IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 o
IBL Project Cost
V1.13 G. Darbo & H. Pernegger
![Page 2: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/2.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 2
Credits for the Costs Partial list of people consulted and contributing to the cost evaluation:
• J.Joseph: ROD • C.Meroni: cables, PP2 • S.Kersten: DCS. HV/LV PS • N.Wermes: Modules, Bump-Bonding, Sensors (planar) • M.Garcia-Scivers: internal services, flex-hybrid • T.Flick, G.Lenzen, KK Gan: opto components • D.Giugni: stave mechanics • M.Battistin: cooling plant • N.Hartman, G.Mornacchi, M.Nessi, H.Pernegger, R.Veness, R.Vuillermet: beam-pipe, installation, ALARA, global supports • F.Faccio & K.Kloukinas: chip design in 0.13 µm technology • Xxx: forgotten credits…
Comments: • Cost incertitude is still large and not uniformly evaluated for all the components. This because early
phase of the project has still many technical solution undecided. • Costs which are not included:
• Contingency is not put in – should be of the order of 25% for this kind of project – who takes the deliverable as in kind contribution need to consider an “hidden contingency”.
• Subsistence at CERN (manpower is only for installation) – support to manpower at CERN must be shared between home institutes and subsistence funds accessible to the project.
• Manpower at the institutes
![Page 3: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/3.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 3
Cost Profile Payments for construction is peaked in 2012
Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed):
• 2 FTE 2010 & 2011 • 4 FTE 2012, 2013, 2014 • + Same amount of FTEʼs from Institutes
Support to stay at CERN for IBL management: • IBL PL, ENG Coordinators
SR1/IBL operation: • 30k – 2010 • 50k – 2011, 2012, 2013, 2014
![Page 4: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/4.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 4
Cost Profile – WBS
Some large orders as FE-I4, sensor, bump-bonding and beam pipe are “quantised” and could significantly change the profile
• FE-I4 v1 (500k) submission foreseen by the end of this year. Payment put in 2010.
![Page 5: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/5.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 5
Costs Breakdown – Prototype, Construction, Jigs…
Prototype cost is 1.0 MCH • FE-I4, sensor, stave, bump-bonding need substantial prototyping
Many jig for integrating the detector and for insertion/extraction Manpower considered in the IBL cost only for installation
• Need to add subsistence + support for IBL management members.
![Page 6: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/6.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 6
WBS-1: Sensors
Only a fraction of the prototyping cost is included for sensor prototyping with FE-I4: • Motivation was that cost is shared with sLHC R&D – in particular 3D sensors are underestimated
since we want to proceed the development of the 3 sensor flavours: CNM (Barcellona), FBK (Trento), Stanford/SINTEF (SLAC/OSLO)
• Feedback needed from NCP if this model works: IBL & sLHC sharing of cost. • Diamonds are not in the WBS – under investigation engineering and system impact to
keep diamond option open for the prototyping phase Production cost
• Cost considers a 40% yield from produced tiles to accepted bare modules and 20% lost in all other assembly steps (~125 wafer) – the cost is tight for 3D – should have good contingency for planar, while diamonds are a factor 3 too low.
![Page 7: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/7.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 7
WBS-2: Electronics
FE-I4 contribute to 1.3 MCH • Schedule strongly depend on them • Payment are 80% at “tape-out”, 20% on chip delivery (~3 months after)
![Page 8: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/8.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 8
WBS-3: Hybridisation
Bump-bonding contributes for 90% of this package • Bump-bonding development for both 3D and Planar sensors. • We want two bump-bonding vendors brought to qualification before
production tender • Only one vendor used for production – pixel used two vendors for production
of a much larger system
![Page 9: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/9.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 9
WBS-4: Local Supports
This package has: • Bare stave prototype • Bare stave production • Loaded stave with modules
![Page 10: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/10.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 10
WBS-5: Internal Services
This package has: • Signals from EoS (was PP0 in Pixel) to PP1 • Power from EoS to PP1 • HV from EoS to PP1 • Cooling pipes from EoS to PP1 • PP1 patch pannel
![Page 11: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/11.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 11
WBS-6: Beam Pipe & Interfaces
This package has: • Beam-pipe extraction / insertion tooling, mock-up • New Be beam-pipe • IBL Support tube (IST): WBS-6.3.1 • Global support to link the IBL to present pixel detector • Support and alignment of beam-pipe
![Page 12: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/12.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 12
WBS-7: Surface Integration
Integration of beam-pipe with staves in SR1 • Partial reuse of ITT (Pixel IntegrationTransport Tool)
Qualification in SR1 of Integrated IBL • Electrical test, optical test, cooling
Portable CO2 system included
![Page 13: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/13.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 13
WBS-8: External Services
“Standard cables” and cooling pipes • Service installation in WBS-10
Box on IDEP for optoboard • Include heating/cooling for the optoboards
PP2 regulator box • PP2 boards are in the WBS-2 (Electronics)
![Page 14: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/14.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 14
WBS-9: External Cooling
Cooling plant • CO2 or C3F8 (also look at mixture of C2F6 and C3F8) • Cooling distribution system (pipes to IBL in WBS-8)
Cooling design qualification • Test setup to perform measurement of thermal parameters (HTC, …)
![Page 15: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/15.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 15
WBS-10: Installation in the Pit
This package include: • ALARA requirements and consultation with specialised firms • Manpower form specialised firms • Installation of services (foreseen ~2 years before IBL package) • Testing after connection of services to IBL • Endoscope, considered an indispensable tool, is in the package.
![Page 16: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/16.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 16
WBS-11: DAQ, DCS, Interlock,…
Off-detector and mainly “off-shelf” electronics • Crates, Racks (need to find space, but not in the cost) • S-link cards (on ROS side) • DCS standard or Pixel hardware • Power supply (LV same of Pixel, HV need to push higher voltage for planar
sensor option) • ROS and S-link destination card responsibility of TDAQ, but quoted in IBL.
![Page 17: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/17.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 17
WBS-12: Test beam & Irradiation
Irradiation and test beam we want to bring control inside IBL project • It was considered not to include in the project cost • Specific activity for IBL need to be recognized in some way
![Page 18: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/18.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 18
Common Orders & Cash
Cash needed in: • WBS1 – sensors / WBS3 – hybridisation : deliverables for Institutes & common orders • WBS2 – electronics (10%): more than 50% are FE-I4 cost. Most in-kind deliverables • WBS4 - local supports / WBS 5 – internal services / WBS 6 – beam-pipe and interfaces
(20%) : many parts, need flexibility • WBS7 – surface integration / WBS11 – DAQ, DCS, PS, Interlock (50%) ; integration
and system test Total: 5.6 MCH M&O-B/Project / Common orders 2.5 MCH / Cash 0.7 MCH
• Adding subsistence would bring ~22% the cash for the not M&O-A part of the project
![Page 19: IBL Project Costdarbo/IBL/kick-off/09-07-08_GD_IBL_kick-off... · Total cost (M&O-A – M&O-B/New project): 9630k Subsistence not included (~500÷700k needed): • 2 FTE 2010 & 2011](https://reader033.fdocuments.in/reader033/viewer/2022050301/5f6a190bf6461b622e747d6b/html5/thumbnails/19.jpg)
IBL Project Cost - V1.13 G. Darbo – INFN / Genova 8 July 2009 19
Conclusions IBL cost evaluated for the whole project:
• 4.0 MCH (M&O-A) + • 5.6 MCH M&O-B/New project • 0.5÷0.7 MCH subsistence at CERN • Contingency (to add) : 25%
Payment profile made on 2014/15 installation
Use the present costing at “interim” to work on MoU • Refine the cost when TDR and MoU will be ready