Activity ID Activity Name Original
Duration
Start Finish
Idaho College of Osteopathic MedicineIdaho College of Osteopathic Medicine 955 06-Dec-16 19-Jul-19
Preconstruction | Design PhasePreconstruction | Design Phase 133 06-Dec-16 17-Apr-17
Pre1000 CMAR RFQ | SOQ submittal 0 06-Dec-16*
Pre1050 CMAR SOQ Review 5 06-Dec-16 12-Dec-16
Pre1100 CMAR Final Interview | Selection 0 16-Dec-16*
Pre1150 CMAR | McAlvain Agreement 0 19-Dec-16*
Pre1200 Design Development | 70% Completion 0 09-Jan-17*
Pre1250 DD Phase Estimate I (70%) 15 09-Jan-17 27-Jan-17
Pre1300 DD Phase Value Analysis | Constructability Review 15 09-Jan-17 27-Jan-17
Pre1325 Project Management Plan - McAlvain 0 30-Jan-17
Pre1350 CoM Early Start Grading Permit Submittal 0 09-Jan-17*
Pre1400 Idaho Power Design Agreement 15 09-Jan-17 27-Jan-17
Pre1425 SWPPP Plan Development 15 09-Jan-17 27-Jan-17
Pre1450 EPA Notice of Intent Filing | 10 Day wait 10 30-Jan-17 10-Feb-17
Pre1500 CoM Early Start Grading Permit Review | Issuance 16 09-Jan-17 30-Jan-17
Pre1525 Groundbreaking Ceremony 0 30-Jan-17*
Pre1550 Phase I GMP Submit - Grading | Foundations 0 07-Feb-17
Pre1600 Phase I GMP Agreement | Owner Notice to Proceed 0 08-Feb-17
Pre2550 Construction Documents | 85% Completion 25 09-Jan-17 10-Feb-17
Pre2650 85% CD Phase Estimate 10 13-Feb-17 24-Feb-17
Pre2675 Quality Management Plan - McAlvain 0 06-Mar-17
Pre2700 Risk Management Plan - McAlvain 0 06-Mar-17
Pre2725 BIM Management Plan - McAlvain 0 06-Mar-17
Pre2775 Phase II GMP Submit - Early Procurement & Key Subs 0 13-Mar-17
Pre2825 Phase II GMP - Owner Approve | Contract Ammendment 0 16-Mar-17
Pre2875 Construction Documents - 100% Completion 11 13-Feb-17 27-Feb-17
Pre3750 CoM Building Permit Submittal | Review 35 28-Feb-17 17-Apr-17
Pre3775 CoM Building Permit | Fees Paid 0 17-Apr-17
Pre3825 Utility Service | ACHD Impact Fees Paid 10 28-Mar-17 10-Apr-17
Pre4000 Phase III GMP Submit - 100% CD | Permit Set Docs 0 11-Apr-17
Pre4500 Phase III GMP - Owner Approve | Contract Ammendment 0 14-Apr-17
ProcurementProcurement 438 09-Jan-17 22-Mar-18
Bidding | SolicitationBidding | Solicitation 95 09-Jan-17 14-Apr-17
ProBid1000 Advertising | Marketing | Subcontractor Prequalification 45 09-Jan-17 10-Mar-17
ProBid1050 Bid Packaging | Instructions 45 09-Jan-17 10-Mar-17
ProBid1100 Phase I Bid Solicitation - Grading | Foundations 12 18-Jan-17 02-Feb-17
ProBid1300 Phase I Pre-Award Meetings | Notices of Intent 2 03-Feb-17 06-Feb-17
ProBid1350 Phase I Bid Awards | Notices to Proceed 0 07-Feb-17
ProBid1400 Phase II Bid Solicitation - Early Procurement | Key Subs 15 13-Feb-17 03-Mar-17
ProBid1450 Phase II Pre-Bid Meeting 1 27-Feb-17 27-Feb-17
ProBid1600 Phase II Pre-Award Meetings | Notices of Intent 5 06-Mar-17 10-Mar-17
ProBid1650 Phase II Bid Awards | Notices to Proceed 0 16-Mar-17
ProBid1700 Phase III Bid Solicitation | Final Pricing - 100% CDs 20 28-Feb-17 27-Mar-17
ProBid1750 Phase III Pre-Bid Meeting | Addenda 10 07-Mar-17 20-Mar-17
ProBid1800 Phase III Bid Review | Pre-Award | Notice of Intent 10 21-Mar-17 03-Apr-17
ProBid1850 Phase III Bid Award | Notices to Proceed 0 14-Apr-17
Contracting | SubmittalsContracting | Submittals 409 07-Feb-17 22-Mar-18
Subcontracts | Purchase & Rental AgreementsSubcontracts | Purchase & Rental Agreements 157 07-Feb-17 13-Jul-17Div. 01 | GeneralDiv. 01 | General 7 07-Feb-17 13-Feb-17
ProSPA.01.1000 Portable Toilets - RA 5 07-Feb-17 13-Feb-17
ProSPA.01.1050 Office Trailer - RA 5 07-Feb-17 13-Feb-17
ProSPA.01.1100 Forklift - RA 5 07-Feb-17 13-Feb-17
ProSPA.01.1150 Surveyor - Subc 0 07-Feb-17Div. 02 | Existing ConditionsDiv. 02 | Existing Conditions 0 07-Feb-17 07-Feb-17
ProSPA.02.1000 Sawcutting | Core Drilling - PA 0 07-Feb-17Div. 03 | ConcreteDiv. 03 | Concrete 87 14-Feb-17 11-May-17
ProSPA.03.1000 Concrete Foundations | Flatwork - Subc 5 14-Feb-17 20-Feb-17
ProSPA.03.1050 Concrete Reinforcement - Subc 5 14-Feb-17 20-Feb-17
ProSPA.03.1100 Concrete Grind | polish - Subc 5 05-May-17 11-May-17
ProSPA.03.1150 Concrete Curb & Gutter - Subc 5 05-May-17 11-May-17
ProSPA.03.1200 Precast Concrete - Subc 5 05-May-17 11-May-17Div. 04 | MasonryDiv. 04 | Masonry 21 28-Apr-17 18-May-17
ProSPA.04.1000 Masonry - Subc 5 28-Apr-17 04-May-17
ProSPA.04.1050 Scaffold - RA 5 12-May-17 18-May-17Div. 05 | MetalsDiv. 05 | Metals 57 16-Mar-17 11-May-17
ProSPA.05.1000 Structural | Misc. Steel Supply - Subc 0 16-Mar-17
ProSPA.05.1050 Structural Steel Erect - Subc 0 16-Mar-17
ProSPA.05.1100 Metal Flashings | Coping - Subc 5 05-May-17 11-May-17
ProSPA.05.1150 Metal Framing - Subc 5 28-Apr-17 04-May-17Div. 06 | Woods, Plastics & CompositesDiv. 06 | Woods, Plastics & Composites 14 28-Apr-17 11-May-17
ProSPA.06.1000 Rough Carpentry - Subc 5 05-May-17 11-May-17
ProSPA.06.1050 Architectural Woodwork - Subc 5 28-Apr-17 04-May-17
ProSPA.06.1100 Millworks | Cabinetry | Countertops - Subc 5 28-Apr-17 04-May-17Div. 07 | Thermal & Moisture ProtectionDiv. 07 | Thermal & Moisture Protection 87 14-Feb-17 11-May-17
ProSPA.07.1000 Insulation - Subc 5 05-May-17 11-May-17
ProSPA.07.1050 Rigid Insulation - PA 5 14-Feb-17 20-Feb-17
ProSPA.07.1100 Dampproofing | Waterproofing - Subc 5 14-Feb-17 20-Feb-17
ProSPA.07.1150 TPO Roofing - Subc 5 05-May-17 11-May-17
ProSPA.07.1200 Metal Wall | Roof Paneling - Subc 5 28-Apr-17 04-May-17
ProSPA.07.1250 Fluid Applied Air Barrier - Subc 5 28-Apr-17 04-May-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
06-Dec-16
06-Dec-16 17-Apr-17, Preconstruction | Design Phase
06-Dec-16* CMAR RFQ | SOQ submittal
06-Dec-16 CMAR SOQ Review
16-Dec-16* CMAR Final Interview | Selection
19-Dec-16* CMAR | McAlvain Agreement
09-Jan-17* Design Development | 70% Completion
09-Jan-17 DD Phase Estimate I (70%)
09-Jan-17 DD Phase Value Analysis | Constructability Review
30-Jan-17 Project Management Plan - McAlvain
09-Jan-17* CoM Early Start Grading Permit Submittal
09-Jan-17 Idaho Power Design Agreement
09-Jan-17 SWPPP Plan Development
30-Jan-17 EPA Notice of Intent Filing | 10 Day wait
09-Jan-17 CoM Early Start Grading Permit Review | Issuance
30-Jan-17* Groundbreaking Ceremony
07-Feb-17 Phase I GMP Submit - Grading | Foundations
08-Feb-17 Phase I GMP Agreement | Owner Notice to Proceed
09-Jan-17 Construction Documents | 85% Completion
13-Feb-17 85% CD Phase Estimate
06-Mar-17 Quality Management Plan - McAlvain
06-Mar-17 Risk Management Plan - McAlvain
06-Mar-17 BIM Management Plan - McAlvain
13-Mar-17 Phase II GMP Submit - Early Procurement & Key Subs
16-Mar-17 Phase II GMP - Owner Approve | Contract Ammendment
13-Feb-17 Construction Documents - 100% Completion
28-Feb-17 CoM Building Permit Submittal | Review
17-Apr-17 CoM Building Permit | Fees Paid
28-Mar-17 Utility Service | ACHD Impact Fees Paid
11-Apr-17 Phase III GMP Submit - 100% CD | Permit Set Docs
14-Apr-17 Phase III GMP - Owner Approve | Contract Ammendment
09-Jan-17 22-Mar-18, Procurement
09-Jan-17 14-Apr-17, Bidding | Solicitation
09-Jan-17 Advertising | Marketing | Subcontractor Prequalification
09-Jan-17 Bid Packaging | Instructions
18-Jan-17 Phase I Bid Solicitation - Grading | Foundations
03-Feb-17 Phase I Pre-Award Meetings | Notices of Intent
07-Feb-17 Phase I Bid Awards | Notices to Proceed
13-Feb-17 Phase II Bid Solicitation - Early Procurement | Key Subs
27-Feb-17 Phase II Pre-Bid Meeting
06-Mar-17 Phase II Pre-Award Meetings | Notices of Intent
16-Mar-17 Phase II Bid Awards | Notices to Proceed
28-Feb-17 Phase III Bid Solicitation | Final Pricing - 100% CDs
07-Mar-17 Phase III Pre-Bid Meeting | Addenda
21-Mar-17 Phase III Bid Review | Pre-Award | Notice of Intent
14-Apr-17 Phase III Bid Award | Notices to Proceed
07-Feb-17 22-Mar-18, Contracting | Submittals
07-Feb-17 13-Jul-17, Subcontracts | Purchase & Rental Agreements
07-Feb-17 13-Feb-17, Div. 01 | General07-Feb-17 Portable Toilets - RA
07-Feb-17 Office Trailer - RA
07-Feb-17 Forklift - RA
07-Feb-17 Surveyor - Subc
07-Feb-17 07-Feb-17, Div. 02 | Existing Conditions07-Feb-17 Sawcutting | Core Drilling - PA
14-Feb-17 11-May-17, Div. 03 | Concrete14-Feb-17 Concrete Foundations | Flatwork - Subc
14-Feb-17 Concrete Reinforcement - Subc
05-May-17 Concrete Grind | polish - Subc
05-May-17 Concrete Curb & Gutter - Subc
05-May-17 Precast Concrete - Subc
28-Apr-17 18-May-17, Div. 04 | Masonry28-Apr-17 Masonry - Subc
12-May-17 Scaffold - RA
16-Mar-17 11-May-17, Div. 05 | Metals16-Mar-17 Structural | Misc. Steel Supply - Subc
16-Mar-17 Structural Steel Erect - Subc
05-May-17 Metal Flashings | Coping - Subc
28-Apr-17 Metal Framing - Subc
28-Apr-17 11-May-17, Div. 06 | Woods, Plastics & Composites05-May-17 Rough Carpentry - Subc
28-Apr-17 Architectural Woodwork - Subc
28-Apr-17 Millworks | Cabinetry | Countertops - Subc
14-Feb-17 11-May-17, Div. 07 | Thermal & Moisture Protection05-May-17 Insulation - Subc
14-Feb-17 Rigid Insulation - PA
14-Feb-17 Dampproofing | Waterproofing - Subc
05-May-17 TPO Roofing - Subc
28-Apr-17 Metal Wall | Roof Paneling - Subc
28-Apr-17 Fluid Applied Air Barrier - Subc
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 1 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ProSPA.07.1300 Spray Applied Fire Proofing - Subc 5 21-Apr-17 27-Apr-17
ProSPA.07.1350 Joint Filler | Sealants - Subc 5 05-May-17 11-May-17
ProSPA.07.1400 Miscellaneous Sheet Metal - Subc 5 05-May-17 11-May-17Div. 08 | Doors & WindowsDiv. 08 | Doors & Windows 35 14-Apr-17 18-May-17
ProSPA.08.1000 Doors | Frames | Hardware - Subc 5 05-May-17 11-May-17
ProSPA.08.1050 Access Controls - Subc 5 05-May-17 11-May-17
ProSPA.08.1100 Storefront | Curtainwall - Subc 0 14-Apr-17
ProSPA.08.1150 Fire Doors - Subc 5 28-Apr-17 04-May-17
ProSPA.08.1200 Door | Hardware Install - Subc 5 12-May-17 18-May-17
ProSPA.08.1250 Specialty Doors - Subc 5 05-May-17 11-May-17Div. 09 | FinishesDiv. 09 | Finishes 7 05-May-17 11-May-17
ProSPA.09.1000 Painting - Subc 5 05-May-17 11-May-17
ProSPA.09.1050 Tile - Subc 5 05-May-17 11-May-17
ProSPA.09.1100 Carpet - Subc 5 05-May-17 11-May-17
ProSPA.09.1150 Specialty Flooring - Subc 5 05-May-17 11-May-17Div. 10 | SpecialtiesDiv. 10 | Specialties 14 05-May-17 18-May-17
ProSPA.10.1000 Visual Displays - PA 5 12-May-17 18-May-17
ProSPA.10.1050 Restroom Partitions | Accessories - PA 5 12-May-17 18-May-17
ProSPA.10.1100 Lockers | Post Boxes - PA 5 12-May-17 18-May-17
ProSPA.10.1150 DIRTT Partition Walls - Subc 5 05-May-17 11-May-17
ProSPA.10.1200 Signage - Subc 5 12-May-17 18-May-17Div. 11 | EquipmentDiv. 11 | Equipment 63 12-May-17 13-Jul-17
ProSPA.11.1000 Audio | Visual Package - Subc 5 12-May-17 18-May-17
ProSPA.11.1050 Audio-Video Package - FF&E 5 07-Jul-17 13-Jul-17
ProSPA.11.1100 Food Service Equipment - FF&E 5 07-Jul-17 13-Jul-17
ProSPA.11.1150 Healthcare Equipment - FF&E 5 07-Jul-17 13-Jul-17Div. 12 | FurnishingsDiv. 12 | Furnishings 64 16-Mar-17 18-May-17
ProSPA.12.1000 Roller Window Shades - Subc 5 12-May-17 18-May-17
ProSPA.12.1050 Lecterns - Subc 5 12-May-17 18-May-17
ProSPA.12.1100 Auditorium Seating - Subc 5 05-May-17 11-May-17
ProSPA.12.1150 Entrance Floor Mats & Frames - PA 5 16-Mar-17 22-Mar-17
ProSPA.12.1200 Bicycle Racks - PA 5 12-May-17 18-May-17
ProSPA.12.1250 Site Tables | Chairs | Trash Bins - PA 5 12-May-17 18-May-17Div. 13 | Specialty ConstructionDiv. 13 | Specialty Construction 7 12-May-17 18-May-17
ProSPA.13.1000 Water Feature | Fountain Equipment - PA 5 12-May-17 18-May-17Div. 14 | Conveying EquipmentDiv. 14 | Conveying Equipment 0 16-Mar-17 16-Mar-17
ProSPA.14.1000 Elevators - Subc 0 16-Mar-17Div. 21 | Fire SuppressionDiv. 21 | Fire Suppression 0 16-Mar-17 16-Mar-17
ProSPA.21.1000 Fire Sprinkler - Subc 0 16-Mar-17Div. 22 | PlumbingDiv. 22 | Plumbing 0 16-Mar-17 16-Mar-17
ProSPA.22.1000 Plumbing | Wet Mechanical - Subc 0 16-Mar-17Div. 23 | HVACDiv. 23 | HVAC 36 16-Mar-17 20-Apr-17
ProSPA.23.1000 Dry Mechanical - Subc 0 16-Mar-17
ProSPA.23.1050 Test & Balance - Subc 5 14-Apr-17 20-Apr-17Div. 25 | Integrated AutomationDiv. 25 | Integrated Automation 7 21-Apr-17 27-Apr-17
ProSPA.25.1000 Building Automation System - Subc 5 21-Apr-17 27-Apr-17Div. 26 | ElectricalDiv. 26 | Electrical 0 16-Mar-17 16-Mar-17
ProSPA.26.1000 Electrical - Subc 0 16-Mar-17Div. 27 | CommunicationsDiv. 27 | Communications 7 28-Apr-17 04-May-17
ProSPA.27.1000 Phone | Data - Subc 5 28-Apr-17 04-May-17
ProSPA.27.1050 Phone Service - PA 5 28-Apr-17 04-May-17Div. 28 | Electronic Safety & SecurityDiv. 28 | Electronic Safety & Security 14 21-Apr-17 04-May-17
ProSPA.28.1000 Security System - Subc 5 28-Apr-17 04-May-17
ProSPA.28.1050 Fire Alarm - Subc 5 21-Apr-17 27-Apr-17Div. 31 | EarthworkDiv. 31 | Earthwork 0 07-Feb-17 07-Feb-17
ProSPA.31.1000 Earthwork | Structural Excavation - Subc 0 07-Feb-17Div. 32 | Exterior ImprovementsDiv. 32 | Exterior Improvements 7 12-May-17 18-May-17
ProSPA.32.1000 Asphalt Paving - Subc 5 12-May-17 18-May-17
ProSPA.32.1050 Landscape | Irrigation - Subc 5 12-May-17 18-May-17
ProSPA.32.1100 Striping | Site Signage- Subc 5 12-May-17 18-May-17
ProSPA.32.1150 Brick Paving - Subc 5 12-May-17 18-May-17Div. 33 | UtilitiesDiv. 33 | Utilities 7 23-Mar-17 29-Mar-17
ProSPA.33.1000 Utilities - Subc 5 23-Mar-17 29-Mar-17
Submittals - Delivered | Reviewed | ApprovedSubmittals - Delivered | Reviewed | Approved 409 07-Feb-17 22-Mar-18Div. 01 | GeneralDiv. 01 | General 86 15-Feb-17 11-May-17
Sub.D.01.1000 01 29 73 | Schedule of Values 10 21-Apr-17 04-May-17
Sub.D.01.1050 01 31 19 | Pre-installation Meetings 10 21-Apr-17 04-May-17
Sub.D.01.1100 01 35 29 | Health, Safety, and Emergency Response Plan 10 15-Feb-17 28-Feb-17
Sub.D.01.1150 01 45 16 | Field Quality Control Procedures 10 15-Feb-17 28-Feb-17
Sub.D.01.1200 01 74 19 | Construction Waste Management & Disposal 10 15-Feb-17 28-Feb-17
Sub.D.01.1250 01 81 19 | Indoor Air Quality Requirements 10 28-Apr-17 11-May-17Div. 02 | Existing ConditionsDiv. 02 | Existing Conditions 7 07-Feb-17 13-Feb-17
Sub.D.02.1000 02 21 13 | Site Survey 5 07-Feb-17 13-Feb-17
Sub.D.02.1050 02 41 13 | Selective Site Demolition 5 07-Feb-17 13-Feb-17Div. 03 | ConcreteDiv. 03 | Concrete 206 21-Feb-17 14-Sep-17
Sub.D.03.1000 03 15 00 | Concrete Accessories 10 14-Mar-17 27-Mar-17
Sub.D.03.1050 03 20 00 | Concrete Reinforcing 15 14-Mar-17 03-Apr-17
Sub.D.03.1100 03 22 00 | Welded Wire Fabric Reinforcing 10 14-Mar-17 27-Mar-17
Sub.D.03.1150 03 30 00 | CIP Concrete Mix Designs 10 07-Mar-17 20-Mar-17
Sub.D.03.1200 03 39 00 | Concrete Curing 10 14-Mar-17 27-Mar-17
Sub.D.03.1250 03 40 00 | Precast Concrete 30 04-Aug-17 14-Sep-17
Sub.D.03.1300 03 60 00 | Grouting 15 21-Feb-17 13-Mar-17Div. 04 | MasonryDiv. 04 | Masonry 49 26-May-17 13-Jul-17
Sub.D.04.1000 04 05 16 | Masonry Grout 10 02-Jun-17 15-Jun-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
21-Apr-17 Spray Applied Fire Proofing - Subc
05-May-17 Joint Filler | Sealants - Subc
05-May-17 Miscellaneous Sheet Metal - Subc
14-Apr-17 18-May-17, Div. 08 | Doors & Windows05-May-17 Doors | Frames | Hardware - Subc
05-May-17 Access Controls - Subc
14-Apr-17 Storefront | Curtainwall - Subc
28-Apr-17 Fire Doors - Subc
12-May-17 Door | Hardware Install - Subc
05-May-17 Specialty Doors - Subc
05-May-17 11-May-17, Div. 09 | Finishes05-May-17 Painting - Subc
05-May-17 Tile - Subc
05-May-17 Carpet - Subc
05-May-17 Specialty Flooring - Subc
05-May-17 18-May-17, Div. 10 | Specialties12-May-17 Visual Displays - PA
12-May-17 Restroom Partitions | Accessories - PA
12-May-17 Lockers | Post Boxes - PA
05-May-17 DIRTT Partition Walls - Subc
12-May-17 Signage - Subc
12-May-17 13-Jul-17, Div. 11 | Equipment12-May-17 Audio | Visual Package - Subc
07-Jul-17 Audio-Video Package - FF&E
07-Jul-17 Food Service Equipment - FF&E
07-Jul-17 Healthcare Equipment - FF&E
16-Mar-17 18-May-17, Div. 12 | Furnishings12-May-17 Roller Window Shades - Subc
12-May-17 Lecterns - Subc
05-May-17 Auditorium Seating - Subc
16-Mar-17 Entrance Floor Mats & Frames - PA
12-May-17 Bicycle Racks - PA
12-May-17 Site Tables | Chairs | Trash Bins - PA
12-May-17 18-May-17, Div. 13 | Specialty Construction12-May-17 Water Feature | Fountain Equipment - PA
16-Mar-17 16-Mar-17, Div. 14 | Conveying Equipment16-Mar-17 Elevators - Subc
16-Mar-17 16-Mar-17, Div. 21 | Fire Suppression16-Mar-17 Fire Sprinkler - Subc
16-Mar-17 16-Mar-17, Div. 22 | Plumbing16-Mar-17 Plumbing | Wet Mechanical - Subc
16-Mar-17 20-Apr-17, Div. 23 | HVAC16-Mar-17 Dry Mechanical - Subc
14-Apr-17 Test & Balance - Subc
21-Apr-17 27-Apr-17, Div. 25 | Integrated Automation21-Apr-17 Building Automation System - Subc
16-Mar-17 16-Mar-17, Div. 26 | Electrical16-Mar-17 Electrical - Subc
28-Apr-17 04-May-17, Div. 27 | Communications28-Apr-17 Phone | Data - Subc
28-Apr-17 Phone Service - PA
21-Apr-17 04-May-17, Div. 28 | Electronic Safety & Security28-Apr-17 Security System - Subc
21-Apr-17 Fire Alarm - Subc
07-Feb-17 07-Feb-17, Div. 31 | Earthwork07-Feb-17 Earthwork | Structural Excavation - Subc
12-May-17 18-May-17, Div. 32 | Exterior Improvements12-May-17 Asphalt Paving - Subc
12-May-17 Landscape | Irrigation - Subc
12-May-17 Striping | Site Signage- Subc
12-May-17 Brick Paving - Subc
23-Mar-17 29-Mar-17, Div. 33 | Utilities23-Mar-17 Utilities - Subc
07-Feb-17 22-Mar-18, Submittals - Delivered | Reviewed | Approved
15-Feb-17 11-May-17, Div. 01 | General21-Apr-17 01 29 73 | Schedule of Values
21-Apr-17 01 31 19 | Pre-installation Meetings
15-Feb-17 01 35 29 | Health, Safety, and Emergency Response Plan
15-Feb-17 01 45 16 | Field Quality Control Procedures
15-Feb-17 01 74 19 | Construction Waste Management & Disposal
28-Apr-17 01 81 19 | Indoor Air Quality Requirements
07-Feb-17 13-Feb-17, Div. 02 | Existing Conditions07-Feb-17 02 21 13 | Site Survey
07-Feb-17 02 41 13 | Selective Site Demolition
21-Feb-17 14-Sep-17, Div. 03 | Concrete14-Mar-17 03 15 00 | Concrete Accessories
14-Mar-17 03 20 00 | Concrete Reinforcing
14-Mar-17 03 22 00 | Welded Wire Fabric Reinforcing
07-Mar-17 03 30 00 | CIP Concrete Mix Designs
14-Mar-17 03 39 00 | Concrete Curing
04-Aug-17 03 40 00 | Precast Concrete
21-Feb-17 03 60 00 | Grouting
26-May-17 13-Jul-17, Div. 04 | Masonry02-Jun-17 04 05 16 | Masonry Grout
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 2 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
Sub.D.04.1050 04 05 19 | Masonry Reinforcing 15 26-May-17 15-Jun-17
Sub.D.04.1100 04 05 23 | Masonry Accessories 10 26-May-17 08-Jun-17
Sub.D.04.1150 04 20 00 | Unit Masonry 15 26-May-17 15-Jun-17
Sub.D.04.1200 04 21 13 | Brick Masonry 20 16-Jun-17 13-Jul-17
Sub.D.04.1250 04 42 10 | Exterior Stone Cladding 20 16-Jun-17 13-Jul-17Div. 05 | MetalsDiv. 05 | Metals 85 23-Mar-17 15-Jun-17
Sub.D.05.0950 05 12 00 | Anchor Bolt Drawings 7 23-Mar-17 31-Mar-17
Sub.D.05.1000 05 12 00 | Structural Steel Framing 30 06-Apr-17 17-May-17
Sub.D.05.1050 05 30 00 | Metal Decking 10 13-Apr-17 26-Apr-17
Sub.D.05.1100 05 40 00 | Cold-Formed Metal Framing 15 26-May-17 15-Jun-17
Sub.D.05.1200 05 51 00 | Metal Stairs 15 20-Apr-17 10-May-17
Sub.D.05.1250 05 73 00 | Decorative Metal Railings 15 04-May-17 24-May-17Div. 06 | Woods, Plastics & CompositesDiv. 06 | Woods, Plastics & Composites 84 28-Jul-17 19-Oct-17
Sub.D.06.1000 06 10 53 | Miscellaneous Rough Carpentry 10 04-Aug-17 17-Aug-17
Sub.D.06.1050 06 16 43 | Gypsum Sheathing 10 28-Jul-17 10-Aug-17
Sub.D.06.1100 06 22 00 | Millwork 20 22-Sep-17 19-Oct-17
Sub.D.06.1150 06 40 00 | Architectural Woodwork 20 22-Sep-17 19-Oct-17
Sub.D.06.1200 06 41 13 | Wood-Veneer-Faced Architectural Cabinets 20 22-Sep-17 19-Oct-17
Sub.D.06.1250 06 42 16 | Wood Veneer Paneling 20 22-Sep-17 19-Oct-17
Sub.D.06.1300 06 61 16 | Solid Surfacing Fabrication 20 22-Sep-17 19-Oct-17Div. 07 | Thermal & Moisture ProtectionDiv. 07 | Thermal & Moisture Protection 248 07-Mar-17 09-Nov-17
Sub.D.07.1000 07 10 00 | Dampproofing and Waterproofing 10 07-Mar-17 20-Mar-17
Sub.D.07.1050 07 21 00 | Thermal Insulation 10 04-Aug-17 17-Aug-17
Sub.D.07.1100 07 22 00 | Roof & Deck Insulation 10 27-Oct-17 09-Nov-17
Sub.D.07.1150 07 26 16 | Below-Grade Vapor Retarders 10 07-Mar-17 20-Mar-17
Sub.D.07.1200 07 27 26 | Fluid-Applied Membrane Air Barriers 10 02-Jun-17 15-Jun-17
Sub.D.07.1250 07 41 13 | Metal Roof Panels 20 16-Jun-17 13-Jul-17
Sub.D.07.1300 07 42 13 | Metal Wall Panels 20 16-Jun-17 13-Jul-17
Sub.D.07.1350 07 54 00 | Thermoplastic Membrane Roofing 20 15-Sep-17 12-Oct-17
Sub.D.07.1400 07 60 00 | Flashing & Sheet Metal 15 09-Jun-17 29-Jun-17
Sub.D.07.1450 07 81 00 | Applied Fireproofing 10 12-May-17 25-May-17
Sub.D.07.1500 07 92 13 | Elastomeric Joint Sealants 10 23-Jun-17 06-Jul-17Div. 08 | Doors & WindowsDiv. 08 | Doors & Windows 140 12-May-17 28-Sep-17
Sub.D.08.1000 08 11 13 | Hollow Metal Doors & Frames 10 09-Jun-17 22-Jun-17
Sub.D.08.1050 08 12 16 | Aluminum Frames 15 12-May-17 01-Jun-17
Sub.D.08.1100 08 14 00 | Wood Doors 10 15-Sep-17 28-Sep-17
Sub.D.08.1150 08 31 00 | Access Doors & Panels 10 15-Sep-17 28-Sep-17
Sub.D.08.1200 08 33 00 | Coiling Doors & Grilles 15 14-Jul-17 03-Aug-17
Sub.D.08.1250 08 35 13 | Folding Fire Doors 15 14-Jul-17 03-Aug-17
Sub.D.08.1300 08 40 00 | Entrances, Storefronts, and Curtain Walls 45 16-Jun-17 17-Aug-17
Sub.D.08.1350 08 71 00 | Door Hardware 30 23-Jun-17 03-Aug-17
Sub.D.08.1400 08 81 00 | Glass Glazing 15 07-Jul-17 27-Jul-17Div. 09 | FinishesDiv. 09 | Finishes 175 02-Jun-17 23-Nov-17
Sub.D.09.1000 09 21 16 | Gypsum Board Assemblies 10 02-Jun-17 15-Jun-17
Sub.D.09.1050 09 22 16 | Non-Structural Metal Framing 15 02-Jun-17 22-Jun-17
Sub.D.09.1100 09 30 13 | Ceramic Tiling 20 29-Sep-17 26-Oct-17
Sub.D.09.1150 09 51 23 | Acoustical Tile Ceiling 15 22-Sep-17 12-Oct-17
Sub.D.09.1200 09 54 26 | Linear Wood Ceilings 20 22-Sep-17 19-Oct-17
Sub.D.09.1250 09 62 00 | Specialty Flooring 20 27-Oct-17 23-Nov-17
Sub.D.09.1300 09 68 13 | Tile Carpeting 20 27-Oct-17 23-Nov-17
Sub.D.09.1350 09 72 00 | Wall Coverings 15 27-Oct-17 16-Nov-17
Sub.D.09.1400 09 80 00 | Acoustical Treatment 10 23-Jun-17 06-Jul-17
Sub.D.09.1450 09 91 23 | Interior Painting 20 27-Oct-17 23-Nov-17
Sub.D.09.1500 09 96 00 | High Perfromance Coatings 20 27-Oct-17 23-Nov-17Div. 10 | SpecialtiesDiv. 10 | Specialties 147 30-Jun-17 23-Nov-17
Sub.D.10.1000 10 11 33 | Sliding Visual Display Units 15 01-Sep-17 21-Sep-17
Sub.D.10.1050 10 12 00 | Display Cases 15 18-Aug-17 07-Sep-17
Sub.D.10.1100 10 14 00 | Signage 15 03-Nov-17 23-Nov-17
Sub.D.10.1150 10 21 13 | Toilet Compartments 10 01-Sep-17 14-Sep-17
Sub.D.10.1200 10 22 19 | Demountable Partitions - DIRTT Wall System 30 25-Aug-17 05-Oct-17
Sub.D.10.1250 10 28 13 | Toilet Accessories 10 30-Jun-17 13-Jul-17
Sub.D.10.1300 10 51 16 | Wood Lockers 15 08-Sep-17 28-Sep-17
Sub.D.10.1350 10 55 00 | Postal Specialties 15 11-Aug-17 31-Aug-17
Sub.D.10.1400 10 71 13 | Exterior Sun Control Devices 30 07-Jul-17 17-Aug-17Div. 11 | EquipmentDiv. 11 | Equipment 84 05-May-17 27-Jul-17
Sub.D.11.1000 11 14 53 | Pedestrian Security Equipment 10 05-May-17 18-May-17
Sub.D.11.1050 11 40 00 | Food Service Equipment 10 14-Jul-17 27-Jul-17
Sub.D.11.1100 11 52 00 | Audio-Visual Equipment 10 14-Jul-17 27-Jul-17
Sub.D.11.1150 11 70 00 | Healthcare Equipment 10 14-Jul-17 27-Jul-17Div. 12 | FurnishingsDiv. 12 | Furnishings 239 30-Mar-17 23-Nov-17
Sub.D.12.1000 12 24 13 | Roller Window Shades 10 03-Nov-17 16-Nov-17
Sub.D.12.1150 12 36 61 | Simulated Stone Countertops 15 08-Sep-17 28-Sep-17
Sub.D.12.1200 12 48 13 | Entrance Floor Mats & Frames 10 30-Mar-17 12-Apr-17
Sub.D.12.1250 12 56 39 | Lecterns 15 22-Sep-17 12-Oct-17
Sub.D.12.1300 12 61 00 | Fixed Audience Seating 30 15-Sep-17 26-Oct-17
Sub.D.12.1350 12 93 00 | Site Furnishings 15 03-Nov-17 23-Nov-17
Sub.D.12.1400 12 93 13 | Bicycle Racks 10 03-Nov-17 16-Nov-17Div. 13 | Special ConstructionDiv. 13 | Special Construction 42 22-Sep-17 02-Nov-17
Sub.D.13.1000 13 12 13 | Exterior Fountains 30 22-Sep-17 02-Nov-17Div. 14 | Conveying EquipmentDiv. 14 | Conveying Equipment 28 13-Apr-17 10-May-17
Sub.D.14.1000 14 20 00 | Elevators 20 13-Apr-17 10-May-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
26-May-17 04 05 19 | Masonry Reinforcing
26-May-17 04 05 23 | Masonry Accessories
26-May-17 04 20 00 | Unit Masonry
16-Jun-17 04 21 13 | Brick Masonry
16-Jun-17 04 42 10 | Exterior Stone Cladding
23-Mar-17 15-Jun-17, Div. 05 | Metals23-Mar-17 05 12 00 | Anchor Bolt Drawings
06-Apr-17 05 12 00 | Structural Steel Framing
13-Apr-17 05 30 00 | Metal Decking
26-May-17 05 40 00 | Cold-Formed Metal Framing
20-Apr-17 05 51 00 | Metal Stairs
04-May-17 05 73 00 | Decorative Metal Railings
28-Jul-17 19-Oct-17, Div. 06 | Woods, Plastics & Composites04-Aug-17 06 10 53 | Miscellaneous Rough Carpentry
28-Jul-17 06 16 43 | Gypsum Sheathing
22-Sep-17 06 22 00 | Millwork
22-Sep-17 06 40 00 | Architectural Woodwork
22-Sep-17 06 41 13 | Wood-Veneer-Faced Architectural Cabinets
22-Sep-17 06 42 16 | Wood Veneer Paneling
22-Sep-17 06 61 16 | Solid Surfacing Fabrication
07-Mar-17 09-Nov-17, Div. 07 | Thermal & Moisture Protection07-Mar-17 07 10 00 | Dampproofing and Waterproofing
04-Aug-17 07 21 00 | Thermal Insulation
27-Oct-17 07 22 00 | Roof & Deck Insulation
07-Mar-17 07 26 16 | Below-Grade Vapor Retarders
02-Jun-17 07 27 26 | Fluid-Applied Membrane Air Barriers
16-Jun-17 07 41 13 | Metal Roof Panels
16-Jun-17 07 42 13 | Metal Wall Panels
15-Sep-17 07 54 00 | Thermoplastic Membrane Roofing
09-Jun-17 07 60 00 | Flashing & Sheet Metal
12-May-17 07 81 00 | Applied Fireproofing
23-Jun-17 07 92 13 | Elastomeric Joint Sealants
12-May-17 28-Sep-17, Div. 08 | Doors & Windows09-Jun-17 08 11 13 | Hollow Metal Doors & Frames
12-May-17 08 12 16 | Aluminum Frames
15-Sep-17 08 14 00 | Wood Doors
15-Sep-17 08 31 00 | Access Doors & Panels
14-Jul-17 08 33 00 | Coiling Doors & Grilles
14-Jul-17 08 35 13 | Folding Fire Doors
16-Jun-17 08 40 00 | Entrances, Storefronts, and Curtain Walls
23-Jun-17 08 71 00 | Door Hardware
07-Jul-17 08 81 00 | Glass Glazing
02-Jun-17 23-Nov-17, Div. 09 | Finishes02-Jun-17 09 21 16 | Gypsum Board Assemblies
02-Jun-17 09 22 16 | Non-Structural Metal Framing
29-Sep-17 09 30 13 | Ceramic Tiling
22-Sep-17 09 51 23 | Acoustical Tile Ceiling
22-Sep-17 09 54 26 | Linear Wood Ceilings
27-Oct-17 09 62 00 | Specialty Flooring
27-Oct-17 09 68 13 | Tile Carpeting
27-Oct-17 09 72 00 | Wall Coverings
23-Jun-17 09 80 00 | Acoustical Treatment
27-Oct-17 09 91 23 | Interior Painting
27-Oct-17 09 96 00 | High Perfromance Coatings
30-Jun-17 23-Nov-17, Div. 10 | Specialties01-Sep-17 10 11 33 | Sliding Visual Display Units
18-Aug-17 10 12 00 | Display Cases
03-Nov-17 10 14 00 | Signage
01-Sep-17 10 21 13 | Toilet Compartments
25-Aug-17 10 22 19 | Demountable Partitions - DIRTT Wall System
30-Jun-17 10 28 13 | Toilet Accessories
08-Sep-17 10 51 16 | Wood Lockers
11-Aug-17 10 55 00 | Postal Specialties
07-Jul-17 10 71 13 | Exterior Sun Control Devices
05-May-17 27-Jul-17, Div. 11 | Equipment05-May-17 11 14 53 | Pedestrian Security Equipment
14-Jul-17 11 40 00 | Food Service Equipment
14-Jul-17 11 52 00 | Audio-Visual Equipment
14-Jul-17 11 70 00 | Healthcare Equipment
30-Mar-17 23-Nov-17, Div. 12 | Furnishings03-Nov-17 12 24 13 | Roller Window Shades
08-Sep-17 12 36 61 | Simulated Stone Countertops
30-Mar-17 12 48 13 | Entrance Floor Mats & Frames
22-Sep-17 12 56 39 | Lecterns
15-Sep-17 12 61 00 | Fixed Audience Seating
03-Nov-17 12 93 00 | Site Furnishings
03-Nov-17 12 93 13 | Bicycle Racks
22-Sep-17 02-Nov-17, Div. 13 | Special Construction22-Sep-17 13 12 13 | Exterior Fountains
13-Apr-17 10-May-17, Div. 14 | Conveying Equipment13-Apr-17 14 20 00 | Elevators
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 3 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
Div. 21 | Fire SuppressionDiv. 21 | Fire Suppression 42 30-Mar-17 10-May-17Sub.D.21.1000 21 13 13 | Wet-Pipe Sprinkler System 30 30-Mar-17 10-May-17
Div. 22 | PlumbingDiv. 22 | Plumbing 224 23-Mar-17 01-Nov-17Sub.D.22.1000 22 05 29 | Hangers & Supports for Plumbing Piping & Equipment 15 06-Apr-17 26-Apr-17
Sub.D.22.1050 22 10 00 | Plumbing Piping & Pumps 15 12-Oct-17 01-Nov-17
Sub.D.22.1100 22 11 16 | Domestic Water Piping 15 23-Mar-17 12-Apr-17
Sub.D.22.1150 22 13 16 | Sanitary Waste & Vent Piping 15 23-Mar-17 12-Apr-17
Sub.D.22.1200 22 14 13 | Facility Storm Drainage Piping 15 23-Mar-17 12-Apr-17
Sub.D.22.1250 22 34 00 | Fuel-Fired Domestic Water Heaters 15 06-Apr-17 26-Apr-17
Sub.D.22.1300 22 40 00 | Plumbing Fixtures 15 27-Apr-17 17-May-17
Sub.D.22.1350 22 52 00 | Fountain Plumbing System 15 08-Jun-17 28-Jun-17Div. 23 | HVACDiv. 23 | HVAC 63 13-Apr-17 14-Jun-17
Sub.D.23.1000 23 09 13 | Instrumentation and Control Devices for HVAC 20 18-May-17 14-Jun-17
Sub.D.23.1050 23 09 93 | Sequence of Operations for HVAC Controls 20 18-May-17 14-Jun-17
Sub.D.23.1100 23 11 23 | Natural-Gas Piping 10 13-Apr-17 26-Apr-17
Sub.D.23.1150 23 31 13 | Metal Ducts 15 27-Apr-17 17-May-17
Sub.D.23.1200 23 32 33 | Air-Distribution Ceiling Plenums 15 27-Apr-17 17-May-17
Sub.D.23.1250 23 36 16 | Variable-Air-Volume Units 20 27-Apr-17 24-May-17
Sub.D.23.1300 23 37 13 | Diffusers, Registers, and Grilles 15 18-May-17 07-Jun-17
Sub.D.23.1350 23 52 00 | Heating Boilers 20 27-Apr-17 24-May-17
Sub.D.23.1400 23 74 00 | Packaged Outdoor HVAC Equipment 20 27-Apr-17 24-May-17
Sub.D.23.1450 23 81 26 | Split-System Air-Conditioners 20 18-May-17 14-Jun-17Div. 25 | Integrated AutomationDiv. 25 | Integrated Automation 42 13-Oct-17 23-Nov-17
Sub.D.25.1000 Conductors & Cables for Integrated Automation 10 13-Oct-17 26-Oct-17
Sub.D.25.1050 25 10 00 | Integrated Automation Network Equipment 15 13-Oct-17 02-Nov-17
Sub.D.25.1100 25 90 00 | Integrated Automation Control Sequences 30 13-Oct-17 23-Nov-17Div. 26 | ElectricalDiv. 26 | Electrical 91 06-Apr-17 05-Jul-17
Sub.D.26.1000 26 05 33 | Raceway & Boxes for Electrical System 10 13-Apr-17 26-Apr-17
Sub.D.26.1050 26 05 73 | Overcurrent Protective Devices Coordination Study 20 18-May-17 14-Jun-17
Sub.D.26.1100 26 09 23 | Lighting Control Devices 15 27-Apr-17 17-May-17
Sub.D.26.1150 26 12 00 | Medium-Voltage Transformers 15 06-Apr-17 26-Apr-17
Sub.D.26.1200 26 13 13 | Medium-Voltage Circuit Breaker Switchgear 15 06-Apr-17 26-Apr-17
Sub.D.26.1250 26 24 13 | Switchboards | gear 15 27-Apr-17 17-May-17
Sub.D.26.1300 26 24 16 | Panelboards 15 27-Apr-17 17-May-17
Sub.D.26.1350 26 51 13 | Interior Lighting Fixtures, Lamps & Ballasts 20 08-Jun-17 05-Jul-17Div. 27 | CommunicationsDiv. 27 | Communications 0Div. 28 | Electronic Safety & SecurityDiv. 28 | Electronic Safety & Security 63 16-Jun-17 17-Aug-17
Sub.D.28.1000 28 13 00 | Access Control 30 16-Jun-17 27-Jul-17
Sub.D.28.1050 28 16 00 | Intrusion Detection 30 16-Jun-17 27-Jul-17
Sub.D.28.1100 28 20 00 | Electronic Surveilance 30 16-Jun-17 27-Jul-17
Sub.D.28.1150 28 31 00 | Fire Detection & Alarm 20 21-Jul-17 17-Aug-17Div. 31 | EarthworkDiv. 31 | Earthwork 0Div. 32 | Exterior ImprovementsDiv. 32 | Exterior Improvements 388 28-Feb-17 22-Mar-18
Sub.D.32.1000 32 11 00 | Base Courses 10 28-Feb-17 13-Mar-17
Sub.D.32.1050 32 12 16 | Asphalt Paving 10 15-Dec-17 28-Dec-17
Sub.D.32.1100 32 13 16 | Concrete Paving 10 08-Aug-17 21-Aug-17
Sub.D.32.1150 32 13 16 | Decorative Concrete Paving 30 08-Aug-17 18-Sep-17
Sub.D.32.1200 32 14 16 | Brick Unit Paving 15 03-Nov-17 23-Nov-17
Sub.D.32.1250 32 16 00 | Concrete Curb & Gutter 10 08-Dec-17 21-Dec-17
Sub.D.32.1300 32 17 23 | Pavement Markings 10 15-Dec-17 28-Dec-17
Sub.D.32.1350 32 17 26 | Tactile Warning Surfacing 10 27-Jun-17 10-Jul-17
Sub.D.32.1400 32 80 00 | Irrigation 15 15-Dec-17 04-Jan-18
Sub.D.32.1450 32 91 13 | Soil Preparation 10 15-Dec-17 28-Dec-17
Sub.D.32.1500 32 93 43 | Trees 20 23-Feb-18 22-Mar-18Div. 33 | UtilitiesDiv. 33 | Utilities 14 06-Apr-17 19-Apr-17
Sub.D.33.1000 33 11 00 | Water Utility Distribution Piping 10 06-Apr-17 19-Apr-17
Sub.D.33.1050 33 31 00 | Sanitary Utility Sewerage Piping 10 06-Apr-17 19-Apr-17
Sub.D.33.1100 33 41 00 | Storm Utility Drainage Piping 10 06-Apr-17 19-Apr-17
Material Lead Time | DeliveryMaterial Lead Time | Delivery 0Div. 03 | ConcreteDiv. 03 | Concrete 0Div. 04 | MasonryDiv. 04 | Masonry 0Div. 05 | MetalsDiv. 05 | Metals 0Div. 06 | Woods, Plastics & CompositesDiv. 06 | Woods, Plastics & Composites 0Div. 07 | Thermal & Moisture ProtectionDiv. 07 | Thermal & Moisture Protection 0Div. 08 | Doors & WindowsDiv. 08 | Doors & Windows 0Div. 09 | FinishesDiv. 09 | Finishes 0Div. 10 | SpecialtiesDiv. 10 | Specialties 0Div. 11 | EquipmentDiv. 11 | Equipment 0Div. 12 | FurnishingsDiv. 12 | Furnishings 0Div. 13 | Special ConstructionDiv. 13 | Special Construction 0Div. 14 | Conveying EquipmentDiv. 14 | Conveying Equipment 0Div. 21 | Fire SuppressionDiv. 21 | Fire Suppression 0Div. 22 | PlumbingDiv. 22 | Plumbing 0Div. 23 | HVACDiv. 23 | HVAC 0Div. 25 | Integrated AutomationDiv. 25 | Integrated Automation 0Div. 26 | ElectricalDiv. 26 | Electrical 0Div. 27 | CommunicationsDiv. 27 | Communications 0Div. 28 | Electronic Safety & SecurityDiv. 28 | Electronic Safety & Security 0Div. 31 | EarthworkDiv. 31 | Earthwork 0Div. 32 | Exterior ImprovementsDiv. 32 | Exterior Improvements 0Div. 33 | UtilitiesDiv. 33 | Utilities 0
ConstructionConstruction 548 08-Feb-17 10-Aug-18
Pre-Installation | Mock-Up | CoordinationPre-Installation | Mock-Up | Coordination 463 09-Feb-17 18-May-18
Div. 01 | GeneralDiv. 01 | General 96 30-Mar-17 04-Jul-17
ConPIC.01.1000 BIM Coordination Kick-Off Meeting 0 30-Mar-17
ConPIC.01.1050 BIM Clash Detection | Resolution Meetings 30 06-Apr-17 17-May-17
ConPIC.01.1100 BIM Field Coordination Meeting - 1st Floor East 0 06-Jun-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
30-Mar-17 10-May-17, Div. 21 | Fire Suppression30-Mar-17 21 13 13 | Wet-Pipe Sprinkler System
23-Mar-17 01-Nov-17, Div. 22 | Plumbing06-Apr-17 22 05 29 | Hangers & Supports for Plumbing Piping & Equipment
12-Oct-17 22 10 00 | Plumbing Piping & Pumps
23-Mar-17 22 11 16 | Domestic Water Piping
23-Mar-17 22 13 16 | Sanitary Waste & Vent Piping
23-Mar-17 22 14 13 | Facility Storm Drainage Piping
06-Apr-17 22 34 00 | Fuel-Fired Domestic Water Heaters
27-Apr-17 22 40 00 | Plumbing Fixtures
08-Jun-17 22 52 00 | Fountain Plumbing System
13-Apr-17 14-Jun-17, Div. 23 | HVAC18-May-17 23 09 13 | Instrumentation and Control Devices for HVAC
18-May-17 23 09 93 | Sequence of Operations for HVAC Controls
13-Apr-17 23 11 23 | Natural-Gas Piping
27-Apr-17 23 31 13 | Metal Ducts
27-Apr-17 23 32 33 | Air-Distribution Ceiling Plenums
27-Apr-17 23 36 16 | Variable-Air-Volume Units
18-May-17 23 37 13 | Diffusers, Registers, and Grilles
27-Apr-17 23 52 00 | Heating Boilers
27-Apr-17 23 74 00 | Packaged Outdoor HVAC Equipment
18-May-17 23 81 26 | Split-System Air-Conditioners
13-Oct-17 23-Nov-17, Div. 25 | Integrated Automation13-Oct-17 Conductors & Cables for Integrated Automation
13-Oct-17 25 10 00 | Integrated Automation Network Equipment
13-Oct-17 25 90 00 | Integrated Automation Control Sequences
06-Apr-17 05-Jul-17, Div. 26 | Electrical13-Apr-17 26 05 33 | Raceway & Boxes for Electrical System
18-May-17 26 05 73 | Overcurrent Protective Devices Coordination Study
27-Apr-17 26 09 23 | Lighting Control Devices
06-Apr-17 26 12 00 | Medium-Voltage Transformers
06-Apr-17 26 13 13 | Medium-Voltage Circuit Breaker Switchgear
27-Apr-17 26 24 13 | Switchboards | gear
27-Apr-17 26 24 16 | Panelboards
08-Jun-17 26 51 13 | Interior Lighting Fixtures, Lamps & Ballasts
16-Jun-17 17-Aug-17, Div. 28 | Electronic Safety & Security16-Jun-17 28 13 00 | Access Control
16-Jun-17 28 16 00 | Intrusion Detection
16-Jun-17 28 20 00 | Electronic Surveilance
21-Jul-17 28 31 00 | Fire Detection & Alarm
28-Feb-17 22-Mar-18, Div. 32 | Exterior Improvements28-Feb-17 32 11 00 | Base Courses
15-Dec-17 32 12 16 | Asphalt Paving
08-Aug-17 32 13 16 | Concrete Paving
08-Aug-17 32 13 16 | Decorative Concrete Paving
03-Nov-17 32 14 16 | Brick Unit Paving
08-Dec-17 32 16 00 | Concrete Curb & Gutter
15-Dec-17 32 17 23 | Pavement Markings
27-Jun-17 32 17 26 | Tactile Warning Surfacing
15-Dec-17 32 80 00 | Irrigation
15-Dec-17 32 91 13 | Soil Preparation
23-Feb-18 32 93 43 | Trees
06-Apr-17 19-Apr-17, Div. 33 | Utilities06-Apr-17 33 11 00 | Water Utility Distribution Piping
06-Apr-17 33 31 00 | Sanitary Utility Sewerage Piping
06-Apr-17 33 41 00 | Storm Utility Drainage Piping
08-Feb-17 10-Aug-18, Construction
09-Feb-17 18-May-18, Pre-Installation | Mock-Up | Coordination
30-Mar-17 04-Jul-17, Div. 01 | General
30-Mar-17 BIM Coordination Kick-Off Meeting
06-Apr-17 BIM Clash Detection | Resolution Meetings
06-Jun-17 BIM Field Coordination Meeting - 1st Floor East
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 4 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConPIC.01.1150 BIM Field Coordination Meeting - 1st Floor North 0 09-Jun-17
ConPIC.01.1200 BIM Field Coordination Meeting - 2nd Floor North 0 19-Jun-17
ConPIC.01.1250 BIM Field Coordination Meeting - 3rd Floor North 0 04-Jul-17
Div. 02 | Existing ConditionsDiv. 02 | Existing Conditions 0 09-Feb-17 09-Feb-17
ConPIC.02.1000 Surveyor Pre-Start Meeting 0 09-Feb-17
Div. 03 | ConcreteDiv. 03 | Concrete 399 12-Apr-17 16-May-18
ConPIC.03.0950 Concrete Foundations Pre-install Meeting 0 12-Apr-17
ConPIC.03.1000 Slab On Grade Pre-Install Meeting 0 02-Jun-17
ConPIC.03.1050 Slab on Deck Pre-Install Meeting 0 26-May-17
ConPIC.03.1100 Decorative Concrete Paving Mock-Up Panels 0 27-Apr-18
ConPIC.03.1150 Decorative Concrete Paving Pre-Install Meeting 0 16-May-18
Div. 04 | MasonryDiv. 04 | Masonry 14 09-Aug-17 23-Aug-17
ConPIC.04.1000 Stone Veneer Mock-Up Wall Panel 0 09-Aug-17
ConPIC.04.1050 Stone Veneer Pre-Install Meeting 0 23-Aug-17
Div. 05 | MetalsDiv. 05 | Metals 91 06-Apr-17 06-Jul-17
ConPIC.05.1000 Steel Fab Plant Inspection | Mill Certs 0 13-Apr-17
ConPIC.05.1050 Pre-Fabrication Sequence Loading Coordination Meeting 0 06-Apr-17
ConPIC.05.1100 Steel Erection Pre-Install Meeting 0 18-Apr-17
ConPIC.05.1150 Structural Framing Pre-Install Meeting 0 20-Jun-17
ConPIC.05.1200 Decorative Metal Railing Mock-Up 0 06-Jul-17
Div. 06 | Woods, Plastics & CompositesDiv. 06 | Woods, Plastics & Composites 19 10-Nov-17 29-Nov-17
ConPIC.06.1000 Architectural Millwork Pre-Fab Meeting 0 10-Nov-17
ConPIC.06.1050 Wood Panel Pre-Install Meeting 0 29-Nov-17
Div. 07 | Thermal & Moisture ProtectionDiv. 07 | Thermal & Moisture Protection 199 06-Mar-17 21-Sep-17
ConPIC.07.1050 Waterproofing Pre-Install Meeting 0 06-Mar-17
ConPIC.07.1100 Fluid Applied Air Barrier Pre-Install Meeting | Mock-Up 0 14-Jul-17
ConPIC.07.1150 Spray Applied Fire Proofing Pre-Install Meeting 0 13-Jun-17
ConPIC.07.1200 Metal Wall Panel Mock-Up 0 07-Sep-17
ConPIC.07.1250 Metal Wall Panel Pre-Install Meeting 0 21-Sep-17
ConPIC.07.1300 TPO Roofing Pre-Install Meeting 0 31-Aug-17
ConPIC.07.1350 Metal Flashings Pre-Install Meeting 0 10-Jul-17
Div. 08 | Doors & WindowsDiv. 08 | Doors & Windows 78 03-Aug-17 20-Oct-17
ConPIC.08.1000 Storefront | Curtainwall Pre-Install Meeting 0 13-Oct-17
ConPIC.08.1050 Interior Door Frames Pre-Install Meeting 0 03-Aug-17
ConPIC.08.1100 Doors | Hardware Pre-Install Meeting 0 20-Oct-17
ConPIC.08.1150 Access Controls Rough-in Coordination Kick-Off Meeting 0 18-Aug-17
Div. 09 | FinishesDiv. 09 | Finishes 180 13-Sep-17 12-Mar-18
ConPIC.09.1000 Tile Pre-Install Meeting 0 18-Sep-17
ConPIC.09.1050 Paint Pre-Install Meeting 0 13-Sep-17
ConPIC.09.1100 Carpet Pre-Install Meeting 0 12-Mar-18
Div. 10 | SpecialtiesDiv. 10 | Specialties 24 20-Oct-17 13-Nov-17
ConPIC.10.1000 DIRTT Partition Wall Pre-Install Meeting 0 20-Oct-17
ConPIC.10.1050 Restroom Partitions | Accessories Pre-Install Meeting 0 13-Nov-17
Div. 11 | SpecialtiesDiv. 11 | Specialties 0Div. 12 | FurnishingsDiv. 12 | Furnishings 68 17-Jan-18 26-Mar-18
ConPIC.12.1000 Lecture Hall Stadium Seating Coordination Meeting 0 17-Jan-18
ConPIC.12.1050 Lecture Hall Stadium Seating Pre-Install Meeting 0 26-Mar-18
Div. 13 | Special ConstructionDiv. 13 | Special Construction 0Div. 14 | Conveying EquipmentDiv. 14 | Conveying Equipment 146 21-Sep-17 14-Feb-18
ConPIC.14.1000 DBS Elevator Shaft Inspection 0 21-Sep-17
ConPIC.14.1050 Elevator Pre-Install Checklist 0 06-Nov-17
ConPIC.14.1100 Elevator Pre-Install Meeting 0 14-Feb-18
Div. 21 | Fire SuppressionDiv. 21 | Fire Suppression 89 30-Mar-17 27-Jun-17
ConPIC.21.1000 Fire Flow Verification 0 30-Mar-17
ConPIC.21.1050 Fire Sprinkler Pre-Install Meeting 0 27-Jun-17
Div. 22 | PlumbingDiv. 22 | Plumbing 149 08-May-17 04-Oct-17
ConPIC.22.1000 Below Grade Plumbing Pre-Install Meeting 0 08-May-17
ConPIC.22.1050 Above Grade | Suspended Plumbing Pre-Install Meeting 0 03-Aug-17
ConPIC.22.1100 Restroom Fixtures Pre-Install Meeting 0 04-Oct-17
Div. 23 | HVACDiv. 23 | HVAC 295 11-Jul-17 02-May-18
ConPIC.23.1000 HVAC Ductwork | Installation Pre-Install Meeting 0 11-Jul-17
ConPIC.23.1050 Roof Top Equipment Pre-Install Meeting 0 25-Sep-17
ConPIC.23.1100 TAB Pre-Start Meeting 0 02-May-18
Div. 25 | Integrated AutomationDiv. 25 | Integrated Automation 7 09-May-18 16-May-18
ConPIC.25.1000 Sequence of Controls Coordination Meetings 0 09-May-18
ConPIC.25.1050 BAS | Programming Pre-Install Meeting 0 16-May-18
Div. 26 | ElectricalDiv. 26 | Electrical 233 08-May-17 27-Dec-17
ConPIC.26.1000 Electrical Underground Pre-Install Meeting 0 08-May-17
ConPIC.26.1050 Electrical Rough-In Pre-Install Meeting 0 13-Jul-17
ConPIC.26.1100 Pre-Building Energize Coordination Meeting 0 27-Dec-17
Div. 27 | CommunicationsDiv. 27 | Communications 62 09-Aug-17 10-Oct-17
ConPIC.27.1000 Communications Rough-In Coordination Meeting 0 09-Aug-17
ConPIC.27.1050 Communications Cabling Pre-Install Meeting 0 10-Oct-17
Div. 28 | Electronic Safety & SecurityDiv. 28 | Electronic Safety & Security 282 09-Aug-17 18-May-18
ConPIC.28.1000 Access Controls | Door Hardware Coordination Meetings 0 09-Aug-17
ConPIC.28.1050 Security Rough-In Coordination Meeting 0 09-Aug-17
ConPIC.28.1100 Security Pre-Install Meeting 0 18-May-18
Div. 31 | EarthworkDiv. 31 | Earthwork 0 13-Feb-17 13-Feb-17
ConPIC.31.1000 Mass Excavation Pre-Start Coordination Meeting 0 13-Feb-17
Div. 32 | Exterior ImprovementsDiv. 32 | Exterior Improvements 0 17-Apr-18 17-Apr-18
ConPIC.32.1000 Water Feature | Fountain Pre-install Meeting 0 17-Apr-18
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
09-Jun-17 BIM Field Coordination Meeting - 1st Floor North
19-Jun-17 BIM Field Coordination Meeting - 2nd Floor North
04-Jul-17 BIM Field Coordination Meeting - 3rd Floor North
09-Feb-17 09-Feb-17, Div. 02 | Existing Conditions
09-Feb-17 Surveyor Pre-Start Meeting
12-Apr-17 16-May-18, Div. 03 | Concrete
12-Apr-17 Concrete Foundations Pre-install Meeting
02-Jun-17 Slab On Grade Pre-Install Meeting
26-May-17 Slab on Deck Pre-Install Meeting
27-Apr-18 Decorative Concrete Paving Mock-Up Panels
16-May-18 Decorative Concrete Paving Pre-Install Meeting
09-Aug-17 23-Aug-17, Div. 04 | Masonry
09-Aug-17 Stone Veneer Mock-Up Wall Panel
23-Aug-17 Stone Veneer Pre-Install Meeting
06-Apr-17 06-Jul-17, Div. 05 | Metals
13-Apr-17 Steel Fab Plant Inspection | Mill Certs
06-Apr-17 Pre-Fabrication Sequence Loading Coordination Meeting
18-Apr-17 Steel Erection Pre-Install Meeting
20-Jun-17 Structural Framing Pre-Install Meeting
06-Jul-17 Decorative Metal Railing Mock-Up
10-Nov-17 29-Nov-17, Div. 06 | Woods, Plastics & Composites
10-Nov-17 Architectural Millwork Pre-Fab Meeting
29-Nov-17 Wood Panel Pre-Install Meeting
06-Mar-17 21-Sep-17, Div. 07 | Thermal & Moisture Protection
06-Mar-17 Waterproofing Pre-Install Meeting
14-Jul-17 Fluid Applied Air Barrier Pre-Install Meeting | Mock-Up
13-Jun-17 Spray Applied Fire Proofing Pre-Install Meeting
07-Sep-17 Metal Wall Panel Mock-Up
21-Sep-17 Metal Wall Panel Pre-Install Meeting
31-Aug-17 TPO Roofing Pre-Install Meeting
10-Jul-17 Metal Flashings Pre-Install Meeting
03-Aug-17 20-Oct-17, Div. 08 | Doors & Windows
13-Oct-17 Storefront | Curtainwall Pre-Install Meeting
03-Aug-17 Interior Door Frames Pre-Install Meeting
20-Oct-17 Doors | Hardware Pre-Install Meeting
18-Aug-17 Access Controls Rough-in Coordination Kick-Off Meeting
13-Sep-17 12-Mar-18, Div. 09 | Finishes
18-Sep-17 Tile Pre-Install Meeting
13-Sep-17 Paint Pre-Install Meeting
12-Mar-18 Carpet Pre-Install Meeting
20-Oct-17 13-Nov-17, Div. 10 | Specialties
20-Oct-17 DIRTT Partition Wall Pre-Install Meeting
13-Nov-17 Restroom Partitions | Accessories Pre-Install Meeting
17-Jan-18 26-Mar-18, Div. 12 | Furnishings
17-Jan-18 Lecture Hall Stadium Seating Coordination Meeting
26-Mar-18 Lecture Hall Stadium Seating Pre-Install Meeting
21-Sep-17 14-Feb-18, Div. 14 | Conveying Equipment
21-Sep-17 DBS Elevator Shaft Inspection
06-Nov-17 Elevator Pre-Install Checklist
14-Feb-18 Elevator Pre-Install Meeting
30-Mar-17 27-Jun-17, Div. 21 | Fire Suppression
30-Mar-17 Fire Flow Verification
27-Jun-17 Fire Sprinkler Pre-Install Meeting
08-May-17 04-Oct-17, Div. 22 | Plumbing
08-May-17 Below Grade Plumbing Pre-Install Meeting
03-Aug-17 Above Grade | Suspended Plumbing Pre-Install Meeting
04-Oct-17 Restroom Fixtures Pre-Install Meeting
11-Jul-17 02-May-18, Div. 23 | HVAC
11-Jul-17 HVAC Ductwork | Installation Pre-Install Meeting
25-Sep-17 Roof Top Equipment Pre-Install Meeting
02-May-18 TAB Pre-Start Meeting
09-May-18 16-May-18, Div. 25 | Integrated Automation
09-May-18 Sequence of Controls Coordination Meetings
16-May-18 BAS | Programming Pre-Install Meeting
08-May-17 27-Dec-17, Div. 26 | Electrical
08-May-17 Electrical Underground Pre-Install Meeting
13-Jul-17 Electrical Rough-In Pre-Install Meeting
27-Dec-17 Pre-Building Energize Coordination Meeting
09-Aug-17 10-Oct-17, Div. 27 | Communications
09-Aug-17 Communications Rough-In Coordination Meeting
10-Oct-17 Communications Cabling Pre-Install Meeting
09-Aug-17 18-May-18, Div. 28 | Electronic Safety & Security
09-Aug-17 Access Controls | Door Hardware Coordination Meetings
09-Aug-17 Security Rough-In Coordination Meeting
18-May-18 Security Pre-Install Meeting
13-Feb-17 13-Feb-17, Div. 31 | Earthwork
13-Feb-17 Mass Excavation Pre-Start Coordination Meeting
17-Apr-18 17-Apr-18, Div. 32 | Exterior Improvements
17-Apr-18 Water Feature | Fountain Pre-install Meeting
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 5 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
Div. 33 | UtilitiesDiv. 33 | Utilities 0 13-Apr-17 13-Apr-17
ConPIC.33.1000 Underground Utilities Pre-Install Meeting 0 13-Apr-17 13-Apr-17
Building PadBuilding Pad 79 08-Feb-17 27-Apr-17
ConBP1000 On-site mobilization | Trailer Set-up 2 08-Feb-17 09-Feb-17
ConBP1050 Site Fencing | SWPPP BMPs 2 09-Feb-17 10-Feb-17
ConBP1100 Site Signage | Postings 2 09-Feb-17 10-Feb-17
ConBP1150 Control | Surface Demo Survey 2 10-Feb-17 13-Feb-17
ConBP1200 Surface Structure Demolition | Decommission 4 14-Feb-17 17-Feb-17
ConBP1250 Building Pad Over-excavation (5') | Subgrade Compaction 12 20-Feb-17 07-Mar-17
ConBP1275 Elevator Pit Foundation Waterproofing Membrane 1 08-Mar-17 08-Mar-17
ConBP1300 Elevator Pit Foundations | Walls 7 09-Mar-17 17-Mar-17
ConBP1350 Building Pad Structural Fill | Partial Subgrade 6 16-Mar-17 23-Mar-17
ConBP1375 East Wing Footing | Foundation Waterproofing Mebrane 3 24-Mar-17 28-Mar-17
ConBP1400 East Wing Spread | Continuous Footings 7 03-Apr-17 11-Apr-17
ConBP1450 East Wing Concrete Stem Walls | Rigid Insulation 5 07-Apr-17 13-Apr-17
ConBP1500 East Wing Structural Fill | Finish Subgrade 6 12-Apr-17 19-Apr-17
ConBP1550 East Wing Pad Certification | Grade & Compaction 2 19-Apr-17 20-Apr-17
ConBP1600 North Wing Footing | Foundation Waterproofing Membrane 3 29-Mar-17 31-Mar-17
ConBP1650 North Wing Spread | Continuous Footings 8 10-Apr-17 19-Apr-17
ConBP1700 North Wing Concrete Stem Walls | Rigid Insulation 6 17-Apr-17 24-Apr-17
ConBP1750 North Wing Structural Fill | Finish Subgrade 5 21-Apr-17 27-Apr-17
ConBP1800 North Wing Pad Certification | Grade & Compaction 0 27-Apr-17
Site DevelopmentSite Development 416 17-Apr-17 06-Jun-18
ConSD1000 Utilies Survey 1 17-Apr-17 17-Apr-17
ConSD1050 Idaho Power Service | Joint Trench 9 17-Apr-17 27-Apr-17
ConSD1100 Idaho Power Temporary Service Set 5 28-Apr-17 04-May-17
ConSD1150 Intermountain Gas Service Line 5 28-Apr-17 04-May-17
ConSD1200 Sanitary Sewerage Trench | Piping - 5' outside 5 18-Apr-17 24-Apr-17
ConSD1250 Storm Service Trench | Piping - 5' outside 5 25-Apr-17 01-May-17
ConSD1300 Building Water Main Service - 5' outside 5 02-May-17 08-May-17
ConSD1350 Fire Service Line | Hydrant Risers - Inside Building Manifold 5 09-May-17 15-May-17
ConSD1400 Idaho Power Building Transformer Set 0 09-Jun-17
ConSD1450 Intermountain Gas Manifold | Meter Set 0 08-Sep-17
ConSD1800 East Site Finish Subgrade 3 14-Feb-18 16-Feb-18
ConSD1850 East Site Electrical Rough-In | Lighting 4 19-Feb-18 22-Feb-18
ConSD1900 East Site Irrigation Rough-In 4 19-Feb-18 22-Feb-18
ConSD1950 East Site Curb & Gutter 4 23-Feb-18 28-Feb-18
ConSD2000 East Site Sidewalk Fine Grade | Concrete Placement 7 01-Mar-18 09-Mar-18
ConSD2750 North Site Finish Subgrade 3 19-Feb-18 21-Feb-18
ConSD2800 North Site Utility Grade Set 1 22-Feb-18 22-Feb-18
ConSD2850 North Site Electrical Rough-In | Lighting 4 22-Feb-18 27-Feb-18
ConSD2900 North Site Irrigation Rough-In 4 22-Feb-18 27-Feb-18
ConSD2950 North Site Curb & Gutter | Concrete Landscape Edging 5 28-Feb-18 06-Mar-18
ConSD3000 North Site Sidewalk Fine Grade | Concrete Placement 9 07-Mar-18 19-Mar-18
ConSD3050 North Site Sidewalk Runnels 3 20-Mar-18 22-Mar-18
ConSD3100 North Site Landscape Topsoil | Irrigation 5 07-Mar-18 13-Mar-18
ConSD3150 North Site Landscape Sod | Plantings | Ground Cover 5 14-Mar-18 20-Mar-18
ConSD4200 West Site Finish Subgrade 4 11-Apr-18 16-Apr-18
ConSD4250 West Site Utility Grade Set 2 17-Apr-18 18-Apr-18
ConSD4300 West Site Electrical Rough-In | Lighting 4 17-Apr-18 20-Apr-18
ConSD4350 West Site Irrigation Rough-In 4 17-Apr-18 20-Apr-18
ConSD4400 West Site Curb & Gutter | Concrete Landscape Edging 5 23-Apr-18 27-Apr-18
ConSD4450 West Site Sidewalk Fine Grading | Concrete Placement 8 30-Apr-18 09-May-18
ConSD4500 West Site Sidewalk Runnels 2 10-May-18 11-May-18
ConSD4550 West Site Landscape Topsoil | Irrigation 5 10-May-18 16-May-18
ConSD4600 West Site Landscape Sod | Plantings | Ground Cover 5 17-May-18 23-May-18
ConSD5000 South Site Finish Subgrade 3 21-Mar-18 23-Mar-18
ConSD5050 South Site Utility Grade Set 2 26-Mar-18 27-Mar-18
ConSD5100 South Site Electrical Rough-In | Lighting 4 26-Mar-18 29-Mar-18
ConSD5150 South Site Irrigation Rough-In 4 26-Mar-18 29-Mar-18
ConSD5200 South Site Curb & Gutter |Concrete Landscape Edging 6 30-Mar-18 06-Apr-18
ConSD5250 South Site Sidewalk Fine Grading | Concrete Placement 7 09-Apr-18 17-Apr-18
ConSD5300 South Site Sidewalk Runnels 2 18-Apr-18 19-Apr-18
ConSD5350 South Site Landscape Topsoil | Irrigation 5 18-Apr-18 24-Apr-18
ConSD5400 South Site Landscape Sod | Plantings | Ground Cover 5 18-Apr-18 24-Apr-18
ConSD6000 Site Boundary Blue Top | Fine Grade 6 24-May-18 31-May-18
ConSD6050 Site Asphalt Paving 0 01-Jun-18
ConSD6100 Parking Striping | Signage | Wheel Stops 4 01-Jun-18 06-Jun-18
CourtyardCourtyard 66 17-Apr-18 21-Jun-18
ConCy1000 Finish Subgrade Prep | Utility Grade Adjustments 9 17-Apr-18 27-Apr-18
ConCy1050 Site Electrical Rough-In | Lighting & Power 6 24-Apr-18 01-May-18
ConCy1100 Site Irrigation Rough-In 6 24-Apr-18 01-May-18
ConCy1150 Concrete Landscape Edging 5 01-May-18 07-May-18
ConCy1200 Water Feature UG Plumbing 8 26-Apr-18 07-May-18
ConCy1250 Concrete Seating | Fountain Walls 6 08-May-18 15-May-18
ConCy1300 Concrete Paving | Stone Paver Fine Grade Prep 4 16-May-18 21-May-18
ConCy1325 Bicycle Racks 2 16-May-18 17-May-18
ConCy1350 Standard Concrete Sidewalk Placement 5 18-May-18 24-May-18
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
13-Apr-17 13-Apr-17, Div. 33 | Utilities
Underground Utilities Pre-Install Meeting
08-Feb-17 27-Apr-17, Building Pad
08-Feb-17 On-site mobilization | Trailer Set-up
09-Feb-17 Site Fencing | SWPPP BMPs
09-Feb-17 Site Signage | Postings
10-Feb-17 Control | Surface Demo Survey
14-Feb-17 Surface Structure Demolition | Decommission
20-Feb-17 Building Pad Over-excavation (5') | Subgrade Compaction
08-Mar-17 Elevator Pit Foundation Waterproofing Membrane
09-Mar-17 Elevator Pit Foundations | Walls
16-Mar-17 Building Pad Structural Fill | Partial Subgrade
24-Mar-17 East Wing Footing | Foundation Waterproofing Mebrane
03-Apr-17 East Wing Spread | Continuous Footings
07-Apr-17 East Wing Concrete Stem Walls | Rigid Insulation
12-Apr-17 East Wing Structural Fill | Finish Subgrade
19-Apr-17 East Wing Pad Certification | Grade & Compaction
29-Mar-17 North Wing Footing | Foundation Waterproofing Membrane
10-Apr-17 North Wing Spread | Continuous Footings
17-Apr-17 North Wing Concrete Stem Walls | Rigid Insulation
21-Apr-17 North Wing Structural Fill | Finish Subgrade
27-Apr-17 North Wing Pad Certification | Grade & Compaction
17-Apr-17 06-Jun-18, Site Development
17-Apr-17 Utilies Survey
17-Apr-17 Idaho Power Service | Joint Trench
28-Apr-17 Idaho Power Temporary Service Set
28-Apr-17 Intermountain Gas Service Line
18-Apr-17 Sanitary Sewerage Trench | Piping - 5' outside
25-Apr-17 Storm Service Trench | Piping - 5' outside
02-May-17 Building Water Main Service - 5' outside
09-May-17 Fire Service Line | Hydrant Risers - Inside Building Manifold
09-Jun-17 Idaho Power Building Transformer Set
08-Sep-17 Intermountain Gas Manifold | Meter Set
14-Feb-18 East Site Finish Subgrade
19-Feb-18 East Site Electrical Rough-In | Lighting
19-Feb-18 East Site Irrigation Rough-In
23-Feb-18 East Site Curb & Gutter
01-Mar-18 East Site Sidewalk Fine Grade | Concrete Placement
19-Feb-18 North Site Finish Subgrade
22-Feb-18 North Site Utility Grade Set
22-Feb-18 North Site Electrical Rough-In | Lighting
22-Feb-18 North Site Irrigation Rough-In
28-Feb-18 North Site Curb & Gutter | Concrete Landscape Edging
07-Mar-18 North Site Sidewalk Fine Grade | Concrete Placement
20-Mar-18 North Site Sidewalk Runnels
07-Mar-18 North Site Landscape Topsoil | Irrigation
14-Mar-18 North Site Landscape Sod | Plantings | Ground Cover
11-Apr-18 West Site Finish Subgrade
17-Apr-18 West Site Utility Grade Set
17-Apr-18 West Site Electrical Rough-In | Lighting
17-Apr-18 West Site Irrigation Rough-In
23-Apr-18 West Site Curb & Gutter | Concrete Landscape Edging
30-Apr-18 West Site Sidewalk Fine Grading | Concrete Placement
10-May-18 West Site Sidewalk Runnels
10-May-18 West Site Landscape Topsoil | Irrigation
17-May-18 West Site Landscape Sod | Plantings | Ground Cover
21-Mar-18 South Site Finish Subgrade
26-Mar-18 South Site Utility Grade Set
26-Mar-18 South Site Electrical Rough-In | Lighting
26-Mar-18 South Site Irrigation Rough-In
30-Mar-18 South Site Curb & Gutter |Concrete Landscape Edging
09-Apr-18 South Site Sidewalk Fine Grading | Concrete Placement
18-Apr-18 South Site Sidewalk Runnels
18-Apr-18 South Site Landscape Topsoil | Irrigation
18-Apr-18 South Site Landscape Sod | Plantings | Ground Cover
24-May-18 Site Boundary Blue Top | Fine Grade
01-Jun-18 Site Asphalt Paving
01-Jun-18 Parking Striping | Signage | Wheel Stops
17-Apr-18 21-Jun-18, Courtyard
17-Apr-18 Finish Subgrade Prep | Utility Grade Adjustments
24-Apr-18 Site Electrical Rough-In | Lighting & Power
24-Apr-18 Site Irrigation Rough-In
01-May-18 Concrete Landscape Edging
26-Apr-18 Water Feature UG Plumbing
08-May-18 Concrete Seating | Fountain Walls
16-May-18 Concrete Paving | Stone Paver Fine Grade Prep
16-May-18 Bicycle Racks
18-May-18 Standard Concrete Sidewalk Placement
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 6 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConCy1400 Stone Drainage Runnels 2 25-May-18 28-May-18
ConCy1450 Decorative Concrete | Stone Paver Installation 12 23-May-18 07-Jun-18
ConCy1500 Landscaping Topsoil & Irrigation 6 31-May-18 07-Jun-18
ConCy1550 Landscape Sod | Planting | Ground Cover 7 08-Jun-18 18-Jun-18
ConCy1600 Water Feature Detail Finish | Start-Up 10 08-Jun-18 21-Jun-18
ConCy1650 Site Furnishings | Flagpoles | Signage 8 08-Jun-18 19-Jun-18
Core | StructureCore | Structure 95 21-Apr-17 24-Jul-17
East WingEast Wing 74 21-Apr-17 03-Jul-17
ConCSe1000 Anchor Bolt Survey | Certification 2 21-Apr-17 24-Apr-17
ConCSe1050 Structural Steel Columns | Beams | Joist 7 25-Apr-17 03-May-17
ConCSe1100 Metal Roof Low | High Decking 7 02-May-17 10-May-17
ConCSe1150 Structural Steel Welding | Final Bolt-Up 5 09-May-17 15-May-17
ConCSe1200 Plumbing Undergound 7 11-May-17 19-May-17
ConCSe1250 Electrical Underground 7 11-May-17 19-May-17
ConCSe1300 Finish Fine Grading 4 18-May-17 23-May-17
ConCSe1350 SOG Vapor Barrier | WWM Reinforcement 4 23-May-17 26-May-17
ConCSe1400 Slab On Grade Concrete Placements 6 25-May-17 01-Jun-17
ConCSe1450 SOG Wet Cure 10 30-May-17 12-Jun-17
ConCSe1500 Column Base Grouting | Pour Back 3 13-Jun-17 15-Jun-17
ConCSe1550 Overhead Mechanical Hangers 8 08-Jun-17 19-Jun-17
ConCSe1575 TOW Metal Track | Exterior Wall Clips 8 08-Jun-17 19-Jun-17
ConCSe1600 Lecture Hall - Composite Concrete Roof 10 23-May-17 05-Jun-17
ConCSe2000 Spray Applied Fire Proofing 10 20-Jun-17 03-Jul-17
North WingsNorth Wings 89 27-Apr-17 24-Jul-17
ConCSn1000 Anchor Bolt Survey | Certification 2 27-Apr-17 28-Apr-17
ConCSn1050 Structural Steel Columns | Beams 15 01-May-17 19-May-17
ConCSn1100 2nd Floor - Metal Decking | Slab Edge Angle | Stud Welding 5 11-May-17 17-May-17
ConCSn1150 2nd Floor - Perimeter Safety Cabling 1 18-May-17 18-May-17
ConCSn1200 1st-2nd Floor Moment Frame Welding | Bolt Torque 5 18-May-17 24-May-17
ConCSn1250 1st-2nd Floor Stair Stringers | Landings 3 22-May-17 24-May-17
ConCSn2000 3rd Floor - Metal Decking | Slab Edge Angle | Stud Welding 5 18-May-17 24-May-17
ConCSn2050 3rd Floor - Perimeter Safety Cabling 1 25-May-17 25-May-17
ConCSn2100 2nd-3rd Floor Moment Frame Welding | Bolt Torque 5 25-May-17 31-May-17
ConCSn2150 2nd-3rd Stair Stringers | Landings 3 01-Jun-17 05-Jun-17
ConCSn3000 Roof Level - Metal Decking | Mechanical Frames 5 01-Jun-17 07-Jun-17
ConCSn3050 3rd-Roof Moment Frame Welding | Bolt Torque 5 08-Jun-17 14-Jun-17
ConCSn4000 Plumbing Underground - 1st Floor 8 18-May-17 29-May-17
ConCSn4050 Electrical Underground - 1st Floor 8 18-May-17 29-May-17
ConCSn4100 Finish Fine Grading | Vapor Barrier - 1st Floor 6 26-May-17 02-Jun-17
ConCSn4150 WWM Reinforcement | Concrete SOG Placements - 1st Floor 9 31-May-17 12-Jun-17
ConCSn4175 Wet Cure Concrete SOG - 1st Floor 14 08-Jun-17 27-Jun-17
ConCSn4200 Overhead Mechanical Hangers | Supports - 1st Floor 10 26-May-17 08-Jun-17
ConCSn4250 TOW Metal Track | Exterior Wall Clips - 1st Floor 9 19-Jun-17 29-Jun-17
ConCSn4300 Elevator Support Columns - 1st Floor 2 28-Jun-17 29-Jun-17
ConCSn4400 Spray Applied Fire Proofing - 1st Floor 8 30-Jun-17 11-Jul-17
ConCSn5000 Through Deck Sleeves | Hanger Drops - 2nd Floor 5 25-May-17 31-May-17
ConCSn5050 Plumbing | Electrical Floor Boxes, Drains & Conduit - 2nd Floor 5 25-May-17 31-May-17
ConCSn5100 Slab Edge Curtain Wall Embeds | Welded Dowels - 2nd Floor 5 25-May-17 31-May-17
ConCSn5150 Slab on Deck Reinforcement - 2nd Floor 5 30-May-17 05-Jun-17
ConCSn5200 SOD Concrete Placements - 2nd Floor 4 02-Jun-17 07-Jun-17
ConCSn5250 Stair Tread | Landing Concrete Placement - 2nd Floor 2 08-Jun-17 09-Jun-17
ConCSn5350 Wet Cure Concrete SOD - 2nd Floor 9 06-Jun-17 16-Jun-17
ConCSn5400 Elevator Support Columns - 2nd Floor 2 16-Jun-17 19-Jun-17
ConCSn5450 Overhead Mechanical Hangers | Supports - 2nd Floor 5 19-Jun-17 23-Jun-17
ConCSn5500 TOW Metal Track | Exterior Wall Clips - 2nd Floor 8 19-Jun-17 28-Jun-17
ConCSn5550 Spray Applied Fire Proofing - 2nd Floor 7 04-Jul-17 12-Jul-17
ConCSn6050 Through Deck Sleeves | Hanger Drops - 3rd Floor 5 08-Jun-17 14-Jun-17
ConCSn6100 Plumbing Floor Drains | Electrical Foor Boxes & Conduit - 3rd Floor 5 08-Jun-17 14-Jun-17
ConCSn6150 Slab Edge Curtain Wall Embeds | Welded Dowels - 3rd Floor 5 08-Jun-17 14-Jun-17
ConCSn6200 Slab on Deck Reinforcement - 3rd Floor 4 15-Jun-17 20-Jun-17
ConCSn6250 SOD Concrete Placements - 3rd Floor 4 19-Jun-17 22-Jun-17
ConCSn6300 Stair Tread | Landing Concrete Placement - 3rd Floor 2 23-Jun-17 26-Jun-17
ConCSn6350 Wet Cure Concrete SOD - 3rd Floor 9 21-Jun-17 03-Jul-17
ConCSn6400 Elevator Support Columns - 3rd Floor 2 03-Jul-17 04-Jul-17
ConCSn6450 Overhead Mechanical Hangers | Supports - 3rd Floor 5 04-Jul-17 10-Jul-17
ConCSn6500 TOW Metal Track | Exterior Wall Clips - 3rd Floor 8 04-Jul-17 13-Jul-17
ConCSn6550 Spray Applied Fire Proofing - 3rd Floor 7 14-Jul-17 24-Jul-17
East Wing - Shell | EggEast Wing - Shell | Egg 356 11-May-17 01-May-18
Exterior Finish | SystemsExterior Finish | Systems 315 11-May-17 21-Mar-18East ElevationEast Elevation 156 27-Jun-17 29-Nov-17
ConEwEfE1000 Exterior Wall Framing 10 27-Jun-17 10-Jul-17
ConEwEfE1050 Exterior Wall Sheathing 8 07-Jul-17 18-Jul-17
ConEwEfE1100 Metal Flashings 4 18-Jul-17 21-Jul-17
ConEwEfE1150 Fluid Applied Air Barrier 6 20-Jul-17 27-Jul-17
ConEwEfE1200 Z-furring & Rigid Insulation 6 26-Jul-17 02-Aug-17
ConEwEfE1250 Stone Veneer 13 25-Aug-17 12-Sep-17
ConEwEfE1300 Storefront Window Frames 11 20-Oct-17 03-Nov-17
ConEwEfE1350 Exterior Doors 6 13-Sep-17 20-Sep-17
ConEwEfE1450 Elastomeric Joint Sealants 5 06-Nov-17 10-Nov-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
25-May-18 Stone Drainage Runnels
23-May-18 Decorative Concrete | Stone Paver Installation
31-May-18 Landscaping Topsoil & Irrigation
08-Jun-18 Landscape Sod | Planting | Ground Cover
08-Jun-18 Water Feature Detail Finish | Start-Up
08-Jun-18 Site Furnishings | Flagpoles | Signage
21-Apr-17 24-Jul-17, Core | Structure
21-Apr-17 03-Jul-17, East Wing
21-Apr-17 Anchor Bolt Survey | Certification
25-Apr-17 Structural Steel Columns | Beams | Joist
02-May-17 Metal Roof Low | High Decking
09-May-17 Structural Steel Welding | Final Bolt-Up
11-May-17 Plumbing Undergound
11-May-17 Electrical Underground
18-May-17 Finish Fine Grading
23-May-17 SOG Vapor Barrier | WWM Reinforcement
25-May-17 Slab On Grade Concrete Placements
30-May-17 SOG Wet Cure
13-Jun-17 Column Base Grouting | Pour Back
08-Jun-17 Overhead Mechanical Hangers
08-Jun-17 TOW Metal Track | Exterior Wall Clips
23-May-17 Lecture Hall - Composite Concrete Roof
20-Jun-17 Spray Applied Fire Proofing
27-Apr-17 24-Jul-17, North Wings
27-Apr-17 Anchor Bolt Survey | Certification
01-May-17 Structural Steel Columns | Beams
11-May-17 2nd Floor - Metal Decking | Slab Edge Angle | Stud Welding
18-May-17 2nd Floor - Perimeter Safety Cabling
18-May-17 1st-2nd Floor Moment Frame Welding | Bolt Torque
22-May-17 1st-2nd Floor Stair Stringers | Landings
18-May-17 3rd Floor - Metal Decking | Slab Edge Angle | Stud Welding
25-May-17 3rd Floor - Perimeter Safety Cabling
25-May-17 2nd-3rd Floor Moment Frame Welding | Bolt Torque
01-Jun-17 2nd-3rd Stair Stringers | Landings
01-Jun-17 Roof Level - Metal Decking | Mechanical Frames
08-Jun-17 3rd-Roof Moment Frame Welding | Bolt Torque
18-May-17 Plumbing Underground - 1st Floor
18-May-17 Electrical Underground - 1st Floor
26-May-17 Finish Fine Grading | Vapor Barrier - 1st Floor
31-May-17 WWM Reinforcement | Concrete SOG Placements - 1st Floor
08-Jun-17 Wet Cure Concrete SOG - 1st Floor
26-May-17 Overhead Mechanical Hangers | Supports - 1st Floor
19-Jun-17 TOW Metal Track | Exterior Wall Clips - 1st Floor
28-Jun-17 Elevator Support Columns - 1st Floor
30-Jun-17 Spray Applied Fire Proofing - 1st Floor
25-May-17 Through Deck Sleeves | Hanger Drops - 2nd Floor
25-May-17 Plumbing | Electrical Floor Boxes, Drains & Conduit - 2nd Floor
25-May-17 Slab Edge Curtain Wall Embeds | Welded Dowels - 2nd Floor
30-May-17 Slab on Deck Reinforcement - 2nd Floor
02-Jun-17 SOD Concrete Placements - 2nd Floor
08-Jun-17 Stair Tread | Landing Concrete Placement - 2nd Floor
06-Jun-17 Wet Cure Concrete SOD - 2nd Floor
16-Jun-17 Elevator Support Columns - 2nd Floor
19-Jun-17 Overhead Mechanical Hangers | Supports - 2nd Floor
19-Jun-17 TOW Metal Track | Exterior Wall Clips - 2nd Floor
04-Jul-17 Spray Applied Fire Proofing - 2nd Floor
08-Jun-17 Through Deck Sleeves | Hanger Drops - 3rd Floor
08-Jun-17 Plumbing Floor Drains | Electrical Foor Boxes & Conduit - 3rd Floor
08-Jun-17 Slab Edge Curtain Wall Embeds | Welded Dowels - 3rd Floor
15-Jun-17 Slab on Deck Reinforcement - 3rd Floor
19-Jun-17 SOD Concrete Placements - 3rd Floor
23-Jun-17 Stair Tread | Landing Concrete Placement - 3rd Floor
21-Jun-17 Wet Cure Concrete SOD - 3rd Floor
03-Jul-17 Elevator Support Columns - 3rd Floor
04-Jul-17 Overhead Mechanical Hangers | Supports - 3rd Floor
04-Jul-17 TOW Metal Track | Exterior Wall Clips - 3rd Floor
14-Jul-17 Spray Applied Fire Proofing - 3rd Floor
11-May-17 01-May-18, East Wing - Shell | Egg
11-May-17 21-Mar-18, Exterior Finish | Systems
27-Jun-17 29-Nov-17, East Elevation27-Jun-17 Exterior Wall Framing
07-Jul-17 Exterior Wall Sheathing
18-Jul-17 Metal Flashings
20-Jul-17 Fluid Applied Air Barrier
26-Jul-17 Z-furring & Rigid Insulation
25-Aug-17 Stone Veneer
20-Oct-17 Storefront Window Frames
13-Sep-17 Exterior Doors
06-Nov-17 Elastomeric Joint Sealants
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 7 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConEwEfE1500 Exterior Wall Lighting 5 23-Nov-17 29-Nov-17South ElevationSouth Elevation 148 11-Jul-17 05-Dec-17
ConEwEfS1000 Exterior Wall Framing 5 11-Jul-17 17-Jul-17
ConEwEfS1050 Exterior Wall Sheathing 5 11-Jul-17 17-Jul-17
ConEwEfS1100 Metal Flashings 2 19-Jul-17 20-Jul-17
ConEwEfS1150 Fluid Applied Air Barrier 4 24-Jul-17 27-Jul-17
ConEwEfS1200 Z-furring & Rigid Insulation 6 28-Jul-17 04-Aug-17
ConEwEfS1250 Stone Veneer 8 13-Sep-17 22-Sep-17
ConEwEfS1300 Storefront Window Frames 4 06-Nov-17 09-Nov-17
ConEwEfS1350 Metal Wall Paneling 13 25-Sep-17 11-Oct-17
ConEwEfS1750 Elastomeric Joint Sealants 4 12-Oct-17 17-Oct-17
ConEwEfS1800 Exterior Wall Lighting 4 30-Nov-17 05-Dec-17West ElevationWest Elevation 246 19-Jul-17 21-Mar-18
ConEwEfW1000Exterior Wall Framing 10 19-Jul-17 01-Aug-17
ConEwEfW1050Exterior Wall Sheathing 9 27-Jul-17 08-Aug-17
ConEwEfW1100Metal Flashings 5 07-Aug-17 11-Aug-17
ConEwEfW1150Fluid Applied Air Barrier 8 14-Aug-17 23-Aug-17
ConEwEfW1200Z-furring & Rigid Insulation 7 21-Aug-17 29-Aug-17
ConEwEfW1250Stone Veneer 13 06-Oct-17 24-Oct-17
ConEwEfW1300Storefront Window Frames 16 25-Oct-17 15-Nov-17
ConEwEfW1350Canopied Walkway | Lighting Rough-In 6 25-Oct-17 01-Nov-17
ConEwEfW1400Canopied Walkway | Metal Soffit 11 02-Nov-17 16-Nov-17
ConEwEfW1450Canopied Walkway Rigid Insulation | Pro-board 9 02-Nov-17 14-Nov-17
ConEwEfW1650Canopied Walkway Metal Wall | Roof Paneling 11 09-Nov-17 23-Nov-17
ConEwEfW1700Storefront Doors | Operators 9 24-Nov-17 06-Dec-17
ConEwEfW1850Elastomeric joint Sealants 5 24-Nov-17 30-Nov-17
ConEwEfW1900Exterior Wall Lighting 5 06-Dec-17 12-Dec-17
ConEwEfW1950Stainless Steel Solar Fabric 11 07-Mar-18 21-Mar-18
ConEwEfW2000Exposed Column Covers 10 07-Mar-18 20-Mar-18North ElevationNorth Elevation 155 11-Jul-17 12-Dec-17
ConEwEfN1000 Exterior Wall Framing 6 11-Jul-17 18-Jul-17
ConEwEfN1050 Exterior Wall Sheathing 6 19-Jul-17 26-Jul-17
ConEwEfN1100 Metal Flashings 3 27-Jul-17 31-Jul-17
ConEwEfN1150 Fluid Applied Air Barrier 4 01-Aug-17 04-Aug-17
ConEwEfN1200 Z-furring & Rigid Insulation 6 07-Aug-17 14-Aug-17
ConEwEfN1250 Stone Veneer 9 25-Sep-17 05-Oct-17
ConEwEfN1350 Elastomeric Joint Sealants 5 06-Oct-17 12-Oct-17
ConEwEfN1400 Exterior Wall Lighting 5 06-Dec-17 12-Dec-17Roof AreaRoof Area 182 11-May-17 08-Nov-17
ConEwEfR1000 Parapet Wall Electrical Rough-In 8 02-Aug-17 11-Aug-17
ConEwEfR1050 Parapet Wall Sheathing 11 14-Aug-17 28-Aug-17
ConEwEfR1100 Roof Deck Penetrations | Drain Bodies | Curbs 9 11-May-17 23-May-17
ConEwEfR1250 Roof Hatch | Reglets & Flashings 7 29-Aug-17 06-Sep-17
ConEwEfR1450 80mil TPO Membrane | Insulation | Pro-board 17 07-Sep-17 29-Sep-17
ConEwEfR1500 TPO Walk-pads 5 02-Oct-17 06-Oct-17
ConEwEfR1550 Prefinished Metal Coping Cap 11 25-Oct-17 08-Nov-17
ConEwEfR1800 Roof Top Mechanical Equipment Set 5 02-Oct-17 06-Oct-17
ConEwEfR1850 Satellite Dishes | Antenna 3 02-Oct-17 04-Oct-17
Interior Finish | SystemsInterior Finish | Systems 302 04-Jul-17 01-May-18Instructional SpacesInstructional Spaces 302 04-Jul-17 01-May-18
ConEwIfIS1000 Fire Sprinkler Main | Branch Piping 10 04-Jul-17 17-Jul-17
ConEwIfIS1050 HVAC Ductwork | Insulation 15 18-Jul-17 07-Aug-17
ConEwIfIS1100 Mechanical Overhead Piping 15 08-Aug-17 28-Aug-17
ConEwIfIS1150 Electrical Overhead Rough-In 15 18-Jul-17 07-Aug-17
ConEwIfIS1200 Interior Wall Framing | Furring 12 08-Aug-17 23-Aug-17
ConEwIfIS1250 Interior Wall Rough-In | MEP 9 24-Aug-17 05-Sep-17
ConEwIfIS1300 Interior Wall Insulation | Blocking | Backing 6 06-Sep-17 13-Sep-17
ConEwIfIS1350 Drywall Sheathing 9 14-Sep-17 26-Sep-17
ConEwIfIS1400 Acoustical Sealant | Drywall Taping 14 27-Sep-17 16-Oct-17
ConEwIfIS1450 Lecture Hall Ceiling Framing | MEP Rough-In | Data Cabling 15 17-Oct-17 06-Nov-17
ConEwIfIS1475 Lecture Hall Ceiling | Project Screens 6 01-Nov-17 08-Nov-17
ConEwIfIS1500 Lecture Hall Ceiling | Drywall & Taping 20 15-Nov-17 12-Dec-17
ConEwIfIS1550 Lecture Hall Ceiling | Wood Panel & Trim 20 13-Dec-17 09-Jan-18
ConEwIfIS1575 Lecture Hall Ceiling | Acoustical Ceiling 15 03-Jan-18 23-Jan-18
ConEwIfIS1600 Lecture Hall Ceiling | Fixtures & Trim 10 17-Jan-18 30-Jan-18
ConEwIfIS1650 Lecture Hall Raised Stadium Floor Framing 15 24-Jan-18 13-Feb-18
ConEwIfIS1700 Lecture Hall Raised Floor MEP Rough-In | Sheathing 10 07-Feb-18 20-Feb-18
ConEwIfIS1750 Lecture Hall Wall Paneling | Woodwork 20 21-Feb-18 20-Mar-18
ConEwIfIS1800 Lecture Hall Visual Displays | Whiteboards 8 15-Mar-18 26-Mar-18
ConEwIfIS1850 Lecture Hall Carpet Flooring 8 21-Mar-18 30-Mar-18
ConEwIfIS1900 Lecture Hall Stadium Seating 12 02-Apr-18 17-Apr-18
ConEwIfIS1950 Lecture Hall Doors & Hardware 10 18-Apr-18 01-May-18General Building SpacesGeneral Building Spaces 135 18-Jul-17 29-Nov-17
ConEwIfGBS1000Fire Sprinkler Main | Branch Piping 4 18-Jul-17 21-Jul-17
ConEwIfGBS1050HVAC Ductwork | Insulation 7 24-Jul-17 01-Aug-17
ConEwIfGBS1100Mechanical Overhead Piping 7 02-Aug-17 10-Aug-17
ConEwIfGBS1150Electrical Overhead Rough-In 7 24-Jul-17 01-Aug-17
ConEwIfGBS1200Interior Wall Framing | Furring 8 02-Aug-17 11-Aug-17
ConEwIfGBS1250Interior Wall Rough-In | MEP 7 14-Aug-17 22-Aug-17
ConEwIfGBS1300Interior Wall Insulation | Blocking | Backing 4 23-Aug-17 28-Aug-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
23-Nov-17 Exterior Wall Lighting
11-Jul-17 05-Dec-17, South Elevation11-Jul-17 Exterior Wall Framing
11-Jul-17 Exterior Wall Sheathing
19-Jul-17 Metal Flashings
24-Jul-17 Fluid Applied Air Barrier
28-Jul-17 Z-furring & Rigid Insulation
13-Sep-17 Stone Veneer
06-Nov-17 Storefront Window Frames
25-Sep-17 Metal Wall Paneling
12-Oct-17 Elastomeric Joint Sealants
30-Nov-17 Exterior Wall Lighting
19-Jul-17 21-Mar-18, West Elevation19-Jul-17 Exterior Wall Framing
27-Jul-17 Exterior Wall Sheathing
07-Aug-17 Metal Flashings
14-Aug-17 Fluid Applied Air Barrier
21-Aug-17 Z-furring & Rigid Insulation
06-Oct-17 Stone Veneer
25-Oct-17 Storefront Window Frames
25-Oct-17 Canopied Walkway | Lighting Rough-In
02-Nov-17 Canopied Walkway | Metal Soffit
02-Nov-17 Canopied Walkway Rigid Insulation | Pro-board
09-Nov-17 Canopied Walkway Metal Wall | Roof Paneling
24-Nov-17 Storefront Doors | Operators
24-Nov-17 Elastomeric joint Sealants
06-Dec-17 Exterior Wall Lighting
07-Mar-18 Stainless Steel Solar Fabric
07-Mar-18 Exposed Column Covers
11-Jul-17 12-Dec-17, North Elevation11-Jul-17 Exterior Wall Framing
19-Jul-17 Exterior Wall Sheathing
27-Jul-17 Metal Flashings
01-Aug-17 Fluid Applied Air Barrier
07-Aug-17 Z-furring & Rigid Insulation
25-Sep-17 Stone Veneer
06-Oct-17 Elastomeric Joint Sealants
06-Dec-17 Exterior Wall Lighting
11-May-17 08-Nov-17, Roof Area02-Aug-17 Parapet Wall Electrical Rough-In
14-Aug-17 Parapet Wall Sheathing
11-May-17 Roof Deck Penetrations | Drain Bodies | Curbs
29-Aug-17 Roof Hatch | Reglets & Flashings
07-Sep-17 80mil TPO Membrane | Insulation | Pro-board
02-Oct-17 TPO Walk-pads
25-Oct-17 Prefinished Metal Coping Cap
02-Oct-17 Roof Top Mechanical Equipment Set
02-Oct-17 Satellite Dishes | Antenna
04-Jul-17 01-May-18, Interior Finish | Systems
04-Jul-17 01-May-18, Instructional Spaces04-Jul-17 Fire Sprinkler Main | Branch Piping
18-Jul-17 HVAC Ductwork | Insulation
08-Aug-17 Mechanical Overhead Piping
18-Jul-17 Electrical Overhead Rough-In
08-Aug-17 Interior Wall Framing | Furring
24-Aug-17 Interior Wall Rough-In | MEP
06-Sep-17 Interior Wall Insulation | Blocking | Backing
14-Sep-17 Drywall Sheathing
27-Sep-17 Acoustical Sealant | Drywall Taping
17-Oct-17 Lecture Hall Ceiling Framing | MEP Rough-In | Data Cabling
01-Nov-17 Lecture Hall Ceiling | Project Screens
15-Nov-17 Lecture Hall Ceiling | Drywall & Taping
13-Dec-17 Lecture Hall Ceiling | Wood Panel & Trim
03-Jan-18 Lecture Hall Ceiling | Acoustical Ceiling
17-Jan-18 Lecture Hall Ceiling | Fixtures & Trim
24-Jan-18 Lecture Hall Raised Stadium Floor Framing
07-Feb-18 Lecture Hall Raised Floor MEP Rough-In | Sheathing
21-Feb-18 Lecture Hall Wall Paneling | Woodwork
15-Mar-18 Lecture Hall Visual Displays | Whiteboards
21-Mar-18 Lecture Hall Carpet Flooring
02-Apr-18 Lecture Hall Stadium Seating
18-Apr-18 Lecture Hall Doors & Hardware
18-Jul-17 29-Nov-17, General Building Spaces18-Jul-17 Fire Sprinkler Main | Branch Piping
24-Jul-17 HVAC Ductwork | Insulation
02-Aug-17 Mechanical Overhead Piping
24-Jul-17 Electrical Overhead Rough-In
02-Aug-17 Interior Wall Framing | Furring
14-Aug-17 Interior Wall Rough-In | MEP
23-Aug-17 Interior Wall Insulation | Blocking | Backing
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 8 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConEwIfGBS1350Restroom Ceiling Framing 8 14-Aug-17 23-Aug-17
ConEwIfGBS1400Restroom Ceiling MEP Rough-In 8 24-Aug-17 04-Sep-17
ConEwIfGBS1450Restroom Wall | Ceiling Sheathing & Taping 10 05-Sep-17 18-Sep-17
ConEwIfGBS1500Restroom Prime & One-Coat 4 19-Sep-17 22-Sep-17
ConEwIfGBS1525Restroom Countertops 5 20-Oct-17 26-Oct-17
ConEwIfGBS1550Restroom Floor | Wall Tile 10 25-Sep-17 06-Oct-17
ConEwIfGBS1650Restroom Plumbing Fixtures 6 09-Oct-17 16-Oct-17
ConEwIfGBS1700Restroom Lighting Fixtures | mechanical Trim 6 17-Oct-17 24-Oct-17
ConEwIfGBS1750Restroom Partitions | Accessories 6 17-Nov-17 24-Nov-17
ConEwIfGBS1800Restroom Doors 3 27-Nov-17 29-Nov-17
ConEwIfGBS1850Fire Riser Manifold 3 24-Jul-17 26-Jul-17
ConEwIfGBS1900Concrete Floor Grind | Sealer 3 03-Oct-17 05-Oct-17
ConEwIfGBS1950Suspended Lighting 3 06-Oct-17 10-Oct-17
ConEwIfGBS2000Mop Sinks | FRP Wall Wrap 6 06-Oct-17 13-Oct-17
ConEwIfGBS2050MEP Trim-out 15 04-Oct-17 24-Oct-17
ConEwIfGBS2100Doors & Hardware 10 25-Oct-17 07-Nov-17Student Support SpaceStudent Support Space 267 24-Jul-17 16-Apr-18
ConEwIfSSS1000Fire Sprinkler Branch Piping 2 24-Jul-17 25-Jul-17
ConEwIfSSS1050HVAC Ductwork | Insulation 4 26-Jul-17 31-Jul-17
ConEwIfSSS1100Mechanical Overhead Piping 4 01-Aug-17 04-Aug-17
ConEwIfSSS1150Electrical Overhead Rough-In 4 26-Jul-17 31-Jul-17
ConEwIfSSS1200Interior Wall Framing | Furring 5 01-Aug-17 07-Aug-17
ConEwIfSSS1250Interior Wall Rough-In | MEP 4 08-Aug-17 11-Aug-17
ConEwIfSSS1300Interior Wall Insulation | Blocking | Backing 3 14-Aug-17 16-Aug-17
ConEwIfSSS1350Ceiling Framing | MEP Rough-In 9 17-Aug-17 29-Aug-17
ConEwIfSSS1400Ceiling Sheathing | Taping | Painting 12 30-Aug-17 14-Sep-17
ConEwIfSSS1450Acoustical Ceiling Grid 7 15-Sep-17 25-Sep-17
ConEwIfSSS1500Lockers | Architectural Woodwork 12 21-Mar-18 05-Apr-18
ConEwIfSSS1550Carpet Flooring | Rubber Base 7 06-Apr-18 16-Apr-18Corridors | VestibulesCorridors | Vestibules 289 10-Jul-17 24-Apr-18
ConEwIfCV1000MEP Overhead | BIM Coordination 12 10-Jul-17 25-Jul-17
ConEwIfCV1050Pilaster | soffit Framing 15 07-Feb-18 27-Feb-18
ConEwIfCV1100Drywall Sheathing | Taping 15 21-Feb-18 13-Mar-18
ConEwIfCV1150Wood Pilaster Wrap | Ceiling Panels 15 07-Mar-18 27-Mar-18
ConEwIfCV1200Acoustical Ceiling Grid 10 21-Mar-18 03-Apr-18
ConEwIfCV1250MEP Ceiling Trim | Devices 10 28-Mar-18 10-Apr-18
ConEwIfCV1300Corridor | Vestibule Flooring 10 11-Apr-18 24-Apr-18
North Wing - Shell | EggNorth Wing - Shell | Egg 322 11-Jul-17 28-May-18
Exterior Finish | SystemsExterior Finish | Systems 310 11-Jul-17 16-May-18East ElevationEast Elevation 196 25-Jul-17 05-Feb-18
ConNwEfE1000 Exterior Wall Framing 12 25-Jul-17 09-Aug-17
ConNwEfE1050 Exterior Wall Sheathing 10 10-Aug-17 23-Aug-17
ConNwEfE1100 Metal Flashings 5 24-Aug-17 30-Aug-17
ConNwEfE1150 Fluid Applied Air Barrier 10 31-Aug-17 13-Sep-17
ConNwEfE1200 Z-furring & Rigid Insulation 7 14-Sep-17 22-Sep-17
ConNwEfE1250 Stone Veneer 14 25-Oct-17 13-Nov-17
ConNwEfE1300 Storefront Window Frames | Glazing 7 14-Nov-17 22-Nov-17
ConNwEfE1400 Exterior Doors 6 14-Nov-17 21-Nov-17
ConNwEfE1450 Rigid Insulation | Pro-board 7 23-Nov-17 01-Dec-17
ConNwEfE1500 Metal Wall | Roof Paneling 13 04-Dec-17 20-Dec-17
ConNwEfE1550 Elastomeric Joint Sealants 5 21-Dec-17 27-Dec-17
ConNwEfE1600 Exterior Wall Lighting 3 01-Feb-18 05-Feb-18North ElevationNorth Elevation 260 10-Aug-17 26-Apr-18
ConNwEfN1000Exterior Wall Framing 20 10-Aug-17 06-Sep-17
ConNwEfN1050Exterior Wall Sheathing 14 07-Sep-17 26-Sep-17
ConNwEfN1100Metal Flashings 7 27-Sep-17 05-Oct-17
ConNwEfN1150Fluid Applied Air Barrier 13 06-Oct-17 24-Oct-17
ConNwEfN1200Z-furring & Rigid Insulation 13 25-Oct-17 10-Nov-17
ConNwEfN1250Stone Veneer 22 14-Nov-17 13-Dec-17
ConNwEfN1300Storefront Window Frames | Glazing 7 14-Dec-17 22-Dec-17
ConNwEfN1350Curtain Wall Frames | Glazing | Spandrel 22 14-Dec-17 12-Jan-18
ConNwEfN1400Curtain Wall Slab Edge Firestop 8 15-Jan-18 24-Jan-18
ConNwEfN1450Rigid Insulation | Pro-Board 8 15-Jan-18 24-Jan-18
ConNwEfN1500Metal Wall | Soffit | Roof Paneling 14 25-Jan-18 13-Feb-18
ConNwEfN1550Exterior Storefront Doors & Operators 8 25-Dec-17 03-Jan-18
ConNwEfN1600Exposed Column Cover Wraps 9 14-Feb-18 26-Feb-18
ConNwEfN1650Elastomeric Joint Sealants 8 27-Feb-18 08-Mar-18
ConNwEfN1700Exterior Wall | Soffit Lighting 6 14-Mar-18 21-Mar-18
ConNwEfN1750Building Signage 5 20-Apr-18 26-Apr-18South ElevationSouth Elevation 209 24-Aug-17 20-Mar-18
ConNwEfS1000 Exterior Wall Framing 20 24-Aug-17 20-Sep-17
ConNwEfS1050 Exterior Wall Sheathing 12 21-Sep-17 06-Oct-17
ConNwEfS1100 Metal Flashings 6 09-Oct-17 16-Oct-17
ConNwEfS1150 Fluid Applied Air Barrier 12 17-Oct-17 01-Nov-17
ConNwEfS1200 Z-furring & Rigid Insulation 12 02-Nov-17 17-Nov-17
ConNwEfS1250 Stone Veneer 21 20-Nov-17 18-Dec-17
ConNwEfS1450 Storefront Window Frames | Glazing 10 19-Dec-17 01-Jan-18
ConNwEfS1500 Curtain Wall Frames | Glazing | Spandrel 32 15-Jan-18 27-Feb-18
ConNwEfS1550 Curtain Wall Slab Edge Firestop 15 28-Feb-18 20-Mar-18
ConNwEfS1575 Rigid Insulation | Pro-board 8 02-Jan-18 11-Jan-18
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
14-Aug-17 Restroom Ceiling Framing
24-Aug-17 Restroom Ceiling MEP Rough-In
05-Sep-17 Restroom Wall | Ceiling Sheathing & Taping
19-Sep-17 Restroom Prime & One-Coat
20-Oct-17 Restroom Countertops
25-Sep-17 Restroom Floor | Wall Tile
09-Oct-17 Restroom Plumbing Fixtures
17-Oct-17 Restroom Lighting Fixtures | mechanical Trim
17-Nov-17 Restroom Partitions | Accessories
27-Nov-17 Restroom Doors
24-Jul-17 Fire Riser Manifold
03-Oct-17 Concrete Floor Grind | Sealer
06-Oct-17 Suspended Lighting
06-Oct-17 Mop Sinks | FRP Wall Wrap
04-Oct-17 MEP Trim-out
25-Oct-17 Doors & Hardware
24-Jul-17 16-Apr-18, Student Support Space24-Jul-17 Fire Sprinkler Branch Piping
26-Jul-17 HVAC Ductwork | Insulation
01-Aug-17 Mechanical Overhead Piping
26-Jul-17 Electrical Overhead Rough-In
01-Aug-17 Interior Wall Framing | Furring
08-Aug-17 Interior Wall Rough-In | MEP
14-Aug-17 Interior Wall Insulation | Blocking | Backing
17-Aug-17 Ceiling Framing | MEP Rough-In
30-Aug-17 Ceiling Sheathing | Taping | Painting
15-Sep-17 Acoustical Ceiling Grid
21-Mar-18 Lockers | Architectural Woodwork
06-Apr-18 Carpet Flooring | Rubber Base
10-Jul-17 24-Apr-18, Corridors | Vestibules10-Jul-17 MEP Overhead | BIM Coordination
07-Feb-18 Pilaster | soffit Framing
21-Feb-18 Drywall Sheathing | Taping
07-Mar-18 Wood Pilaster Wrap | Ceiling Panels
21-Mar-18 Acoustical Ceiling Grid
28-Mar-18 MEP Ceiling Trim | Devices
11-Apr-18 Corridor | Vestibule Flooring
11-Jul-17 28-May-18, North Wing - Shell | Egg
11-Jul-17 16-May-18, Exterior Finish | Systems
25-Jul-17 05-Feb-18, East Elevation25-Jul-17 Exterior Wall Framing
10-Aug-17 Exterior Wall Sheathing
24-Aug-17 Metal Flashings
31-Aug-17 Fluid Applied Air Barrier
14-Sep-17 Z-furring & Rigid Insulation
25-Oct-17 Stone Veneer
14-Nov-17 Storefront Window Frames | Glazing
14-Nov-17 Exterior Doors
23-Nov-17 Rigid Insulation | Pro-board
04-Dec-17 Metal Wall | Roof Paneling
21-Dec-17 Elastomeric Joint Sealants
01-Feb-18 Exterior Wall Lighting
10-Aug-17 26-Apr-18, North Elevation10-Aug-17 Exterior Wall Framing
07-Sep-17 Exterior Wall Sheathing
27-Sep-17 Metal Flashings
06-Oct-17 Fluid Applied Air Barrier
25-Oct-17 Z-furring & Rigid Insulation
14-Nov-17 Stone Veneer
14-Dec-17 Storefront Window Frames | Glazing
14-Dec-17 Curtain Wall Frames | Glazing | Spandrel
15-Jan-18 Curtain Wall Slab Edge Firestop
15-Jan-18 Rigid Insulation | Pro-Board
25-Jan-18 Metal Wall | Soffit | Roof Paneling
25-Dec-17 Exterior Storefront Doors & Operators
14-Feb-18 Exposed Column Cover Wraps
27-Feb-18 Elastomeric Joint Sealants
14-Mar-18 Exterior Wall | Soffit Lighting
20-Apr-18 Building Signage
24-Aug-17 20-Mar-18, South Elevation24-Aug-17 Exterior Wall Framing
21-Sep-17 Exterior Wall Sheathing
09-Oct-17 Metal Flashings
17-Oct-17 Fluid Applied Air Barrier
02-Nov-17 Z-furring & Rigid Insulation
20-Nov-17 Stone Veneer
19-Dec-17 Storefront Window Frames | Glazing
15-Jan-18 Curtain Wall Frames | Glazing | Spandrel
28-Feb-18 Curtain Wall Slab Edge Firestop
02-Jan-18 Rigid Insulation | Pro-board
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 9 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConNwEfS1600 Metal Wall | Soffit |Roof Paneling 16 12-Jan-18 02-Feb-18
ConNwEfS1650 Storefront Doors & Operators 8 02-Jan-18 11-Jan-18
ConNwEfS1700 Solar Shades | Louvers 15 28-Feb-18 20-Mar-18
ConNwEfS1750 Exposed Column Cover Wraps 9 05-Feb-18 15-Feb-18
ConNwEfS1800 Elastomeric Joint Sealants 5 16-Feb-18 22-Feb-18
ConNwEfS1850 Exterior Wall | Soffit Lighting 7 05-Mar-18 13-Mar-18West ElevationWest Elevation 252 07-Sep-17 16-May-18
ConNwEfW1000Exterior Wall Framing 12 07-Sep-17 22-Sep-17
ConNwEfW1050Exterior Wall Sheathing 9 25-Sep-17 05-Oct-17
ConNwEfW1150Metal Flashings 4 06-Oct-17 11-Oct-17
ConNwEfW1200Fluid Applied Air Barrier 7 12-Oct-17 20-Oct-17
ConNwEfW1250Z-furring & Rigid Insulation 7 23-Oct-17 31-Oct-17
ConNwEfW1300Stone Veneer 13 19-Dec-17 04-Jan-18
ConNwEfW1350Curtain Wall Frames | Glazing | Spandrell 24 21-Feb-18 26-Mar-18
ConNwEfW1400Curtain Wall Slab Edge Firestop 8 27-Mar-18 05-Apr-18
ConNwEfW1450Rigid Insulation | Pro-board 6 19-Mar-18 26-Mar-18
ConNwEfW1500Metal Wall | Soffit | Roof Paneling 14 22-Mar-18 10-Apr-18
ConNwEfW1550Exposed Column Cover Wraps 8 11-Apr-18 20-Apr-18
ConNwEfW1600Elastomeric Joint Sealants 8 23-Apr-18 02-May-18
ConNwEfW1650Stainless Steel Fabic Solar Shades 7 08-May-18 16-May-18
ConNwEfW1700Exterior Wall | Soffit Lighting 8 11-Apr-18 20-Apr-18Roof AreaRoof Area 186 11-Jul-17 12-Jan-18
ConNwEfR1150 Parapet Wall Electrical Rough-In 9 12-Sep-17 22-Sep-17
ConNwEfR1200 Parapet Wall Sheathing 9 25-Sep-17 05-Oct-17
ConNwEfR1300 Roof Deck Penetrations | Drain Bodies | Curbs 7 11-Jul-17 19-Jul-17
ConNwEfR1350 Roof Hatch | Reglets & Flashings 7 20-Jul-17 28-Jul-17
ConNwEfR1600 80mil TPO Membrane | Insulation | Pro-board 20 06-Oct-17 02-Nov-17
ConNwEfR1650 TPO Walk-pads 4 03-Nov-17 08-Nov-17
ConNwEfR1700 Prefinished Metal Coping Cap 6 05-Jan-18 12-Jan-18
ConNwEfR1900 Roof Top Mechanical Equipment Set 4 03-Nov-17 08-Nov-17
ConNwEfR1950 Satellite Dishes | Antenna 2 21-Dec-17 22-Dec-17
1st Floor - Interior Finish | Systems1st Floor - Interior Finish | Systems 314 19-Jul-17 28-May-18AdmissionsAdmissions 99 19-Jul-17 25-Oct-17
ConNwIfA1000 Fire Sprinkler Piping 6 19-Jul-17 26-Jul-17
ConNwIfA1050 Mechanical Ductwork | Insulation 7 19-Jul-17 27-Jul-17
ConNwIfA1100 Electrical | Plumbing Overhead 7 27-Jul-17 04-Aug-17
ConNwIfA1150 Interior Wall Framings | MEP Rough-In 9 28-Jul-17 09-Aug-17
ConNwIfA1200 Interior Wall Insulation | Blocking | Backing 4 10-Aug-17 15-Aug-17
ConNwIfA1250 Soffit Ceiling Framings | MEP Rough-In 9 10-Aug-17 22-Aug-17
ConNwIfA1300 Interior Wall | soffit Drywall 9 23-Aug-17 04-Sep-17
ConNwIfA1350 Acoustical Sealants | Drywall Taping 9 05-Sep-17 15-Sep-17
ConNwIfA1400 Prime and One-Coat Paint 4 18-Sep-17 21-Sep-17
ConNwIfA1450 Acoustical Ceiling Grid | MEP Trim 6 22-Sep-17 29-Sep-17
ConNwIfA1500 Millworks | Casework | Countertops & Sills 8 02-Oct-17 11-Oct-17
ConNwIfA1550 Carpet Flooring | Base 6 12-Oct-17 19-Oct-17
ConNwIfA1600 Doors & Hardware 4 20-Oct-17 25-Oct-17Library | Quiet StudyLibrary | Quiet Study 114 27-Jul-17 17-Nov-17
ConNwIfL1650 Fire Sprinkler Piping 6 27-Jul-17 03-Aug-17
ConNwIfL1700 Mechanical Ductwork | Insulation 7 04-Aug-17 14-Aug-17
ConNwIfL1750 Electrical | Plumbing Overhead 7 04-Aug-17 14-Aug-17
ConNwIfL1800 Interior Wall Framings | MEP Rough-In 9 15-Aug-17 25-Aug-17
ConNwIfL1850 Interior Wall Insulation | Blocking | Backing 4 28-Aug-17 31-Aug-17
ConNwIfL1900 Soffit Ceiling Framings | MEP Rough-In 9 28-Aug-17 07-Sep-17
ConNwIfL1950 Interior Wall | soffit Drywall 9 08-Sep-17 20-Sep-17
ConNwIfL2000 Acoustical Sealants | Drywall Taping 9 21-Sep-17 03-Oct-17
ConNwIfL2050 Prime and One-Coat Paint 5 04-Oct-17 10-Oct-17
ConNwIfL2100 Acoustical Ceiling Grid | MEP Trim 8 11-Oct-17 20-Oct-17
ConNwIfL2150 Millworks | Casework | Countertops & Sills 8 23-Oct-17 01-Nov-17
ConNwIfL2200 Carpet Flooring | Base 7 02-Nov-17 10-Nov-17
ConNwIfL2250 Doors & Hardware 5 13-Nov-17 17-Nov-17IT | General Building SpacesIT | General Building Spaces 298 04-Aug-17 28-May-18
ConNwIfITG1000Mechanical | Electrical Overhead 4 04-Aug-17 09-Aug-17
ConNwIfITG1050Interior Wall Framing | MEP Rough-In 5 10-Aug-17 16-Aug-17
ConNwIfITG1100Interior Wall Insulation | Blocking | Backing 3 17-Aug-17 21-Aug-17
ConNwIfITG1150Electrical Room Drywall | Taping 5 22-Aug-17 28-Aug-17
ConNwIfITG1200Electrical Room Paint | Plywood Backboard 3 29-Aug-17 31-Aug-17
ConNwIfITG1250Electrical Room Concrete Floor Grind | Sealer 3 01-Sep-17 05-Sep-17
ConNwIfITG1300Electrical Room Transformer | Panels | Switchgear 12 06-Sep-17 21-Sep-17
ConNwIfITG1350Restroom Ceiling Framing | MEP Rough-In 8 17-Aug-17 28-Aug-17
ConNwIfITG1400Restroom Wall | Ceiling Sheathing 4 29-Aug-17 01-Sep-17
ConNwIfITG1450Restroom Drywall Taping | One-Coat Painting 7 04-Sep-17 12-Sep-17
ConNwIfITG1500Restroom Countertops 2 13-Sep-17 14-Sep-17
ConNwIfITG1550Restroom Floor | Wall Tile 8 15-Sep-17 26-Sep-17
ConNwIfITG1600Restroom Plumbing | Lighting Fixtures 6 27-Sep-17 04-Oct-17
ConNwIfITG1650Restroom Partitions | Accessories 5 05-Oct-17 11-Oct-17
ConNwIfITG1700Restroom | Storage Room Doors 2 12-Oct-17 13-Oct-17
ConNwIfITG1750Lobby Drywall | Taping | Painting 9 11-Apr-18 23-Apr-18
ConNwIfITG1800Lobby Precast Stair Treades 5 15-Sep-17 21-Sep-17
ConNwIfITG1850Lobby Decorative Stair Railings 9 07-Sep-17 19-Sep-17
ConNwIfITG1875Lobby Lighting | Mechanical Trim 10 24-Apr-18 07-May-18
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
12-Jan-18 Metal Wall | Soffit |Roof Paneling
02-Jan-18 Storefront Doors & Operators
28-Feb-18 Solar Shades | Louvers
05-Feb-18 Exposed Column Cover Wraps
16-Feb-18 Elastomeric Joint Sealants
05-Mar-18 Exterior Wall | Soffit Lighting
07-Sep-17 16-May-18, West Elevation07-Sep-17 Exterior Wall Framing
25-Sep-17 Exterior Wall Sheathing
06-Oct-17 Metal Flashings
12-Oct-17 Fluid Applied Air Barrier
23-Oct-17 Z-furring & Rigid Insulation
19-Dec-17 Stone Veneer
21-Feb-18 Curtain Wall Frames | Glazing | Spandrell
27-Mar-18 Curtain Wall Slab Edge Firestop
19-Mar-18 Rigid Insulation | Pro-board
22-Mar-18 Metal Wall | Soffit | Roof Paneling
11-Apr-18 Exposed Column Cover Wraps
23-Apr-18 Elastomeric Joint Sealants
08-May-18 Stainless Steel Fabic Solar Shades
11-Apr-18 Exterior Wall | Soffit Lighting
11-Jul-17 12-Jan-18, Roof Area12-Sep-17 Parapet Wall Electrical Rough-In
25-Sep-17 Parapet Wall Sheathing
11-Jul-17 Roof Deck Penetrations | Drain Bodies | Curbs
20-Jul-17 Roof Hatch | Reglets & Flashings
06-Oct-17 80mil TPO Membrane | Insulation | Pro-board
03-Nov-17 TPO Walk-pads
05-Jan-18 Prefinished Metal Coping Cap
03-Nov-17 Roof Top Mechanical Equipment Set
21-Dec-17 Satellite Dishes | Antenna
19-Jul-17 28-May-18, 1st Floor - Interior Finish | Systems
19-Jul-17 25-Oct-17, Admissions19-Jul-17 Fire Sprinkler Piping
19-Jul-17 Mechanical Ductwork | Insulation
27-Jul-17 Electrical | Plumbing Overhead
28-Jul-17 Interior Wall Framings | MEP Rough-In
10-Aug-17 Interior Wall Insulation | Blocking | Backing
10-Aug-17 Soffit Ceiling Framings | MEP Rough-In
23-Aug-17 Interior Wall | soffit Drywall
05-Sep-17 Acoustical Sealants | Drywall Taping
18-Sep-17 Prime and One-Coat Paint
22-Sep-17 Acoustical Ceiling Grid | MEP Trim
02-Oct-17 Millworks | Casework | Countertops & Sills
12-Oct-17 Carpet Flooring | Base
20-Oct-17 Doors & Hardware
27-Jul-17 17-Nov-17, Library | Quiet Study27-Jul-17 Fire Sprinkler Piping
04-Aug-17 Mechanical Ductwork | Insulation
04-Aug-17 Electrical | Plumbing Overhead
15-Aug-17 Interior Wall Framings | MEP Rough-In
28-Aug-17 Interior Wall Insulation | Blocking | Backing
28-Aug-17 Soffit Ceiling Framings | MEP Rough-In
08-Sep-17 Interior Wall | soffit Drywall
21-Sep-17 Acoustical Sealants | Drywall Taping
04-Oct-17 Prime and One-Coat Paint
11-Oct-17 Acoustical Ceiling Grid | MEP Trim
23-Oct-17 Millworks | Casework | Countertops & Sills
02-Nov-17 Carpet Flooring | Base
13-Nov-17 Doors & Hardware
04-Aug-17 28-May-18, IT | General Building Spaces04-Aug-17 Mechanical | Electrical Overhead
10-Aug-17 Interior Wall Framing | MEP Rough-In
17-Aug-17 Interior Wall Insulation | Blocking | Backing
22-Aug-17 Electrical Room Drywall | Taping
29-Aug-17 Electrical Room Paint | Plywood Backboard
01-Sep-17 Electrical Room Concrete Floor Grind | Sealer
06-Sep-17 Electrical Room Transformer | Panels | Switchgear
17-Aug-17 Restroom Ceiling Framing | MEP Rough-In
29-Aug-17 Restroom Wall | Ceiling Sheathing
04-Sep-17 Restroom Drywall Taping | One-Coat Painting
13-Sep-17 Restroom Countertops
15-Sep-17 Restroom Floor | Wall Tile
27-Sep-17 Restroom Plumbing | Lighting Fixtures
05-Oct-17 Restroom Partitions | Accessories
12-Oct-17 Restroom | Storage Room Doors
11-Apr-18 Lobby Drywall | Taping | Painting
15-Sep-17 Lobby Precast Stair Treades
07-Sep-17 Lobby Decorative Stair Railings
24-Apr-18 Lobby Lighting | Mechanical Trim
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 10 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConNwIfITG1900Lobby Flooring 5 08-May-18 14-May-18
ConNwIfITG1950Lobby Wall Paneling | Millworks 5 15-May-18 21-May-18
ConNwIfITG2000Lobby Directories | Furnishings 5 22-May-18 28-May-18Instructional | student Support SpacesInstructional | student Support Spaces 259 04-Aug-17 19-Apr-18
ConNwIfIS2300 Fire Sprinkler Piping 4 04-Aug-17 09-Aug-17
ConNwIfIS2350 Mechanical Ductwork | Insulation 4 10-Aug-17 15-Aug-17
ConNwIfIS2400 Electrical | Plumbing Overhead 4 10-Aug-17 15-Aug-17
ConNwIfIS2450 Interior Wall Framings | MEP Rough-In 8 07-Feb-18 16-Feb-18
ConNwIfIS2500 Interior Wall Insulation | Blocking | Backing 4 19-Feb-18 22-Feb-18
ConNwIfIS2550 Soffit Ceiling Framings | MEP Rough-In 8 19-Feb-18 28-Feb-18
ConNwIfIS2600 Interior Wall | soffit Drywall 7 01-Mar-18 09-Mar-18
ConNwIfIS2650 Acoustical Sealants | Drywall Taping 9 12-Mar-18 22-Mar-18
ConNwIfIS2700 Prime and One-Coat Paint 4 23-Mar-18 28-Mar-18
ConNwIfIS2750 Acoustical Ceiling Grid | MEP Trim 6 29-Mar-18 05-Apr-18
ConNwIfIS2800 Millworks | Casework | Countertops & Sills 5 23-Mar-18 29-Mar-18
ConNwIfIS2850 Carpet Flooring | Base 5 30-Mar-18 05-Apr-18
ConNwIfIS2900 Doors & Hardware 5 06-Apr-18 12-Apr-18
ConNwIfIS2950 Markerboards - Finish Trim 5 13-Apr-18 19-Apr-18Corridors | VestibulesCorridors | Vestibules 302 19-Jul-17 16-May-18
ConNwIfCV1400MEP Overhead | BIM Coordination 8 19-Jul-17 28-Jul-17
ConNwIfCV1450Pilaster | soffit Framing 8 19-Feb-18 28-Feb-18
ConNwIfCV1500Elevator | Stairwell Shaft Walls 6 31-Jul-17 07-Aug-17
ConNwIfCV1700Drywall Sheathing | Taping 13 01-Mar-18 19-Mar-18
ConNwIfCV1750Wood Pilaster Wrap | Ceiling Panels 10 20-Mar-18 02-Apr-18
ConNwIfCV1800Acoustical Ceiling Grid 6 03-Apr-18 10-Apr-18
ConNwIfCV1850Painting 5 11-Apr-18 17-Apr-18
ConNwIfCV1950MEP Ceiling Trim | Devices 7 18-Apr-18 26-Apr-18
ConNwIfCV2000Corridor | Vestibule Flooring 9 27-Apr-18 09-May-18
ConNwIfCV2050Railings | Wainscott 5 10-May-18 16-May-18
2nd Floor - Interior Finish | Systems2nd Floor - Interior Finish | Systems 230 24-Aug-17 10-Apr-18OMM SpaceOMM Space 96 24-Aug-17 27-Nov-17
ConNwIf2OMM3000Fire Sprinkler Piping 5 24-Aug-17 30-Aug-17
ConNwIfI2OMM3050Mechanical Ductwork | Insulation 5 31-Aug-17 06-Sep-17
ConNwIfI2OMM3100Electrical | Plumbing Overhead 5 31-Aug-17 06-Sep-17
ConNwIfI2OMM3150Interior Wall Framings | MEP Rough-In 5 07-Sep-17 13-Sep-17
ConNwIfI2OMM3200Interior Wall Insulation | Blocking | Backing 3 14-Sep-17 18-Sep-17
ConNwIfI2OMM3250Soffit Ceiling Framings | MEP Rough-In 6 14-Sep-17 21-Sep-17
ConNwIfI2OMM3300Interior Wall | soffit Drywall 4 22-Sep-17 27-Sep-17
ConNwIfI2OMM3350Acoustical Sealants | Drywall Taping 8 28-Sep-17 09-Oct-17
ConNwIfI2OMM3400Prime and One-Coat Paint 4 10-Oct-17 13-Oct-17
ConNwIfI2OMM3450Acoustical Ceiling Grid | MEP Trim 9 16-Oct-17 26-Oct-17
ConNwIfI2OMM3500Millworks | Casework | Countertops & Sills 7 27-Oct-17 06-Nov-17
ConNwIfI2OMM3550Carpet | Laminate Flooring & Base 7 07-Nov-17 15-Nov-17
ConNwIfI2OMM3600Doors & Hardware 5 16-Nov-17 22-Nov-17
ConNwIfI2OMM3650Markerboards | Finish trim 3 23-Nov-17 27-Nov-17OSCE SpacesOSCE Spaces 139 31-Aug-17 16-Jan-18
ConNwIfI2OSCE3700Fire Sprinkler Piping 5 31-Aug-17 06-Sep-17
ConNwIfI2OSCE3750Mechanical Ductwork | Insulation 8 07-Sep-17 18-Sep-17
ConNwIfI2OSCE3800Electrical | Plumbing Overhead 8 07-Sep-17 18-Sep-17
ConNwIfI2OSCE3850Interior Wall Framings | MEP Rough-In 13 19-Sep-17 05-Oct-17
ConNwIfI2OSCE3900Interior Wall Insulation | Blocking | Backing 6 06-Oct-17 13-Oct-17
ConNwIfI2OSCE3950Soffit Ceiling Framings | MEP Rough-In 11 06-Oct-17 20-Oct-17
ConNwIfI2OSCE4000Interior Wall | soffit Drywall 9 23-Oct-17 02-Nov-17
ConNwIfI2OSCE4050Acoustical Sealants | Drywall Taping 11 03-Nov-17 17-Nov-17
ConNwIfI2OSCE4100Prime and One-Coat Paint 6 20-Nov-17 27-Nov-17
ConNwIfI2OSCE4150Acoustical Ceiling Grid | MEP Trim 9 28-Nov-17 08-Dec-17
ConNwIfI2OSCE4200Millworks | Casework | Countertops & Sills 8 11-Dec-17 20-Dec-17
ConNwIfI2OSCE4250Carpet | Laminate Flooring & Base 9 21-Dec-17 02-Jan-18
ConNwIfI2OSCE4300Doors & Hardware 6 03-Jan-18 10-Jan-18
ConNwIfI2OSCE4350Markerboards | Finish Trim 4 11-Jan-18 16-Jan-18Instructional | Student Support SpaceInstructional | Student Support Space 110 07-Sep-17 25-Dec-17
ConNwIfI2ISSS3000Fire Sprinkler Piping 5 07-Sep-17 13-Sep-17
ConNwIfI2ISSS3050Mechanical Ductwork | Insulation 6 14-Sep-17 21-Sep-17
ConNwIfI2ISSS3100Electrical | Plumbing Overhead 6 14-Sep-17 21-Sep-17
ConNwIfI2ISSS3150Interior Wall Framings | MEP Rough-In 9 22-Sep-17 04-Oct-17
ConNwIfI2ISSS3200Interior Wall Insulation | Blocking | Backing 4 05-Oct-17 10-Oct-17
ConNwIfI2ISSS3250Soffit Ceiling Framings | MEP Rough-In 7 05-Oct-17 13-Oct-17
ConNwIfI2ISSS3300Interior Wall | soffit Drywall 7 16-Oct-17 24-Oct-17
ConNwIfI2ISSS3350Acoustical Sealants | Drywall Taping 9 25-Oct-17 06-Nov-17
ConNwIfI2ISSS3400Prime and One-Coat Paint 4 07-Nov-17 10-Nov-17
ConNwIfI2ISSS3450Acoustical Ceiling Grid | MEP Trim 7 13-Nov-17 21-Nov-17
ConNwIfI2ISSS3500Millworks | Casework | Countertops & Sills 8 22-Nov-17 01-Dec-17
ConNwIfI2ISSS3550Carpet | Laminate Flooring & Base 9 04-Dec-17 14-Dec-17
ConNwIfI2ISSS3600Doors & Hardware 4 15-Dec-17 20-Dec-17
ConNwIfI2ISSS3650Markerboards | Finish Trim 3 21-Dec-17 25-Dec-17IT | General Building SpacesIT | General Building Spaces 229 25-Aug-17 10-Apr-18
ConNwIf2ITGBS1950Mechanical | Electrical Overhead 4 25-Aug-17 30-Aug-17
ConNwIf2ITGBS2000Interior Wall Framing | MEP Rough-In 5 31-Aug-17 06-Sep-17
ConNwIf2ITGBS2050Interior Wall Insulation | Blocking | Backing 2 07-Sep-17 08-Sep-17
ConNwIf2ITGBS2100Electrical | TDR Room Drywall | Taping 6 11-Sep-17 18-Sep-17
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
08-May-18 Lobby Flooring
15-May-18 Lobby Wall Paneling | Millworks
22-May-18 Lobby Directories | Furnishings
04-Aug-17 19-Apr-18, Instructional | student Support Spaces04-Aug-17 Fire Sprinkler Piping
10-Aug-17 Mechanical Ductwork | Insulation
10-Aug-17 Electrical | Plumbing Overhead
07-Feb-18 Interior Wall Framings | MEP Rough-In
19-Feb-18 Interior Wall Insulation | Blocking | Backing
19-Feb-18 Soffit Ceiling Framings | MEP Rough-In
01-Mar-18 Interior Wall | soffit Drywall
12-Mar-18 Acoustical Sealants | Drywall Taping
23-Mar-18 Prime and One-Coat Paint
29-Mar-18 Acoustical Ceiling Grid | MEP Trim
23-Mar-18 Millworks | Casework | Countertops & Sills
30-Mar-18 Carpet Flooring | Base
06-Apr-18 Doors & Hardware
13-Apr-18 Markerboards - Finish Trim
19-Jul-17 16-May-18, Corridors | Vestibules19-Jul-17 MEP Overhead | BIM Coordination
19-Feb-18 Pilaster | soffit Framing
31-Jul-17 Elevator | Stairwell Shaft Walls
01-Mar-18 Drywall Sheathing | Taping
20-Mar-18 Wood Pilaster Wrap | Ceiling Panels
03-Apr-18 Acoustical Ceiling Grid
11-Apr-18 Painting
18-Apr-18 MEP Ceiling Trim | Devices
27-Apr-18 Corridor | Vestibule Flooring
10-May-18 Railings | Wainscott
24-Aug-17 10-Apr-18, 2nd Floor - Interior Finish | Systems
24-Aug-17 27-Nov-17, OMM Space24-Aug-17 Fire Sprinkler Piping
31-Aug-17 Mechanical Ductwork | Insulation
31-Aug-17 Electrical | Plumbing Overhead
07-Sep-17 Interior Wall Framings | MEP Rough-In
14-Sep-17 Interior Wall Insulation | Blocking | Backing
14-Sep-17 Soffit Ceiling Framings | MEP Rough-In
22-Sep-17 Interior Wall | soffit Drywall
28-Sep-17 Acoustical Sealants | Drywall Taping
10-Oct-17 Prime and One-Coat Paint
16-Oct-17 Acoustical Ceiling Grid | MEP Trim
27-Oct-17 Millworks | Casework | Countertops & Sills
07-Nov-17 Carpet | Laminate Flooring & Base
16-Nov-17 Doors & Hardware
23-Nov-17 Markerboards | Finish trim
31-Aug-17 16-Jan-18, OSCE Spaces31-Aug-17 Fire Sprinkler Piping
07-Sep-17 Mechanical Ductwork | Insulation
07-Sep-17 Electrical | Plumbing Overhead
19-Sep-17 Interior Wall Framings | MEP Rough-In
06-Oct-17 Interior Wall Insulation | Blocking | Backing
06-Oct-17 Soffit Ceiling Framings | MEP Rough-In
23-Oct-17 Interior Wall | soffit Drywall
03-Nov-17 Acoustical Sealants | Drywall Taping
20-Nov-17 Prime and One-Coat Paint
28-Nov-17 Acoustical Ceiling Grid | MEP Trim
11-Dec-17 Millworks | Casework | Countertops & Sills
21-Dec-17 Carpet | Laminate Flooring & Base
03-Jan-18 Doors & Hardware
11-Jan-18 Markerboards | Finish Trim
07-Sep-17 25-Dec-17, Instructional | Student Support Space07-Sep-17 Fire Sprinkler Piping
14-Sep-17 Mechanical Ductwork | Insulation
14-Sep-17 Electrical | Plumbing Overhead
22-Sep-17 Interior Wall Framings | MEP Rough-In
05-Oct-17 Interior Wall Insulation | Blocking | Backing
05-Oct-17 Soffit Ceiling Framings | MEP Rough-In
16-Oct-17 Interior Wall | soffit Drywall
25-Oct-17 Acoustical Sealants | Drywall Taping
07-Nov-17 Prime and One-Coat Paint
13-Nov-17 Acoustical Ceiling Grid | MEP Trim
22-Nov-17 Millworks | Casework | Countertops & Sills
04-Dec-17 Carpet | Laminate Flooring & Base
15-Dec-17 Doors & Hardware
21-Dec-17 Markerboards | Finish Trim
25-Aug-17 10-Apr-18, IT | General Building Spaces25-Aug-17 Mechanical | Electrical Overhead
31-Aug-17 Interior Wall Framing | MEP Rough-In
07-Sep-17 Interior Wall Insulation | Blocking | Backing
11-Sep-17 Electrical | TDR Room Drywall | Taping
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 11 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConNwIf2ITGBS2150Electrical | TDR Room Paint | Plywood Backboard 3 19-Sep-17 21-Sep-17
ConNwIf2ITGBS2200Electrical | TDR Room Concrete Floor Grind | Sealer 3 22-Sep-17 26-Sep-17
ConNwIf2ITGBS2250Electrical Room Transformer | Panels 12 27-Sep-17 12-Oct-17
ConNwIf2ITGBS2300Restroom Ceiling Framing | MEP Rough-In 7 07-Sep-17 15-Sep-17
ConNwIf2ITGBS2350Restroom Wall | Ceiling Sheathing 5 18-Sep-17 22-Sep-17
ConNwIf2ITGBS2400Restroom Drywall Taping | One-Coat Painting 7 25-Sep-17 03-Oct-17
ConNwIf2ITGBS2450Restroom Countertops 2 04-Oct-17 05-Oct-17
ConNwIf2ITGBS2500Restroom Floor | Wall Tile 9 06-Oct-17 18-Oct-17
ConNwIf2ITGBS2550Restroom Plumbing | Lighting Fixtures 6 19-Oct-17 26-Oct-17
ConNwIf2ITGBS2600Restroom Partitions | Accessories 6 27-Oct-17 03-Nov-17
ConNwIf2ITGBS2650Restroom | Storage Room Doors 3 06-Nov-17 08-Nov-17
ConNwIf2ITGBS2700Open Lobby Drywall | Taping | Painting 15 21-Mar-18 10-Apr-18
ConNwIf2ITGBS2750Open Lobby Precast Stair Treads 5 22-Sep-17 28-Sep-17
ConNwIf2ITGBS2800Open Lobby Decorative Stair Railings 5 20-Sep-17 26-Sep-17
ConNwIf2ITGBS2850Open Lobby Flooring 8 28-Mar-18 06-Apr-18Corridors | VestibulesCorridors | Vestibules 167 25-Aug-17 07-Feb-18
ConNwIf2CV1550MEP Overhead | BIM Coordination 8 25-Aug-17 05-Sep-17
ConNwIf2CV1600Pilaster | soffit Framing 12 25-Oct-17 09-Nov-17
ConNwIf2CV1650Elevator | Stairwell | Mechanical Shaft Walls 6 06-Sep-17 13-Sep-17
ConNwIf2CV1850Drywall Sheathing | Taping 15 10-Nov-17 30-Nov-17
ConNwIf2CV1900Wood Pilaster Wrap | Ceiling Panels 12 01-Dec-17 18-Dec-17
ConNwIf2CV2150Acoustical Ceiling Grid 10 19-Dec-17 01-Jan-18
ConNwIf2CV2175Painting 6 02-Jan-18 09-Jan-18
ConNwIf2CV2200MEP Ceiling Trim | Devices 8 10-Jan-18 19-Jan-18
ConNwIf2CV2250Corridor | Vestibule Flooring 8 22-Jan-18 31-Jan-18
ConNwIf2CV2300Railings | Wainscott 5 01-Feb-18 07-Feb-18
3rd Floor - Interior Finish | Systems3rd Floor - Interior Finish | Systems 198 27-Sep-17 12-Apr-18Faculty Office SpaceFaculty Office Space 157 03-Oct-17 08-Mar-18
ConNwIf3FOS3000Fire Sprinkler Piping 6 03-Oct-17 10-Oct-17
ConNwIf3FOS3050Mechanical Ductwork | Insulation 8 11-Oct-17 20-Oct-17
ConNwIf3FOS3100Electrical | Plumbing Overhead 8 11-Oct-17 20-Oct-17
ConNwIf3FOS3150Interior Wall Framings | MEP Rough-In 14 23-Oct-17 09-Nov-17
ConNwIf3FOS3200Interior Wall Insulation | Blocking | Backing 6 10-Nov-17 17-Nov-17
ConNwIf3FOS3250Soffit Ceiling Framings | MEP Rough-In 12 10-Nov-17 27-Nov-17
ConNwIf3FOS3300Interior Wall | soffit Drywall 12 28-Nov-17 13-Dec-17
ConNwIf3FOS3350Acoustical Sealants | Drywall Taping 12 14-Dec-17 29-Dec-17
ConNwIf3FOS3400Prime and One-Coat Paint 6 01-Jan-18 08-Jan-18
ConNwIf3FOS3450Acoustical Ceiling Grid | MEP Trim 12 09-Jan-18 24-Jan-18
ConNwIf3FOS3500Millworks | Casework | Countertops & Sills 8 25-Jan-18 05-Feb-18
ConNwIf3FOS3550Carpet Flooring | Base 9 06-Feb-18 16-Feb-18
ConNwIf3FOS3600Doors & Hardware 8 19-Feb-18 28-Feb-18
ConNwIf3FOS3650Markerboards | Finish Trim 6 01-Mar-18 08-Mar-18Admin Office | Student Suppor SpaceAdmin Office | Student Suppor Space 129 11-Oct-17 16-Feb-18
ConNwIf3AOSSS3000Fire Sprinkler Piping 6 11-Oct-17 18-Oct-17
ConNwIf3AOSSS3050Mechanical Ductwork | Insulation 6 19-Oct-17 26-Oct-17
ConNwIf3AOSSS3100Electrical | Plumbing Overhead 6 19-Oct-17 26-Oct-17
ConNwIf3AOSSS3150Interior Wall Framings | MEP Rough-In 10 27-Oct-17 09-Nov-17
ConNwIf3AOSSS3200Interior Wall Insulation | Blocking | Backing 5 10-Nov-17 16-Nov-17
ConNwIf3AOSSS3250Soffit Ceiling Framings | MEP Rough-In 8 10-Nov-17 21-Nov-17
ConNwIf3AOSSS3300Interior Wall | soffit Drywall 12 22-Nov-17 07-Dec-17
ConNwIf3AOSSS3350Acoustical Sealants | Drywall Taping 12 08-Dec-17 25-Dec-17
ConNwIf3AOSSS3400Prime and One-Coat Paint 5 26-Dec-17 01-Jan-18
ConNwIf3AOSSS3450Acoustical Ceiling Grid | MEP Trim 9 02-Jan-18 12-Jan-18
ConNwIf3AOSSS3500Millworks | Casework | Countertops & Sills 8 15-Jan-18 24-Jan-18
ConNwIf3AOSSS3550Carpet Flooring | Base 8 25-Jan-18 05-Feb-18
ConNwIf3AOSSS3600Doors & Hardware 6 06-Feb-18 13-Feb-18
ConNwIf3AOSSS3650Markerboards | Finish Trim 3 14-Feb-18 16-Feb-18IT | General Building SpacesIT | General Building Spaces 182 27-Sep-17 27-Mar-18
ConNwIf3ITGBS2900Mechanical | Electrical Overhead 3 11-Oct-17 13-Oct-17
ConNwIf3ITGBS2950Interior Wall Framing | MEP Rough-In 4 16-Oct-17 19-Oct-17
ConNwIf3ITGBS3000Interior Wall Insulation | Blocking | Backing 2 20-Oct-17 23-Oct-17
ConNwIf3ITGBS3050Electrical | TDR Room Drywall | Taping 4 24-Oct-17 27-Oct-17
ConNwIf3ITGBS3100Electrical | TDR Room Paint | Plywood Backboard 3 30-Oct-17 01-Nov-17
ConNwIf3ITGBS3150Electrical | TDR Room Concrete Floor Grind | Sealer 2 02-Nov-17 03-Nov-17
ConNwIf3ITGBS3200Electrical Room Transformer | Panels | Switchgear 12 06-Nov-17 21-Nov-17
ConNwIf3ITGBS3250Restroom Ceiling Framing | MEP Rough-In 6 20-Oct-17 27-Oct-17
ConNwIf3ITGBS3300Restroom Wall | Ceiling Sheathing 2 30-Oct-17 31-Oct-17
ConNwIf3ITGBS3350Restroom Drywall Taping | One-Coat Painting 7 01-Nov-17 09-Nov-17
ConNwIf3ITGBS3400Restroom Countertops 2 10-Nov-17 13-Nov-17
ConNwIf3ITGBS3450Restroom Floor | Wall Tile 8 14-Nov-17 23-Nov-17
ConNwIf3ITGBS3500Restroom Plumbing | Lighting Fixtures 6 24-Nov-17 01-Dec-17
ConNwIf3ITGBS3550Restroom Partitions | Accessories 5 04-Dec-17 08-Dec-17
ConNwIf3ITGBS3600Restroom | Storage Room Doors 2 11-Dec-17 12-Dec-17
ConNwIf3ITGBS3650Open Lobby Drywall | Taping | Painting 15 28-Feb-18 20-Mar-18
ConNwIf3ITGBS3700Open Lobby Precast Stair Treads 5 29-Sep-17 05-Oct-17
ConNwIf3ITGBS3750Open Lobby Decorative Stair Railings 5 27-Sep-17 03-Oct-17
ConNwIf3ITGBS3800Open Lobby Flooring 5 21-Mar-18 27-Mar-18Corridors | VestibulesCorridors | Vestibules 191 04-Oct-17 12-Apr-18
ConNwIf3CV1700MEP Overhead | BIM Coordination 8 04-Oct-17 13-Oct-17
ConNwIf3CV1750Pilaster | soffit Framing 10 05-Jan-18 18-Jan-18
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
19-Sep-17 Electrical | TDR Room Paint | Plywood Backboard
22-Sep-17 Electrical | TDR Room Concrete Floor Grind | Sealer
27-Sep-17 Electrical Room Transformer | Panels
07-Sep-17 Restroom Ceiling Framing | MEP Rough-In
18-Sep-17 Restroom Wall | Ceiling Sheathing
25-Sep-17 Restroom Drywall Taping | One-Coat Painting
04-Oct-17 Restroom Countertops
06-Oct-17 Restroom Floor | Wall Tile
19-Oct-17 Restroom Plumbing | Lighting Fixtures
27-Oct-17 Restroom Partitions | Accessories
06-Nov-17 Restroom | Storage Room Doors
21-Mar-18 Open Lobby Drywall | Taping | Painting
22-Sep-17 Open Lobby Precast Stair Treads
20-Sep-17 Open Lobby Decorative Stair Railings
28-Mar-18 Open Lobby Flooring
25-Aug-17 07-Feb-18, Corridors | Vestibules25-Aug-17 MEP Overhead | BIM Coordination
25-Oct-17 Pilaster | soffit Framing
06-Sep-17 Elevator | Stairwell | Mechanical Shaft Walls
10-Nov-17 Drywall Sheathing | Taping
01-Dec-17 Wood Pilaster Wrap | Ceiling Panels
19-Dec-17 Acoustical Ceiling Grid
02-Jan-18 Painting
10-Jan-18 MEP Ceiling Trim | Devices
22-Jan-18 Corridor | Vestibule Flooring
01-Feb-18 Railings | Wainscott
27-Sep-17 12-Apr-18, 3rd Floor - Interior Finish | Systems
03-Oct-17 08-Mar-18, Faculty Office Space03-Oct-17 Fire Sprinkler Piping
11-Oct-17 Mechanical Ductwork | Insulation
11-Oct-17 Electrical | Plumbing Overhead
23-Oct-17 Interior Wall Framings | MEP Rough-In
10-Nov-17 Interior Wall Insulation | Blocking | Backing
10-Nov-17 Soffit Ceiling Framings | MEP Rough-In
28-Nov-17 Interior Wall | soffit Drywall
14-Dec-17 Acoustical Sealants | Drywall Taping
01-Jan-18 Prime and One-Coat Paint
09-Jan-18 Acoustical Ceiling Grid | MEP Trim
25-Jan-18 Millworks | Casework | Countertops & Sills
06-Feb-18 Carpet Flooring | Base
19-Feb-18 Doors & Hardware
01-Mar-18 Markerboards | Finish Trim
11-Oct-17 16-Feb-18, Admin Office | Student Suppor Space11-Oct-17 Fire Sprinkler Piping
19-Oct-17 Mechanical Ductwork | Insulation
19-Oct-17 Electrical | Plumbing Overhead
27-Oct-17 Interior Wall Framings | MEP Rough-In
10-Nov-17 Interior Wall Insulation | Blocking | Backing
10-Nov-17 Soffit Ceiling Framings | MEP Rough-In
22-Nov-17 Interior Wall | soffit Drywall
08-Dec-17 Acoustical Sealants | Drywall Taping
26-Dec-17 Prime and One-Coat Paint
02-Jan-18 Acoustical Ceiling Grid | MEP Trim
15-Jan-18 Millworks | Casework | Countertops & Sills
25-Jan-18 Carpet Flooring | Base
06-Feb-18 Doors & Hardware
14-Feb-18 Markerboards | Finish Trim
27-Sep-17 27-Mar-18, IT | General Building Spaces11-Oct-17 Mechanical | Electrical Overhead
16-Oct-17 Interior Wall Framing | MEP Rough-In
20-Oct-17 Interior Wall Insulation | Blocking | Backing
24-Oct-17 Electrical | TDR Room Drywall | Taping
30-Oct-17 Electrical | TDR Room Paint | Plywood Backboard
02-Nov-17 Electrical | TDR Room Concrete Floor Grind | Sealer
06-Nov-17 Electrical Room Transformer | Panels | Switchgear
20-Oct-17 Restroom Ceiling Framing | MEP Rough-In
30-Oct-17 Restroom Wall | Ceiling Sheathing
01-Nov-17 Restroom Drywall Taping | One-Coat Painting
10-Nov-17 Restroom Countertops
14-Nov-17 Restroom Floor | Wall Tile
24-Nov-17 Restroom Plumbing | Lighting Fixtures
04-Dec-17 Restroom Partitions | Accessories
11-Dec-17 Restroom | Storage Room Doors
28-Feb-18 Open Lobby Drywall | Taping | Painting
29-Sep-17 Open Lobby Precast Stair Treads
27-Sep-17 Open Lobby Decorative Stair Railings
21-Mar-18 Open Lobby Flooring
04-Oct-17 12-Apr-18, Corridors | Vestibules04-Oct-17 MEP Overhead | BIM Coordination
05-Jan-18 Pilaster | soffit Framing
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 12 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Activity ID Activity Name Original
Duration
Start Finish
ConNwIf3CV1800Elevator | Stairwell | Mechanical Shaft Walls 10 16-Oct-17 27-Oct-17
ConNwIf3CV1950Drywall Sheathing | Taping 13 19-Jan-18 06-Feb-18
ConNwIf3CV2000Wood Pilaster Wrap | Ceiling Panels 9 07-Feb-18 19-Feb-18
ConNwIf3CV2225Painting 6 20-Feb-18 27-Feb-18
ConNwIf3CV2400Acoustical Ceiling Grid 9 28-Feb-18 12-Mar-18
ConNwIf3CV2450MEP Ceiling Trim | Devices 9 13-Mar-18 23-Mar-18
ConNwIf3CV2500Corridor | Vestibule Flooring 9 26-Mar-18 05-Apr-18
ConNwIf3CV2550Railings | Wainscott 5 06-Apr-18 12-Apr-18
Services | Commissioning | ActivationServices | Commissioning | Activation 332 12-Sep-17 10-Aug-18
ConSCA1000 Main Switchgear Energized 5 03-Jan-18 09-Jan-18
ConSCA1050 Domestic Water Service Meter 5 12-Sep-17 18-Sep-17
ConSCA1100 Fire Sprinkler System Charged 5 16-Nov-17 22-Nov-17
ConSCA1150 Elevator Delivery | Installation 20 21-Feb-18 20-Mar-18
ConSCA1200 Phone Demark | Dial Tone 5 01-Feb-18* 07-Feb-18
ConSCA1250 Air Handling Unit Start-Ups 5 04-Apr-18 10-Apr-18
ConSCA1300 Boiler Start-Up 5 25-Apr-18 01-May-18
ConSCA1350 Exhaust | Supply Fans Start Up 5 02-May-18 08-May-18
ConSCA1400 Test Air & Balance 20 09-May-18 05-Jun-18
ConSCA1450 Building Purge | Duct Cleaning 10 06-Jun-18 19-Jun-18
ConSCA1500 ATC | BAS Controls Programming 30 23-May-18 03-Jul-18
ConSCA1525 Security System | Camera Equipment Install - FF&E 20 01-Jun-18* 28-Jun-18
ConSCA1550 Owner Occupancy Plan 0 02-Apr-18*
ConSCA1600 Fire Alarm Testing 15 16-Apr-18* 04-May-18
ConSCA1650 Elevator Inspection 5 02-May-18 08-May-18
ConSCA1700 DBS Life Safety | Trade Final Inspections 15 09-May-18 29-May-18
ConSCA1750 Punchlist Detailing 10 14-May-18* 25-May-18
ConSCA1800 Access Control Programming | Door Keying 10 01-May-18* 14-May-18
ConSCA1825 Final Construction Cleaning 5 21-May-18 25-May-18
ConSCA1850 Letters of Conformance 3 28-May-18 30-May-18
ConSCA1900 Certificate of Occupancy 0 31-May-18
ConSCA1950 Substantial Completion 0 01-Jun-18
ConSCA2000 Owner Benficial Occupancy | Move-In 20 01-Jun-18 28-Jun-18
ConSCA2050 Operational Monitoring | Testing 20 01-Jun-18 28-Jun-18
ConSCA2100 Move-In Repairs | Cleaning 10 29-Jun-18 12-Jul-18
ConSCA2150 Final Punchlist Completion | Verification 5 13-Jul-18 19-Jul-18
ConSCA2200 Notice of Final Completion 0 20-Jul-18
ConSCA2300 First Day of Class 0 10-Aug-18*
Post-ConstructionPost-Construction 444 01-May-18 19-Jul-19
PostC1000 O&M Manual Assembly | Delivery 20 01-May-18* 28-May-18
PostC1050 As-Built Drawings 20 01-Jun-18* 28-Jun-18
PostC1100 Operations & Maintenance Personnel Training 20 01-Jun-18* 28-Jun-18
PostC2150 Construction Contract Closeout 15 20-Jul-18 09-Aug-18
PostC2175 Final Retention Billing 0 24-Aug-18
PostC2250 Final Project Review | Report - Lessons Learned 0 07-Sep-18
PostC2350 11 Month Warranty Walk 0 19-Jul-19
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
16-Oct-17 Elevator | Stairwell | Mechanical Shaft Walls
19-Jan-18 Drywall Sheathing | Taping
07-Feb-18 Wood Pilaster Wrap | Ceiling Panels
20-Feb-18 Painting
28-Feb-18 Acoustical Ceiling Grid
13-Mar-18 MEP Ceiling Trim | Devices
26-Mar-18 Corridor | Vestibule Flooring
06-Apr-18 Railings | Wainscott
12-Sep-17 10-Aug-18, Services | Commissioning | Activation
03-Jan-18 Main Switchgear Energized
12-Sep-17 Domestic Water Service Meter
16-Nov-17 Fire Sprinkler System Charged
21-Feb-18 Elevator Delivery | Installation
01-Feb-18* Phone Demark | Dial Tone
04-Apr-18 Air Handling Unit Start-Ups
25-Apr-18 Boiler Start-Up
02-May-18 Exhaust | Supply Fans Start Up
09-May-18 Test Air & Balance
06-Jun-18 Building Purge | Duct Cleaning
23-May-18 ATC | BAS Controls Programming
01-Jun-18* Security System | Camera Equipment Install - FF&E
02-Apr-18* Owner Occupancy Plan
16-Apr-18* Fire Alarm Testing
02-May-18 Elevator Inspection
09-May-18 DBS Life Safety | Trade Final Inspections
14-May-18* Punchlist Detailing
01-May-18* Access Control Programming | Door Keying
21-May-18 Final Construction Cleaning
28-May-18 Letters of Conformance
31-May-18 Certificate of Occupancy
01-Jun-18 Substantial Completion
01-Jun-18 Owner Benficial Occupancy | Move-In
01-Jun-18 Operational Monitoring | Testing
29-Jun-18 Move-In Repairs | Cleaning
13-Jul-18 Final Punchlist Completion | Verification
20-Jul-18 Notice of Final Completion
10-Aug-18* First Day of Class
01-May-18
01-May-18* O&M Manual Assembly | Delivery
01-Jun-18* As-Built Drawings
01-Jun-18* Operations & Maintenance Personnel Training
20-Jul-18 Construction Contract Closeout
24-Aug-18 Final Retention Billing
07-Sep-18 Final Project Review | Report - Lessons Learned
Idaho College of Osteopathic Medicine | Boise, Idaho
Conceptual Project Delivery Schedule
Date Revision Checked Approved
01-Dec-16 DRAFT - Conceptual JN JN
05-Dec-16 DRAFT - Conceptual Rev.1 JN CG
Page 13 of 13 Information is Proprietary & Confidential - Redistribution or use without prior written authorization is prohibited. Schedule is preliminary and conceptual - intended to provide a general understanding of potential
pathway to completion. Schedule is not intended to capture all task items necessary for completion of project scope.
Staging area Option 1A
Gated entry point
Storage Trailers andSubcontractor Parking
Option 1B
Right E. Corporate Drive
Right E. Watertower Ln Right S. Locust Grove Rd.
Construction Entrance Irrigation Canal
Maintenance Road
Right S. Stratford Dr.
Storage Trailers andSubcontractor Parking
Option 1C
E. Central Drive
I84 West
S. Meridian Rd
Idaho College of Osteopathic Medicine
Conceptual Logistics Plan Delivery Travel Routing
E. Central Drive
Idaho Collegeof Osteopathic
Medicine
So. Locust Grove Rd | E. Central Drive
Idaho College of Osteopathic Medicine
Conceptual Logistics PlanAlternative Site Access | Irrigation Canal Maintenance Rood
Construction Site
Delivery Staging
Canal Bridge
Alternative Site Access Approach
Main site entry and exit will occur via irrigation canalmaintenance road, east of ISU parking lot entrance off E.Central Drive. Secondary delivery staging area is rentedfarm space with driveway access from So. Locust Grove.
Rented ACE bridge placed over irrigation canal forconnection of staging area with site access drive.
Intersection of South Locust Grove |
East Central Drive
Canal Road
Partial sidewalk removal
Driveway Approach
Grade Cut & Stabilize
Gated Site Entry
Canal Maintenance Road
Canal Maintenance Road
Idaho College ofOsteopathic medicine
Crane &Floor
Loading
Gates
Gates
6' screened chainlink fence
6' screened chainlink fence
Gates
Waste
Concrete
Wash
Toilets
Storage
Conex Boxes
Crushed RockDriveway
Toilets
Material Unloading& truck Turnaround
Construction
Office Trailer
ACE TempCanal Bridge
Gates
Inspector | Guest
Parking
Material PreFab |
Secured Storage
Con
struc
tion
Offi
ce Tr
aile
r
GenSet
Fire Dept. Access
Fire Dept. Access
College of Osteopathic Medicine
Site Logistics Plan Equipment | Materials | Processing
Prim
ary
Deliv
ery
Acce
ss R
oad