    ID Task Name Duration InfoX % Complete Start Finish

    1 Pre-Project 9 days 100% Mon 10/5/09 Thu 10/15/09

    18 Project 53.25 days 14% Mon 10/5/09 Thu 12/17/09

    19 Project Management 40 days 2% Mon 10/19/09 Fri 12/11/09

    20 Project Timeline 40 days 0% Mon 10/19/09 Fri 12/11/09

    21 Project Start 0 days 0% Mon 10/19/09 Mon 10/19/0922 Project Preparation 5 days 0% Mon 10/19/09 Fri 10/23/09

    23 Plan 5 days 0% Mon 10/19/09 Fri 10/23/09

    24 Blueprint 0 days 0% Fri 10/23/09 Fri 10/23/09

    25 Analyze 0 days 0% Fri 10/23/09 Fri 10/23/09

    26 Design 0 days 0% Fri 10/23/09 Fri 10/23/09

    27 Realization 25 days 0% Mon 10/26/09 Fri 11/27/09

    28 Build 15 days 0% Mon 10/26/09 Fri 11/13/09

    29 Test 10 days 0% Mon 11/16/09 Fri 11/27/09

    30 Final Preparation 5 days 0% Mon 11/30/09 Fri 12/4/09

    31 Deploy 5 days 0% Mon 11/30/09 Fri 12/4/09

    32 Release & Support 5 days 0% Fri 12/4/09 Fri 12/11/09

    33 Go-Live 0 hrs 0% Fri 12/4/09 Fri 12/4/09

    34 Support 5 days 0% Mon 12/7/09 Fri 12/11/09

    35 Project Kickoff Meeting 1 day 100% Tue 10/20/09 Tue 10/20/09

    36 Kickoff Meeting 1 day 100% Tue 10/20/09 Tue 10/20/09

    37 Milestone: Kickoff Meeting Complete 0 days 100% Tue 10/20/09 Tue 10/20/09

    38 Application 50.25 days 12% Mon 10/5/09 Mon 12/14/09

    39 Project Preparation 14 days 99% Mon 10/5/09 Fri 10/23/09

    40 Plan 4 days 100% Mon 10/19/09 Fri 10/23/09

    41 Phase Startup 1 min 100% Mon 10/19/09 Mon 10/19/09

    42 Customer Data Review 3 days 100% Mon 10/19/09 Thu 10/22/09

    43 Base Setup Review 1 day 100% Thu 10/22/09 Fri 10/23/09

    44 Milestone: End of Project Preparation 0 days 0% Mon 10/5/09 Mon 10/5/09

    45 Realization 32.25 days 8% Mon 10/26/09 Wed 12/9/09

    46 Build 27.25 days 9% Mon 10/26/09 Wed 12/2/09

    47 Phase Startup 1 min 100% Mon 10/26/09 Mon 10/26/09

    48 Base Setup Configuration 3.75 days 0% Wed 11/4/09 Mon 11/9/09

    49 Marketing 2.25 days 0% Wed 11/4/09 Fri 11/6/0950 Campaign Management 0.75 days 0% Wed 11/4/09 Wed 11/4/09

    51 Base Setup Configuration 4 hrs 0% Wed 11/4/09 Wed 11/4/09

    52 Unit Test 2 hrs 0% Wed 11/4/09 Wed 11/4/09

    53 Lead Management 0.75 days 0% Wed 11/4/09 Thu 11/5/09

    54 Base Setup Configuration 4 hrs 0% Wed 11/4/09 Thu 11/5/09

    55 Unit Test 2 hrs 0% Thu 11/5/09 Thu 11/5/09

    Task

    SplitProgress

    Milestone

    SummaryProject Summary

    External Tasks

    External MilestoneDeadline

    Page 1

    Project: 3.2.020_Project Plan

    Date: Thu 11/5/09

  • 8/14/2019 ICON - Project Plan 05-Nov-09a

    2/4

  • 8/14/2019 ICON - Project Plan 05-Nov-09a

    3/4

  • 8/14/2019 ICON - Project Plan 05-Nov-09a

    4/4