Edition 3 / Revision 1 TRANSPORT FOR NSW June 2020 TRANSPORT FOR NSW (TfNSW) QA SPECIFICATION B261 ERECTION OF STRUCTURAL ALUMINIUM NOTICE This document is a Transport for NSW QA Specification. It has been developed for use with roadworks and bridgeworks contracts let by Transport for NSW or by local councils in NSW. It is not suitable for any other purpose and must not be used for any other purpose or in any other context. Copyright in this document belongs to Transport for NSW. REVISION REGISTER Ed/Rev Number Clause Number Description of Revision Authorised By Date Ed 1/Rev 0 First Issued GM,CMS 25.11.91 Ed 2/Rev 0 Converted to Word 6 format and clause numbers changed. GM, RNIC (W Ho) 23.07.97 Clauses renumbered. 1.2 References updated. 1.3 Hold Point replaced by QUALITY PLAN submissions. 5 Hold Points re-defined 5, 7 Surveyor’s qualifications defined. 6 Clause - Service Bolts deleted Ed 2/Rev 1 Annexure B261/1 New schedule listing Identified Records GM, RNIC 03.05.00 Ed 3/Rev 0 “Notice” RTA PO Box and Fax numbers updated GM, IC 15.05.09 Foreword Foreword, incorporating copyright clause, added Global Text revised to direct imperative style. “shall” replaced by “must”. Clauses rearranged and renumbered. Reformatting and minor editing to clarify intent. 1.2.5 Definitions of “you” and “your” added. 1.3 Retitled to “PROJECT QUALITY PLAN”. Requirement for Project Quality Plan to comply with Annexure B261/D added. Annex M References updated. Ed 3/Rev 1 Global References to “Roads and Maritime Services” or “RMS” changed to “Transport for NSW” or “TfNSW” respectively. DCS 22.06.20

Transcript of IC-QA-B261 - Erection of Structural Aluminium

Page 1: IC-QA-B261 - Erection of Structural Aluminium

Edition 3 / Revision 1 TRANSPORT FOR NSW

June 2020

TRANSPORT FOR NSW (TfNSW)

QA SPECIFICATION B261

ERECTION OF STRUCTURAL ALUMINIUM

NOTICE

This document is a Transport for NSW QA Specification. It has been developed for use with

roadworks and bridgeworks contracts let by Transport for NSW or by local councils in NSW. It is not

suitable for any other purpose and must not be used for any other purpose or in any other context.

Copyright in this document belongs to Transport for NSW.

REVISION REGISTER

Ed/Rev

Number

Clause

Number Description of Revision

Authorised

By Date

Ed 1/Rev 0 First Issued GM,CMS 25.11.91

Ed 2/Rev 0 Converted to Word 6 format and clause

numbers changed.

GM, RNIC (W Ho)

23.07.97

Clauses renumbered.

1.2 References updated.

1.3 Hold Point replaced by QUALITY PLAN

submissions.

5 Hold Points re-defined

5, 7 Surveyor’s qualifications defined.

6 Clause - Service Bolts deleted

Ed 2/Rev 1 Annexure

B261/1

New schedule listing Identified Records GM, RNIC 03.05.00

Ed 3/Rev 0 “Notice” RTA PO Box and Fax numbers updated GM, IC 15.05.09

Foreword Foreword, incorporating copyright clause,

added

Global Text revised to direct imperative style.

“shall” replaced by “must”.

Clauses rearranged and renumbered.

Reformatting and minor editing to clarify

intent.

1.2.5 Definitions of “you” and “your” added.

1.3 Retitled to “PROJECT QUALITY PLAN”.

Requirement for Project Quality Plan to

comply with Annexure B261/D added.

Annex M References updated.

Ed 3/Rev 1 Global References to “Roads and Maritime

Services” or “RMS” changed to “Transport

for NSW” or “TfNSW” respectively.

DCS 22.06.20

Page 2: IC-QA-B261 - Erection of Structural Aluminium
Page 3: IC-QA-B261 - Erection of Structural Aluminium

Edition 3 / Revision 1 TRANSPORT FOR NSW

June 2020

QA SPECIFICATION B261

ERECTION OF STRUCTURAL

ALUMINIUM

Copyright – Transport for NSW

IC-QA-B261

VERSION FOR:

DATE:

Page 4: IC-QA-B261 - Erection of Structural Aluminium
Page 5: IC-QA-B261 - Erection of Structural Aluminium

Erection of Structural Aluminium B261

Ed 3 / Rev 1 i

CONTENTS

CLAUSE PAGE

FOREWORD ............................................................................................................................................... II TfNSW Copyright and Use of this Document ............................................................................... ii Revisions to Previous Version ....................................................................................................... ii Project Specific Changes ............................................................................................................... ii

1 GENERAL ........................................................................................................................................ 1 1.1 Scope .............................................................................................................................. 1 1.2 Structure of the Specification ......................................................................................... 1 1.3 Planning Documents ....................................................................................................... 1

2 HANDLING AND STORAGE .............................................................................................................. 2

3 POSITIONING OF BEARINGS ............................................................................................................ 3

4 EXPANSION JOINTS......................................................................................................................... 3

5 TEMPORARY SUPPORTING STRUCTURES ....................................................................................... 3

6 ASSEMBLY...................................................................................................................................... 3 6.1 General Requirements .................................................................................................... 3 6.2 Bolted Connections ........................................................................................................ 4

7 CERTIFICATION OF PROFILE ........................................................................................................... 4

8 REMOVAL OF TEMPORARY SUPPORTING STRUCTURES ................................................................. 4

ANNEXURE B261/A – PROJECT SPECIFIC REQUIREMENTS ...................................................................... 5

ANNEXURE B261/B – (NOT USED) ........................................................................................................... 5

ANNEXURE R261/C – SCHEDULES OF HOLD POINTS AND IDENTIFIED RECORDS .................................... 5 C1 Schedule of Hold Points ................................................................................................. 5 C2 Schedule of Identified Records....................................................................................... 5

ANNEXURE B261/D – PLANNING DOCUMENTS ....................................................................................... 5

ANNEXURES B261/E TO B261/L – (NOT USED) ....................................................................................... 7

ANNEXURE B261/M – REFERENCED DOCUMENTS .................................................................................. 7

LAST PAGE OF THIS DOCUMENT IS ............................................................................................................ 7

Page 6: IC-QA-B261 - Erection of Structural Aluminium

B261 Erection of Structural Aluminium

ii Ed 3 / Rev 1

FOREWORD

TFNSW COPYRIGHT AND USE OF THIS DOCUMENT

Copyright in this document belongs to Transport for NSW.

When this document forms part of a contract

This document should be read with all the documents forming the Contract.

When this document does not form part of a contract

This copy is not a controlled document. Observe the Notice that appears on the first page of the copy

controlled by TfNSW. A full copy of the latest version of the document is available on the TfNSW

Internet website: http://www.rms.nsw.gov.au/business-industry/partners-

suppliers/specifications/index.html

REVISIONS TO PREVIOUS VERSION

This document has been revised from Specification TfNSW B261 Edition 3 Revision 0.

All revisions to the previous version (other than minor editorial and project specific changes) are

indicated by a vertical line in the margin as shown here, except when it is a new edition and the text

has been extensively rewritten.

PROJECT SPECIFIC CHANGES

Any project specific changes are indicated in the following manner:

(a) Text which is additional to the base document and which is included in the Specification is

shown in bold italics e.g. Additional Text.

(b) Text which has been deleted from the base document and which is not included in the

Specification is shown struck out e.g. Deleted Text.

Page 7: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Ed 3 / Rev 1 1

TfNSW QA SPECIFICATION B261

ERECTION OF STRUCTURAL ALUMINIUM

1 GENERAL

1.1 SCOPE

This Specification sets out the requirements for the erection of structural aluminium in bridges or

associated structures, including expansion joints.

1.2 STRUCTURE OF THE SPECIFICATION

This Specification includes a series of annexures that detail additional requirements.

1.2.1 Details of Work

Project specific details of work are shown in Annexure B261/A.

1.2.2 (Not Used)

1.2.3 Schedules of HOLD POINTS and Identified Records

The schedules in Annexure B261/C list the HOLD POINTS that must be observed. Refer to

Specification TfNSW Q for the definition of HOLD POINTS.

The records listed in Annexure B261/C are Identified Records for the purposes of TfNSW Q

Annexure Q/E.

1.2.4 Referenced Documents

Unless specified otherwise, the applicable issue of a referenced document must be the issue current at

the date one week before the closing date for tenders.

Standards, specifications and test methods are referred to in abbreviated form (e.g. AS 1234). For

convenience, the full titles are given in Annexure B261/M.

1.2.5 Definitions

The terms “you” and “your” mean “the Contractor” and “the Contractor’s” respectively.

1.3 PLANNING DOCUMENTS

The PROJECT QUALITY PLAN must include each of the documents and requirements listed in

Annexure B261/D and must be implemented.

Supply, as part of your PROJECT QUALITY PLAN, details of proposed erection equipment and

proposed erection method which must include, but not be limited to, the following:

(a) Details of proposed erection equipment, including:

Page 8: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

B261 Erection of Structural Aluminium

2 Ed 3 / Rev 1

(i) Type and capacity (at operating radius) of lifting equipment;

(ii) Site set-up of lifting equipment, including plan and elevation sketches, assessment of

supporting ground conditions, and minimum clearances to aerial electrical cables;

(iii) Length and slope of slings, diameter and safe working capacity of slings, and sling force;

(iv) Lifting device on member, lifting points, and measures to prevent damage to protective

coatings;

(v) Welding equipment and bolting equipment;

(vi) Lighting equipment if applicable;

(vii) A certificate and calculations by an Engineer who is a Member of Engineers Australia

with experience in this field to verify that the equipment nominated will be used within

safe working capacities.

(b) Details of proposed erection method, including:

(i) Falsework details including design calculations and certification by an Engineer who is a

Member of Engineers Australia with experience in this field verifying that the falsework

has been designed in accordance with the relevant Australian Standards;

(ii) Method of stabilising or bracing members during storage, assembly and erection;

(iii) Method of positioning of bearings;

(iv) Method of determining and adjusting profile;

(v) Method of alignment of components;

(vi) Method and order of assembly including temporary fixing;

(vii) Bolting procedures including method of aligning holes, method of marking bolts,

tightening and records;

(viii) Storage of components;

(ix) Record forms;

(x) Removal of falsework;

(xi) A certificate from an Engineer who is a Member of Engineers Australia with experience

in this field verifying that the proposed erection methods conform to the Specification and

the requirements of the Work Health and Safety Act.

2 HANDLING AND STORAGE

At all times, handle and store structural aluminium members so that the material, protective coatings

and parts are kept clean and free from damage.

Place aluminium to be stored on supports above the ground. Place and store girders and beams

upright. Prefabricated truss segments may be stored in the horizontal position. Adequately support all

members and segments at points sufficiently close together to prevent damage from deflection.

Sort and store all small articles, such as bolts, loose splice plates etc above ground.

Page 9: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Erection of Structural Aluminium B261

Ed 3 / Rev 1 3

3 POSITIONING OF BEARINGS

To allow for the change in length of the members under dead load and temperature variations, position

the bearings so that the horizontal distance between the centres of base plates is as shown on the

Drawings at the specified temperature.

Correct measurements for conditions different to that for which the measuring equipment is calibrated.

Minor variations in the bearing heights or grades must be taken up in the mortar pad.

4 EXPANSION JOINTS

The expansion joint details have been dimensioned for the mean temperature shown on the Drawings.

To allow for the changes in length caused by temperature variations, place the expansion joints so that

the clear distance across the expansion gap will be as shown on the Drawings at the specified

temperature.

Set the dimension of the expansion gap within the following tolerances:

for spans < 50 m – 0, + 5 mm

for spans > 50 m – 0, +10 mm

5 TEMPORARY SUPPORTING STRUCTURES

Arrange the supports for members with provision for fine adjustment to achieve the required profile

detailed on the Drawings.

Submit a certificate by a qualified Surveyor eligible for membership of the Institution of Surveyors,

Australia or the Institution of Engineering and Mining Surveyors, Australia verifying that the profile

of the formwork is in accordance with the profile shown on the Drawings. Detail allowances for

settlement and joint take-up.

HOLD POINT

Process Held: Erection of structural aluminium.

Submission Details: A certificate in accordance with Clause 5.

Release of Hold Point: The Principal will examine the certificate and may carry out surveillance and

audit, prior to authorising the release of the Hold Point.

6 ASSEMBLY

6.1 GENERAL REQUIREMENTS

Give the Principal five working days notice of your intention to commence assembly of members.

Page 10: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

B261 Erection of Structural Aluminium

4 Ed 3 / Rev 1

Assemble the members and/or components as shown on the Drawings accurately using the

identification marks. Handle the material carefully so that individual parts will not be bent, twisted or

damaged in any way.

Wherever necessary, fix adequate temporary bracing to the aluminium to ensure that the parts that

have been erected are stable and will not be overstressed. Leave such temporary bracing in position

until sufficient permanent bracing has been installed.

6.2 BOLTED CONNECTIONS

6.2.1 General Requirements

Bolts used for the erection of structural aluminium must be made from stainless steel conforming to

ASTM A276 Grade 316 and must be in accordance with TfNSW B240. Bolts must be copper free.

Joints must be bearing-type joints.

6.2.2 Tightening Method

Tighten bolts to "snug tight" condition as defined in AS 5100.6.

Check the "snug-tight" condition on joints containing more than eight bolts by a second run over the

bolts.

6.2.3 Certification of Bolting

Submit a certificate by an Engineer who is a Member of Engineers Australia with experience in this

field to verify that the bolting was carried out in accordance with the Specification.

7 CERTIFICATION OF PROFILE

Submit a diagram certified by a qualified Surveyor eligible for membership of the Institution of

Surveyors, Australia or the Institution of Engineering and Mining Surveyors, Australia that sets out the

profile of the completed member(s) in relation to the profile shown on the Drawings.

8 REMOVAL OF TEMPORARY SUPPORTING STRUCTURES

Remove all temporary structures and construction equipment before final acceptance.

Remove bed logs, temporary piles and trestles, temporary concrete bases, etc used in the construction

operation.

Do not support or attach equipment for pulling piles or for removing falsework to any portion of the

new structure.

Page 11: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Erection of Structural Aluminium B261

Ed 3 / Rev 1 5

ANNEXURE B261/A – PROJECT SPECIFIC REQUIREMENTS

Insert any project specific requirements here. If there are none, delete this comment and replace the

title with “(NOT USED)”

ANNEXURE B261/B – (NOT USED)

ANNEXURE R261/C – SCHEDULES OF HOLD POINTS AND

IDENTIFIED RECORDS

Refer to Clause 1.2.3.

C1 SCHEDULE OF HOLD POINTS

Clause Description

5 Falsework Profile

C2 SCHEDULE OF IDENTIFIED RECORDS

The records listed below are Identified Records for the purposes of TfNSW Q Annexure Q/E.

Clause Description of Identified Record

6.2.3 Certificate by a qualified Engineer to verify that the bolting was carried out in

accordance with the Specification

7 Diagram certified by Surveyor that sets out the profile of the completed member(s) in

relation to the profile shown on the Drawings

ANNEXURE B261/D – PLANNING DOCUMENTS

Refer to Clause 1.3.

The following documents are a summary of documents that must be included in the PROJECT

QUALITY PLAN. The requirements of this Specification and others included in the Contract must be

reviewed to determine documentation requirements in addition to the following:

The information to be submitted as part of the PROJECT QUALITY PLAN must include, but is not

limited to, the following:

(a) Details of the proposed erection equipment and proposed erection method (Clause 1.3);

(b) Details of method of handling and storage of structural aluminium members (Clause 2);

Page 12: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

B261 Erection of Structural Aluminium

6 Ed 3 / Rev 1

(c) Details of temporary supporting structures (Clause 5)

Page 13: IC-QA-B261 - Erection of Structural Aluminium

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Erection of Structural Aluminium B261

Ed 3 / Rev 1 7

ANNEXURES B261/E TO B261/L – (NOT USED)

ANNEXURE B261/M – REFERENCED DOCUMENTS

Refer to Clause 1.2.4.

TfNSW Specifications

TfNSW Q Quality Management System

TfNSW B240 Steel Fasteners

Australian Standards

AS 5100 Bridge design

AS 5100.6 Steel and composite construction

ASTM Standards

ASTM A276 Standard Specification for Stainless Steel Bars and Shapes

NSW Government

Work Health and Safety Act 2011