IBL Presentation rev FINAL

33
2012/2013 IBL Experience Dion Botha - Electrical Engineering Student

Transcript of IBL Presentation rev FINAL

Page 1: IBL Presentation rev FINAL

2012/2013 IBL Experience

Dion Botha - Electrical Engineering Student

Page 2: IBL Presentation rev FINAL

22

Presentation Contents

• 4 major projects (introduction, my role, professional growth)– Major Hazard Facility (MHF)– M2 Transformer Temperature Alarms– M2 Paper Break Camera System– Recovery Boiler’s 5 & 6 (R5/6) Superheater Tube Temperature

Probes• Training / experiance• Life in the Valley

Page 3: IBL Presentation rev FINAL

33

MHFIntroduction• Australian Paper (Maryvale mill) is a MHF• Safety Case

– How we manage safety at our MHF

My Role• Finding and tagging ~100 untagged MHF assets

Page 4: IBL Presentation rev FINAL

44

MHFMy Role• Managed the updating of BECA marked piping and

instrumentation diagrams (P&IDs) show all MHF assets

• Added previously unrecorded MHF assets to instrument calibration system (Caltrack)

Page 5: IBL Presentation rev FINAL

55

MHFMy Role• Documented ‘unreachable’ MHF assets

– Created work requests for area assistance• Attend MHF meetings to report progress

– Worked within WorkSafe MHF licence renewal deadline

Page 6: IBL Presentation rev FINAL

66

Professional Growth• Read P&IDs• Locate assets• Maryvale mill• Safety

– Personal protective equipment (PPE)– Signing into areas

• MHF– Identification of MHF locations & critical assets

MHF

Page 7: IBL Presentation rev FINAL

77

M2 Transformer Temperature AlarmsIntroduction

Page 8: IBL Presentation rev FINAL

88

My Role• Investigated old switching type indicators• Sourced and purchased new site standard WIKA

indicator/transmitters• Documentation

– Loop connection diagrams– Junction box drawings

• Installation• Distributed Control System (DCS)

– Logic– Human Machine Interface (HMI) Graphics

• Commissioning

M2 Transformer Temperature Alarms

Page 9: IBL Presentation rev FINAL

99

At Transformers

M2 Transformer Temperature Alarms

Before After

Page 10: IBL Presentation rev FINAL

1010

Wiring to DCS I/O

M2 Transformer Temperature Alarms

Page 11: IBL Presentation rev FINAL

1111

DCS HMI

M2 Transformer Temperature Alarms

Page 12: IBL Presentation rev FINAL

1212

DCS HMI

M2 Transformer Temperature Alarms

Page 13: IBL Presentation rev FINAL

1313

Professional Growth• Transformers• Temperature switching indicators and transmitters• Thread Standards• Metso DNA DCS

M2 Transformer Temperature Alarms

Page 14: IBL Presentation rev FINAL

1414

M2 Paper Break Camera SystemIntroduction• Making paper is not a perfect process• Paper breaks

– Hard to diagnose (insects, falling debris, dripping, inconsistent pulp from the head box etc.)

– Unplanned downtime expense– Camera system

• Portable trial camera system (WEBVISION)

Purchased and installed at M2

Decided to reinstall at M2

Moved to other paper machinesReinstallation

at M2

Page 15: IBL Presentation rev FINAL

1515

Justification for Reinstallation

M2 Paper Break Camera System

M2 unplanned downtime cost $3388/hour M2 average breaks per day (2011) 3.72 (rose to ~6 in 2012) M2 average break time 12 minutes Average break cost $677.60/break M2 paper machine production 290 days/year Saving assuming one break per day reduction $196,504/year Project cost $30,000 Return on investment (ROI) 555%

Page 16: IBL Presentation rev FINAL

1616

My Role• Read available documentation• Diagnosed reason that camera system was not functioning:

– Sourced and replaced broken switch to power up WEBVISION system.– Fixed non functioning capture computers

• Power supply replaced with a spare• HDD formatted and imaged with working capture unit’s HDD• Swapped single input video card with dual input card from M4

• Wrote a scope of work– Extracted drawings from WEBVISION documentation and organise boilermakers to make up

brackets for cameras and lights– Assisted electricians with installation

• Prepare cameras (power/video connections, housing, focus, aperture, exposure zoom)

• Create/updated company documentation• Training and handover

M2 Paper Break Camera System

Page 17: IBL Presentation rev FINAL

1717

M2 Paper Break Camera System

Before After

Field Racks and Instrument Air

Page 18: IBL Presentation rev FINAL

1818

M2 Paper Break Camera SystemCameras and Lights

Page 19: IBL Presentation rev FINAL

1919

Control Station

M2 Paper Break Camera System

Page 20: IBL Presentation rev FINAL

2020

Operators Station

M2 Paper Break Camera System

Page 21: IBL Presentation rev FINAL

2121

M2 Paper Break Camera SystemCamera Locations

Page 22: IBL Presentation rev FINAL

2222

Professional Growth• Cameras

– Aperture– Exposure– Focus– Lighting– Fault finding

• Better estimate installation times• Process of getting work done• Communication with trades

M2 Paper Break Camera System

Page 23: IBL Presentation rev FINAL

2323

R5/6 Superheater Tube Temperature ProbesIntroduction

24°C200°C240°C280°C320°C

12.4mV12.9mV13.6mV14.2mV

HMI(Operators

Station)…

Page 24: IBL Presentation rev FINAL

2424

• Old

• New

R5/6 Superheater Tube Temperature Probes

Bailey DCS

ABB DCSTemperature transmitter

HMI

Page 25: IBL Presentation rev FINAL

2525

My Role• Ascertain what work had already been completed and what

was left to do• Prepare wiring diagrams for remaining work

R5/6 Superheater Tube Temperature Probes

Page 26: IBL Presentation rev FINAL

2626

My Role• Prepare loop connection diagrams for each loop (135)

R5/6 Superheater Tube Temperature Probes

Page 27: IBL Presentation rev FINAL

2727

My Role• Source quotes for remaining work

– Relocation of 89 loops from R5 and 46 loops from R6

• Manage contractors work• Commission

– Check wiring/cabling/ferrules are correct– Programming of transmitters and making sure each loop is functioning correctly– Enabling new DCS programming and linking to operators graphics (HMI)

R5/6 Superheater Tube Temperature Probes

Page 28: IBL Presentation rev FINAL

2828

Professional Growth• Wiring diagrams and loop connection diagrams are

essential for:– Installation– Decommissioning– System analysis and modification– Fault finding

• Temperature sensors• Manage contractors work• Bailey and ABB DCS

R5/6 Superheater Tube Temperature Probes

Page 29: IBL Presentation rev FINAL

2929

• CMMS (PBS4)• Thermal imaging• DC motor maintenance• DCS

– METSO– ABB

• Electrical Equipment in Hazardous Areas (EEHA)• Cardiopulmonary resuscitation (CPR)• Job Safety Analysis (JSA)• Transformer Oil Sampling

Training / Experience

Page 30: IBL Presentation rev FINAL

3030

• Netball – 2 seasons (Churchill)• Badminton – 2 seasons (Traralgon)• Indoor cricket – 2nd seasons (Traralgon)• Golf – AP Golf Day• Latrobe Young Professionals (LYP) group events• Fishing at Lake Hyland

Life in the Valley

Page 31: IBL Presentation rev FINAL

3131

Staff

• Daryl Adams - E/I Engineer - HV, SESO• Alex ‘Zac’ Crewe - Power/Recovery E/I Engineer• Steven Gooda - DCS Engineer• Jeff Buckett – Head of Maintenance - E/I • Andrew Sun - Asset Management Engineer• Muditha Hasthanayake - M1 & M2 E/I Engineer• Milinda Senanayake - Graduate E/I Engineer• Tom Hagley - M3 E/I Engineer• Edward Trickett – General Manager - Paper• Trevor Niejalke - M1/M2/M3 E/I Superintendent• Anthony Beckett - M5 Production Superintendent• Alan Jenkinson - M5 E/I Engineer• Raymond Smith - 2011 IBL Mechanical Engineering Student• Brendan Jilbert - M1/M2 Machine Manager

Acknowledgements

Page 32: IBL Presentation rev FINAL

3232

Trades/Technicians

• David Lothian - M1/2/3 E/I• Bill Vansambeek - DCS Technician• Andrew Daly - E/I Central Workshop Planner• Rodney Hewat - E/I Central Workshop L/H & Acting SESO• Ben Bowen - Central Workshop E/I• Rudy Bence, Contractor – VB & Co planner• Nick Calla - M1/M2/M3 E/I Planner• Craig Bassi - HP Technician• Brian Spiteri – Boilermakers

Young Professionals

Acknowledgements

Page 33: IBL Presentation rev FINAL

Questions