IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1!...

28
12.6.27 1 Accident at TEPCO’s FukushimaDaiichi NPP Possible underlying factors influencing decision-making, preparedness and risk management Accident at TEPCO’s FukushimaDaiichi NPP FukushimaDaini1 FukushimaDaiichi4 Akira OMOTO Professor, Tokyo Institute of Technology, and Commissioner, Atomic Energy Commission [Note] The views expressed in these slides do not represent the consensus official view of AEC, Titech, NISA nor Utilities Outline IAEA Technical Meeting, 2012June, A. Omoto 2 Introduc.on Four cri.cal areas UT study Accident Inves.ga.on Commi:ees Discussion Concluding remarks

Transcript of IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1!...

Page 1: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

1  

Accident  at  TEPCO’s  Fukushima-­‐Daiichi  NPP  Possible underlying factors influencing decision-making,

preparedness and risk management

Accident  at  TEPCO’s  Fukushima-­‐Daiichi  NPP  

Fukushima-­‐Daini-­‐1 Fukushima-­‐Daiichi-­‐4

Akira OMOTO Professor, Tokyo Institute of Technology, and Commissioner, Atomic Energy Commission

[Note] The views expressed in these slides do not represent the consensus official view of AEC, Titech, NISA nor Utilities

Outline

IAEA Technical Meeting, 2012June, A. Omoto 2

     Introduc.on  

             Four  cri.cal  areas  

           UT  study  

           Accident  Inves.ga.on  Commi:ees  

        Discussion  

         Concluding  remarks  

Page 2: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

2  

Hazard  source

Radiological  consequence  to  human

1.  Preven9on  by  design  -­‐Natural  hazard

2.  (level4)  Accident  Management 3.  (level5)Emergency  Plan

Avoid  Core  Melt

Avoid  large  release

-­‐SBO  and  LUHS

4. Safety regulation

 Try  to  extract  possible  underlying  issues  that  may  have  existed  in  the  background     from  cri9cal  areas  that  failed  to  prevent  migra9on  to  disaster,  and    

 from  UT  (University  of  Tokyo)  study     from  Accident  Inves9ga9on  CommiTees’  reports  

 “Four  cri9cal  areas”  in  Fukushima  Accident  using  Swiss  cheese  model  

Overall  approach  

IAEA Technical Meeting, 2012June, A. Omoto 3

 Why  [may]  have  existed?   No  explicit  causal  rela9onship  study  yet  that  includes          cultural,  organiza9onal  and  societal  issues  

 What  is  meant  by  “underlying  factors”?   Factors  influencing  decision-­‐making  and  resultant  causal  chain  of  events;    Culture    Competence,  knowledge  and  understanding    Safety  management  and  oversight    Interac9on  between  nuclear  experts    

•   and  organiza9on,  •   and  society,  •   and  experts  in  other  disciplines  

 Possibly  formulated  in  the  history  of  NE  programme  

Overall  approach  

IAEA Technical Meeting, 2012June, A. Omoto 4

Page 3: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

3  

created  contribu9ng  factors  

IAEA Technical Meeting, 2012June, A. Omoto 5

Company,  Management,  Government,  Regulator,  Society  

Causal  chain  of  event

Evolving  from  classical  technical  causal  chain  model  to  involve  managerial  and  societal  factors  to  a  new  model  such  as    

Accident  is  the  result  of  flawed  processes  involving  interac=ons  among  people,  societal  and  organiza=onal  structures,  engineering  ac=vi=es,  and  physical  system  components  that  lead  to  viola=ng  the  system  safety  constraints.  (Nancy  G.  Leveson,  “Engineering  a  Safer  World”)  

underlying  factors

               Introduc.on  

       Four  cri.cal  areas  

           UT  study  

             Accident  Inves.ga.on  Commi:ees  

        Discussion  

           Concluding  remarks  

IAEA Technical Meeting, 2012June, A. Omoto 6

Page 4: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

4  

Critical area  1)  Design  

1.  ProtecAon  against  natural  hazard    Recognizing  uncertain9es  in  natural  science    Preparedness  to  “beyond  assumed  condi9ons”  

2.   Plant  capability  against  SBO  (StaAon  Blackout  w/o  any  AC/DC)  and  isolaAon  from  UHS  (UlAmate  Heat  Sink)  

IAEA Technical Meeting, 2012June, A. Omoto 7

Tsunami    earthquake

[SOURCE]    T.  Lay  et  al,  “Outer  trench-­‐slope  faul=ng  and  the  2011  Mw9.0      off  the  Pacific  coast  of  Tohoku  Earthquake”,  Earth  Planets  Space,  63,  713-­‐718,  2011

Japan  trench  

Plate  boundary  earthquakes

Outer  trench-­‐slope    faulAng

Three  Tsunami  source  areas  

IAEA Technical Meeting, 2012June, A. Omoto 8

Page 5: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

5  

  2002  JSCE  (Japanese  Society  of  Civil  Engineers)  guideline  on  design    protec9on  against  Tsunami  at  nuclear  power  plants    Modifica9on  by  U9li9es  in  2002  based  on  this  guideline  

  2002.7  Long-­‐tern  Projec9on    by  Earthquake  Research  Hq.  :  Tsunami  earthquake  may  occur  anywhere  along  J  trench  in  Tohoku  area  

  Tsunami  Probabilis9c    Hazard  study    U9li9es  joint  study  on  probabilis9c  Tsunami                  hazard  (2002-­‐)  and  source  model    TEPCO’s  analy9cal  results    (2006)                did  not  lead  to  prac9cal  ac9ons                            [SOURCE]  TEPCO’s  final  inves=ga=on  report,  20June2012  

  Methodology  guide  from  JSCE  using  logic  tree  to  represent  epistemic  uncertain9es    (2007)  

                                   [SOURCE]  T.  Annaka,  “Logic-­‐tree  Approach  for  Probabilis=c  Tsunami  Hazard  Analysis  and  its                                                  Applica=ons  to  the  Japanese  Coasts”,  Pure  and  Applied  Geophysics,  164(2007)  577-­‐592,  2007

ProtecAon  against  Tsunami  

IAEA Technical Meeting, 2012June, A. Omoto 9

 Off-­‐Fukushima  coast   Historically  limited  Tsunami  record  of  significant  inunda9on  height     Es9mated  weak  coupling  and  con9nuous  slip  in  this  region                                [SOURCE]  T.  Matsuzawa,  Kagaku  (Science),  2011  Vol  81  No.10  

 TEPCO’s  Tsunami  study  (2008)  by  hypothe9cally  assuming  M8.3  “off-­‐Sanriku”  (N.  of  J  trench)  earthquake  source  at  off-­‐Fukushima  coast    

•   Resultant  inunda9on  height  of  15.7m  •   TEPCO  had  asked  JSCE  to  review    

               [SOURCE]  TEPCO’s  final  Inves=ga=on  report,  20June2012,                hgp://www.tepco.co.jp/en/press/corp-­‐com/release/2012/1205638_1870.html  

 Nevertheless,  in  hindsight,  delibera9on  of  “what  happens  if  the  calculated  inunda9on  height  in  2008  study  was  correct?”   for  defense-­‐in-­‐depth,  this    could  have  changed  the  whole  story  

 IAEA  Tsunami  workshop  at  Kalpakkam  2005   23  cases  of  NPP  external  flooding                            [SOURCE]  A.  Godoy,  Kalpakkam  WS  

IAEA Technical Meeting, 2012June, A. Omoto 10

Page 6: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

6  

1.  Probabilis9c  Tsunami  Hazard  Analysis  In  2006,  TEPCO  conducted  a  hypothe9cal  analysis  u9lizing  this  JSCE  Probabilis9c  Tsunami  Hazard  Analysis  methodology  and  it  showed  that  the  occurrence  of  a  tsunami  exceeding  10  m  could  only  occur  once  every  100  thousand  to  a  million  years.  However,  this  analysis  was  conducted  for  the  purpose  of  confirming  adaptability  and  improving  methods  that  at  the  9me  were  s9ll  in  development.  Thus,  TEPCO  did  not  interpret  this  figure  to  literally  mean  the  actual  frequency  of  tsunamis  that  could  strike  the  nuclear  power  plant  in  Fukushima.   2.  Asked  for  JSCE  review    …in  2008,  TEPCO  conducted  another  trial  calcula9on  u9lizing  the  wave  source  model  of  the  Meiji  Sanriku-­‐oki  Earthquake  along  the  trench  off-­‐shore  Fukushima  (the  result:  15.7  m).  However,  the  validity  of  this  wave  source  model  had  been  in  ques9on.  TEPCO  has  requested  that  JSCE  review  the  suitability  of  this  hypothesis…..  3.  Jogan  Tsunami  (year  869)  TEPCO  conducted  tsunami  deposit  surveys,  and  as  a  result,  an  al9tude  of  about  4m  in  the  northern  part  of  Fukushima  Prefecture  was  confirmed  for  the  tsunami  deposits  carried  by  the  Jogan  tsunami  while  no  tsunami  deposits  were  found  in  the  southern  part.  As  there  were  inconsistencies  between  the  results  of  the  inves9ga9on  and  the  trial  calcula9on  via  using  the  proposed  wave  source  model  (the  result:  9.2  m),  TEPCO  considered  it  necessary  to  conduct  further  inves9ga9on  and  research  in  order  to  determine  the  wave  source  of  the  Jogan  tsunami.  

*  TEPCO’s  argument  

IAEA Technical Meeting, 2012June, A. Omoto 11

[SOURCE]  www.tepco.co.jp/en/nu/fukushima-­‐np/info/index-­‐e.html

 Report  from  the  Central  Disaster  Management  Council,  2011Sept28  

 3.11  was  caused  by  simultaneous  occurrence  of          “Japan  trench  earthquakes  “  &    “Tsunami  earthquake”    

 Former  principles  for  hazard  assump9on  [note]  need  to  be          fundamentally  reviewed  

                           [note]  Seismic  intensity  and  Tsunami  heights  not                                                      reproducible  by  the  seismic  source  model  was                                                      regarded  as  having  low  probability  of  occurrence                                    [SOURCE]  hgp://www.bousai.go.jp/jishin/chubou/higashinihon/houkoku.pdf  

IAEA Technical Meeting, 2012June, A. Omoto 12

Page 7: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

7  

IAEA Technical Meeting, 2012June, A. Omoto 13

Tsunami  earthquake  :  a  dominant  source

Underlying  issues  that  may  have  existed  in  the  background

1. Interpreta9on  of  uncertain9es  in  natural  science  2. Understanding  of  difficulty  in  decision-­‐making  under  uncertain9es  

3. Cau9ous  assessment  and  prepara9on  to  beyond  assumed  condi9on  (yet,  to  what  extent?)    

  What  if  the  assumed  condi9on  by  Tsunami  experts  was  wrong(2002,  2006)  or  right(2008)?  

  Flooding  analysis*  could  have  strengthened  level  of  protec9on  

*  Limited-­‐scope  study  was  done  on  flooding  in  “beyond  assumed  condi9ons”  for  intake  structure  •  Reliance  on  Air-­‐cooled  EDG  capability,  if  UHS  is  lost  •  Feed  and  Bleed  capability  of  BWR  in  the  case  UHS  is  lost  

was  well  understood  

IAEA Technical Meeting, 2012June, A. Omoto 14

Page 8: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

8  

SBO  rule   comply  with  US  1988  SBO  rule   “30  minutes  rule”:    Not  a  decisive  factor  as  following  operaAon  shows   0-24hrs into the accident: Core water makeup by use of stored energy (RCIC/HPCI))  24 hrs: Depressurize RCS and LP injection  32 hrs: Heat dissipation to the alternative heat sink by containment scrubbing venting  

Depressurization

Depressurization

Rx Pressure

RCIC Flow

Depressurization Venting

Drywell Pressure

Wetwell Temperature

Wetwell Pressure

Drywell Temperature

2Pd

Pd

FP Flow

Loss of water inventory equivalent to Decay Heat

RPV water level

Fuel uncovered time period is short. (less than 1 hour)

IAEA Technical Meeting, 2012June, A. Omoto 15

14  NPPs  affected  by  Tsunami:  What  made  differences?

Onagawa (3 units; 2 in operation)

Fukushima-I (6 units; 1,2,3 in operation)

Fukushima-II (4 units in operation)

Tokai (1 unit in operation)

GL>Tsunami

GL>Tsunami

Tsunami Inundation height SBO

Isolation from UHS

GL(10-13m) < Tsunami (11.5-15.5m)

GL(12m) < Tsunami (12-14.5m)

Power available

- All offsite Pwr& EDG were lost except for 1F6 air-cooled EDG - 1F5 power supplied from 1F6

Not completely

Completely isolated from the sea

Almost complete isolation

- One offsite power was available

Availability  of  power  (offsite  or  EDG  +    in-­‐plant  power  center)  and  SAM    implementaAon  was  a  decisive  factor,  especially;  

   Ground  Level  height  &  enclosure  against  Tsunami  [saved  Onagawa  and  Tokai]     Emergency  power  using  alterna9ve  heat  sink  &  loca9on  of  power  supply              equipments  [saved  1F6]     SAM  for  power  inter-­‐connec9on  with  adjacent  unit  [saved  1F5]     SAM  using  a  single  available  offsite  power  [saved  2F]

Not completely

IAEA Technical Meeting, 2012June, A. Omoto 16

Page 9: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

9  

1.   Robust  and  workable  Accident  Management  

2.    The  role  of  containment  system  in  SA  condiAon    Suspected  significant  leakage  (reduced  drywell  pressure)  from  1F2  

containment  due  to  over-­‐temperature  (3.15AM)  [SOURCE]  K.  Miyata,  AESJ,  

26May2012:  possibly  leading  to  significant  fallout  in  the  North-­‐West  due  to  precipita9on  

  High  level  assurance  of  avoiding  land  contamina9on  (filter,  over-­‐pressure  &  over-­‐temperature  protec9on)  

  2ndary  containment  management  (external  event,  hydrogen  combus9on  outside  of  the  CV)  

  CV  isola9on  vs.  over-­‐riding  to  enable  cooling  

Critical area  2)  Level  4  Defense-­‐in-­‐depth  

IAEA Technical Meeting, 2012June, A. Omoto 17

Level 4 Defense-in-depth (INSAG-10): Control of severe conditions including prevention of accident progression and mitigation of the consequences of severe accident

AMG  not  robust  enough  to  be  effec9ve/executable  under  plant  damage  condi9ons  by  high  Tsunami  

Robustness  of  AMG

IAEA Technical Meeting, 2012June, A. Omoto 18

Page 10: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

10  

Short  term     Reactor  water  makeup  by  AC-­‐independent  IC/RCIC/HPCI  

Then,  while  trying  to  restore  AC/DC  power  and  Heat  Sink     Depressurize  Reactor  Coolant  System  by  Safety/Relief  Valves     Ac9vate  Low  Pressure  injec9on  systems     Containment  vent  to  avoid  over-­‐pressure  failure  

14.46                      Earthquake,  Loss  of  offsite  power,  Start  of  EDG,  IC/RCIC  15.27-­‐                  Tsunami  followed  by  Loss  of  AC/DC,  Isola9on  from  UHS  

Given  this  situaAon,  operaAon  to  avoid  core  damage  

Core  degrada9on  followed  by  Hydrogen  explosion  

Require  workable/effec9ve  AM  

Failure  of  RCIC/HPCI  on  the  3rd  and  4th  day  Delayed  ven9ng,  de-­‐pressuriza9on  of  RCS  and  LP  injec9on  

IAEA Technical Meeting, 2012June, A. Omoto 19

  Limited  available  resources  and  scaTered  debris/tanks    Field  works  risked  their  lives  under  devasta9on/radia9on  and  fear  

of  hydrogen  explosions  and  asershock  (TEPCO  report)  

Limited  available  resources  under  harsh  environment  

IAEA Technical Meeting, 2012June, A. Omoto 20

Page 11: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

11  

a)  External  cooling  of  containment    Over-­‐temperature  protecAon  

b)  Filtered  venAng      Over-­‐pressure  protecAon    Land  contaminaAon  

[SOURCE]hgp://www.aec.go.jp/jicst/NC/tyoki/sakutei/siryo/sakutei13/siryo1-­‐3.pdf  

IAEA Technical Meeting, 2012June, A. Omoto 21

Japanese  UAliAes  announced  measures  to  over-­‐temperature  failure  and  Filtered  venAng  (2012Feb)

1.  Sensi9vity  to  risks  arising  from    external  events  and  their  impact  to    AMG  ac9ons  

2.  “Accident  will  not  happen  here”          leading  to  lack  of  realism  in  SAM  

3.  Lack  of  societal  safety  goal,  by  considera9on  of  offsite  cost,  power  replacement  costs,  in  addi9on  to  acute  and  latent  cancer  fatali9es    

4.  Con9nuous  safety  improvement  hindered  by;        a)  “prisoner’s  dilemma”  situa9on  with  the  society  under  distrust  

  Safety  modifica9on  is  taken  as  evidence  of  unsafe  plant        b)  insufficient  learning  from  good  prac9ces  in  risk  management  

  From  modifica9ons  based  on  findings  in  IPEEE    From  protec9ons  under  B5b  clause  [informed  to  regulatory  body  (NISA/JNES)  

from  USNRC  in  2003/2007,  but  no  ac9on  by  them]  IAEA Technical Meeting, 2012June, A. Omoto 22

Underlying  factors  that  may  have  existed  in  the  background

Page 12: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

12  

[SOURCE]  Courtesy  of  K.  Tateiwa,  Presenta=on  to  US-­‐EPA,  20January2012

Yet,  high  moral  among  field  workers  at  Fukushima  Ref.:  Voices  of  TEPCO’s  field  workers  from  TEPCO  report’s  Appendix    (hgp://www.tepco.co.jp/cc/press/betu11_j/images/111222p.pdf)

   Offsite  center’s  func9on  was  lost       Implementa9on  of  EP  (No9ce  to  the  public  on  evacua9on,  vehicle,            Iodine  tablet  etc)     Delinea9on  of  responsibility  including  PM’s  role     Poor  communica9on  (PM  office  and  Gov  officials  in  CMC  etc)     Misunderstanding  between  PM  office  and  TEPCO  on  “withdrawal”     Systema9c  collec9on  of  informa9on  and  sharing/dissemina9on       Poor  record-­‐keeping  on  Government’s  decision-­‐making  process  

Needs  to  revisit   Delinea9on  of  responsibility,  command  line,  coordina9on,     Design  and  func9on  of  “offsite  center”   Offsite  emergency  plan  (scope  of  EPZ,  preparedness)   Communica9on  system   Mobile  equipments  

CriAcal  area  3)  Level  5:  Emergency  Plan  and  Crisis  Management    

Observed  problems  (ICANPS  interim  report,  NAIIC  statement  and  others)

IAEA Technical Meeting, 2012June, A. Omoto 24

Page 13: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

13  

1.    Emergency  Plan:  Poten9al  “assump=ons”  problem  in  the  most  basics    level  of  safety  culture  hierarchy  model    “Accident  will  not  happen  here”      Leading  to  lack  of  realism  in  seung  offsite  center  facili9es  and  

evacua9on  plan  (communica9on  tool,  vehicles  for  evacua9on,  road…)  [source]  report  from  the  associa=on  of  municipali=es  having  NPPs  

hgp://www.aec.go.jp/jicst/NC/iinkai/teirei/siryo2012/siryo19/siryo1-­‐1.pdf  

2.  Understanding  of  delinea9on  of  responsibility      Interna9onal  prac9ces  is  Onsite  primarily  by  Operator  and  

Offsite  by  local  government,  both  under  advices  from  regula9on  etc  

  No  FEMA  in  Japan  

IAEA Technical Meeting, 2012June, A. Omoto 25

Underlying  factors  that  [may]  have  existed  in  the  background

HOW  A  NEW  EMPLOYEE  LEARNS  THE  WORK  CULTURE  

Assumptions

Concepts Knowledge

Slogans, Values

Use of Time

Patterns of Behaviour

Physical Things

“Social Fabric”

Assumptions

Espoused Values

Artefacts

Invisible

Visible

Documents Language

SOURCE:  IAEA-­‐TECDOC-­‐1329,  Safety  culture  in  nuclear  installa.ons

IAEA Technical Meeting, 2012June, A. Omoto 26

Page 14: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

14  

Regula9on   Responsibili9es  not  in  a  single  regulatory  body            (Ex)  development  of  regulatory  guide  by  NSC,  licensing  by  NISA   Technical  competence/Effec9veness  in  safety  regula9on          (Ex)  Requirements  on  SBO,  SAM  (Severe  Accident  Management)  

U9lity     Effec9veness  of  risk  management  as  primary  responsible  body  

•  Use  of  risk  informa9on  to  address  vulnerabili9es    •  “Sensi9vity  “to  safety-­‐related  issues/informa9on      •  Technical  competence  and  autude  towards  “uncertain9es”    •  Effec9veness  of  JANTI,  established  in  2004  emula9ng  INPO  

Regula9on/U9lity     Focus  on  Quality  Assurance/Compliance  rather  than  risks,  seemingly  especially  on  formality  of  documents  and  evidences  rather  than  substance  (aser  2002)   Avoidance  of  land  contamina9on:  should  have  had  higher  priority  

CriAcal  area      4)  Safety  regulaAon  (and  assurance  of  safety)  

IAEA Technical Meeting, 2012June, A. Omoto 27

1. Technical  exper=se  and  regulatory  effec=veness  to  reduce  risks  of  regulatory  body  

2.  Risk  management  for  responsible  use    addressing  vulnerabili9es      ATen9veness  to  good  prac9ces  in  the  world    con9nuous  improvement  approach  

3.  Assump=on  relevant  to  severe  accident?    “Accident  will  not  happen  here”  

IAEA Technical Meeting, 2012June, A. Omoto 28

Underlying  factors  that  may  have  existed  in  the  background

Page 15: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

15  

               Introduc.on  

                   Four  cri.cal  areas  

       UT  study  

           Accident  Inves.ga.on  Commi:ees  

        Discussion  

           Concluding  remarks  

IAEA Technical Meeting, 2012June, A. Omoto 29

   Technical  issues  leading  to  nuclear  disaster:  Mostly  understood     University  of  Tokyo’s  GONERI  (Nuclear  GCOE)  project  to  study            “Why  nuclear  community  in  Japan  failed  to  prevent  this  accident”  

  A  series  of  interviews  by  GCOE  members  to  24  recognized                        nuclear  experts  (University,  Regulator,  AEC,  U9lity,                        Industry,  research  ins9tute,  NPO  cri9cs)  

  To  help  changes;          -­‐  Iden9fy  weakness    in  culture/organiza9on/interface          -­‐  Avoid  accidents  of  different  types  but  by  similar  root  causes  

 Changes  in  such  areas  as      Organiza9onal  Culture    Interac9on  with  Natural  Science  and  understanding  of  

uncertain9es  on  the  part  of  Natural  Science        Risk  management  by  Owner/Operator    

 Results  presented  at  GLOBAL  2011  “Safety  and  Security  issues  in  the  light  of  the  accident  at  TEPCO’s  Fukushima-­‐Daiichi  NPP”  (A.  Omoto,  K.  Juraku,  S.  Tanaka)  

UT  project  to  find  vulnerability  and  strengthen  safety  

IAEA Technical Meeting, 2012June, A. Omoto 30

Page 16: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

16  

 Degraded  safety  culture  (complacency,  lack  of  sensi9vity  to  informa9on,    delayed  ac9on  to  alert,  over-­‐confidence  on  NPP  safety)   Lack  of  tension  between  Regulators/Operators   Too  busy  in  caring  day-­‐by-­‐day  problems   Inappropriate  crisis  management   Society  takes  risk-­‐related  ac9ons,     modifica9ons  as  evidence  of  unsafe  plants   Failure  of  safety  regula9on   No  cross-­‐cuung  safety  experts  in  Japan   Why  nuclear  experts  had  accepted  risks  that          (in  hindsight)  the  society  cannot  accept?

Why  cauAous  acAons  against  Tsunami  was  not  enough?    

WHY  FAILED  TO  PREVENT  (incl.  accident  progression  &    consequence)  ?

Why  prevenAon/miAgaAon  against  BDBE  was  not  enough  or  did  not  funcAon  well?    

 Focus  on  internal  events   Not  enough  aTen9on  to        localiza9on  of  designs  from  US        origin,  by  considering  natural        environment,  intensive  use  of              coastal  area   Lack  of  communica9on  &      mutual  understanding  between  natural  science  and  engineering  on  uncertainty  and  design  margin  

Expressed views and discussions in the interviews

IAEA Technical Meeting, 2012June, A. Omoto 31

Issues identifiable even before Fukushima

 Isola9on  from  global  safety  regime   Experts  in  a  cacoon,  lack  of  dialogue          with  the  society   No  cross-­‐cuung  safety  experts   Lack  of  sense  of  responsibility  as  an              individual

What prevent taking corrective actions?  Operator  is  a  King,  no  cri9cism   No  ques9on  asked  to  NE  programme          implemented  under  the  Na9onal  Policy   “Loose  lips  sink  ships”   Too  busy  to  care

If  you  had  recognized  such  issues,  what  acAons  were  taken?

  Improved  Emergency  preparedness          in  the  light  of  2007  KK  earthquake            such  as  construc9on  of    seismic            isola9on  ERC      Rainey  project,  CAP    “Safety  alert”  reports    Crea9on  of  local  commiTee  at  KK  to          improve  safety  (equally  manned  by          pro-­‐,  an9-­‐  and  neural)

Issues identifiable even before Fukushima

Actions were taken …but not enough (TEPCO)

Actions were not necessarily taken

IAEA Technical Meeting, 2012June, A. Omoto 32

Page 17: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

17  

   Accident  was  caused  by  defects  in  regulatory  system   Delay  in  reflec9ng  new  scien9fic/technical  findings  

 Delayed  regulatory  ac9ons  to  review  Tsunami   Lack  of  sensi9vity  to  interna9onal  trends  and  incidents  and        delayed  ac9ons  (Ex.  IPEEE,  B5b)   Focus  on  hardware  and  structural  integrity  issue     Inappropriate  delinea9on  of  responsibility  between  NISA  and  NSC                  (Ex.  Licensing  criteria  by  NSC,  while  NISA  to  use  it)   Poor  technical  exper9se  in  NPP  design  and  opera9on  

       (frequent  staff  shuffling  system  in  Japanese  government)   Japanese  regulatory  body  put  emphasis  on  hardware,  rather  than            focus  on  elements  raised  in  IAEA’s  safety  fundamentals  (or  INSAG-­‐12)     Heavy  focus  by  NISA  on  QA  drove  NPP  staff  completely  occupied  by            documenta9on  and  no  9me  to  visit  plants  or  to  think  about  safety  

Expressed views on regulation

IAEA Technical Meeting, 2012June, A. Omoto 33

 Degraded  safety  culture   Appoin9ng  non-­‐technical  staff  to  plant  manager  by  placing  high          priority  for  interface  with  local  community/government   Lack  of  sensi9vity  and  learning  autude  from  interna9onal  trends          and  foreign  incidents     Not  willing  to  take  ac9ons  before  something  happens  (Ex.  2007  KK          Earthquake  was  an  alarm  signal,    without  which  U9lity  would  have          taken  no  serious  ac9on  to  natural  hazards)   Lack  of  knowledge  in  opera9on  by  NPP  staff  members  other  than          those  in  Opera9ons  Department  

 Complacency  :  2007  KK  Earthquake  had  proved  that  safety  can  be          maintained  even  by  an  earthquake  exceeding  Design  Basis   Misunderstanding  may  existed  that  safety  is  assured  by  compliance  to          regulatory  requirements  

Expressed  views  on  UAlity’s  aktude  to  safety    

IAEA Technical Meeting, 2012June, A. Omoto 34

Page 18: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

18  

(Natural  hazards)   U9lity  adhered  to  US-­‐origin  design;  delay  in  localiza9on  by  paying  aTen9on  to  Japanese  unique  condi9ons  (natural  hazard,  highly-­‐populated  coastal  line)     Focus  on  internal  events,  not  on  external  or  security-­‐related  events   Lack  of  dialogue  may  have  led  to  misunderstanding  of  “uncertain9es”  in  Natural  Science  

(Blinded  by  day-­‐by-­‐day  business)   Blinded  by  day-­‐by-­‐day  business  and  put  safety  issues  aside   Less  opportunity  to  think  about  design  and  safety.  Increased  focus  on  day-­‐by-­‐day  Opera9on  &  Maintenance,  and  on  QA  documenta9on  

(Experts  of  nuclear  safety)   Decline  in  the  Nr.  of  safety  experts  as  SAM  “had  completed”   Defense-­‐in-­‐depth  not  appropriately  interpreted,  forgot  residual  risks   Focus  on  probability  rather  than  consequence     No  cross-­‐cuung  safety  experts  in  Japan  

Expressed  views  on  Nuclear  community’s    generic  aktude  to  safety    

IAEA Technical Meeting, 2012June, A. Omoto 35

(Interac9on  with  Society)   Engineers  are  supposed  to  create  societal  value,  but  had  limited            communica9on  with  the  society  on  what  the  society  expects   Con9nuous  improvements  by  nuclear  u9lity  hindered  by  fear  that  the          society  may  take  safety-­‐related  modifica9ons  as  evidence  of  unsafe          plants  (amid  sharply  polarized  views  on  NP)…like  prisoner’s    dilemma,          failure  to  achieve  a  goal  (safety)  due  to  distrust  to  each  other  

(U9lity  business  environment  and  organiza9onal  culture)   Deregula9on  changed  Management  autude  towards  compe99veness            of  nuclear  power  in  power  genera9on  op9ons   Giant  coopera9on.  Delay  in  ac9ons.  Arrogant   Risk  Management  focused  rela9onship  with  the  local  community,  not            LPHC  risk  

(Experts  in  nuclear  community)   Weakness  in  taking  responsibility  as  an  individual   “Communica9on  specialists”  may  have  reduced  opportuni9es  for              experts  dialogue  with  the  society  

Expressed  views  on  InteracAon  with  Society,    Culture,  OrganizaAon  

IAEA Technical Meeting, 2012June, A. Omoto 36

Page 19: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

19  

Three-level model of Safety Culture Artefacts-­‐Visible  Signs      (gree9ng  rituals,  dress,  housekeeping  –  visible)  

Espoused  Values      (values  that  are  adopted  and  supported  by        a  person  or  organiza=on  based  on          strategies/  goals)  

Basic  Assump.ons  (Such  as  “human  nature  good  or  evil”)  

Assumptions

Espoused Values

Artefacts

“Social Fabric”

visible

invisible

[SOURCE] originally by Edgar Schein, former professor at the MIT Sloan School of Management, expert on organizational culture

IAEA Technical Meeting, 2012June, A. Omoto 37

 Severe Accident will not happen here  Safety is assured by satisfying regulatory requirements  Plant manager’s priority is relationship with locals  Loose lips sink ships  Nuclear power is supported by a nationally endorsed policy

“Safe and feel safe (by the society)”

Use of time  Blinded by day-by-day business and became insensitive to LPHC risks or put aside safety issues for later actions  Seal-in questions

Visible  Signs

Espoused  Values  

Action pattern  Poor consideration of external event risks  Lack of learning attitude from global best practices  Not sensitive to criticism from outside

Observation: By way of analogy

Suspected  “Basic    Assump.ons”  

Slogan  

IAEA Technical Meeting, 2012June, A. Omoto 38

Page 20: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

20  

Prof.  D.  Klein  (Former  chairman  of  USNRC,  Ripon  Forum,  Summer  2011)   The  LL  from  Fukushima  are  many,  but  what  may  be  surprising  is  how  few  may  actually  apply  to  US  plants.   In  a  culture  where  it  is  impolite  to  say  “no”  and  where  ritual  must  be  observed  before  all  else,  I  think  that  Western  style  “safety  culture”  will  be  very  hard  for  the  Japanese  to  accept  Ludger  Mohrbach,  VGB  PowerTech  (April  15,  2011)   Ques9on:  Is  this  accident  a  maTer  of  residual  risk  of  nuclear  energy?No,  it  is  rather  a  maTer  of  obviously  having  ignored  a  high  specific  risk  Prof.  Oka  (Waseda  University,  HP)   The  accident  is  deeply  rooted  in  Japanese  society  and  culture;  lack  of  responsibility  by  the  Government,  lack  of  open  dialogue,  closed  experts’  community  Prof.  Yagawa  (AESJ  journal)   World-­‐class  manufacturing    but  not  built  on  basic  R&D  on  NP  Prof.  Hatamura  (in  his  book  on  “Assume  condi9ons  not  assumed”)   If  you  do  not  think  beyond  assumed  condi9ons,  you  are  not  prepared  enough  

CollecAng  informaAon  from  other  analysis/statements  

IAEA Technical Meeting, 2012June, A. Omoto 39

Prof.  S.  Takemori  (in  his  book  on  na9onal  nuclear  policy  and  u9lity)   “Implicit  protec9on”  by  the  Government  over  u9lity’ implementa9on  of  NP  policy  (business)  caused  poor  risk  management  by  u9li9es  and  the  financial  market  relied  on  this  “protec9on”  

Prof.  T.  Kikkawa  (in  his  book  on  TEPCo  –  the  root  cause  of  failure)   Failed  to  recognize  that  poor  risk  management  to  nuclear  accident  was  the  largest  threat  to  the  company   Expecta9on  on  “implicit  protec9on”  by  the  Government  over  u9li9es  implemen9ng  na9onal  NP  policy  

Prof.  J.  Ahn  (UCB,  Iwanami  “Science”)   The  way  NE  policy  is  determined  and  implemented  needs  scru9ny  

CollecAng  informaAon  from  other  analysis/statements  

IAEA Technical Meeting, 2012June, A. Omoto 40

Page 21: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

21  

Weakness  in  achieving  responsible  use:  

               1)  Interac9on  with  outside  (society,  scien9fic  community,                            safety  experts  in  other  area,  global  nuclear  safety  regime)  

               2)  Addressing  societal  value  

               3)  Tension  and  sensi9vity  

               4)  Effec9ve  safety  management  and  oversight    

ObservaAons

IAEA Technical Meeting, 2012June, A. Omoto 41

               Introduc.on  

             Four  cri.cal  areas  

           UT  study  

  Accident  Inves.ga.on  Commi:ees  

        Discussion  

         Concluding  remarks  

IAEA Technical Meeting, 2012June, A. Omoto 42

Page 22: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

22  

  Government  report  to  the  IAEA  (June/September2011)  :  28  Lessons  in  5  specific  areas  (Preven9on  of  Severe  Accident,  Severe  Accident  Management  (SAM),  Emergency  response,  Safety  infrastructure,  culture)  

Key  points  are;  1.  Design  considera9ons  against  natural  hazards  2.  Design  considera9ons  against  SBO  (Sta9on  Blackout)  and  Isola9on            from  UHS  (Ul9mate  Heat  Sink)  3.  Completeness/effec9veness  of  SAM  4.  Emergency  Management  5.  Safety  regula9on  and  safety  culture  6.  Mul9ple  unit  installa9on  7.  Spent  Fuel  Pool  design  

[source]  hgp://www.me=.go.jp/earthquake/nuclear/backdrop/20110911.html  

Government  reports  and  Lessons  Learned    

IAEA Technical Meeting, 2012June, A. Omoto 43

 NPO  “Rebuild  Japan”  [RJIF]          (report  published,  February2012)    

  Prevailed  “safety  myth”  leading  to  lack  of  precau9ons  by  considering  “beyond  assumed  condi9ons”  

  Capability  of  regulators  as  compared  with  TEPCO’s   Weak  risk  governance  under  implementa9on  of  Government-­‐

endorsed  NE  policy  by  U9li9es    Crisis  management  and  leadership  (conflic9ng  view  on  PM’s  role  

from  Congressional  CommiTee)                  [source]  hgp://rebuildjpn.org/en/project  

  Diet  (Congressional)    Inves9ga9on  CommiTee  [NAIIC]        (ongoing,  to  be  released  in  June2012)  :  Informa9on  released  

9June2012  centered  around  the  role  by  PM  and  the  Cabinet    PM’s  role  in  crisis  management    and  crisis  management  system    Dissemina9on  of  informa9on  (predic9on  of  FP  dispersion)    Priority  not  on  protec9on  of  health  of  the  local  residents                    [source]  hgp://www.naiic.jp/wp-­‐content/uploads/2012/06/RontenSeiri2F_20120609.pdf  

Key  issues  raised  by  the  three  invesAgaAon  commimees  

IAEA Technical Meeting, 2012June, A. Omoto 44

Page 23: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

23  

  Government  Inves9ga9on  CommiTee  [ICANPS]    (interim  report  in  Dec  2011,  final  report  to  be  released  in  July2012))  

  Emergency  response  center  (local/government-­‐TEPCO)  and  evacua9on  

  TEPCO’s  Accident  Management   Measures  against  natural  hazard  and  severe  accident  

Raised  issues  of;  •  Insufficient  measures  by  TEPCO  in  preven9on    •  Insufficient  capability  of  regulatory  body  •  Failure  in  risk  communica9on  •  Fragmented  exper9se  in  diverse  disciplines  

[SOURCE]  hgp://icanps.go.jp/eng/interim-­‐report.html  

Key  issues  raised  by  the  three  invesAgaAon  commimees  

IAEA Technical Meeting, 2012June, A. Omoto 45

  Corporate  risk  management  programme  (since  2007)    Fully  recognized  high  risks  associated  with  Earthquake  and  

Tsunami      Failed  short  of  recognizing  the  risk  of  complete  loss  of  safety  

func9ons  by  high  Tsunami  

  Reported  ac9ons  for  safety  culture,  based  on  2002  falsifica9on  issue  and  WANO  corporate  peer  review  2008      7  traits  of  safety  culture  

[SOURCE]  TEPCO’s  final  inves9ga9on  report,  20June2012,  hTp://www.tepco.co.jp/en/press/corp-­‐com/release/2012/1205638_1870.html  

TEPCO’s  invesAgaAon  commimee  report  

IAEA Technical Meeting, 2012June, A. Omoto 46

Page 24: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

24  

IAEA Technical Meeting, 2012June, A. Omoto 47

               Introduc.on  

             Four  cri.cal  areas  

           UT  study  

           Accident  Inves.ga.on  Commi:ees  

  Discussion  

           Concluding  remarks  

1)  Weakness  of  “nuclear  professionals’  community”  in  interac9on  with  outside  (society,  scien9fic  community,  safety  experts  in  other  area,  global  nuclear  safety  regime)  

  Lack  of  societal  safety  goal,  for  assurance  of  no/limited  land  contamina9on  

  Interpreta9on  of  uncertainty  in  natural  science    Failure  of  risk  communica9on  

2)  “Prisoner’s  dilemma”  situa9on  in  safety  improvement  under  distrust  to  each  other  amid  polariza9on  on  nuclear  issues  

3)  Possible  lack  of  tension  between  Operator  and  Regulator  (Government)  due  to  implicit  view  of  Government-­‐endorsed  NE  policy  implemented  by  Nuclear  U9li9es.  

4)  Some  concern  that  individuals  were  not  willing  to  take  responsibility  in  an  organiza9on  in  an  environment  of  “loose-­‐lip-­‐sunk-­‐ship”.  (UT  study)

Key  underlying  factors  (I)  InteracAon  of  individual,  organizaAon  &  society  

IAEA Technical Meeting, 2012June, A. Omoto 48

Page 25: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

25  

1)  Assump9ons  in  the  most  basic  level  of  safety  culture      “Accident  will  not  happen  here”  (AM,  EP)    Over-­‐confidence  in  safety  due  to  equipment  reliability  (system  

safety  vs  focus  on  equipment  reliability)  

2)  Priority  (U:  U9li9es,  G:  General  in  community,  R:  Regulator)    (U)  Interac9on  with  the  local  government  and  township    (R)  Formality  of  QA  and  compliance,  rather  than  risk  management    (U,  R)  Equipment  reliability  and  maintenance  

3)  Weakness  in  responsible  use  [Operator]    Risk  management  in  “Government-­‐endorsed-­‐business”       Individual’s  responsibility  in  Japanese  organiza9on       Yet,  high  moral  among  TEPCO’s  field  workers  at  Fukushima  in                    managing  the  Accident  (as  evidenced  by  22Dec2011TEPCO  report)  

4)  Weakness  in  responsibility  to  protect  public  health  and        environment  [Government]  

hgp://www.aec.go.jp/jicst/NC/iinkai/teirei/siryo2012/siryo19/siryo1-­‐1.pdf  

Key  underlying  factors  (II)  Cultural  factors

IAEA Technical Meeting, 2012June, A. Omoto 49

1)  Priority  on  Technical  competence/knowledge  in  safety:              Not  necessarily  high  in  Operator  nor  Regulator    (Examples)  

  Frequent  shuffling  of  regulatory  staff  in  Government    Head  of  NISA  when  3.11  occurred    Plant  manager:  Operator’s  priority  on  interac9on  with  the  local  government  

and  township  (Plant  Manager,  for  instance)      Heavy  outsourcing  by  Operator  to  Contractors  

•  Staff/GWe  at  NPP:  150  (TEPCo)  vs  350-­‐800  (world  average)  

2)  Competence/knowledge/Understandings  of:    Cliff  edge  characteris9cs  associated  with  flooding  as  compared  with  

earthquake    Decision-­‐making  under  epistemic  uncertain9es  &  defense-­‐in-­‐depth    Status  and  behavior  of  IC  (as  reported  in  ICANPS  report)    Iodine  tablet    Re-­‐cri9cality  

Key  underlying  factors  (III)  Competence/Knowledge/Understanding

IAEA Technical Meeting, 2012June, A. Omoto 50

Page 26: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

26  

1)  Organiza9onal  seung  to  manage    safety-­‐related  issues                        Safety  is  everybody’s  business                        Decision  process  on  mul9-­‐disciplinary  issues  

2)    Effec9ve  independent  safety  oversight    

3)  Historical  evolu9on    Response  to  TMI/Chernobyl    Falsifica9on  issue  that  surfaced  in  2002  as  an  alarming  

sigh  of  cultural  issue    Earthquake  at  Kashiwazaki-­‐Kariwa  site  in  2007  as  an  

alarming  sign  of  site  characteriza9on  and  preparedness  to  LPHC  risk  

Ref. CAIB report on NASA

Key  underlying  factors  (IV)  EffecAve  safety  management  and  oversight

IAEA Technical Meeting, 2012June, A. Omoto 51

  All  the  above  (Interac9on  of  Individual/Organiza9on/Society,  Culture  and  Competence/Knowledge/Understanding)  would  influence    decision-­‐making,  preparedness  and  ac9ons  for  risk  management  

  Decision-­‐making  on    •  Precau9onary  measures  against  LPHC  events  •  Level  4  &5  Defense-­‐in-­‐Depth  

  Typical  ques9ons  required  before  decision-­‐making;  •  ”Do  we  really  know  implicit  assump9ons  in  the  analysis?”  •  “What  if  the  assumed  condi9on  was  wrong?”  •  “What  is  our  bias  in  our  organiza9onal  culture?”  •  “What  are  the  global  best  prac9ces?”  

Leading  to  inappropriate  decision-­‐making,  preparedness    and  acAons  for  risk  management

IAEA Technical Meeting, 2012June, A. Omoto 52

Page 27: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

27  

Lack of basic Understanding (21%)

Over-confidence (17%)

Lack of attention to multi-disciplinary aspect (17%)

Pressure (Time/ Management) (15%)

Illusive delineation of responsibility (10%)

Others (21%)

(Performance  Improvement  Interna=onal,  MIT  seminar,  1994)

Analysis  of  failure  of  decision-­‐making  on  technical  issues  

IAEA Technical Meeting, 2012June, A. Omoto 53

  LimitaAon:  You  have  limited  knowledge/experience  &  Your  imaginaAon  is  limited    “I  know  one  thing,  that  I  know  nothing”    (Socrates  )    Collect  and  Use  database  /  best  prac9ces  /  Lessons  Learned    Yet  there  are  uncertain9es  (aleatoric  &  epistemic:  data,  scenario,  

modeling)    Intensive  discussion  with  experts  from  different  disciplines  

  Bias:  Your  have  a  bias  you  yourself  do  not  recognize    Analyze  why  your  (your  organiza9on)  made  bad  decisions    Independent  review  

  AssumpAons:  “What  are  the  assumed  condiAons  in  your  decision?”    What  if  the  assumed  condi9on  is  wrong?    

For  knowledgeable  decision  making  

IAEA Technical Meeting, 2012June, A. Omoto 54

Page 28: IAEA ™ Omoto Final · 2013. 11. 6. · 12.6.27! 1! Accident(at(TEPCO’s(Fukushima6Daiichi(NPP(Possible underlying factors influencing decision-making, preparedness and risk management

12.6.27  

28  

  Poten9al  key  underlying  factors    Interac9on  of  individual,  organiza9on  and  society    Cultural  factors    Competence/Knowledge/Understainding    Effec9ve  safety  management  and  oversight  

  Change  of  interac9on/culture/process  relevant  to    underlying  issues              to  avoid  another  severe  accident  by  different  accident  scenario  but  

by  similar  root  cause    

CONCLUDING  REMARKS

IAEA Technical Meeting, 2012June, A. Omoto 55

Thank  you  for  your  a:en.on