ICIMOD Seminar Kathmandu Dec.3 4, 2013 MAHAKALI … Mahakali... · India:DhauliGanga, Gori, Ram...

31
ICIMOD Seminar KathmanduDec.34, 2013 MAHAKALI FLOODJUNE 2013 Case Study Presented by: Prakash Paudel

Transcript of ICIMOD Seminar Kathmandu Dec.3 4, 2013 MAHAKALI … Mahakali... · India:DhauliGanga, Gori, Ram...

ICIMOD Seminar ‐Kathmandu‐ Dec.3‐4, 2013

MAHAKALI FLOOD‐ JUNE 2013

Case Study Presented by:

Prakash Paudel

MONSOON BACKGROUND

June 2013

Monsoon Activation in June 2013

Common Glacier Range in the Himalayas

Er. Prakash Paudel

General Interpretation(Common Flooding Process adapted from USAC Report)

• Heavy Rainfall and Cloudburst in the area• Melting of Glacier to add run‐off• Heavy land erosion, slides and mass‐movement insaturated fragile geology

• Heavily loaded water flow (flood) triggeringfurther devastation

• More loss in Unprotected area and low levelsettlement while protected area more Safe

• Failure or opening of Water body add to moreflooding and devastation

Er. Prakash Paudel

MAHAKALI‐A Major Border River in Nepal

Mahakali & Its Tributaries

Mahakali Catchment1. Length of the River: 233 Km.2. Tributaries: 

India: Dhauli Ganga, Gori, Ram GangaNepal: Chamelia , Surnaya & Rangun

3. Catchment area: 15260 sq.km. India: 9943 sq.km.; Nepal: 5317 sq.km.

6. Maximum Historical Discharge: 14915 m3/s 7. Average discharge: 557 m3/s8. Average rainfall Intensity: 1891 mm (1990).9. Max. rainfall intensity: 3055 mm (1990).

Extreme Rainfall in the Area

24‐Hr 17‐18 June 2013Monthly Rainfall in Dipayal:June 2013 (221 mm measured on June 18)

Extreme Rainfall & Flood Discharge in the Area in June 2013

• In India, all the 13‐districts of Uttarakhanda State felt Extreme Rainfall in the week June 13‐19, 2013

• In Dipayal, Nepal also 222 mm rainfall was recorded in 24 hr (17‐18 June 2013) 

• Flood Discharge in Mahakali River in Sarda Barrage in 17‐18 June 2013 (15430 m3/sec)  exceeded the Historical Records (14915 m3/sec in 1934 AD)

Recent Flood Events : June 2013(Kedarnathji Area)

Kedarnath City  washed awayRoad to Gauri kund collapsed

Er. Prakash Paudel

Flood Measurement (Cusecs) in Mahakali(River Discharge from 17-June:00 hrs. to 18-Jun:1200 hrs.)

200

250

300

350

400

450

500

550

600

12 15 18 21 24 27 30 33 36

Thou

sand

s

Measured Data100‐Y (Design)

Er. Prakash Paudel

DISASTER EVENTS

PHOTO FEATURE

The Darchula Disaster• Light rainfall on 17‐Jun Day time• Flood in Mahakali started on Mid‐night 17th

• People in Darchula Khalanga started to evacuate their houses, shops and utilized structures from mid‐night (Tapovan, Bangabazar, Main Bazar, Golphai and Namaskar)

• In the morning Mahakali carried muddy flow full of debris which was deposited on full river width

• Heavy devastation started from morning of 18th

• Flow diverted to Left to enhance Channelization on this side with deposition process on the  Right

River Bank Settlement in Darchula HQ

INDIA

TOWN SETTLEMENTDIVERSION STUDS

ROAD WAYDIVERSION STUDS

GARDENR.C.C. RETAINING WALL

MAJOR DIVERSION STRUCTURES

THE RIVER MAHAKALI

NEPAL DIVERSION STRUCTURES

LOW‐LAND SETTLEMENTTOWN SETTLEMENT

Er. Prakash Paudel

Loss Estimation in Darchula

HUMAN LIFE: 00 LAND LOSS 29 Ha.HOUSE (FULLY) 129 No. HUTS (FULL) 32 No.HOUSE (PARTIAL) 55   No. EDUCATION 7    No.HOUSE (RISK) 167 No. ROADS 4 Kms

Protection Wall in River Bank, Landslide (meter): 9350Cost of Replacement of Structure Land (M.NRs.): 3150Cost of Mitigation/Protection Structures (M.NRs.): 2025Cost of Emergency Mitigation Works (M.NRs.): 25

Area affected: Dasarathnagar; Chhengru/Ringertali; Ghat bazar;  Tinkerkheda; Main Khalanga; Hospital; Galphai; Ghatta; Namaskar; Other Villages in Khalanga; Other VDCs.

Dhauliganga Dam Section

SECTION THROUGH CONDUIT SPILLWAY

Er. Prakash Paudel

Dhauliganga HEP Project : InformationS. N. ITEMS DATA UNIT01 CATHMENT AREA 1360 Sq. Km.02 DESIGN FLOOD DISCHARGE 3210 Cu. m./sec.03 TOTAL POWER (4 No. X 70) 280 M.W.04 DAM HEIGHT 56 meter05 ACTIVE RESERVOIR CAPACITY 1.54 Million Cu.m.06 TOTAL RESERVOIR CAPACITY 6.20 Million Cu.m.07 POND (MAX. WATER) LEVEL 1348.50 meter

08 FULL SUPPLY LEVEL 1345.00 meter09 MIN. POWER OPERATING LEVEL 1330.00 meter10 SLUICE CAPACITY 3210 Cu. m./sec.11 SLUICE CREST LEVEL 1302.00 (?) Meter12 SLUICE GATE OPENING (3X10X6) 180 Sq. meter

Er. Prakash Paudel

Observation on Sluice (Spillway) Operation

• Crest of Sluice Gates are 46.5 m. below Pond Leveland 28.0 m. below the minimum operating level

• Sluice Gates have full capacity to discharge thedesign flood of the river viz. 3210 Cu. m. / sec

• The Project broucher (POYRY) explains that the gatedSpillway or the Sluices are designed“……. to efficient flushing (of sediment) from thereservoir during periods of flood.”

• Hence when the reservoir is having excess water orsediment, the Sluice Gates are normally opened

Er. Prakash Paudel

Impression on Flood Event

• On the day of heavy rainfall, the soil of the areacrossed the limit of Saturation and failed stability,hence started falling down along with Water

• Like other rivers, Dhauliganga carried larger amountof heavy sediment and debris entering the reservoir

• In Dhauliganga Dam Power channel was closed andSluices were opened on the day to flush out theSediment during filling of the Reservoir

• The river Dhauliganga combined with main Mahakaliriver in Tawaghat which ultimately triggered Darchula

Er. Prakash Paudel

Bank Erosion by Mahakali

AFTER June 17 flood

Washed Road Way

Er. Prakash Paudel

Main Bazar Falling

Er. Prakash Paudel

Effect on Downstream of Mahakali

Downstream of Sarada Barrage Banbasa (India) and Kanchanpur (Nepal)

Er. Prakash Paudel

Flooding in Mahakali River(Downstream of Sarda Barrage cum Bridge)

11Bhujela

1213, Pipariya

BHIMDATTA  

N‐I Border

Suspension Bridge

Barrage

CHANDANI SARDA NAHAR(INDIA)

MAHAKALI NAHAR(NEPAL) 

MAHAKALI RIVER

Esc. Ch. DODHARA

(Not in Scale)N

Er. Prakash Paudel

Pipariya: Buried Settlement/Agriculture

STATUS & REQUIREMENT

RECORD MANAGEMENT, INFORMATION SHARING &FORECASTING MECHANISM

Status of Records, Analysis & Communication

• Less attention paid to this area regarding analysis of Rainfall data & Flood forecasting

• No Hydrological Stations established on middle & upper part of Mahakali (Nepal)

• Flood data managed by India in Tanakpur/Banbasa• No on‐time data sharing mechanism between Nepal & India

• Very poor information sharing system between stake holders inside the country

• Poor lesson learning practice and less public‐awareness 

RECOMMENDATIONS

1. Real time data mechanism for Mahakali and its major Tributaries

2. Real Time Data accessible to the Stakeholders3. The flood forecasting & Information mechanism4. Effective Warning system & Awareness Program5. Legal provision & Practical action against River 

Encroachment6. Committed Master (Action) Plan by the 

Government with adequate shared resources 

THANK YOU ALL !

Mahakali River Flood in Darchula Nepal _18-June-2013.mp4