Services

425 105 535 374 - -30% The amount proposed by the cabinet is lower than planned

Audit 0 90 90 70 -5% Ongoing activities up to the end of the year for the auditing of final accountability

Base Cost 2630 6475 9105 8700 -5% Better management of

Contingencies

(5% physical +

5% financing)

265 645 910 0

-100%

Any mobilization of contingency

Total Cost

2900

7100 10 000

8700

-13% Rational use of planned resources

IDB PROJECT COMPLETION REPORT (PCR)

23

VI. FINANCING PLAN

MAJOR CHANGES IN PROJECT'S FINANCING PLAN AND REASONS THEREOF.

Item Estimated at the Appraisal (expressed in

US$)

Estimated at the Appraisal (expressed in

local currency)

Actual (expressed in

US$)

Actual (expressed in

local currency)

FC LC Total FC LC Total FC LC Total FC LC Total

IDB 10,7 5350 10,50 5250

Government 2,5 1250 3.50 1770

OFID 6,9 3450 6,0 3000

Total Cost 20,2 10100 20,0 10020

The main change is from OFID contribution, instead of US$ 7 billion, the amount of

the agreement was US$ 6 million and the gap was be taken by the Government.

IDB PROJECT COMPLETION REPORT (PCR)

24

VII. IMPLEMENTATION SCHEDULE .

Components At Appraisal Actual Major Changes and Reasons

Start Date Completion Date

Period (Years/Months

Start Date Completion Date Period (Years/ Months)

Civil Work

Delay in recruitment procedure of the consultant, mismanagement at the

beginning of project, low absorption capacity at the beginning

Support to Community Development

Mismanagement at the beginning of project, low capacity of the expert at the

beginning

Sustainable Crop, Livestock and Fishing Production

Mismanagement and lack of

strategic and operational documents for the intervention at the beginning of project, fair

capacity of existing experts delaying the action for more than 3 years

Project Management Unit

Delay in the beginning of the project and completion procedures for the action

conducted, preparation of second phase documents, payment of the salary by the

government for part of the period

Consultancy Services

Important delay for recruitment of the consultant, lack of a thorough database for such a cabinet at level of execution agency

April 2019 September 2011 27Months July 2013 April 2015 18 Months

April 2008 September 2012 41 Months July /2013 Juin 2015 23 Months

April 2008 December 2012 56 Months May /2013 Juin 2015 25 Months

January 2008 Sept. 2012 57 Months January 2010 31/12/2015 72 Months

April 2009 September 2011 27 Months December 2012 31/12/2015 36 months

IDB PROJECT COMPLETION REPORT (PCR)

25

Audit

Any change

Overall

Delay in setting procedure for core documents of the loans at the government level (judicial

appraisal, authorization for loan convention signing, recruitment procedure with

non-objections of the Bank Delay of first disbursement by the Bank, mismanagement by

the staff the PMU at the beginning of the project Delays in funds disbursements

for contractors, particularly in the second financing agency (OFID)

Dec 2011 1 month at the end of every year 5 years November /2011 31/12/2015 5 years

January 2008 31/12/2012 5 years February 2010 December 2015 5 years 11 months

IDB PROJECT COMPLETION REPORT (PCR)

26

VIII. DISBURSEMENT AMOUNTS AND DATES

Item Mode-1 (CFA F, million) Mode-2 (specify

currency)

Mode-3 (specify

currency)

Total

Total Approved 10010

Amount Cancelled None

Available Balance 10010

Total Disbursed 8787

Annual Disbursements

2010 204

2011 141

2012 415

2013 1027

2014 2564

2015 1943

2016 2404 (awaited payment from OFID, IDB and

Cameroonian government)

TOTAL 8700

IX. MAJOR CHANGES EXPERIENCED DURING IMPLEMENTATION

SUMMARY OF THE MAJOR CHANGES EXPERIENCED DURING PROJECT

IMPLEMENTATION COVERING KEY AREAS

Item Major Changes Experienced During Implementation

Key Comments, Observations, Conclusions

1. Economy The economy of the project area is closely tied to the national economy. In this way, Cameroon, like most of the developing countries, which began its evolution toward and industrialized country, presents up to now an economic situation characterized by a strong dominance of the rural sector, a low industrialization, an inflationary trend, which gives a rate of economic growth relatively low to ensure a genuine growth leading the country to the emergence within the timescale. The main criteria for convergence, despite a clear improvement still remain weak. The Gross Domestic Product (GDP), which is fairly low in view of the real potential and its rate of growth, does not allow an increase of the economy in real term. In addition, the inflationary pressures were important up to 2013. The main solution is the diversification of the products that have to be exported that means most of the raw products have to be transformed.

The Project action is focused on revenue increase and diversification is covering the main constraints of national and local economy. The conducted actions need to be consolidated to fully permit the rural people in the area prior to the welfare amelioration and to contribute to the national economy in the other hand. Efforts have to be made to transform most of the products.

2. Main Sector

As for the national economy, the rural sector remained the best one for the intended economy growth. The substantial changes are due to the market prices in the last 2 - 3 years of project implementation.

Global economical context is slowly changing and by the end of this year the price situation will be better and the producers who are ready to produce more will surely increase their production (and income.

3. Sub- Main sub-sectors concerned are agriculture, The coming months and years are

IDB PROJECT COMPLETION REPORT (PCR)

27

sector husbandry and fish production. The above situation is seemly transferred to these sub-sectors.

promising; a second phase will be highly recommended and waited by all the rural populations for whom the action and infrastructures are realized. They are fully ready through capacity building and with the new techniques of production at their disposal.

4. Project

Objectives

The objective of the project is to contribute to poverty reduction, to improve food security and living conditions of the population in the project area. The specific objective is to: (i) increase, crop, livestock and fisheries production; (ii) diversify income generating activities; (iii) increase number of classrooms, health centres and potable water points; (iv) strengthen self-management and production capacities of the beneficiary population; and (v) protection of river banks and degraded areas as well as identifying measures to preserve biodiversity through the natural reserve parks of Waza and Kalamaloue. These objectives are remained unchanged.

All the planned objectives are achieved.

Scope/

Components To achieve these objectives, there are 5 main components that are developed: Civil work, community development, sustainable production and environmental protection.

Some components are readjusted to take into consideration the real needs of producers. All project actions are oriented to rural populations; the participatory approach is best way to ameliorate their welfare, acting on their real preoccupation and the main production constraints.

Civil Work The socioeconomic and the hydro-agricultural infrastructure development have contributed to reinforce the action of the Project. The land, availability of rice production is highly ameliorated for producers. It is the same for the level of production. The major changes concerned the number of infrastructures which are multiplied even by 2 for big part due to financial availability.

Civil Work The infrastructures constructed for rural people are relevant, technically of best quality and easy for maintenance by rural people. Community based small management organizations are the best way to assure sustainability

Support for community development The producers of the project area are well organized to be aware of the sustainability of the production actions and infrastructures. The way that those infrastructures are managed by the producers now is a good indicator to the future sustainability. So the main changes in this area this strategically approach of implication of the main actors to take over the management of the infrastructures and common use spaces. The support on community development is very important tool of project success.

Support for community development It is very important in a Project like PDRI to ensure the sustainability of the infrastructures by organizing producers to take care of them. The local authorities are part of the organization

IDB PROJECT COMPLETION REPORT (PCR)

28

Sustainable Crop Production of improved and certified seeds; Rehabilitation of areas to produce rice and vegetables on more than 1,300 hectares; Introduction of new high-yield varieties of rice, vegetables, cowpea and soya bean; Protection from flood of more than 10,000 hectares of maize and cowpea around Lake Chad area for the production of at least 25,000 tons of maize per year.

Sustainable Crop Organizations of producers are able to respect the raining season or irrigated crop calendars; Capacities are building to take over the management of heavy investment (sluice dams, large scale irrigation land, etc.) Elaboration of projects and raising funds (though loan line mainly).

Livestock and Fisheries During the implementation of the project, the main changes for these issues concerned the:

Improvement and the living conditions of the population.

Securing food of the populace and the surplus sell of fish, poultry, beef, sheep and goats,

The increase of producers income;

The substantial reduction in mortality of small ruminants, cattle and poultry.

Fish production is important following the creation of nursery centre.

The implementation of new innovations and techniques to enable increase in quantity and quality of products;

The increase in production of forages crops (brachiaria and stylosanthes), which had positive effect in animals.

Livestock and Fisheries The implementation of project activities went well despite the difficulties encountered: The inaccessibility of most areas during the raining season is a big constraint of selling fresh fish; Inappropriate techniques of production for the important products have to be tackle all over the project zone.

Location(s) The project location is not changed. Furthermore, as indicated on the appraisal, the Mayo Danay division will be concerned with the second phase, But with the news actions and projects in this area, the second phase has to be concentrated on the same area facing numbers of constraints.

The news actions are concentrating to SEMRY structure for rice production on more than 8,000 ha. The new project is this one supported by World Bank for a total amount of CFA 54 billion (around US$ 108 million) for regional management as a whole.

Cost The Total cost of the project is remained unchanged, but the contribution of OFID is modified (from US$ 7 million to 6 million) and the contribution of government was consequently modified to take into account the gap of CFA 500 million.

All the three financing agencies have respected the planned amount. The disbursements were not relevant and the OFID-IDB couple was not well operational for disbursements procedures.

Financing

Plan

The financing plan had not been changed completely. It is just the amount planned for the OFID funds that was being reduced and consequently the counterpart contribution was increased.

An efficient financing plan will be rigorously applied for a better implementation of any other Project. And a delay in mobilizing funds planned has an important impact on project outputs because the contractors are not totally engaged if the payments are not going on just after accomplishing of contracts.

Implementa

tion

Schedule

The implementation schedule is linked to the financing plan and the capacity of the PMU staff to manage the difficulties by anticipating problems and solutions. Most of the delay is the result of lack of disbursements in time scale and the fair management capacity of the PMU at the beginning (particularly the

All the actors have to sure that financing plan will be respected according to the implementation schedule and the PMU staff are totally has the relevant management capacity.

IDB PROJECT COMPLETION REPORT (PCR)

29

coordinator). Procurement

Procedures There are no changes on procurement procedures, there were only but the procurement and the financing plan and the action programmed are not fully respected.

All the procurement procedures and the possible modifications have to be known at the appraisal level. The changing in internal procedures has to be in conformity with the international standards. The agreement signed must be the reference instead of internal procedures.

Executing

Agency

Any changes are noted according to executing agency apart from the acceleration of the disbursement of the counterpart funds (more than CFA 1 billion in less than two years)

The executing agency and the PMU staff have to work in a regulator base to ovoid misunderstandings and CAA will be informed by the Governor if the is some change.

PMU Due to mismanagement of the project at the beginning for more than 3 years, adjustments have been done to boost the implementation. After the first period the level of the physical and financial realizations as so limited.

The main problem of the PMU at this moment is the disbursements problems for those contractors waiting for long time. Some of them are gone to court of for judiciary procedures.

Partners All the partners have been mobilized after the change made in the PMU staff and the positive attitude of all of them was a key element for the relevant results of the Project.

The PMU have to be closer to the executing agency and it has to be fully aware of management problems by anticipating actions, proposing relevant solutions and has to be in contact with the Bank in permanent base. Project implementation needs a strong PMU particularly a good coordinator and other partners. That is the main weakness of the PMU at the beginning of the Project.

Crédit du

Sahel (a

Particulaire

Partner)

At the project appraisal only one Micro finance agency is retained to manage the loan line of CFA 1 billion; the agreement and the procedures' manual are not respected by the structure. That is in term of procedure and scope of the financing activities (and the amount also). Monitoring in field reveals that producers are not satisfied at all. Many problems are raised during the credit distribution. PDRI has mobilized three structures to monitor all the process on the field

Action has to be taken to solve this crucial problem of the loan line by clarifying the responsibilities of the different actors and the role of the project. The activities to be financed and the amount that can be submitted is another problem presented by producers among others. The use of the revolving funds has to be discussed deeply.

Consultants For the main consultant, who is in-charge of all technical studies, preparation of procurement documents and monitoring of the execution of infrastructures, the programmed human resources is not fully mobilized and those who are available are relatively fair in experience and capacity for technical studies and elaboration of documents of tender. The other expertise has been mobilized to achieve the documents.

The process of recruitment of this consultant has to be very rigours with a relevant shortlist coming from bother the Bank and the Cameroonian Government. In the other hand the amount paid has to be consequently important to mobilize all the needed expertise.

Contractors/

Suppliers

There are no major changes with contractors, service suppliers; the main problem remained the non-payment of most of the OFID financing action and delay of IDB payments. Two contractors had abandoned the work for non-payment of their first 'bill" all of them financed by OFID funds, some of them went to

When the contracts are signed and the work done, the delays of payment have to be known by all the actors. According to the procedure (Bank's internal procedure), the approximately date of payment has to be communicated to the project or to the CAA in order to inform

IDB PROJECT COMPLETION REPORT (PCR)

30

the justice for the same reasons. other actors (contactors and Ministry of publics contracts)

Local

Beneficiaries

The beneficiaries change the attitude to project when the real action was conducted, from July 2013 up to the end of the project. They have very positive appreciation of the project actions.

Any project must have a well developed strategy towards the beneficiaries according to the action that have to be conducted by integrating them at the beginning stage and have to be informed if any problem arises during the implementation period.

Other - Local authorities

The implication of the local authorities (traditional, administrative, councillors) is a key to project success, they are playing an important role on the village level for conflict resolution (for example). Those actors have been integrated as part of the Project implementation.

At appraisal stage, traditional rulers and local authorities have to be considered as actor's foot the implementation of the Project. However their role has to clearly define.

X. COMPLIANCE WITH LOAN COVENENTS

Loan Covenant Responsible Agency

Compliance Outcome Comments

Loan Agreement Project N°CM0053 Dated June 4, 2008 For an amount of - ID 7,000,000 - US$ 10,500,000 (IDB) The second Loan Agreement with OFID dated November 4, 2008 N°1214P For a total amount of - US$ 6,000,000

Ministry of Economy, Planning And Regional Development (MINEPAT)

1. Crop, livestock and fishing production increased. 2. Income generating activities diversified. 3. Number of classrooms, health centres and potable water points increased. 4. Self-management and production capacities of the beneficiary population strengthened. 5. River banks and degraded areas protected (for a large scale action) as well as measures to preserve biodiversity through waza national park mainly.

More than 95% of outcomes achieved. All those activities needed consolidation through a second phase and other main constraints (lack of roads, conservation/transformation of products, limitation of fish harvesting).

IDB PROJECT COMPLETION REPORT (PCR)

31

XI. PERFORMANCE RATING SUMMARY (SCORES AND RATINGS ARE AUTO-GENERATED BASED ON ASSESSMENTS MADE IN OTHER SECTIONS)

Broader Criteria Sub-Criteria Rating Score Rating (HS/S/ PS/ U/HU)

1. Project Objectives and Framework Dimensions

Objectives (relevance, achievability and consistency)

3 S

Use and strength log frame (logical, measurable and thorough)

3 S

Overall Sub-score 3 S

2. Cost and Time Performance

Cost Over/Under Run/Savings 4 HS

Adherence to original schedule 2.5 S

Overall Sub-score 3.25 HS

3. Institutional Performance

Bank Performance 2.5 S

Beneficiary Performance 3 S

Executing Agency Performance 3 S

PMU Performance 3 S

Partners Performance 2.5 S

Consultants Performance 2 PS

Contractors/Suppliers Performance 3 S

Overall Sub-score 2.90 S

4. Output and Outcome Performance

Achievement of Outputs 4 S

Achievement of Outcomes 3 S

Overall Sub-score 3.5 HS

5. Preliminary Impacts 3 PS

6. Sustainability 3,15 HS

OVERALL PERFORMANCE 3.02 HS

XII. RESPONSIBLE BANK STAFF

Position At. Appraisal At. Complétion

Sector Department Director

MUSA SYLLA

Division Manager ABAKAR ABDOURASSOUL

SOHAIL MAQBOOL MALIK

Project Officer/Leader ABDELWAHAB CHARIF SEYDOU KANE

PCR Team Leader

PCR Team Member

IDB PROJECT COMPLETION REPORT (PCR)

32

PART-2: PROJECT IN CONTEXT

A. PROJECT CONTEXT AND RATIONALE

SUMMARY OF THE CONTEXT AND RATIONAL FOR THE BANK

ASSISTANCE.

SUBSTANTIAL CHANGES IN THE ABOVE DURING IMPLEMENTATION

Cameroon Government is committed to the improvement of the growth of its economy based on the rural sector for almost four years. The rural sector is one of the key relevant sectors to be activated for boosting the country’s economy for the purpose of poverty alleviation and creating jobs for the youth. In addition, the areas subject to the problems of insecurity are those who come in priority. In doing so, the action of the Bank in the Logone and Chari division is an anticipation of the current strategy of the Cameroonian Government in the development in those particular areas. On the overall plan, the Bank is one of the partners whose support in constantly increasing. In this perspective, the Bank led a mission in February 2015 for a triennial programming of its support in Cameroon. It is important to note that the financial requirements of the country are concentrated in seven main areas among others. That is (i) road infrastructure, (ii) port infrastructure, airports and railway; (iii) the energy infrastructure and hydraulic, (iv) adjustments stalled, (v) industrial infrastructure and mining, (vi) urban development and social and (vii) information technology and tourism. The bank, to support the development of Cameroon, envisaged for the coming three years in seven specific areas, (1) agriculture and rural development, (2) infrastructure, (3) human development, (4) livestock, fisheries and animal industries, (5) water and sanitation, (6) scientific research and (7) energy and transport. The total number of projects to be funded during the next three years is 14 for a total amount of around CFA 349.11 billion and the contribution of the IDB could be CFA 279.29 billion including US$ 30 billion for phase II of the Chari-Logone Project and the components will be within the framework of the programme.

B. PROJECT OBJECTIVES AND COMPONENTS THE PROJECT DEVELOPMENT OBJECTIVES

The objective of the project is to contribute to poverty reduction, to improve food security and living conditions of the population in the project area. The specific objective is to: (i) increase, crop, livestock and fisheries production, (ii) diversify income generating activities, (iii) increase number of classrooms, health centres and potable water points, (iv) strengthen self-management and production capacities of the beneficiary population, (v) and protection of river banks and degraded areas as well as identifying measures to preserve biodiversity through Waza national park.

There is any substantial changes in the project objectives

Project Objective Dimensions Assessment Rating Score (0-4)

Relevant Relevance to the country development priorities.

In Logone and Chari division, the level of poverty is the higher one (around 70%) and reduced the rural population welfare. PDRI-CL is one the most important actions in the area with an integrated approach addressing agriculture, livestock, fishing, civil work and environmental issues.

3.5

Achievable Objectives that could be achieved with the project inputs and in the expected timeframe.

The Staff of the Project work hardly to achieve all those objectives despite some crucial difficulties as mentioned above.

3

Consistent Consistent with the Bank’s country or

The project is in perfect coherence with the overall priorities, because it

3.5

IDB PROJECT COMPLETION REPORT (PCR)

33

regional strategy, and overall priorities.

addresses crucial issues (development community, sustainable crops, civil works, livestock, natural resources management)

3. HOW EACH PROJECT COMPONENT CONTRIBUTES TO ACHIEVING THE PROJECT DEVELOPMENT OBJECTIVES

Civil work Support for community development

Sustainable crop, livestock and fish production Natural resource management

Civil work: The implementation of civil work facilitated access to water, to health centres for the population. The Project constructed open air slaughterhouses, storage structure, and vaccination parks for animals. These infrastructures will help significantly the population to improve their production and their welfare. The water management to secure more than 1,300 ha for rice production and vegetables. Sluice dams to secure more than 10,000 ha were maize for at least a total production of 25,000 tons per year. Support for community development The Project supports the community development (training, sensitization, diagnostic…). Building capacity for innovative techniques for crop production and productivity, the sustainability of infrastructures was totally integrated. Sustainable crop, livestock and fish production: This component contributes to achieve the objectives by innovative action, such as fish and poultry breeding. The target group increased the quantity of fish and poultry, and also their income. Action on crop production is very relevant because the amelioration of yield and productivity have impacted significantly the total production in the area. That is an important mean of improving income for rural population. Natural resource management: This component contributes to reforestation by planting trees in the area of the Project. The Kalamaloue and waza National Parks are the main protected areas in the Far north Region. And the biodiversity is concentrated is those two parks. Do to so, limits of kalamaloue national park was identified and secured. The surroundings populations are fully sensitized on the importance to preserve the natural resources around the zone. Studies have been conducted in Waa National Park to clarify the actions that can be done there to reinforce the protection of the wildlife in this National Park in the second phase.

C. SUMMARY OF PROJECT LOG FRAME (PROJECT HAS INCOMPLETED

LOG FRAME AT APPRAISAL) 1. THE LOG FRAME. Major changes in activities, outputs, outcomes and indicators during implementation by comparing targets at appraisal and actual at completion.

ACTIVITIES OUTPUTS Expected Outcomes (% of produce impacted by project action

Indicateurs to bé Measured

Civil Work

Rehabilitation of irrigated lands abandoned by SEMRY for more than 23 years.

2 irrigated fields are rehabilitated (namely Ziamdo and Ndou).

6 perimeters are rehabilitated for a total area of around 1,300 hectares for mainly rice production (a total quantity induced of about 20,000 tons per year). Apart the rice production, populations are using those area for vegetables with high

Quantity of

cereal

produced per

year

% of

improvement

of crop yields

(%) increase in

productivity

% of increase

IDB PROJECT COMPLETION REPORT (PCR)

34

added value. The revenues have been improved and the ratio of return to capital employed presented on Appendix is a very good indicator

in quantity of

vegetable

% of income

increased

Construction of rural health centres equipped with water facilities and basic medical materials.

4 health centres constructed and equipped.

Improved by health of

rural population by the

amelioration of access

to health structures

The number of

patients

treated

% odd

reduction of

recurrent

illness in rural

area

% of patient

transported

from villages to

towns

Construction/rehabilitation and equipment of classrooms

32 classrooms constructed/rehabilitate and equipped with tables and chairs

Reduction of

number of students

per classroom

Better quality of

education

% of reduction

of the ratio

% of success

for exams

% of females in

school

Construction of open air slaughter houses

07 open air slaughterhouses constructed equipped with water point for cleaning at head quarters of councils

Amelioration of sanitary condition of meat consumed by the population.

Better control of the quality of meat

Proper

management of

meat all over the

town of the council

Better control by

the council of meat

sold

% of increased

number of

animals per

day

% of illness due

to bad quality

of meat.

Number of

animals really

inspected by

% of taxes paid

to council from

animal

slaughter

Construction and equipment of a modern slaughterhouse in Kousseri town.

01 modern slaughterhouse constructed in Kousseri town.

Civil Works

Construction of water points for human use

62 water points (50boreholes and 12 well rehabilitated) 08 boreholes , using solar-powered energy for cattle (6,000 l in capacity each) 19 boreholes for tree irrigation (11 with the human energy pumper system)

Increase in animal

production.

Increase in weigh of

cattle.

Availability of water

for human being

Increased in

vegetable and fruit

production.

Use of low cost

alternative

% of animal

increased

% of weigh

increase in

animals

% of the cattle

and small

ruminants

remained in

villages

Quantity of

Construction of the boreholes for cattle

Construction of boreholes with small motor pumping system for agro forestry

IDB PROJECT COMPLETION REPORT (PCR)

35

and vegetable production

technologies

directly available an

easy for a good

adaptability to local

use and

maintenance

increase in

irrigated production

systems

vegetables and

fruit production

due to these

structures

(ongoing).

% increase in

revenue

related to the

irrigation

system

Construction of boreholes with small motor pumping system for agro forestry and vegetable production

Construction of a sludge dam on distributaries of Chouara river

02 sludge dams constructed on distributaries of Chouara and Ndjargoudja rivers

Protection from flood of the maize produced around lake Chad

Increase in maize and cowpea production.

Increasing in the number of farmers around these areas.

Subsequent increase in revenues of producers.

Stability of farmers increase in number

of fish harvesters amelioration of

living conditions in rural area

permanent use of water from albeit river

% of area

secured

Quantity of

maize and

cowpea

produced

% of farmers

increased

number of

farmers

producing all

over the year

% of new

farmers

arriving

(ongoing)

% of increase

of farm size

% of population

using energy

services

% of increase

in crop

production and

livestock

development

due to the

presence of

water in Lebed

river

Construction and infrastructure downstream of Maga dam for a better drainage of water and hydrolith of Elbeid river

Drainage work on some canals ahead of the Mayo vrick river, Maga's dam downstream

Electrification of villages using solar energy

Two villages of Afade and Amchilga, a third one is ongoing Other villages are programmed (financed by additional Government fund)

Support to Communiât Development

Support for

Basic

economic

organization

s (micro

finance

institutions,

cooperative

s,

associations

of

producers,

Diagnosis and

organization of

community based

associations to

manage rehabilitated

perimeters and other

common

infrastructures (fish

market, sluice dams,

storage structures,

vaccination parks,

water points for

Producers are organized in their activities and for sustainable use of infrastructures and common use spaces The support on community based development is very important for sustainability of project’s action and activities.

- Number of

community

organization fully

functional around

200).

- Bargaining of

producers in the

process of price

negotiation in all

markets (ongoing).

- Number of

IDB PROJECT COMPLETION REPORT (PCR)

36

women,

youths,

artisans

etc.).

Strengtheni

ng of

producer

organization

s, their

professional

ism and

their self-

managemen

t

capabilities.

Strengthening of producer organizations, their professionalism and their self-management capabilities

Creation and/or strengthening of Village Savings and Credit Self-managed (CVECA).

livestock, water

points for human

use, common area

for vegetable

production, etc.).

More than 600 basic

economic

organizations are

supported for an

amount of CFA 880

millions to reinforce

their production

systems by

acquisition of inputs

and small scale

production

materials.

200 organizations

created and

capacities built.

A peasant management committees are putted in place

organizations which

received credit

- % of credit

disbursed

- % of saving from

the income

generated by

activities financed

by the credits

Sustainable crop production

Promotion of cowpea and vegetables

Introduction of innovative techniques of production and new varieties

Consequent amelioration of quantity produced Increase in income Diversification of the sources of revenue

% increase in

revenues from

vegetables

% of total

revenue due to

fruit production

% of increase

of the

contribution of

crops to the

total revenue

% of revenue

due to cowpea

produced

% of different

crops in farmer

gross revenues

Promotion of tree/crop production system (Agro forestry)

Construction of 12 water points

Amelioration of total

revenues

Increase in

productivity

Crop protection, particularly cowpea, soya bean around lake Chad areas

Crop protection of 2,500 hectares of cowpea and soybean

Amelioration of cash crop production Increase of cash revenue Amelioration of living conditions Increase in number of

IDB PROJECT COMPLETION REPORT (PCR)

37

Diversification of crops produced per farmer: sweet potatoes, sugar cane, new vegetable crop... Ameliorated seeds distribution to farmers Adequate exploitation of rehabilitated irrigation perimeters and secure the maize production from floods

100 ha of extra product for farmers (sweet potatoes, sugar cane, banana, fruit production, etc.)

crops cultivated number of new

crop

introduced

increase in

quantity of

maize

% increased of

rice produced.

% of increase

in total revenue

per farmer.

OVERALLL SUSTAINABLE PRODUCTION

At least 33% of the populations of the intervention zone are satisfied with the consumption needs due to the project's action

Amelioration of living conditions Satisfaction of consumption needs Amelioration of food security Contribution to poverty alleviation

- % of population satisfying their consumption needs - % of population saving part of their revenue after satisfying the consumption needs - Total gross margin created all over the project area

Sustainable Livestock and Fishing Production

Support and capacity building in insensitive cattle production

60 producers

trained directly

concerned

600 indirect

beneficiaries

Increase of cattle

meat production in

quantity and quality.

Revenue of

populations is

ameliorated.

Increase of small

ruminant meat

production in

quantity and quality.

Revenue of

populations is

ameliorated.

Quantity of

cattle and small

ruminants

produced

Amount of

revenue

increases from

animal

production

(around CFA

450 million)

Support and building capacity of animal holders in small ruminant production

60 producers

trained directly

concerned

600 indirect

beneficiaries

Animal Heath amelioration

80 000 Small

ruminants are

protected from

diseases

8000 direct

beneficiaries

Reduction of 30% of the rate of mortality of small ruminants Increase in revenue from livestock production

% of the small

ruminant

mortally in the

area

% of revenue

increase due to

health

amelioration

IDB PROJECT COMPLETION REPORT (PCR)

38

Acquisition of control materials (canoes) for sustainable fishing Support of aquaculture in Project area

05 Canoes acquired

and distributed.

5,000 fisher men

controlled 60,000

Fingerling of catfish

distributed;

10,000 fingerlings of

carp distributed;

160 bags of feed

distributed;

12 fish farmers

trained

2 tons of fish

produced;

240 beneficiaries

Increase of fish

production in

quantity and quality.

Sources of

revenues are

diversified.

Total revenue of fish

producers is

increased.

increase in

availability of fish in

the project area

Increase of protein

quantity consumed.

% of the fish

produced vs.

fish captured

from rivers and

lake in three or

four coming

years.

Number of

patrols

organized

% of increased

in protein

consumption

increased of

fish in rivers

and lake Chad

% of increase in

number of

chickens

Amount of

revenue from

chicken selling

(ongoing).

Quantification of

protein

consumed per

person/year

(ongoing).

Support of chicken production at the village level

160 males

distributed.

160 bags of aliments

distributed to

farmers.

1,600 beneficiaries

Strengthen for conservation and transformation techniques for fish producers

50 producers

trained.

500 beneficiaries.

Increase of fish

production in

quantity and quality.

Sources of

revenues are

diversified.

Total revenue of

producers is

increased.

Increase of protein

quantity consumed.

Quantity of fish

transformed.

% of fisheries

revenue due to

transformation

techniques.

Building capacity and support on forage production

- 60 producers trained -500 beneficiaries

Increase of meat production in quality and quantity

The quantity of

meat produced

% of revenue due

to milk

production

Increase of cattle

production due

to forage

Introduction

(ongoing).

Capacity building In forage conservation

- 60 cattle producers trained -300 kg of brachiaria cultivated - 600 beneficiaries

Increase of meat and milk production in quality and quantity

IDB PROJECT COMPLETION REPORT (PCR)

39

Project Management Unit

Recruitment of Coordinator

First Coordinator recruitment at the beginning a one was be recruited because of mismanagement of the first. First Coordinator recruited for three years and 4 moths

Better coordination of the project Strong capacity of negotiation and management of finance and personnel Achievement of objectives and output in timescale Respect of rules and regulations Respect of loan agreement and IDB procedures Better representation of Project Good appreciation by the executing agency and the Governor Good quality of document presented to partners

Experience and

capacities

level of objectives

achieved at time

scale

% of documents

accepted by CAA,

COPIL, MINEPAT

and IDB:

Total amount of

Counterpart fund

mobilized

efficiency of

expenditures

Recruitment of staff

All other staff members were in place before the implementation of project but adjustment was done in 2013 to Bette perform the expertise (including the coordinator)

Strong quality of PMU staff Better coordination of activities Construction or rehabilitation of infrastructure with Better quality Rational use of finances Achievement of objectives and relevant outputs and outcomes

Number of

qualified staff

technical staff

% of actions

towards thud

producers

Number of visit on

feed

number of reports

prepared

quality of

infrastructure and

documents

number of

technical study

reports

numbers of

producers

identified during

implementation

IDB PROJECT COMPLETION REPORT (PCR)

40

Acquisition of field and office materials

4 Vehicles and 3 motorbikes Office material (PC, copiers, printers, etc.)

Work is facilitated in field Working conditions of the staff members are ameliorated

Number vehicles

and motorbikes

Quantity and type

of office

equipment

available

relevance of

equipment

according to

tasks

respect of

timescale for

different tasks

Procurement commission A special procurement

commission is created for the project Meetings are organized regularly All documents are examined by the commission (document of tender, contract, etc.)

Procurement procedures within the timescale Transparency is assured by the presence of an independent observer and the presence of the representative of the Ministry of Publics contrast

Number of

sessions of the

commission

Number of

reports available

number of

contracts signed

% of complained

by candidates

Préparions payement

Documents are prepared according to the procedures All the payments, direct or local, are sent in timescale to CAA Feedback are regularly solicited to CAA or the Bank

All the local payment is made by CAA Direct payment are executed Clearances for OFID payments are prepared and sent to OFID by IDB

Number of

payments at the

level of CAA.

Number of

payments made

directly.

Number of files

returned to the

project for lack

of some

documents

% of total

disbursements

Consultance Services

Supervision, monitoring and control of the contractors’ work Technical studies Preparation of documents for tender

All the needed studies are available at time Documents for tender are available All the infrastructures are controlled in a best way for necessary technical quality

Best quality of infrastructures constructed Respect of timescale for contracts

Number of

technical studies

done

number of

documents for

tender prepared

% of infrastructure

of quality;

% of not finalized

infrastructures

number of

IDB PROJECT COMPLETION REPORT (PCR)

41

contracts

resolution

Audit service

Auditing of procedures and expenditures

Accountability of the Project is audited

All Project accountability is done according to the Agreement and the rules and regulations of Cameroon

Number of audit

reports

Number of certified

financial reports

Number of

certification for

% of bills rejected

MAJOR CHANGES EXPERIENCED DURING IMPLEMENTATION:

1. CIVIL WORK

The main changes are first of all in the number of infrastructures programmed and executed. The executed numbers are more than planned (rehabilitation of irrigated perimeters, sluice dams, livestock markets, water points). On the other hand, the construction of offices and buying cars for civil servants had been considered as the responsibilities of the government through the traditional state budget, all those offices are build by the Government nowadays. In total the major changes are positive and are in interest of rural people (producers) for whom action and activities have been oriented. Last, the rural electrification was introduced to ameliorate the living conditions of rural populations. In the project area there is no electrified village or town except Kousseri.

2. SUPPORT ON COMMUNITY DEVELOPMENT

It is very important for Projects to ensure the sustainability of the infrastructures implemented by organizing producer to take care of them. In this perspective for all the infrastructures, management committees are in place. It is the same for common use resource.

3. SUSTAINABLE CROP, FISH AND LIVESTOCK PRODUCTION

Respect of cultural calendar (timescale).

Building of sluice dams permits water control and allows crops to complete the vegetative cycle

(maize).

Introduction of principles of depreciation process for infrastructures in producer's capacity

building.

Training of produces remained the key factor for sustainability of projects' actions.

Implementation of project activities was well conducted despite some difficulties.

Inaccessibility of markets because of the lack of roads in the raining season is the most important

constraint in the area at this moment.

The second phase of the project has to tackle this issue.

4. BIODIVERSITY CONSERVATION ACTION THROUGH WAZA AND KALAMALOUÉ NATIONAL PARKS

No major changes are observed and the actions implemented are: Determination of the new limits for Kalamaloue national park.

Elaboration of a map indicating the level of degradation of natural resource through GIS process.

Identification of all the surrounding villages and people for the real implication in natural resource

protection within the park.

Organization of information campaigns for the biodiversity conservation.

Organization of seminars for Capacity building for the staff of the park ;

Ecological monitoring System and inventory's techniques are made available.

Identification of main actions for the conservation of biodiversity within the Waza National Park.

IDB PROJECT COMPLETION REPORT (PCR)

42

5. PMU

Member's staff totally aware with rules, regulations and procedures.

Creation of core experts according to the Loan Agreement procedures and Cameroonian Rules and

Regulations.

Development of working capacity towards achievement of the Project objectives, outputs and

outcomes

Develop a capacity to be closer to the main actors or partners of the project to facilitate the

procedures and integrated the changing in Cameroonian institutional environment.

Finalization of log frame and all relevant documents according to the Agreement and needs of the

execution agency.

Development of Participatory Approach to closer with producers and to be able to introduce

innovation.

6. ADMINISTRATIVE AND TRADITIONAL AUTHORITIES

The implication of the local authorities (traditional, administrative, councilors) is a key element of project success, they are playing an important role on the village level for conflict regulations for example. Those actors have been integrated since 2013 as part of the major actors in the field, so they are fully mobilized for the success odd the Project.

2. EXTENT TO WHICH THE LOG FRAME ACHIEVED THE FOLLOWING Log Frame Dimensions Assissent Rating Score

(0-4)

Logiciel Present a logical causal chain for achieving the project development objective.

The log frame presents a logical causal, inspire of the fact that the Project faces many difficulties at the beginning.

3

Mesurable objectives and outcomes

The log frame has tried to express objectives and outcomes of each component in the way that is measurable and quantifiable even if some amelioration are done by the PMU.

3

Th rough Risks and key assumptions.

The log frame presents clearly the most of the risks and key assumptions the Project could face during the implementation. Nevertheless, due to the feasibility study of earlier 2000 some pertinent assumptions are taken into consideration like effect of climate changes on natural resources, the political context and the strategically position of Lake Chad Basin.

2.75

IDB PROJECT COMPLETION REPORT (PCR)

43

Hiérarchie of objectives

Key Performance Indicateurs

Data Collection Agence Critical Assomptions

Overall Goal To contribute to the improvement of food security, poverty reduction and living conditions in concerned area.

By 2015: The proportion of

people living in

poverty reduced by

35%.

The proportion of

undernourished

people in the project

areas reduced by

40%.

National accounts data generated through poverty monitoring database.

A counterpart funds made timely available.

Project Development Objectives: Productivity and subsequent production of crops, livestock and fishing sustainable improved as well as beneficiaries in project area participate in and benefit from the development of their communities.

By Project end: 50% of farmers

benefiting from the

project have

increased their

average real income

by 20%.

Production of crops,

livestock and fishing

increased at least by

30%.

Baseline survey reports, project monitoring reports.

Favorable climate conditions.

Output 1: Food production substantially increased.

By project end: At least 30% of farmers

sell 1/3 of their

production without

lack of food.

Project monitoring and progress reports. Project monitoring reports and studies

Beneficiaries adopt best practices and optimal project coordination.

Output 2: Livestock production substantially increased

By project end, sold quantity of meat: Bovines from 750 to

1700 tons.

Small ruminant from

135 to 345 tons.

" Access to animal health care and market improved.

Output 3: Fishing production substantially increased

By Project end, Quantity of fish sold

from 3500 to 5000

tons.

" Hydrologique conditions remained favorable.

IDB PROJECT COMPLETION REPORT (PCR)

44

Output 4: Sources of revenue of populations diversified

By Project end: At least 40% of farmers

have diversified their

farm activities.

Production of fruits

and vegetables in

project area increased

at least 20%.

" Global economic growth in the country remains favorable.

Output 5: Number of classrooms, health centres and water points increased

By Project end: Water supply

coverage increased.

Ratio pipils/

classrooms

increased.

By project end 20%

more patients treated

in the health centres

covered by the

project

" The government provides human and financial resource timely.

Output 6: Community Development

By project end: Volume of inputs

purchased and

marketed commodity

increased by 20% -

community saving

and credit facilities

functional and

amount of

agricultural lending

increased by 30%.

30 ha community

forestry developed

and a number of

wood supply

increased.

Agricultural input

supply system in the

project area

consolidated and

delivered on time.

Food marketing

information

operational and

farmers sell their

produce at the best

prices.

" The government remains committed to community development.

IDB PROJECT COMPLETION REPORT (PCR)

45

Output 5: Protection of river banks and threatened erosion area as well as measures for the biodiversity preservation through the natural park reserves of Waza and Kalamaloue.

Number ha reforested. Detailed design and tender documents for the rehabilitation of the reserves of Waza and Kalamaloure available and financial resources mobilized.

" Synergy between all stakeholders is ensured.

Activities i- Civil Work ii- Support for

community development.

iii- Sustainable crop, livestock and fish production.

iv- Project Management Unit.

v- Consultancy Services

vi- Audit Base cost Contingencies (10%) Total

9.69 0.72 4.93 1.62 1.07 0.18 18.21 1.81 20.00

D. PROJECT DESIGN AND READINESS FOR IMPLEMENTATION

1. The Chari-Logone Integrated Rural Development Project which the evaluation is based on the feasibility study conducted by the LCBC in early 2000 to engage a cross-border project between Chad and Cameroon, has been influenced in the action chosen for this specific project. In addition, the team of the evaluation has seemed to be not equilibrated in term of subsectors concerned for their constraints in the process of production. Most of action is oriented to animal production, fish harvesting control and the buildings of animal and fishing for civil servants. For these reasons, producers are not fully aware of what exactly the project has to do for them. At the launching of seminar, questions were raised from all the representatives of producers, village leaders, traditional rulers and the mayors to be fully informed for the project actions presented their main constraints for the area in term of rural integrated development. Indeed, the aspects of preparation of instruments for implementation have not fully integrated the populations as main actors by whom and for whom the relevance of outputs is oriented. As well the initial action undertaken by the project was different from those adopted in the assessment document and non-logged in a work plan duly validated by the relevant structures (Comité de pilotage, Minister of Economy and the Bank). It is sure that, the experts of the Bank have made important efforts to straighten the project in its starting phase with several supervision missions falling within the relevant conclusions and recommendations often neglected in their execution by lack of a strategic framework and an operational planning. It is same for the implementing agency that has led several missions to control and supervision with specific recommendations. In addition, the fitting to the evaluation has differentiated as much as possible, the implementation of actions and activities are organized though components "clearly defined" but the lack of vision and clear understanding by the PMU member's staff bad led to a blocking of the project for more than three (3) years. The government and the Bank in their engagement to contribute to the development of the region concerned (among the poorest country) where food insecurity and poverty particularly of young people and women are really present. In this context, measures have been taken both for the management

IDB PROJECT COMPLETION REPORT (PCR)

46

purpose of the project and the mobilization of the necessary resources. Thus, the PMU has been reorganized by change some key members staff (including the coordinator) It is important to note that in less than two years, the Government has mobilized more than CFA 1, 3 billion as counterpart finances. The project has thus taken a new flight path with the accompaniment of the different partners and especially the effective involvement of local populations engaged by the new team. The project has taken a normal direction to the implementation of the action programmed with a tightening of the real needs of the farmers in the area; whether they are farmers, animal producers, fishermen or actors of the different value chains. It is therefore from May 2013 that the different working tools have been developed (strategic framework, operational planning, annual Work Plan consistent with the objectives of the project). The change in the institutional framework of public procurement was be tackle by the coordinator, he had requested to the Minster in charge of Publics Contract to allow the project to go faster by creating a special commission and the Minister accepted, and this procedure was ended in November 05, 2013 with the designation of all the members and the appointment of the chair person. It is within those time constraints that the implementation of project had begun (in November 2013). This project was supposed to implement within 5 years but the national context imposed only 2 year and 6 months in total. Whatever, all the planned actions are conducted and infrastructures are constructed, well appreciated by actors.

2 DESIGN AND READINESS FOR IMPLEMENTATION FOR EACH DIMENSION OF PROJECT Project Design and Readiness for Implementation Dimensions

Assessment Rating Score (0-4)

Realism Project complexity was matched with country capacity and political commitment.

The Chari-Logone Project as well in its fitting that in its implementation addressed the main issues of the rural sector to allow a reduction of poverty and the creation of jobs. These essential guidelines of public authorities are reflected in the strategic documents (DSCE, Vision 2035, strategy the rural sector development, the Government Priority Investment Program and the Three Years Emergency Plan).

3.5

Risk Assessment and Mitigation

Project design included adequate risk analysis.

In the fitting of the project, part of the risks has been taken into account. However, the internal procedures of the Bank have not been considered as risk. The important issue is the role of administrator of OFID funds with the clearances system. When the clearances are not delivered at time it is a bug risk in term of respecting delays. That is one of the major problems projects facing in this crucial period of closing process; that is why the mitigation measures become difficult to identify and apply. The natural resource scarcity mainly the fish was be mitigated by the introduction of fish farming. In the other hand the resilience of lake Chad basin was be considered by reinforcing actions and activities on producers around this area with innovated production techniques to permit them to integrate the change in climate and modification of the production timescale (new crops or varieties are introduced).

3

Compliance with agreed procurement procedures

Project procurement procedures were based on those indicated on Loan agreement and the new rules and regulations in publics contracts introduced later.

All the procedures laid down in the Loan Agreement including the sections 7.02 and 7.03 of Article VII have been respected. At the national level, the procedures for contracting and payments of invoices are in conformity with those of the project. But the procedures are very long for a project with tied period and particularly for Chari-Logone project

3.5

Use of Country Systems

Project financial management, monitoring and/or other systems were based on those

All action related to the system of management of a project under co-financing system are in conformity with the regulations. The special commission created is under the supervision of the Ministry in charge of

3

IDB PROJECT COMPLETION REPORT (PCR)

47

already in use by government and/or other partners.

Publics contracts and the monitoring was in permanent basis.

For the following dimensions, provide separate rating scores for performance of Bank, Beneficiary, Executing agency, PMU.

Rating Score (0-4)

Bank Beneficiary Executing Agency

PMU

Clarity Responsibilities for project implementation were clearly defined.

The responsibility of the project implementation has a very long delay due to the mismanagement at the beginning, the financial aspects are completely changed and the management of PMU is not as indicated in the implementation documents

3.5 3 2.5 3

Implementation Readiness

Necessary implementation documents/arrangements were ready at appraisal.

PIU/consultants

Procurement

Local Financing

At the beginning the consultants are not recruited at time, the first part of the local finance was in place and all the procurement systems are ready. Unfortunately the PMU was not aware with the professionalism at this time. It is new PMU staff that engaged all the procedures to be able to achieve the project objectives with relevant outcomes and pertinent impacts

3 3 3 2

Monitoring Readiness

Monitoring indicators and monitoring plan were agreed upon before project launch.

The monitoring system with measurable indicators was clearly defined in 2013, with the new PMU staff. At the beginning there is any such a document.

3 3 2.75 2

Baseline Data Baseline data were available or were collected during project design.

The baseline data were collected during implementation period, also by new PMU staff (in 2013 for 2012 data). The document is the reference one in the area and use by all the actors

2.5 3 2.5 2

IDB PROJECT COMPLETION REPORT (PCR)

48

E. PROJECT IMPLEMENTATION 1. Major characteristics of project implementation

Based on above mentioned elements, the Chari-Logone Rural integrated Development Project is one of the flagship projects of the government in the Far North Region. The outputs and outcomes of the project are beyond than expected. The fitting of the project in its costs and its programming are substantial in their entirety. However, at appraisal most of the costs were not clearly defined according the actions to be conducted, probably by lack of repository of costs of some infrastructures at the feasibility period (around 1999). The planned actions were not able be respected, because among others, of the delay in producing basic documents, some mismanagement problems by the first PMU staff, fair definition of responsibilities of different actors at beginning, fair disbursements of funds. Then the delay of the initial the implementation period was so important (after 52 months the level of physical realization is around 3.8% for financial disbursement of 4.5%). So the implementation period as planned at the appraisal is totally out of the main expectations. Nevertheless, most of the actors and porters were not totally aware of this crucial problem of the delay of beginning that to be taking in to consideration at the closing time of the project. All the efforts and work done were mostly in two years and the outcomes were well appreciated by the main actor in the field (even though the infrastructures and all the planned actions are undertook in less than 24 months instead of 60 months). However, the Bank which is at the same time administrator of the OFID funds was fairly managed this aspect and has caused great delays in the payments the contractors. It should be noted that up to the end of December, nearly 60% of the OFID funds are not disbursed for lack of Clearances from IDB. But the last measures took will give expected results by clearing all the pending payments and OFID could be able to close the first phase of the project and can be engage don the second phase. Have not done the necessary work and either at the level of the services of the debt in Cameroon or at the level of the OFID, the decisions have to taking quickly. All the funds, for different partners, are mobilized in these few months and due to numbers of payments and the tied period, the total amount was not paid completely probably the project has be closed without paying part of the contractors. This issue has been presented to the Government for a clear closure of the Project. Part of the payments was due to actions conducted at the beginning but justifications were not clear even if the woks were done by enterprises At this closing period, the major changes, as indicated above, cover the adjustments within components to take into account the real needs of the populations on production with the climate change consequences which are the main challenges at the moment. In doing so, the actions of restoration of degraded lands have been strengthened, the introduction of varieties adapted to the water conditions has been committed, the diversification of sources of income has been oriented on the market gardening and the vegetables in the areas closed to the consumers particularly in the urban surroundings areas and in the vicinity of Lake Chad. The access to markets is also has to be taken as one of the important constraints in the area. Lastly, with the new challenge of unemployment, the issue of youth and vulnerable people has to be considered.

Performance of Partners Assessment Rating Score (0-4)

Performance of Beneficiaries This partner have been fully implicated and his implication was one of the important keys of the project success

3.5

Performance of Contractors Part of the contractors which are professionals had done a good job without been paid for their services which cost more than CFA 2 billion from OFID and with some outstanding with IDB.

3

Performance of representatives of main ministries concerned (agriculture, husbandry and fishing, forestry and wildlife, public work, environment, publics contracts)

All the action oriented to the innovations and towards producers is made mainly by those representatives through protocols signed with the project. Some of them are fair in the experience and even trained by the project to do the job they are supposed to do on the field. The project was also an opportunity for them for building their capacities on some relevant.

3

Performance of Credit Du Sahel

The management of the loan line of the non-relevant action of the project. The partner has received the all amount of this line about CFA 1 billion and it supposing that the money is used for any purpose according the their internal agenda. The Convention signed has been used for the reinforcement capacity of the structure.

1.75

IDB PROJECT COMPLETION REPORT (PCR)

49

2. Harmonization.

After the appraisal there is pertinent harmonization of tools and instruments at the level of the implementation of Project. But in the process of appraisal some harmonization is initiated by structures working on field specially the PNVRA but this organization was absent on the field and its approach was not adequate with the needs of producers.

3. For each dimension of project implementation, extent to which the project achieved

Project Implementation Dimensions

Assessment Rating Score (0-4)

Cost Variation

Extent of Adherence to original cost estimate.

The cost of the implementation of infrastructures was totally within the esteemed one (for some of them the cost was even overestimated). Furthermore, there was changing in dollar rate. In total, the cost of the project is fully favourable for the implementation

3.75

Time Schedule

Extent of Adherence to original closing date.

The original closing date is not taken into consideration the important setting documents of the loan in the Cameroonian regulation and the delay of more than 3 years due to management problems at the beginning (these kinds of problems have to be tackled quickly by the tied monitoring). Furthermore, the project was be implemented within 2 years with relevant outcomes.

3

Bank performance

Bank complied with Environmental Safeguards.

By the Bank: measures have been taken to be sure than all aspects are considered during the implementation stage

3.2

By the Beneficiary: the sensitation process and training were the tools used to assure this issue

2.75

Bank complied with Project Covenants.

By the Bank: This project is very particular because many changes are made in both size (Cameroonian part and the Bank) Whatever, the planned objectives were fully achieved

3

By the Beneficiary: At the appraisal, the role of main beneficiary (the producers) is not clearly defined. So sustainability of infrastructures and actions is based on the implication of those actors

2.5

Bank provided with adequate and quality supervision in the form of skills mix and practicality of

By the Bank: Due to the changes mentioned above, the supervision missions were nonsufficient are indicated in the project document. But with the actual project officer the quality of the supervision and practicality of solutions

3.5

IDB PROJECT COMPLETION REPORT (PCR)

50

solutions (e.g. the number of supervision missions/reports, composition of missions; missions’ recommendations and their uptake

proposed are relevant, that is why the implementation was be accomplished within only two years.

By the Beneficiary: At the beginning the contact with the beneficiaries was very fair and their implication to the project implementation completely absent. For the last two years, the beneficiary became the main actors of the success. They are totally implicated at the all level of the implementation process.

3

Bank provided quality management oversight; feedback to the beneficiary.

By the Bank: The management provided oversight was not well organized, probably because the number of project managed by one project officer within the bank. The system has to change as projects were increasing in number. The Feedback was also fair for more long time. The disbursements problems were those of the core ones for the project implementation. Without the clear feedback of what happens up there, it is difficult to proposed a adequate solution

3

By the Beneficiary: The beneficiaries were not totally aware of their role within the project; the sensitization was not well conducted at the beginning of the Project. Nowadays, they are coming to the project to inform the coordinator about the management of loan line with Crédit du Sahel, the sustainable management of infrastructures constructed and very other issues. In the future those beneficiaries will be the core of the success of the all kind of projects in the are

3.5

Beneficiary Performance

Beneficiary complied with Environmental Safeguards.

The beneficiary has to part of the project at appraisal stage but for Chari Logone, it is at the two remaining years of the project that actions have been taken. Beneficiary is now aware with the safeguards environment and the solutions for it

2.75

Beneficiary complied with Project Covenants.

Since 2013, all the project actions were undertaken with the beneficiary and their contribution is well appreciated

3

IDB PROJECT COMPLETION REPORT (PCR)

51

and relevant for outcomes

Beneficiary was responsive to Bank supervision findings and recommendations.

Beneficiary was not totally aware of the role within the Bank activities even for the project implementation.

2

Beneficiary collected and used monitoring information for decision making.

The monitoring system in place at this moment permits beneficiary to collect information and take relevant decision. That is the impact of the building capacity organized by the project.

3

Beneficiary ensured that key implementation systems (procurement, FM) were in place in a timely manner

There is any action by beneficiary for these issues

2

Executing Agency Performance (if applicable)

Executing Agency complied with Environmental Safeguards.

Since the beginning of the project executing agency was totally aware with the issue and decisions have been taken for it

3

Executing Agency complied with Project Covenants.

Executing agency was totally complied with project convenient and all the problems submitted have been solved

3

Executing Agency was responsive to Bank supervision findings and recommendations.

The bank recommendations are always considered and decisions are took to achievements them

2.5

Executing Agency collected and used monitoring information for decision making.

The monitoring system by the executing agency is relevant

3

PMU was adequately staffed to handle the

Fair at the beginning 2

IDB PROJECT COMPLETION REPORT (PCR)

52

PMU Performance (if applicable)

task

PMU was regular in progress reporting

The last two years were fully used to be sure that all the needed reports are available and at time scale

3.5

PMU was responsive to Bank supervision findings and recommendations.

All the bank findings and recommendations were achieved by the project

3.5

PMU used monitoring information for decision making.

The monitoring system organized for the 2 last years is a tool of decision making and the information gendered was used by other projects and services in the region

3.5

PMU complied with Environmental Safeguards

The relevant measures were took to complied with environmental safeguards for staff members, materials and all the infrastructures constructed

3.5

Consultants Performance

Adequacy of consultancy work

Indication of number of consultants recruited, and the adequacy of consultancy work. These issues are presented on the last colon with score ranking in brackets.

1. Main consultant for technical studies, elaboration of document for tender, control and supervision infrastructure work (2) Other important consultants 2. market survey (3.2) 3. baseline data collection (4) 4. diagnosis milk chain value (2.75) 5. market price information system (3) 6. geographical information system (4) 7. biodiversity WNP (4) 8. aquaculture support (3)

Contractors/Suppliers Performance

Quality and Timeliness of Contractors/Suppliers work

Assess quality and timeliness of work by each of the contractors/suppliers and rate them accordingly.

ETS ABAKAR DJIDDA Construction of

3 vaccination parks

2.75

ETS AL MAHANNA Construction of

2 classrooms

3.75

ETS ABBA SAID LIMANE Construction of

1 health centre

3.0

ETS BMB Rehabilitation

of Norma's

youth training centre

3.0

ETS BMB Construction of 1 open air

slaughter

2.0

ETS ADAM BOUKAR Construction of 2 classrooms

4

ETS ADAM BOUKAR Construction of 1 open air

slaughter

3.5

ETS DJAKDJING FOUISSALA

Construction of 2 open air

slaughters

3.75

ETS ANNADJIMA Construction of

1 health centre

2.7.5

ETS ANNADJIMA Construction of 1 vaccination

parks

3

ETS ANNADJIMA Construction 2 cattle markets

3

IDB PROJECT COMPLETION REPORT (PCR)

53

ETS ANNADJIMA Construction 2

sluice dams

2.75

ETS ANNADJIMA Construction

and equipment of Kousseri 's

modern

slaughter

2.75

ETS BRAHIM KALI Equipment for

4 health centres

3.75

ETS HASSANA HAROUNA Construction of

1 health centre

2.75

ETS CIHD Construction 2

boreholes for human use in

Waza area

4

ETS DJANDO Construction of 17 boreholes

for human use in other parts

of zone

3.5

SOCIETE SAT SARL Construction 2 boreholes for

livestock (solar energy pump)

and 01 for

human use

3.2

ETS ABADJI MAHAMAT Construction of

2 boreholes for human use

3

ETS BOUKAR ET FILS Construction of

4 boreholes for irrigation

purpose

3.5

ETS ABACHAROU DIGUIA Construction of

2 classrooms

4

STE IBCC SARL Construction 4 boreholes for

livestock (using solar

energy)

3.5

ETS MAINACOM Construction of 2 classrooms

2.5

ETS ALFA Construction of 1 health centre

4

ETS MAHAMAT DAHIYE Construction of

2 classrooms

2

ETS MAHAMAT DAHIYE Construction of

2 open air slaughters

3

ETS AL AZIZA Construction 1

vaccination park

3

ETS ABAKAR BLAL Construction of 2 classrooms

4

ETS AL GAOU Construction of

2 classrooms

3

ETS MAHI Construction of

2 classrooms

4

ETS MAHI Construction 1 storage room

2.75

ETS MAHI Supply of 102 motor pumps

of vegetable

production (irrigation)

4

ETS MADJI Construction 1 vaccination

park

3.5

ETS SALI HAMADOU Construction 7 vaccination

park

3.75

ETS OUMAROU

HAMADOU

Construction of

2 classrooms

2.75

IDB PROJECT COMPLETION REPORT (PCR)

54

Gpt SDR CAMEROUN /

SDR TCHAD

Rehabilitation

of 6 irrigated perimeters

3.25

AMNE GROUP SARL Supply and installation of

10 higher

capacity pump for irrigated

perimeters

3.5

SOCIETE AMANA SARL Construction of

dam and

hydraulic system in

Maga's dam downstream

area

3

SOCIETE AMANA SARL Construction of fish market

and a landing in Blangoua

4

ETS BARKA ABOUYA Construction of fish nursery

centre

4

ETS FATIHA Supply of small materials and

pesticides for producers

4

ETS MAHAMAT IMAR II Supply of 5

canoes with adequate

equipment for fishing control

3.5

ETS BICHARA OUDA

Construction of

supplementary structures for

PMU's offices

3

CAPHAVET

Supply of

medicines for

livestock vaccination

4

ERCA

Rural electrification

using solar

energy

3

ETS SAHEL GROUP

Rehabilitation

of closing structures of

the offices

2.5

ETS ZAILA ZALAZAHE Construction of 1 vaccination

park

4

ETS ALIFA MADJI

Construction of

1 storage room

for agricultural products

4

STE EMONDE SARL Supply of informatics

materials

CAMI TOYOTA Supply of 4 cars

4

TEXIS Supply of 3 motorcycles

3.5

INTEK

Supply of

information technology

materials at the beginning

of project

3

ETS BRAINSTORE Construction of 2 classerons

3

ETS NGOURA ET FILS Construction of 2 classerons

2.75

ETS VANDI TERI Construction of

2 classerons 4

IDB PROJECT COMPLETION REPORT (PCR)

55

ETS ABOUKAR HASSANA Construction of

2 classerons 4

ETS DARES

Supply

equipment for Ngouma youth

training

centres

3.75

Changes in contract's amounts

Difference in Original and Final Contract Amount The modification of amounts was only for the landing (related to the fish market): Original contract amount: CFA 128,161,004 Final contract amount: CFA 153,111,540

Reasons: The main reason is the appreciation of the distance between the Chari river (the lowest level) and the fish market. The first estimation done by the consultant (the permanent one) is 24 meters and the real distance was 32 meters, so the amount was be adjusted to have a landing site of 32 meters instead of 24 for an optimal use of the infrastructure at any moment of the year.

Score 3.5

F. ACHIEVEMENT OF PROJECT OUTPUTS AND (PRELIMINARY) OUTCOMES AND IMPACTS

ACHIEVEMENT OF OUTPUTS

Expected Outputs Actual Outputs Rating Score (0-4)

Share of Project Cost in %

Weighted Score

1. Civil works Rehabilitation and /construction of classroom

Civil works The civil works component was organized around three main domains of intervention

IDB PROJECT COMPLETION REPORT (PCR)

56

Construction of health centres (includes 1 car, 3 motorized canoe, 2 generator groups, essential drugs); 25 water points for drinking water, 16 boreholes with hand pumps and 09 wells covered with large diameter; 01 modern slaughter equipped; 07 slaughter areas with water sources drying and possibility of hides and skins; 20 Vaccination Parks; Rehabilitation of 3 pools and 01 artesian wells for livestock water supply; 01 fish market stalls with the wind; 01 landing (Blangoua); 01 cattle market; 10 community grain store; 01 water sluice dam for the protection at distributaries CHOUARA; Rehabilitation of perimeters ZIMADO (400 ha) and NDOU (170 ha), 570 ha Construction/rehabilitation of 21 offices for support services

Irrigated perimeters In this sector the actions and activities are oriented to infrastructures prior to the rehabilitation of some irrigated perimeters. The programmed actions are on the Zimado and Ndou perimeters for a total area of 570 ha. Due to financial possibilities, the actions completed are extended to four others (Logone birni, Goulfey, Goulfey Gana and Mara) for a total area of 668 ha. Traditional perimeters in Dole and Biamo (120ha) Finally a total of 1,300 ha are rehabilitated for rice and vegetables production instead of 570 ha as planned.

4

98%

3.92

Sluice dams in the Lake Chad area One dam in chouara was programmed, but two was constructed in Chouara and Ndjargoudja to secure 10,000 hectares of maize (blangoua)

3.75 95% 3.56

Socioeconomic infrastructures These infrastructures concerned are for amelioration purpose of agriculture and livestock production, others for the population welfare (water points, health centres, classrooms and slaughters.) For the civil works infrastructures, at the end of the project; 32 classrooms rehabilitated /constructed equipped with tables and latrines 04 health centres constructed/rehabilitated and equipped with water points, main necessaries materials (laboratory materials and beds) 55 boreholes for human use with pumps and 13 wells rehabilitated (a total of 68 water points) 01 modern slaughterhouse constructed in Kousseri 07 open air slaughters with water points constructed 13 Vaccination Parks 08 pastoral boreholes with a solar energy

3 75% 2.25

IDB PROJECT COMPLETION REPORT (PCR)

57

pump system for livestock water supply (with a permanent capacity of 6.000 l of water each and two jointed water points for human purpose using solar energy) 01 fish market in blangoua 01 a landing in Blangoua 02 cattle markets (Malié and Mazera) 02 big structures for products storage and all kind of commodities in production zones (Ngouma and Mazera) of 12.000 m3 capacity each 02 dam sluice protection in Chouara and Djargoudja (to secure about 12.000 hectares of maize production around Lake Chad) Around 1,300 ha for rice and vegetables production, in Ndou, Zimado, Logone Birni, Mara, Goulfey, Goulfey Gana and traditional perimeters of Dole and Biamo Construction of Zilim dam for the regulation of water in Maga'dam down stream 14 boreholes for irrigation of trees/crop integrated production systems 02 villages electrified through solar energy (Afade and Amchilga), a third one ongoing.

IDB PROJECT COMPLETION REPORT (PCR)

58

2. SUPPORT TO COMMUNITY

DEVELOPMENT

- Support of Basic economic

organizations (micro finance

institutions, cooperative

associations of producers,

women, youths, artisans etc.)

- Development and updating

of local plans of development

- Strengthening Of producer

organizations, their

professionalism and their

self-management capabilities

- Create And / or

strengthening of Village

Savings and Credit Self-

managed (CVECA)

- Financing Awareness

raising, information,

communication with

communities, leadership

development groups,

seminars and exchange of

experience

Community Development -Diagnosis and organization of community based associations for the sustainable management of rehabilitated perimeters and other common infrastructures (fish market, sluice dams, storage structures, vaccination parks, water points for livestock, common area for vegetable production, etc.) -More than 600 basic economic organizations are supported for an amount of CFA 880 millions to reinforce their production systems by acquisition of inputs mainly -200 producer organizations in the different production areas created and their capacities are built - Producers management committees were created for fishermen, livestock holders and agricultural -Strengthening Seed Growers capacities on production standards certified seed; - Diagnosis of the Federation of Farmers of Logone and Chari (FEPROLOC) and other existing umbrella; -Diagnosis and strengthening capacities for different production systems water management and fund raising; -Capacity Building of market gardeners, the use of organic manure and compost making; -Sensitize producer groups on projects elaboration and credit acquisition - the existing cooperatives are identified and their capacities are reinforced in the management skills -Changing modification of status of more than 400 small producer organizations to cooperative structure according OHADA regulations; -Creation and/ or strengthening of Village Savings and Credit Self-managed (CVECA) in six sub-divisions.

3 Fully adequate (100%)

3

Sustainable crop, livestock and fisheries production -Introduce Techniques to improve crop productivity, -Diversified Income generating activities (market gardening Marketing, Packaging and processing products - Access To microcredit by the establishment of a credit line

Sustainable crop, livestock production and fishing are also subdivided into subsections

Sustainable crop production Amelioration of techniques and introduction of improved crop varieties (Rice, sorghum, Soya bean, vegetables, Corn, cowpea and fruit plants); Sensitizing producer organizations and individuals for the establishment of loan line More than 2,000 ha of cowpea covered in term of crop protection; Introduction of improved techniques of transformation

3

100%

3

IDB PROJECT COMPLETION REPORT (PCR)

59

of vegetable to create an added value ; Establishment of price information system; Capacity build for organic fertilizing techniques Support of producers by distributing inputs of small materials The agriculture Subsector is a little bit under the expectations because of the lack of human resource capacity at the beginning of the project. The problem was solved for last two years and actions have been conducted in relevant way Livestock and Fishing Production Strengthening the capacities of farmers (cattle fattening and Ovine); Fight against epizooties Acquisition of 05 canoes for control of fishing harvesting activities; Support the development of village poultry: equipments and introduction of high potential chicken (250 males for a ratio of one male to 15 females); Support for fish farming (creation of the nursery centre, acquisition of foods, etc); Capacity building of fishermen on transformation/conservation techniques; Organizing and Structuring of fishermen; Support with the veterinary medicines Vaccination of more than 200,000 small ruminants Introduction of forage production possibilities (Stylosanthes and Bracharia) innovative techniques for rearing cattle and production of milk

As the results of the actions, populations ensure their food security and sell the surplus of fish, poultry, beef, sheep and goats, increase in income, reduction in mortality of small ruminant's cattle and poultry, development of fish farming, increase in pasture for cattle (Bracharia and Stylosanthes).

3.2

85%

2.72

IDB PROJECT COMPLETION REPORT (PCR)

60

NATURAL RESOURCE MANAGEMENT Concerted -Delimitation growing areas, paths and community forests: -Management Of concerted cross-border transhumance (vaccination and determination of transhumance animals, spatial occupation, date of departure and return) -Realization of forest and fruit tree nurseries -Setting Up defence mechanisms and land restoration (DRS) such as erosion control bounds filter -Actions accomplished during the implementation of the project concerned the following points

Natural resource management has three main subsections

DEFENSE MECHANISMS AND LAND RESTORATION - Information and sensitization of local actors on the issues; - Identification of different area concerned; - Inventory by identifying forest area; - Physical demarcation of zones; - Organization of local monitoring committee - Elaboration and execution of simplified management plans - Distribution of more than 40,000 forest's plants - Organization of plantation campaigns in schools and public spaces - Training and equipment for tree nursery producers (19) PLANNING OF AGROPASTORAL COMMON USE TERRITORIES - Explanation of the process of main actors - Elaboration of main diagnoses - Organization of local actors (development of community organizations) - Identification and organization of different areas; Domestic animal corridors-Access road for Pasture-Access road to water points-Crop production area-Natural and planted Forest area-Pastoralist's camps.

- Determination of crop production and other activities calendar

- Identification main actors and their strategies; - Identification of different type of conflicts; - Determination of rule and regulations for tackling conflicts; BIODIVERSITY CONSERVATION ACTIONS THROUGH WAZA AND KALAMALOUÉ NATIONAL PARKS - Determination of the new limits of Kalamaloue national park - Generation of a Kalamaoule map with the level of degradation of natural resource through GIS process - Identification of all the surrounding villages and people - Organization of information campaigns for the biodiversity conservation around Kalamaloué National park - Organization of seminars for Capacity building of management staff of the park - Organisation of Ecological monitoring System and inventory's techniques-Initiation - development of Geographical Information System for monitoring purpose -Identification of the main actions for the conservation of biodiversity within the Waza National Park

3.5 3.75 4

95% Mostly counterpart (85%) 95%

3.3 3.2 3.8

IDB PROJECT COMPLETION REPORT (PCR)

61

Overall Outputs Score 3.5 94.13 % 3.3

(II). Additional Outputs Due to the main constraints on the field, some outputs are not captured in log frame. Those outcomes concerned the aquaculture that with high level added value, the amelioration of living conditions trough the rural electrification using solar energy. The production of forage is another innovation highly appreciated by farmers. The actions on vegetables are the main source of revenue for the producers. Support on seeds and small materials produced important effects on production and productivity.

ACHIEVEMENT OF OUTCOMES

Expected Outcomes Actual Outcomes Rating Score (0-4)

1. Food production substantially increased.

The population's cereal needs of the project intervention area are estimated at 118,000 tons per year, according to the FAO norms. From 590 000 inhabitants and Logone and Chari Division, more than 170,000 people are not satisfying their cereals consumption needs. Indeed the gap or deficit in cereal is about 34,000 tons per year. The project's actions focused on the increase of the sustainable crop production allow an extra producing of 54,444 for the last two years that means an annual supplementary production of 27,222 tons per year. So the remaining gap is less than 7,000 tons per year and the impacts are yet increasing. In the other hand, the cash crop generated total revenue of CFA 4 billion which can partly be used to realize food self-sufficiency.

3.75

2. Livestock production substantially increased

For the livestock and fishing productions, the project implementation created a total cash revenue of CFA 5, 3 billion (Cattle meat; Milk production; Small ruminant and poultry). In the other hand the increase in their income enables them to satisfy all their basic needs. The actions of the project are succeeded to reduce small ruminant, cattle and poultry mortality in a sustainable way. Some innovative techniques of forage production were introduced to ameliorate the availability of pasture in the area (Bracharia and Stylosanthes), which had a positive effect in animal production have to be reinforced.

3.5

3. Fishing production substantially increased

The fish production is mainly ameliorated trough the introduction of aquaculture, knowing that the resource in rivers and Lake Chad are strongly diminishing due to the irrational management by the civil servants and fishermen. The project had created a nursery centre for this purpose. The direct revenue from the aquaculture conducted by 12 producers is about CFA 35,000,000 just for a first experience. The demands and people interested by the actions were around 900 groups and individuals. The way to sustainable increase of fish production has to combine aquaculture and better management of natural resources in the rivers and Lake. The control and the application of rules and regulations are the main problems. The Ministry in charge of fishing has to develop strategies to increase the number of patrols and change the mentality of the civil servant in charge of control, their capacity was reinforced for this perspective.

2.5

4. Number of classrooms, health centre and water points increased.

The number of classrooms has little bit increased; the actions of the project in this sub-sector are not very substantial, only 32 classrooms are constructed/rehabilitated within the amount allocated for the action. But the remaining needs or the project area is low, it is around 75 classrooms. A special action is ongoing for the construction of the classrooms by the Government so the gap will be covered at the end. The important needs are concentrated on the construction and equipments of health centres. The four (04) health centres

3

IDB PROJECT COMPLETION REPORT (PCR)

62

constructed and equipped by the project are increasing significantly the carrying capacity of the sanitary structures. Most of the equipments are highly appreciated by the actors because it seems to be the best ones in the project area. For the Water points, the number was significant (62) and increases the potential of the area. Nevertheless, the needs, according to the norms are still important, it is 1,637 water points.

5. Protection of river banks and erosion threatened area as well as measures for the biodiversity preservation through the natural park reserves of Waza and Kalamaloue.

This component contributes to reforestation by planting trees in the area of the Project. The Kalamaloue National Park has delimited by the Project, nameplates have put in place to explain the different information of this protected area. Studies have been conducted in Waza National Park to clarify the actions that can be done there to reinforce the protection of the wildlife in this National Park. The river band protection was taken over by the Government for CFA 1 billion for the first phase, action will be continuing

3.5

Overall Outcomes Score 3.3

PRELIMINARY IMPACTS

EXPECTED IMPACTS ACTUAL IMPACTS DURING IMPLEMENTATION (OR INDICATIONS OF LIKELY IMPACTS)

RATING SCORE (0-4)

1. FOOD PRODUCTION

- At least 30% of farmers sell 1/3 of their production without lack of food.

Based on the data recorded in the field, more than 1/3 population of the project area sells at least 170 kg of cereals without lacking food and the other crops are the source of cash revenue. Cowpea procures the most important part of the total revenue (around CFA 3.7 billion all over the project area and for one year)

3.75

Livestock Production - Sold quantity of meat: - Bovines from 750 to 1700

tons. - Small ruminant from 135 to

345 tons.

Total quantity of cattle meat sold per year for the two last years of the implementation of the project is about 82 tons essentially due to the decrease in demand. The past two years, cattle are not sold to Nigeria (the most important market). And actions on cattle take more time to have a relevant impact. But the small ruminants were increased in number and the quantity of meat sold is estimated at 1,232 tons. It’s easy for producers to sell one goat or sheep. Therefore the revenue generated by the sold of meat as an all is about CFA 954 million.

3.20

Fish production - Quantity of fish sold from 3500 to 5000 tons.

The scarcity of fish in the rivers and lake reduce the quantity captured and sold in the project area. Due to this situation, actions on aquaculture were the best opportunity to solve scarcity problem. The quantity sold at this early stage is around 90 tons of beat quality fish for an amount of CFA 35 million for 12 individuals, the revenue per individual is about CFA 2,900,000 just for 4-5 months. This amount is relevant revenue for rural area.

3.25

2. DIVERSIFICATION OF SOURCES OF REVENUE - At least 40% of farmers

have diversified their farm activities

- Production of fruits and vegetables in project area increased at least 20%.

More than 50% of the farmers diversify their activities trough new crops, integration of agriculture and animal production. The vegetables are the main diversification possibilities for farmers. For the last two years, they sold for about CFA 2,73 billion

3.75

3. WATER POINTS, HEALTH CENTERS, CLASSROOM - Water supply coverage

increased.

The actions of the project increase the total water supply even if the remaining needs are higher (about 1,600) The four (04) centres constructed and equipped by the project have increased the number of patients treated up

3.5

IDB PROJECT COMPLETION REPORT (PCR)

63

- Ratio pupils/ classrooms increased

- By project end 20% more patients treated in the health centres covered by the project

to 120,000 people that is more than 40% of the total number of patients.

Community development - Volume of inputs purchased

and marketed commodity increased by 20%

- Community saving and credit facilities functional and amount of agricultural lending increased by 30%.

- 30ha community forestry developed and number ha of wood supply.

- Agricultural input supply system in the project area consolidated and timely delivery.

- Food marketing information operational and farmers sell their produce at the best prices

Inputs purchased through the producer organizations are increased by more than 75%. Producers are well organized to buy inputs and sell their products in the markets; Trough the CVCA and loan line of the project, saving and credit systems are strongly developed throughout the project area the amount of the transactions is more than CFA 1 billion (about US$ 2 million). These transactions continuously developed. The Farmers are better organized and are managing all the rehabilitated perimeters (buying fertilizers, gasoil, using tractors, selling rice and even transforming their products).

3.5

4. Natural resource managements and biodiversity conservation Protection of river banks and erosion threatened area as well as measures for the biodiversity preservation through the natural park reserves of Waza and Kalamaloue.

As mentioned above, the protection of Logone and Chari rivers' band was taken over by the Government for about CFA 1 billion (as hard urgent first phase actions). In this case the actions of protection programmed by the project are oriented towards the sustainable natural resource management within and around the National Parks. A common used forest in Dougoumsilio, Makary sub-division, was supported by putting in place a local management committee; building capacity was initiated on inventory of flora and fauna. For the Kalamaloue national park, actions are oriented to identifying the new limits and developing a map of the park. All surroundings' villages are identified and populations informed on the illegal activities in the park. In Waza park, as mentioned in the appraisal document, all the actions for biodiversity conservation are identified and proposed in the second phase document.

3.5

The preliminary impacts based on the above mentioned elements and on direct revenue generated by the project actions and activities are very relevant and highly appreciated by the populations. The grow revenue estimated for the last three years of intensive works on the project activities is CFA 16,431,235,933 (around US$ 33 million), this revenue is provided by vegetables CFA 2,072,253,333; Soya bean CFA 3,700,000,000; Rice production CFA

OVERALL IMPACTS SCORE 3.5

IDB PROJECT COMPLETION REPORT (PCR)

64

1,887,200,000; maize around Lake Chad CFA 3,240,000,000; Sorghum CFA 200,000,000; Cattle meat CFA 34,000,000; Milk production CFA 4,342,782,600; Small ruminant meat CFA 920,000,000; Fish production CFA 35,000,000. There are some sources of revenue related to the main value added chains which can be estimated later. The user's actions based on the welfare of the populations and building capacities through several techniques are very relevant on management common infrastructures and poverty alleviation. With the implementation of this project, the target populations are received essentials kills and capacities to conduct production activities in the best way by creating more revenue. The standard of living in the area is significantly ameliorated and the populations are better organized to tackle important production constraints. To fully achieve the poverty alleviation process and amelioration of living conditions of youth and vulnerable people as a result of the recent situation in this part of the country, it is necessary to implement a second phase oriented to the main constraints

OVERALL FINANCIAL AND ECONOMIC PERFORMANCE

At Appraisal Actual Rating Score (0-4)

FIRR:

EIRR (ROCE: Return of Capital Employed): 60.9% 4

Overall Financial and Economic Score

5. Risks to sustained achievement of outcomes and impacts The main assumption or risks for sustainability are the level of implication of producers (some of them), the trans-boundary security problem which has an on price of products in rural markets (law level of demand), availability of running capital at the beginning of each production campaign raining season for most of the producer(Because of mismanagement of loan line and the revolving funds) and changing in production system going from raisin season production to irrigated ones (sociocultural problem) but the consequences of climate change have to tackle with water resource management in this area. The last important risk but not the least is the failure of engaging the second phase of the project.

IDB PROJECT COMPLETION REPORT (PCR)

65

G. SUSTAINABILITY

Indicator Assessment Rating Score (0-4)

1. Beneficiary commitment and capacity to maintain the project facilities.

The series of building capacity sessions organized for the populations and all the support for their production systems and organizations putted in place are the key elements for the beneficiaries to maintain the actions of the project in a sustainable way.

3.50

2. Technical sustainability.

The quality of infrastructures and the skills at the disposal of the populations are the best guarantee of sustainability for the technical aspect.

3.75

3. Financial/economic sustainability.

The innovative techniques of production and the diversification of activities in the project area are the main possibilities of financial and economic sustainability. Nevertheless the consolidation of the different actions by a second phase will definitely engage this particular zone in the financial and economic sustainability.

2.75

4. Institutional sustainability.

The implication of representatives of all the ministries concerned and the administrative/traditional authorities is the key of institutional sustainability.

3.00

5. Social Sustainability. The favourable environment for the actions of the project is in the favour of the social sustainability. Nevertheless the actual situation in the area can be a problem for some sub-sectors.

3.20

6. Environmental sustainability.

All technical studies of infrastructures/actions of the project are taking into consideration the environmental aspects. In all these actions, there are Environmental and Social Management Plan (ESMP) for the mitigation negative impacts or reinforce the positive impacts. So the environmental sustainability is assured by these skills. In the other hand, the specific actions were engaged in the biodiversity conservation.

3.50

IDB PROJECT COMPLETION REPORT (PCR)

66

H. LESSONS LEARNED AND RECOMMENDATIONS

1. LESSONS LEARNED

The feasibility study has to closely tied to the main constraints of production and be updated

At appraisal stage the target groups have to be fully implicated for a sustainability of actions.

The cost of the project realistic as possible (knowing that a provision of contingencies is

proposed).

The FIRR and the EIRR have to be known at the appraisal stage (the feasibility study is the best

stage to calculate them) in order to compare with those of the end of the project.

All the instruments and arrangements have to be in place before launching the project.

The financing plan and the disbursements have to be very clear for different actors involved in the

project implementation.

The PMU must have the possibility to manage most of the payments to avoid delays.

The role of local traditional and administrative authorities has to be clarified at the appraisal level.

The tackling of the real needs of populations will produce unexpected outputs, outcomes and

impacts (even a small part of the main constraints); the appraisal stage most deeply appreciates

the real constraints for the actions to be taken.

2. INNOVATIONS, REPLICATION, UP-SCALING

The organization of the baseline database collection was the key skill to appreciate the

contribution of the project at all. So even if the project is ongoing the availability of those data is

essential, so the baseline data were collected in 2013 for 2012 situation. Nevertheless, the data

are a good reference for any rural development actions to be taken in the area.

The most important strategy is to be closer to producers by using the participatory approach

(introduction of this approach gives important results and tackles the sustainability problem).

The Added value chain approach is the adequate possibility to work closely with all the actors

implicated in the revenue generating process for the rural populations. This approach can be

associated with others in the domain of rural development.

Availability of funds in level of the project at any time permit a continuous implementation of the

planned actions over the period, and the main tool is the monitoring of all project's accounts (in

the weekly base) to be sure that the financial aspects will not be part of the constraints. The

project's financial responsible have to be proactive to avoid some disagreements.

Proactively of the PMU is one of the important aspect in project implementation, the coordinator

must be very strong because of the challengers and changing in working environment

3. RECOMMENDATIONS

Summarize project related and general recommendations.Project Related Recommendations (i) For the Bank

1. The appraisal process will integrate all the main actors according to the subsectors take into

IDB PROJECT COMPLETION REPORT (PCR)

67

account 2. All the arrangements have to be ready before the implementation (launching of the project)

process to avoid the prolongation of periods; 3. Inform the executing agency and the PMU on the internal procedures and delays of demand

payments sent trough CAA; 4. Give a possibility to someone in CAA to be informed in a regular base for the disbursement level of

loan for monitoring purpose; 5. Be sure that the recommendations of the Cameroonian's to the Bank are implemented; 6. Indicate the appropriate way for reclamation from PMU or other actors; 7. Engage procedures to have a representative in Cameroon to facilitate the implementation of

projects and the impacts on the populations; 8. Be aware of the poor part of the country for the purpose of poverty alleviation; 9. In total the intervention of the Bank is highly appreciated in the project area because that is the

only project which has worked on different subsets in the rural area with important impacts on revenue procurement, food availability, poverty alleviation and building production capacities on a large scale.

(ii) For the Beneficiary

1. Be part of the main actors of project implementation, beginning the formulation stage up to the

end; 2. Being the target actor, the beneficiaries have to be present for the capacity building training

session; 3. Put in place a system for sustainability of the infrastructures and actions by using part of their

revenue every year, 4. Cooperatives created or reinforced are so many and diverse in the ongoing activities, there is

a need of reorganizing these cooperatives according to the 4-5 main added value chains and at subdivision level; the large scale structure representing all the 10 sub-divisions can be put in place at the divisional level. This structure can be the main representative of all the producers of the Logone and Chari Division;

5. Efficient use of skills related to bargaining power in the process of price negotiation; 6. The resolving funds of the loan line has o be managed for the interest of the producer of the

area, Government has the bigger responsibility to do that

(iii) For any Future Projects or programmes

1. Base the actions and activities on clearly expressed needs of producers; 2. Log framework has to be as completed as possible with all activities, outputs, outcomes, impacts,

indicators and good appreciation of risks and assumptions; 3. The problem of youth and vulnerable people has to be the core aspect to be tackled by adequate

means; 4. The best approach to develop rural area is the identification and tackling of the main constraints

of added value chains (from farm to the tale) and be aware of the revenue gained by the producers;

5. The Natural resource management, particularly the firewood and charcoal problem has to integrated into all projects and programs which have to be developed in this area;

6. The sustainability of actions partly depends on extend to which the local representatives as concerned;

7. The best approach is to sign protocols clarifying responsibilities all each party and some building capacity sessions are necessary for the success;

8. A well organized system of communication is the key success elements I. OVERALL ASSESSMENT.

CRITERIA SUB-CRITERIA/INDICATORS RATING SCORE (0-4)

RATING (HS/S/PS/ U/HU)

Relevance, Consistency, and

Project objectives were relevant to country's development priorities.

3.5 HS

Project objectives could be achieved with the project inputs 2.75 S

IDB PROJECT COMPLETION REPORT (PCR)

68

Achievability of Objectives

and in the expected timescale

Project objectives were consistent with the Banks corporate priorities.

3.5 HS

Overall Sub-score 3.25 HS

Use and Strength of Log frame

The log frame presented a logical causal chain for achieving the project development objectives but the log fame was not complied at the appraisal.

3.0 S

The log frame expressed objectives and outcomes in a way that was measurable and quantifiable.

3.2 HS

The log frame stated the risks and key assumptions but all of them

2.75 S

Overall Sub-score 2.98 S

Cost and Time Performance

Extent of Adherence to original cost estimate, some components are not well estimated, the important difficulties are not well been took into consideration

2.75 S

Extent of Adherence to original closing date. 2.75 S

Overall-Sub-score 2.75 S

Bank Performance

Design and Readiness

Project complexity was matched to country capacity and political commitment.

3.0 S

Project design included adequate risk analysis not all of them 3.5 HS

Project procurement procedures were based on those already agreed upon the Financing Agreement and with other Partners, if any, the changing in national institutional environment has negatively impacted the implementation of the project.

2.75 S

Project financial management, monitoring and/or other systems were based on those already in use by government and/or other partners.

3.5 HS

Responsibilities for project implementation were clearly defined at the appraisal but the implementation important changes are made

3.0 S

Necessary implementation documents (e.g. Specifications, design, procurement documents) were readies at appraisal not all of them.

3.0 S

Monitoring indicators and monitoring plan were agreed upon during the design.

2.5 S

Baseline data were available or were collected during the design, data were collected in 2013

2.5 S

Project Design and Readiness Sub-score 3.0 S

Supervision (Assessment by the Bank)

Bank complied with Environmental Safeguards 3.2 HS

Bank Complied with Project Covenants 3.5 HS

The bank provided quality supervision in the form of skills mix provided and practicality of solutions.

3.0 S

The bank provided quality management oversight. 3.0 S

PCR was delivered on a timely basis 3.0 S

Supervision Sub-Score 3.14 HS

Overall Bank Performance Score 3.1 HS

Beneficiary Performance

Design and Readiness

Responsibilities for project implementation were clearly defined.

2.75 S

Necessary implementation documents (e.g. Specification, design, procurement documents) is ready at appraisal.

3.0 S

Monitoring indicators and monitoring plan were agreed upon and baseline data are available or were being collected in 2013 for reference year of 2012.

2.75 S

Project Design and Readiness Score 2.83 S

Implementation Sub-Score 3.44 HS

IDB PROJECT COMPLETION REPORT (PCR)

69

Overall Beneficiary Performance Score 3.1 HS

Executing Agency Performance (if applicable)

Design and Readiness

Responsibilities for project implementation were clearly defined but not applied

3.5 HS

Necessary implementation documents (e.g. Specification, design, procurement documents) is ready at appraisal some documents were not available.

3.5 HS

Monitoring indicators and monitoring plan were agreed upon and baseline data are available or were being collected.

3.25 S

Project Design and Readiness Score 3.17 HS

Implementation

Beneficiary complied with Environmental Safeguards 2.5 HS

Beneficiary complied with Project Covenants 3.0 HS

The beneficiary was responsive to Bank supervision findings and recommendations.

3.5 HS

Beneficiary collected and used monitoring information for decision-making.

2.5 S

Implementation Sub-Score 2.9 HS

Overall Executing Agency Performance Score 3.0 HS

PMU Performance (if applicable)

Design and Readiness

Responsibilities for project implementation were clearly defined.

2.75 S

Necessary implementation documents (e.g. Specification, design, procurement documents) is ready at appraisal.

2.75 S

Monitoring indicators and monitoring plan were agreed upon and baseline data are available or were being collected.

2.5 S

Project Design and Readiness Score 2.7 S

Implementation

Beneficiary complied with Environmental Safeguards 3.5 HS

Beneficiary complied with Project Covenants 3.5 HS

The beneficiary was responsive to Bank supervision findings and recommendations.

3.5 HS

Beneficiary collected and used monitoring information for decision-making.

3.0 S

Implementation Sub-Score 3.4 HS

Overall PMU Performance Score 3.1 HS

Partners Performance

Performance of CAA is good, reaction at time 3.0 S

Performance of OFID (if applicable) a big problem for disbursements due to lack of clearances from IDB

3.0 S

The performance of the ministries concerned 2.75 S

Performance of Credit du Sahel (loan line) fair 2.5 S

Overall Partners Performance Score 2.8 S

Consultants Performance

Adequacy of consultancy work 2.75 S

Quality and timeliness of consultancy work 2.50 S

Overall Consultants Performance Score 2.63 S

Contractors/ Suppliers Performance

Quality and Timeliness of Contractors/Supplier's works 2.75 S

Difference between Original and Final Contract Amount 3.75 HS

Overall Contractors/suppliers Performance Score 3.25 HS

Outputs and Outcomes Performance

Achievement of outputs 4.0 HS

Achievement of outcomes 3.95 HS

Overall Output and Outcome Score 3.98 HS

Preliminary Impacts (or indications of)

Impacts on revenue and food availability 4 HS

Beneficiary commitment and capacity to maintain the project facilities.

3.75 HS

Technical sustainability. 3.75 HS

IDB PROJECT COMPLETION REPORT (PCR)

70

Sustainability Financial sustainability. 2.75 S

Institutional sustainability. 3.0 S

Social Sustainability. 3.0 S

Environmental sustainability. 3.5 HS

Overall Sustainability Score 3.21 HS

OVERALL PROJECT RATING 3.2 HS

IDB PROJECT COMPLETION REPORT (PCR)

71

J. PROCESSING Steps Comments and Signature Date

Project Officer

PCR Team Leader

Division Manager Clearance

Sector Department Director Approval

IDB PROJECT COMPLETION REPORT (PCR)

72

APPENDIX -1: MAP AND DETAILS OF VARIOUS ITEMS/PROJECT OUTPUTS

IDB PROJECT COMPLETION REPORT (PCR)

73

MAP OF THE PROJECT LOCATION

IDB PROJECT COMPLETION REPORT (PCR)

74

SOME OUTPUTS

IDB PROJECT COMPLETION REPORT (PCR)

75

Water for cattle

IDB PROJECT COMPLETION REPORT (PCR)

76

Photo 3 Heath Centre (zigaguei)

fish nursery

Tractons on Field

IDB PROJECT COMPLETION REPORT (PCR)

77

Some materials for producers after a training session on manure use

Afade village by night

IDB PROJECT COMPLETION REPORT (PCR)

78

Rehabilitated perimeter for rice production

IDB PROJECT COMPLETION REPORT (PCR)

79

ACTUAL ACHIEVEMENT AT PCR

Years component

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

Civil Works

Support to

Community

Development

Sustainable

Crop,

Livestock

and Fishing

Production

Project

Management

Unit

Consultancy

Services

Audit

IDB PROJECT COMPLETION REPORT (PCR)

80

DISBURSEMENTS AND SOURCES OF FUNDS

Sources of Funds Amount of disbursements (in local currency)

Observations

IDB 428 806 721 Total amount taking into consideration the two pending disbursements

164 859 821 Three demands arrived at the IDB offices since one year

422 500 000 Amount of two pending demands

OFID 2 607 589 367 Total amount taking into consideration the pending payments awaiting clearances of IDB

1 413 547 058

Pending payments already cleared and payments ongoing

Counterpart (Gvt) 1833 766 000

Total amount taking into consideration the expenditures of 2016

568000000 For 2016 (368 000 000 are already mobilized)

Amount of three sources

8 700162088

The project has been implemented using 87% of planned money with a substantial economy of more than CFA 1 billion (more than 95% of infrastructures and other activities are implemented, some activities related to animal heath, crop protection and fish production are ongoing be completed before June)

2 404 047 058 Awaited from three financing partners

IDB PROJECT COMPLETION REPORT (PCR)

81

LIST OF MISSIONS CARRIED OUT (WITH DATES, NUMBER OF PERSONS, COMPOSED OF MISSION, STAFF DAYS).

IDB/MINEPAT missions

Dates Composition of the Mission and number

of persons

Purpose of the mission

From May 17/2007 to June

6/2007

1. Br. Abakar Abdourassoul, Head

of project Division, Head of the

mission

2. Br. Abdelwahab Chérif, project

officer, member

3. Br. Moussa Touré, financial

analyst member

4. Dr Abouamé Salé, Ministry of

livestock and fish-ring

(Cameroonian), member

5. Mr Mahamat Abakar, Ministry of

Agriculture (Cameroon), member

Appraisal of the project

From August 10/200 to

August 12/2010

1. Mr. Tchounkoué Pierre Serge,

Director of regional, MINEPAT

(executing agency), head of

mission

2. Mr. Abicho Mahamat, Project

focal Point, member

3. Mr. Marouf Moussa, regional

delegate, member

Monitoring and evaluation

mission

From December 20/2010 to

December 23/2010

1. M. Tchoukoué Pierre Serge,

Director of regional planning,

MINEPAT, Head of mission,

2. A Representative of the

programme of investment,

member

3. A Representative of the COPIL

4. A Representative of the CAA

5. A Representative of the ARMP

6. The coordinator of PNDP

7. The Project focal points

MINEPAT

Capacity building of Project

members staff

On April 11/2011 1. Br. Salem Mohamed Sassi, Agric-

economist,

2. Br. Javed Khan,

3. M. Tantchou, staff member of

Islamic affairs division,

MINEPAT,

4. M. EOCK André Alain, staff

member of CAA

Supervision support and

infrastructures visit

From October 2/2012 to

October 5/2012

1. Br. Javed Khan, head of project

2. Br. Momodou Lamin Ceesay,

PIASR Team leader, member

3. Br. Seydou Kane, member,

Midterm evaluation and

supervision mission

From September 24/2014 to

September/2014

- Bar. Seydou Kane, project officer Supervision mission

IDB PROJECT COMPLETION REPORT (PCR)

82

LIST OF PROJECT'S REPORTS

N° Designation Period

Activities

1. Rapport d'activités de février à juillet 2010 2010

2. Rapport d'activités de janvier à décembre 2011 2011

3. Rapport financier 2011 2011

4. Rapport d'exécution du 1er janvier au 30 juin 2013 2013

5. Rapport annuel d'activités 2013 2014

6. Rapport d'exécution et niveau de mise en œuvre du PTBA 2013 au 31 mai 2014

2014

7. Rapport d'activités du 1er trimestre 2014 2014

8. Rapport d'activités du 1er semestre 2014 2014

9. Rapport 2ème trimestre 2014 2014

10. Rapport 2ème semestre 2014 2015

11. Rapport annuel d'activités 2014 2015

12. Rapport 1er trimestre 2015 2015

13. Rapport 1er semestre 2015 2015

14. Rapport d'activités de 1er janvier 2014 au 09 juin 2015 2015

15. PIASR 2011

16. PIASR 2012

17. PIASR 2014

B Passation des Marchés

18. 1er Rapport semestriel de la CSPM 2011

19. Rapport annuel 2012 2013

20. Rapport de l'Observateur indépendant 2013

21. 1er Rapport semestriel 2014 2014

22. Rapport d'étude des Marchés des activités agropastorales et halieutiques dans le LC

2015

23. Rapport sur la situation de référence de la zone du Projet 2014

C Suivi Crédit

24. Rapport de contrôle de la ligne de crédit FIDACO 2013

25. Rapport d'activités du Crédit du Sahel sur le financement BID-PDRI-CL

2014

26. Rapport mensuel de suivi des activités des Groupements bénéficiaires de crédit CERADEL

2015

27. Rapport final CERADEL 2015

28. Rapport d'activités sur le montage des dossiers de Crédit par ODCAM-RU

2015

29. Rapport de mission du Comité de Suivi et d'Evaluation de la Ligne Microcrédit

2015

IDB PROJECT COMPLETION REPORT (PCR)

83

30. Récapitulatif de l'utilisation des fonds BID par le Crédit du Sahel au 18 mars 2015

2015

D Renforcement des capacités/ Formation

31. Rapport de l'atelier sur l'Appui-accompagnement des groupements maraichers par ACDC

2012

32. Rapport de l'atelier de renforcement des capacités des Producteurs de Ndou

2014

33. Rapport de l'atelier de renforcement des capacités des Producteurs de Zimado

2014

34. Rapport de l'atelier de renforcement des capacités du Comité de Gestion du périmètre rizicole de Zimado

2015

35. Rapport de l'atelier de renforcement des capacités du Comité de Gestion des ouvrages en aval du Mayo Vrick

2015

36. Rapport de l'atelier de renforcement des capacités du Comité de Gestion du barrage de Ndjargoudja

2015

37. Rapport de l'atelier de renforcement des capacités du Comité de Gestion du barrage de Chouara

2014

38. Rapport de l'atelier de renforcement des capacités des Producteurs impliqués dans les agro systèmes sur les outils de gestion et plan de développement à Blangoua

2015

39. Rapport de l'atelier de renforcement des capacités des Producteurs impliqués dans les agro systèmes sur les outils de gestion et plan de développement à Logone Birni

2015

40. Rapport de l'atelier de renforcement des capacités des Producteurs impliqués dans les agro systèmes sur les itinéraires techniques et l'organisation du COGEST de Blangoua

2015

41. Rapport de l'atelier de renforcement des capacités des Producteurs impliqués dans les agro systèmes sur les itinéraires techniques et l'organisation du COGEST de Logone Birni

2015

42. Rapport de formation des promoteurs de l'agroforesterie sur les techniques de plantation et d'entretien d'arbres à Makary

2015

43. Femmes en entreprenariat et développement de Blangoua 2015

44. Comité de gestion du Barrage sur le Chouara à l'usage du fumure organique

2015

45. Formation des promoteurs de l'agroforesterie sur les techniques de plantation et d'entretien d'arbres à Kousseri

2015

46. Diagnostic organisationnel et appui à la structuration des producteurs de niébé de Blangoua

2015

47. Diagnostic organisationnel et appui à la structuration des producteurs de niébé de Hilé Alifa, Makary et Darak

2015

48. Formation des pépiniéristes BET GEOCOPETENCE 2013

49. Rapport de contrôle de qualité des semences dans le département du Logone et Chari

2015

50. Rapport de l'identification exhaustive des maraichers dans les différents bassins de production

2015

51. Rapport de renforcement de capacités des producteurs semenciers déclarés du Logone et Chari

2014

IDB PROJECT COMPLETION REPORT (PCR)

84

52. Rapport de l'atelier de renforcement de capacité en mutation du comité de gestion de Ndjargoudja en coopérative simplifiée

2014

53. Rapport de l'atelier de renforcement de capacité en mutation du comité de gestion de Zimado en coopérative simplifiée

2014

54. Rapport de l'atelier de renforcement de capacité en mutation du comité de gestion de Chouara en coopérative simplifiée

2014

55. Rapport contre-expertise de la Délégation régionale MINEE des points d'eau réalisés par le PDRI-CL

2013

ELEVAGE ET PECHE

56. Rapport de l'atelier de formation sur la structuration des pêcheurs de Logone Birni (phase 1)

2015

57. Rapport de l'atelier de formation sur la structuration des pêcheurs de Logone Birni (phase 2)

2015

58. Rapport de l'atelier de formation sur la structuration des pêcheurs de Blangoua (phase 1)

2015

59. Rapport de l'atelier de formation sur la structuration des pêcheurs de Blangoua (phase 2)

2015

60. Rapport campagne de déparasitage des petits ruminants contre la peste dans l'arrondissement de Makary

2015

61. Rapport sur le diagnostic et l'organisation de la filière lait dans le département du Logone et Chari

2015

62. Rapport sur la vaccination des volailles dans l'arrondissement de Kousseri

2015

63. Rapport sur la vaccination des volailles dans l'arrondissement de Logone Birni

2015

64. Rapport sur la vaccination des volailles dans l'arrondissement de Goulfey

2015

65. Rapport sur la vaccination des volailles dans l'arrondissement de Makary

2015

66. Rapport de l'atelier de formation des pêcheurs sur la pêche responsable à Logone Birni (phase 1)

2015

67. Rapport de l'atelier de formation des pêcheurs sur la pêche responsable à Logone Birni (phase 2)

2015

68. Rapport de l'atelier de formation des pêcheurs sur la pêche responsable à Logone Blangoua (phase 1)

2015

69. Rapport de l'atelier de formation des pêcheurs sur la pêche responsable à Blangoua (phase 2)

2015

70. Rapport sur la promotion de la pisciculture réalisée par ETS AQUACOL DU NORD PLUS

2015

71. Rapport de la campagne de déparasitage et de vaccination des petits ruminants dans l'arrondissement de Kousseri

2014

72. Rapport de la campagne de déparasitage et de vaccination des petits ruminants dans l'arrondissement de Goulfey

2014

73. Rapport de la campagne de déparasitage et de vaccination des petits ruminants dans l'arrondissement de Logone Birni

2014

74. Rapport de l'atelier de formation sur la technique de 2015

IDB PROJECT COMPLETION REPORT (PCR)

85

transformation et de conservation du forage

75. Rapport de l'atelier de formation des GIC impliqués dans l'embouche des ruminants

2014

76. Rapport sur la stratégie de mise en œuvre de l'amélioration de la productivité du poulet villageois dans le département du Logone et Chari

2014

77. Rapport de pré et post formation sur les techniques de production et de conservation du forage

2014

78. Rapport de l'atelier de formation sur l'amélioration de l'élevage du poulet villageois à Logone Birni

2014

79. Rapport de suivi technique et sensibilisation des promoteurs de la pisciculture et des producteurs de poisson en étang dans la zone d'intervention du PDRI-CL réalisé par GIC HOUT

2014

80. Rapport de l'atelier de formation sur l'amélioration de l'élevage du poulet villageois à Kousseri

2014

81. Rapport de l'atelier de mise à niveau des enquêteurs sur les agro systèmes à Kousseri

2014

82. Rapport de campagne générale de sensibilisation et de vulgarisation des populations sur la production de poisson en étang et la gestion durable des ressources halieutiques

2014

83. Rapport de suivi technique des promoteurs de la pisciculture en étang dans la zone d'intervention du PDRI-CL

Juin 2014

84. Rapport de suivi technique des promoteurs de la pisciculture en étang dans la zone d'intervention du PDRI

Juillet 2014

85. Rapport de suivi technique des promoteurs de la pisciculture en étang dans la zone d'intervention du PDRI

Août 2014

86. Rapport de suivi technique des promoteurs de la pisciculture en étang dans la zone d'intervention du PDRI

September 2014

87. Rapport de suivi technique des promoteurs de la pisciculture en étang dans la zone d'intervention du PDRI

October 2014

88. Rapport de l'atelier sur les techniques de conservation de poisson à Logone Birni

2014

89. Rapport de l'atelier sur les techniques de conservation de poisson à Blangoua

2014

90. Rapport de l'atelier de formation sur l'itinéraire technique de cultures fourragères

2015

AGROSYSTEME

91. Rapport technique sur le projet de réhabilitation des routes de désenclavement des zones de production et des circuits d'écoulement sur les marchés locaux et extérieurs

2015

92. Rapport de l'enquête sur les agro systèmes par Dr Amadou Lahamdi

2014

93. Rapport de l'atelier du diagnostic et de renforcement des capacités des OP faîtière (fédérations et coopératives) du Logone et Chari à Kousseri

2014

94. Rapport de l'atelier du diagnostic et de renforcement des faitières à Woulky, Blangoua et Kofia

2014

95. Atelier d'échange et de renforcement des capacités du personnel MINADER et MINEPIA du Logone et Chari, en charge de l'encadrement et du suivi des bénéficiaires des actions du projet

2015

IDB PROJECT COMPLETION REPORT (PCR)

86

96. Rapport d'identification des producteurs de niébé à Blangoua 2014

97. Rapport d'identification des producteurs de niébé à Darak et Hilé-Alifa

2014

98. Rapport d'identification des producteurs de Soja à Blangoua 2014

99. Rapport d'identification des producteurs de soja Hilé Alifa et Darak

2014

100. Rapport d'Atelier de formation des producteurs sur les techniques de production et de protection de niébé à Makary (zones de Darak et Hilé-Alifa)

2014

101. Rapport d'Atelier de formation des producteurs sur les techniques de production et de protection de niébé à Blangoua

2014

102. Rapport d'Atelier de formation des producteurs sur les itinéraires techniques de production de soja à Blangoua

2014

103. Rapport d'Atelier de formation des producteurs sur les itinéraires techniques de production de soja à Makary (Zones de Darak et Hilé Alifa)

2014

104. Rapport d'Atelier de formation des groupements maraichers femmes sur les itinéraires techniques à Kousseri

2014

105. Rapport d'Atelier de formation des groupements maraichers femmes sur les itinéraires techniques à Logone-Birni

2014

106. Rapport d'identification des bas-fonds arrosés par Le barrage de Chouara

2014

107. Rapport d'identification des bas-fonds arrosés par Le barrage de Djargoudja

2014

108. Rapport d'Atelier de formation sur les techniques de séchage et de conservation de gombo, tomate et oignon à Logone Birni

2015

109. Rapport d'Atelier de formation sur les techniques de séchage et de conservation de gombo, tomate et oignon à Kousseri

2015

110. Rapport d'Atelier de formation sur les techniques de séchage et de conservation de gombo, tomate et oignon à Makary

2015

111. Rapport de l'enquête d'identification et diagnostic des greniers villageois

2015

112. Rapport sur l'atelier de renforcement des capacités de gestion et d'organisation des COGEST à Kousseri

2015

113. Rapport sur l'atelier de renforcement des capacités de gestion et d'organisation des COGEST à Makary

2015

114. Rapport sur l'atelier de renforcement des capacités de gestion et d'organisation des COGEST à Logone Birni

2015

IDB PROJECT COMPLETION REPORT (PCR)

87

SUMMARY OF FINANCIAL AND ECONOMIC ANALYSES

The most important item in the economic and financial analysis is the calculation of the rate of

profitability. And the rate which sits in the rural development project is the economic rate of

return.

Calculation of the economic rate of return of the project

As, it has been indicated in the text, the project has experienced some difficulties in stating which

have delayed the effective implementation of its actions during several years and almost all of the

actions have been undertaken in the last years of the project. The estimates that have been made

are based on the period whose consistency has been established and the data contained.

For all of the productions in the intervention area of the project, for the past two years, the

estimates of the gross operating surplus give a total amount of 16,431,235,933 FCFA

The calculation of the profitability ratio for the project (mainly in the last two years with relevant

results), "Return on Capital Employed (ROCE), is based on the capital employed and the amount of

input requirements.

In total, the calculation of the ROCE is based on the gross revenues of production without taking

into account the taxes on the benefit and the total amount of capital used for the implementation

(different funds used). It is important to point out that the economic asset is composed of net

capital assets adjusted (increased) by the working capital needs (running funds).

For the calculation of the current profitability ration, a number of assumptions and realistic data

are taken into account and could be summarized as follows:

The overall tax rate is around 31%, which is a rate very close to the overall tax level in

Cameroon and in most countries of the CEMAC zone (in Cameroon the exact rate in the

secondary and tertiary sector of the economy is 33 %);

The gross income generated by producers is estimated at CFA 16,431,235,933

The total amount of expenses (cost of total inputs used) incurred by the

producers/populations to generate the total gross revenues is estimated at CFA

8,118,102,500 distributed through:

- Vegetable production; CFA 1,198,502,500

- Cowpea production; CFA 1, 822, 500,000

- Rice production; CFA 1, 450, 000,000

- Maize production; CFA 1,988, 900, 000

- Sorghum production; CFA 1, 200, 000, 000

- Cattle meat production; CFA 18, 200, 000

- Milk production; CFA 2, 125, 480, 250

- Small ruminant meat production; CFA 425, 000, 000 and

- Fish production (mostly in aquaculture); CFA 15, 000, 000

The Capital is represented by the amount of funds effectively mobilized trough the three main actors (ODB, OFID and Counterpart fund) for the implementation of the project actions and activities, that is CFA 8,920,866,470. Based on these elements, the calculation of the economic profitability or the ROCE gives us a rate of return or a return to the capital of 60.97 %. The income generated by the economic asset after taxes is of CFA 5,439,129,978. As a result of the calculation, we observe that the economic and financial profitability of the project is very relevant according to most of projects in the area (with a profitability rate of 60.9%). The difficulties in the beginning, which delay the implementation of the project was the main constraint for producing important revenue for the populations in the way of poverty alleviation in this part of the country. These results argue for the consolidation of actions through a second phase of this important and very profitable project (producing more food for consumption, creating revenue for the other needs and ameliorating the welfare of the people).

IDB PROJECT COMPLETION REPORT (PCR)

88

It is clear that they are two types of profitability which are represented by the economic profitability and the financial viability. The Return on Capital employed or ROCE is a profitability ratio that measures how efficiently a project can generate profits from the funds employed that is by comparing the net operating profit to capital (funds) employed. In other words, return on capital employed shown to funders that how their intervention can generate money for populations engaged in the production. The ROCE is a long term profitable ratio showing how effectively inputs are performed to produce outputs and outcomes. That is why ROCE is a more useful ratio than return on equity to evaluate the longevity of projects intervention. The ratio is based on two important calculations: operating revenues considered as profit and funds (capital) employed. The formula of the Return on capital employed is calculated by dividing net operating profit or EBIT or earnings by funds employed. In the framework of the rural development project, the economic rate of return is the most appropriate one.

IDB PROJECT COMPLETION REPORT (PCR)

89

PLANNED VS. ACTUAL PROCUREMENT PLAN

At the appraisal stage any procurement plan was prepared. The first one was prepared in 2010 and submitted to the "Comité de Pilotage" for approval and validated by the Ministry of Economy, Planning and Regional Development. So we are presenting all the procurement plans prepared for the project had been launched. That is, the first one of 2010, and the last two prepared after solving the mismanagement problems.

JOURNAL DE PROGRAMMATION DES MARCHES 2010 MAITRE D’OUVRAGE OU MAITRE D’OUVRAGE DELEGUE : COORDONNATEUR DU PROJET DE DEVELOPPEMENT RURAL INTEGRE CHARI-LOGONE RESPONSABLE EN CHARGE DU SUIVI DE LA PROGRAMMATION : RESPONSABLE DU SUIVI-EVALUATION DU PDRI-CL DATE D’ELABORATION OU DE MISE A JOUR DE LA PROGRAMMATION: MARS 2010 DATE DE TRANSMISSION A L’ARMP: 02 NOVEMBRE 2010

N° Désignation du Projet Financemen

t Imputations budgétaire

Coût prévisionnel

Structure ou agent en charge de l’élaboration du DAO

Observations ou état d’avancement de la procédure

1 Recrutement d’un Cabinet d’Audit

BID 87 300 000 PDRI-CL

2 Recrutement d’un Bureau d’Etudes

BID 300 000 000 PDRI-CL

3 Fourniture de mobilier de bureau

BID 15 000 000 PDRI-CL

4 Fourniture du matériel informatique

BID 15 000 000 PDRI-CL

5 Fourniture de matériel roulant

OFID-BID 123 500 000 PDRI-CL

6 Travaux de construction de 40 forages d’eau potable

BID 160 000 000 PDRI-CL

7 Travaux de construction de 5 forages pastoraux

BID 75 000 000 PDRI-CL

8 Travaux de construction de 13 salles de classe

OFID-Gvt 338 000 000 PDRI-CL

9 Travaux de construction de 3 centres do santé

BID 150 000 000 PDRI-CL

10 Travaux de construction de 2 marchés à bétail

OFID 50 000 000 PDRI-CL

11 Travaux de réfection du CFJA de Ngouma

BID 70 000 000 PDRI-CL

Total: 1 383 800 000 FCFA

IDB PROJECT COMPLETION REPORT (PCR)

90

PLAN DE PASSATION DES MARCHES: PROCEDURE D’APPEL D’OFFRES

Non objection BF 1 mois 1 mois

Proposition

Attribution CSPM

13 Jan 2011 13 Jan 2011 8 déc 8 déc 11 déc 8 déc 9 déc 9 déc 9 déc 9 déc 10 déc

Examen RA

financière et

synthèse

13 Jan 2011 13 Jan 2011 8 déc 8 déc 11 déc 8 déc 9 déc 9 déc 9 déc 9 déc 10 déc

Ouvert Offres

financières

8 Jan 2011 8 Jan 2011 7 déc 7 déc 10 déc 7 déc 8 déc 8 déc 8 déc 8 déc 9 déc

Examine RA

technique

5 jrs 5 jrs 2 jrs 2 jrs 2 jrs 2 jrs 2 jrs 2 jrs 2 jrs 2 jrs 2 jrs

Dépouillement

des offres

3 Jan 2011 3 Jan 2011 4 déc 2010 4 déc 2010 7 déc 2010

4 déc 2010 6 déc 2010 6 déc 2010 6 déc 2010

6 déc 2010

7 déc 2010

Lancement AO 4 déc 2010 4 déc 2010 2 Nov 2010

2 Nov 2010 4 Nov 2010

2 Nov 2010

3 Nov 2010

3 Nov 2010

3 Nov 2010

3 Nov 2010

4 Nov 2010

Non objection BF 1 mois 1 mois

Examine DAO

CSPM

4 Nov 2010 4 Nov 2010 1er Nov 2010

1er Nov 2010 3 Nov 2010

1er Nov 2010

2 Nov 2010

2 Nov 2010

2 Nov 2010

2nov 2010

3 Nov 2010

Season CSPM

Désignation du projet Recrutement d’un Cabinet

d’Audit

Recrutement d’un Bureau

d’Etudes

Fourniture de mobilier de

bureau

Fourniture du matériel

informatique

Fourniture de matériel

roulant

Travaux de construction

de 40

forages d’eau

potable

Travaux de construction

de 5 forages

pastoraux

Travaux de construction

de 13 salles

de classe

Travaux de constructio

n de 3

centres de santé

Travaux de

construct

ion de 2 marchés

à bétail

Travaux de

réfection

du CFJA de

Ngouma

N° 1 2 3 4 5 6 7 8 9 10 11

IDB PROJECT COMPLETION REPORT (PCR)

91

Observation ou état

d’avancement de la

procédure

Notification du

marché

18 mars

2011

18 mars

2011

20 déc

2010

17 Jan

2011

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

Signature marché 18 mars

2011

18 mars

2011

20 déc

2010

17 Jan

2011

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

20 déc 2010

Non objection BF 1 mois 1 mois 1 mois

Examen projet

marché CSPM

18 fév

2011

18 fév

2011

17 déc 2010

17 déc 2010

17 déc 2010

18 déc 2010

18 déc 2010

18 déc 2010

19 déc 2010

19 déc 2010

19 déc

2010

Saisine CSPM 15 fév

2011

15 fév

2011

14 déc

2010

14 déc 2010

14 déc 2010

14 déc 2010

14 déc 2010

14 déc 2010

14 déc 2010

14 déc 2010

14 déc 2010

Préparation projet

de marché et

souscription

5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs 5 jrs

Public résultats 13 fév

2011

13 fév

2011

12 déc 2010

12 déc 2010

12 déc 2010

12 déc 2010

12 déc 2010

12 déc 2010

12 déc 2010

12 déc 2010

12 déc

2010

Désignation du projet Recrutement

d’un Cabinet d’Audit

Recrutement

d’un Bureau d’Etudes

Fourniture

de mobilier de bureau

Fourniture du

matériel informatique

Fourniture

de matériel roulant

Travaux de

construction de 40

forages d’eau

potable

Travaux de

construction de 5 forages

pastoraux

Travaux

de construct

ion de 13 salles de

classe

Travaux de

construction de 3

centres de santé

Travaux

de construct

ion de 2 marchés

à bétail

Travaux

de réfection

du CFJA de

Ngouma

N° 1 2 3 4 5 6 7 8 9 10 11

IDB PROJECT COMPLETION REPORT (PCR)

92

Journal de programmation des Marchés 2013

N° Nature de la prestation et

localité de réalisation Type de

prestation

Montant prévisionnel du Marché (FCFA)

Autorité contractante/Administration bénéficiaire

Mode d'Appel d'Offres

Date lancement de l'Appel d'offres

Date attribution

Marché

Date de signature du Marché

Date probable

de démarrage

Date probable de

réception des

prestations

1 Réhabilitation du Centre de Santé de Parpar Kousseri

BEC 10 000 000 PDRI AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

2 Construction d’un barrage écluse sur le Chouara à Blangoua

AI 180 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

3 Construction d’un Abattoir modern à Kousseri

BEC 200 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

4 Construction de parcs à vaccination à Amchilga

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

5 Construction de parcs à vaccination à Michédiré

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

6 Construction de parcs à vaccination à Takoulwébé

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

7 Construction de parcs à vaccination Amdane

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

IDB PROJECT COMPLETION REPORT (PCR)

93

8 Construction d’Aires d’abattage équipées de forage à Logone Birni

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

9 Construction d’Aires d’abattage équipées de forage à Waza

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

10 Construction d’Aires d’abattage équipées de forage à Hilé Alifa

BEC 15 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

11 Constructions d’un magasin de stockage à Mazra

BEC 48 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

12 Constructions d’un magasin de stockage à Blangoua

BEC 48 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

13 Constructions d’un magasin de stockage à Hilé Alifa

BEC 48 000 000

PDRI

AON

19 November

2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

14 Acquisition de matériel informatique pour l’UGP

AG 29 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

15 Equipement de la Maison de la Femme de Kousseri

AG 8 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

16 Aménagement de la Base-Vie UGP

BEC 25 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

17 Acquisition de 102 Motopompes

AG 26 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

IDB PROJECT COMPLETION REPORT (PCR)

94

Montant total des marchés à passer 1 648 000 000 FCFA Type de prestation:

Route (Route)

Autres Infrastructures (AI) Approvisionnements Généraux (AG)

Services et Prestations Intellectuelles (SPI)

Bâtiments et Equipements Collectifs (BEC)

Mode d’Appel d’Offres :

Appel d’Offres National ou International (AONI)

Appel d’Offres Ouvert ou Restreint (AOOR) Appel d’Offres avec Concours (AOC)

Procédure de Gré à Gré (GG)

Le Coordonnateur

Pr MADI Ali

18 Acquisition de 3 pirogues de contrôle de pêche

BEC 49 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

19 Construction d’un marché à bétail à Mazra

BEC 41 000 000

PDRI

AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

20 Réhabilitation des périmètres rizicoles de Ndou

AI 500 000 000 PDRI AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

21 Réhabilitation des périmètres rizicoles de Zimado

AI 700 000 000 PDRI AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

22 Acquisition de matériel d'exhaure

BEC 400 000 000 PDRI AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

23 Electrification rurale par système solaire

BEC 48 000 000 PDRI AON 19

November 2013

12 décembre

2013

15 décembre

2013

Décembre 2013

Mars 2014

IDB PROJECT COMPLETION REPORT (PCR)

95

Journal de programmation des Marchés 2014

N° Nature de la prestation et

localité de réalisation Type de

prestation

Montant prévisionnel du Marché

Autorité contractante/Administr

ation bénéficiaire

Mode d'Appel d'Offres

Date lancement de l'Appel d'offres

Date attribution

Marché

Date de signature du Marché

Date probabl

e de démarr

age

Date probable de

réception des

prestations

1 Complément réhabilitation du périmètre de Zimado

AI 488 925 000 PDRI AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

2

Réhabilitation périmètres FED (Logone, Mara, Goulfey) et hors blocs (Wémo, Dolé, Sao, Wéra, Biamo, Bodo)

AI 370 976 250

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

3

Construction du barrage écluse de Ndjargoudja et aménagement des points critiques sur le Serbewel (Fadjé et Makary)

AI 368 550 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

4 Constructions d’un bloc de 2 salles de classe équipées au CES de Woulky

BEC 22 697 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

5 Equipement de 4 Centres de santé en latrines, forages et matériels médicaux

AG 84 147 185

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

6

Réalisation de 5 forages à motricité humaine dans l’arrondissement de Waza (Ouska, Misikili, Bourgourou, Yamyam et Ndiguina)

BEC 83 475 000

PDRI AON

23 May 2014

13 juin 2014 22 juin 2014

28 juin 2014

31 août 2014

IDB PROJECT COMPLETION REPORT (PCR)

96

7 Réalisation de forage à motricité humaine (Karagama, Mbré Arabe, Sédé, CES Laka)

71 430 750

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

8 Réalisation de 3 forages pastoraux (Mada, Yobé, Nigué)

BEC 55 451 250

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

9 Construction de 4 parcs à vaccination

BEC 66 780 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

10 Equipement de l’abattoir moderne de Kousseri

BEC 193 525 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

11 Construction d’une aire d’abattage à Mada

BEC 16 695 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

12 Achèvement travaux aire d’abattage de Waza

BEC 10 732 500

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

13 Construction marché de poisson de Blangoua

BEC 149 062 500

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

14 Construction du débarcadère de Blangoua

BEC 125 212 500

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

15 Electrification rurale par énergie solaire à Woulky et Amchilga

AI 89 437 500

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

16 Acquisition du matériel de contrôle de pêche

AG 83 475 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

IDB PROJECT COMPLETION REPORT (PCR)

97

Total 2 399 226 780 FCFA Type de prestation:

Route (Route)

Autres Infrastructures (AI) Approvisionnements Généraux (AG)

Services et Prestations Intellectuelles (SPI)

Bâtiments et Equipements Collectifs (BEC)

Mode d’Appel d’Offres:

Appel d’Offres National ou International (AONI)

Appel d’Offres Ouvert ou Restreint (AOOR) Appel d’Offres avec Concours (AOC)

Procédure de Gré à Gré (GG)

Le Coordonnateur

Pr MADI Ali

17 Réalisation de 3 forages à énergie solaire pour agro foresterie

AG 50 085 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

18

Réalisation de 4 Forages à pompe immergée pour agro foresterie

AG 20 868 750

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

19

Réalisation de 5

Forages à motopompe

pour agro foresterie

AG 23 850 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

20 Equipement du CFJA

de Ngouma en énergie

solaire

AG 23 850 000

PDRI

AON 23 May

2014 13 juin 2014

22 juin 2014

28 juin 2014

31 août 2014

IDB PROJECT COMPLETION REPORT (PCR)

98

SOURCES OF INFORMATION

ACEEN, 2010. Etude de la dynamique reconstitutive du stock de poissons dans les mares

artificielles dans et autour du Parc National de Waza, CADEPI, EGP, Avril 2010.

ANDREA SPRINGER-HEINZE (eds), 2007, Manuel Valuelinks, La méthodologie de Promotion de

Chaîne de Valeur Ajoutée, Première Edition.

BET COMPETENCE, 2015, Etude de faisabilité de Phase II PDRI-CL, Rapport Final mars 2015

Bergonzini J.C. 2005. Changements climatiques, diversité biologique, désertification, et forets.

Silva, RIAT Eds

CAON-FED, 2011. Etablissement de l’état des lieux des régions bénéficiaires des interventions du

PDR-EN, Rapport final, réalisé par Ere et Développement, Coopération Cameroun-Union

Européenne, Yaoundé.

MINEPAT, 2012, Programme Economique de promotion des entreprises moyenne et grande

importance (AGROPOLE)

MINEPAT, 2010. Document de Stratégie pour la Croissance et l’Emploi (DSCE), Yaoundé,

Cameroun.

IDB, 2012, Project Implementation Assessment Support Report October2-5/2012 IDB, 2009, Project Completion Report Format, November 2009 IDB and Cameroonian Government, 2008, Accord de prêt entre le Gouvernement de la République du Cameroun et la Banque Islamique de Développement pour le financement du développement rural intégré du Chari-Logone, Project N° CM-0053 IDB, 2007, Appraisal report of Chari/Logone Integrated Rural Development Project

MIDIMA, 2009. Bilan diagnostic 2008-2009, en vue de l’actualisation du schéma directeur régional

d’aménagement et de développement durable du territoire (SDRADDT) de la région de l’Extrême-

Nord, Rapport final réalisé en 2001 ; Bet Géocompétence, MINEPAT, Yaoundé.

MINADER, 2005 - Document de Stratégie de Développement du Secteur Rural. Yaoundé.

MINADER, 2008. Etude de faisabilité d’un programme de relance durable et de diversification des

productions agricoles en zone cotonnière, Rapport final, préparé par Progress SARL, Etudes et

Développement, Coopération Cameroun-Union Européenne, Yaoundé.

MINEPAT, 2009. Cameroun: Vision 2035, Yaoundé, Cameroun. MINEPAT, Délégation Régionale de l’Extrême Nord (mars 2014). Rapport socioéconomique et les opportunités de développement de la région de l’extrême nord de l’année 2013. OFID and GOVERNEMENT OF CAMEROUN, 2008, Loan Agreement to finance the Chari/Logone integrated Rural Development Project, N°1214P

IDB PROJECT COMPLETION REPORT (PCR)

99

PDRI-CL, 2014. Rapport d’activités sur l’évaluation des clairières et impacts ou effets des

populations riveraines sur les ressources naturelles du Parc National de Kalamaloué, 16-25 Juillet

2014, Composante Gestion des Ressources Naturelles, Par Aladji Iseini et Abdoul Roufaye

Mahamat Chérif, Etudiants-stagiaires ISS au PDRI-CL, Juillet 2014.

PDRI-CL, 2013, 2014, 2015, Rapports trimestriels, semestriels, annuels

PDRP-L&C, 2002. Etude socio-économique complémentaire sur les six périmètres irrigués de

Goulfey, Goulfey Gana, Hillélé, Logone Birni, Mara, Moulouang, Protocole d’accord N° 002/PDRP-

L&C, Rapport provisoire, réalisé par le CEDC, Octobre 2002.

PDRP-L&C, 2003. Mission d’évaluation à mi-parcours du Programme, Rapport d’évaluation version

finale, Kousseri, Cameroun, étude réalisée par Thales engineering & consulting, France.

PDRP-L&C, 2004. Etude socio-économique des cultures de décrue dans les cuvettes aux alentours

du lac Tchad, Protocole d’accord N° 007/PDRP-L&C avec le CEDC, Février 2004.

RGPH, 2010. 3e Recensement Général de la Population et de l’Habitat, 2005. MINEPAT, BUCREP,

Yaoundé, Cameroun.

MINADER, MINEPAT, MINEPIA, 2005. Stratégie de Développement du Secteur Rural (SDSR),

Yaoundé, Cameroun.

SNV, 2009. Stratégies de collecte, de transformation et de commercialisation de la production

locale de lait autour de Maroua, Kousseri et Yagoua, Rapport final, Mars 2009.

IDB PROJECT COMPLETION REPORT (PCR)

100

OTHER DETAILS

Due the relevant results and the specificity of the area, a second phase of the Project has been prepared and submitted.

CHARI/LOGONE RURAL INTEGRATED PROGRAMME II (PDRI-CL II)

OBJECTIVES

The main objective of Chari/Logan II is, the sustainable alleviation of poverty and creation of an important number of jobs for youth in particular through an integrated approach based on the value added chain method and taking into account the of consolidating the achievements of the first phase.

Specific Objectives

The specific objectives of the program in accordance with the strategic axes of intervention include:

1. Making accessible most of important basins of production by linking production areas to different relay or final (consumer) markets (rehabilitation/creation of rural roads);

2. Rehabilitating of remaining irrigated perimeters and creation of others for cereals and vegetable crops produced in the context of sustainable production and productivity (creation/ rehabilitation of irrigation perimeters);

3. Strengthening of production systems and reinforcing aquaculture to ameliorate the production and productivity;

4. Reinforcing value chain efficiency and strengthening of population welfare through socioeconomic infrastructures

5. Strengthening of community development support in term of professionalization of the producers' organizations;

6. Creating of a local development fund to initiate a real action of entrepreneurship.

RESULTS On the basis of the program objectives, the results to be achieved are:

1. All major basins of productions are linked to the main markets by 450 km of dirt road that can be

used in any season;

2. At least 1500 hectares of irrigated perimeters rehabilitated/created;

3. All the production systems of the area are effectively accompanied to ensure production and

productivity, allowing an increase of at least 30% of the income of the producers;

4. The main value added chains are discounted to level for a better distribution of productivity

gained throughout the value chain;

IDB PROJECT COMPLETION REPORT (PCR)

101

To achieve these results, actions have to be organized within different components

SCOPE OF COMPONENTS

Chari/Logone II, will be implemented through five (05) main component

1. CREATION/REHABILITATION OF ROADS

This component is to link all the major producing basins to different markets to allow the

producers to sell their products at any time with acceptable prices to ameliorate their revenues.

This possibility which will be offered to producers is one of the main current constraints in

obtaining the best price for the products by the peasants. The traders buying the different

products are the main beneficiaries of the production activities of peasants who are maintained in

a cycle of dependency. The main roads that connect production areas to markets are not

accessible in the raining seasons. Even with 4WD vehicles in the rainy season, it is almost

impossible to get out of produce in most of production areas. This situation raising not only the

prices of the products on the markets for the consumers, but also and especially the quasi-totality

of the fresh products are inaccessible and destroyed for most of the peasants.

2. HYDRO-AGRICULTURAL LAND PLANNING

In view of the paucity of rain or of their irregularity, the speculation of the rainy season generally

does not manage to complete their cycle of maturity causing IMPORTANT food deficits in the area.

This situation is becoming more frequent and tends to a constant. In so doing, all of the producers

dependent on these crops are still exposed to food insecurity and living below the threshold of

poverty, the Irrigated production systems are the best solution in the area. So creating or

rehabilitating the irrigated perimeters remains the crucial opportunities for producers.

Innovations have to be introduced in the reduction of quantity of water used by ameliorating the

irrigation system.

3. STRENGTHENING OF PRODUCTION SYSTEMS

This component will be the key element of the creation of revenues with the emphasis on the integrated approach to value chain, including the delivery to level requires the actions of related order and those related directly to the production systems. It will be to make the various systems more productive and efficient through the actions of strengthening capacity of producers in the domain of innovative techniques of production and support for production materials taking into account the level of poverty of most of the farmers in the area. The Chari/Logan I had developed the important domain and the preliminary impacts indicate that the alleviation of poverty is growing and these further actions will complete the process engaged and this part of the country will be one of the producers. 4. REINFORCEMENT OF SOCIO-ECONOMIC INFRASTRUCTURES OF ACCOMPANIMENT Despite the presence of a few infrastructures put in place in phase I of the program, and by the other actors having intervened, the upgrading of value chains requires additional structures for storage, those accompanying the activities of livestock particularly vaccination parks, cattle and small ruminant markets and the boreholes for livestock use, amount others. The Total amount of the program is CFA twenty-one Billion seventeen million six hundred twenty two thousand three hundred and seventy-six (CFA 21,017,622 376).

IDB PROJECT COMPLETION REPORT (PCR)

102

APPENDIX -2

PERFORMANCE RATING SCALE

General (applicable to most indicators) Rating Score

If performance is highly satisfactory 4

If performance is satisfactory 3

If performance is partially satisfactory 2 If performance is unsatisfactory 1

If performance is highly unsatisfactory 0

Rating for Cost Variation

If cost variation is within +/- 10 percent of the appraisal cost estimate 4

If cost variation is within +/- 20 percent of the appraisal cost estimate 3

If cost variation is within +/- 30 percent of the appraisal cost estimate 2

If cost variation is within +/- 50 percent of the appraisal cost estimate 1

If cost variation is more than +/- 50 percent of the appraisal cost estimate 0 Rating for Adherence to Time schedule Delay is defined as difference in months between the original closing date and actual closing date

If the delay is less than 12 months 4

If the delay is between 12 to 24 months 3

If the delay is between 24 to 36 months 2

If the delay is between 36 to 48 months 1

If the delay is over 48 months 0

Overall Assessment The overall assessment would be the simple un-weighted average of scores for all indicators, under each criteria/sub-criteria. This will be determined by adding all rating scores and dividing the total by the number of the component indicators. The numerical average will then be converted into descriptive ratings as follows:

Highly Satisfactory (HS) 3< R≤ 4

Satisfactory (S) 2<R≤ 3

Partially Satisfactory (PS) 1<R≤ 2

Unsatisfactory (US) 0.5<R≤1

Highly Unsatisfactory (HUS) 0<R≤0. 5