IBM SCPM MCV Page. September 14, 2014. Navigating the MCV Page. 1. Calendar View Selectors. 2. Refresh Button. Tip: Selecting the Start Date and End Date on the MCV page only sets the date range for the current MCV page. You can set the default date - PowerPoint PPT Presentation

Transcript of IBM SCPM MCV Page

Page 1: IBM SCPM MCV Page

© 2004 E2open. All Rights Reserved.

IBM SCPM MCV Page

April 21, 2023

Page 2: IBM SCPM MCV Page

2SCPM April 21, 2023

Navigating the MCV Page

1. Calendar View Selectors

2. Refresh Button

Tip: Selecting the Start Date and End Date on the MCV page only sets the date range for the current MCV page. You can set the default date range for all MCV pages at the User Preferences page.

Page 3: IBM SCPM MCV Page

3SCPM April 21, 2023

Navigating the MCV Page

1. Data Measures

3. PIT (Point-in-time)

4. Exception Alert

2. Time Buckets5. Data Measure View Tab

Export Icon

Page 4: IBM SCPM MCV Page

4SCPM April 21, 2023

Displaying Additional Data on the MCV Page

1. Click the Configure Collab View icon (A) to access the Table Configurator dialog box.

2. Select the additional data you want to view (B) and the sort order (C).

3. If you want, save your settings as default (D) and click the Update button (E).

A. Table Configurator

B. Data to View

C. Sort Order

E. UpdateD. Save as Default

Page 5: IBM SCPM MCV Page

5SCPM April 21, 2023

Displaying Additional Data on the MCV Page

1. The system displays the data in columns to the left of the Data Measures column (E).

2. If necessary click and drag to the right the Column Display icon (F) to view all the data.

E. Display Area for additional columns

F. Column Display

Page 6: IBM SCPM MCV Page

6SCPM April 21, 2023

Viewing Data Measures on the MCV Page

The system displays the Data Measures column (G) to the left of the dates column.1. Click and Data Measures icon to view all the options.2. From the Display Data Measures list, click the Data Measure name that you do NOT

want to view3. Click the < arrow button to move the Data Measure to the Available Data Measure column4. Click the Update button

G. Data Measures

1

2

3

4

Page 7: IBM SCPM MCV Page

7SCPM April 21, 2023

Collab Details Menu

• The Collab Details icon (i) provides access to collaboration-related data.

A. Message – attach a message to the collab

B. Collab Attribute – view the Material Master collab attribute values

C. Collab Description – view the collab dimensions

D. Site Attribute – view the Material Master

E. Autofill – Enter PIT data and view exceptions before submitting

F. Alternate Parts – view the alternate parts available for the collaboration

i

A

B

C

D

E

F

Page 8: IBM SCPM MCV Page

8SCPM April 21, 2023

Viewing Collab Message

i

2

1. Click the Collab Details icon to display the Collab Details dialog box.

2. Click Message to access the Message data.

3. Click the Subject line to read and reply to an existing message

or

3. Click the Envelope icon to create a new message

3

3

Page 9: IBM SCPM MCV Page

9SCPM April 21, 2023

Viewing Collab Attribute Data

1. Click the Collab Details icon to display the Collab Details dialog box.

2. Click Collab Attribute to access the Material Master data.

1

2

Page 10: IBM SCPM MCV Page

10SCPM April 21, 2023

Viewing Site Attribute Data

1. Click the Collab Details icon to display the Collab Details dialog box.

2. Click Site Attribute to access the Site Attribute data.

1

2

Page 11: IBM SCPM MCV Page

11SCPM April 21, 2023

Viewing Alternate Parts

1. Click the Collab Details icon to display the Collab Details dialog box.

2. Click Alternate Parts to access the Alternate Parts data.

1

2

Page 12: IBM SCPM MCV Page

12SCPM April 21, 2023

Viewing PIT Attributes

A. To view all PIT Attributes for a data measure, click the data measure name.

B. To view the PIT Attributes for a specific PIT, click the value in the PIT.

A B

Page 13: IBM SCPM MCV Page

13SCPM April 21, 2023

Viewing PIT Attributes

At the PIT Info page, you can select the PIT Attributes you want to view:

1. From the User Fields box, click the PIT Attributes you want to view.

2. Click the Refresh button to refresh the view.

1

2

Page 14: IBM SCPM MCV Page

14SCPM April 21, 2023

Viewing the Summary Tab

A. The Summary tab displays the rolled-up values for multiple collaborations you are viewing on the MCV page.

A