I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all...

13
I 11 - OMMMU - - mmmm VA I i Ems -7 o;1- 1 7 ]RI IS H OAK flx:a t"slilU1l row f cld SCltt.4t3 SND rnUC^i1O6r September27, 1996 Mr. Larry Pittiglio U. S. Nuclear Regulatory Commission Division of Waste Management - NMSS Two White Flint North TWFN-7F27 11555 Rockville Pike Rockville, Maryland 20852 SUBJECT: REVISED TRIP REPORT-ON-SITE REVIEW AND LIMITED CONFIRMATORY SURVEY OF THE TROJAN NUCLEAR POWER PLANT ISFSI PROJECT, RANIER, OREGON (DOCKET NO. 72-17; RFTA 9642) Dear Mr. Pittiglio: The Environmental Survey and Site Assessment Program (ESSAP) of the Oak Ridge Institute for Science and Education (ORISE) conducted an on-site review and limited confirmatory survey of the future ISFSI area at the Trojan Nuclear Power Plant. These activities were performed during the period August 19 through 21, 1996 and included a review of the final status survey procedures and documentation, laboratory analytical capabilities, gamma surface scans of the ISFSI area, and the collection of split soil samples. The enclosed revised trip report provides the procedures and results of these activities. Any comments you may have will hs incorporated into the final trip report. Should you have any questions or comments, you may contact me at (423)576-5073 or Eric Abelquist at (423)576-3740. Sincerely, Timothy J. Vitkus Survey Projects Manager Environmental Survey and Site {I . 7/ Assessment Program / \ I I f . - I I TJ V:dka Enclosure 9612030018 960927 PDR ADOCK 05000344 Y PDR cc: R. Uleck, NRC/NMSSITWFN 7F27 D. Tiktinsky. NRC/NMSSITWFN 8A23 D. Fauver, NRC/NMSSI'WFN T-81737 D. Moser, NRC/NMSS/T-7F2 I % ; -lo 1 P.O. BOX 117. o0 .~. ; (; , r 0AA- -^1 -4 2 ^_..&2... A t 1-e- .Jo. V. Everett, NRC/Region IV J. Beck, ORISE/ESSAP E. Abelquist, ORISE/ESSAP File/650 VK RIDGE. TENNESSEE 37831.0117 I.. .. 4 1 ' -I . .1

Transcript of I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all...

Page 1: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

� I 11 - OMMMU- - mmmm VA I i Ems

-7 o;1- 1 7

]RI IS HOAK flx:a t"slilU1l row f cld SCltt.4t3 SND rnUC^i1O6r

September27, 1996

Mr. Larry PittiglioU. S. Nuclear Regulatory CommissionDivision of Waste Management - NMSSTwo White Flint North TWFN-7F2711555 Rockville PikeRockville, Maryland 20852

SUBJECT: REVISED TRIP REPORT-ON-SITE REVIEW AND LIMITED CONFIRMATORYSURVEY OF THE TROJAN NUCLEAR POWER PLANT ISFSI PROJECT, RANIER,OREGON (DOCKET NO. 72-17; RFTA 9642)

Dear Mr. Pittiglio:

The Environmental Survey and Site Assessment Program (ESSAP) of the Oak Ridge Institute for Science andEducation (ORISE) conducted an on-site review and limited confirmatory survey of the future ISFSI area atthe Trojan Nuclear Power Plant. These activities were performed during the period August 19 through 21,1996 and included a review of the final status survey procedures and documentation, laboratory analyticalcapabilities, gamma surface scans of the ISFSI area, and the collection of split soil samples. The enclosedrevised trip report provides the procedures and results of these activities. Any comments you may have willhs incorporated into the final trip report.

Should you have any questions or comments, you may contact me at (423)576-5073 or Eric Abelquist at(423)576-3740.

Sincerely,

Timothy J. VitkusSurvey Projects ManagerEnvironmental Survey and Site {I . 7/

Assessment Program/ \ I I f . - I I

TJ V:dka

Enclosure

9612030018 960927PDR ADOCK 05000344Y PDR

cc: R. Uleck, NRC/NMSSITWFN 7F27D. Tiktinsky. NRC/NMSSITWFN 8A23D. Fauver, NRC/NMSSI'WFN T-81737D. Moser, NRC/NMSS/T-7F2 I

% ; -lo 1 P.O. BOX 117. o0.~. ; (; , r 0AA- -^1 -4 2 ^_..&2... A t 1-e- .Jo.

V. Everett, NRC/Region IVJ. Beck, ORISE/ESSAPE. Abelquist, ORISE/ESSAPFile/650

VK RIDGE. TENNESSEE 37831.0117

I.. . . 4 1 ' -I . .1

Page 2: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

ON-SITE REVIEW ANDLIMITED CONFIRMATORY SURVEY

OF THETROJAN NUCLEAR POWER PLANT ISFSI PROJECT

RANIER, OREGON

INTRODUCTION

Portland General Electric (PGE) plans to decommission the Trojan Nuclear Plant (TNP) located in

Ranier, Oregon. The initial preparations for the decommissioning project will be the construction

of an Independent Spent Fuel Storage Installation (ISFSI) within the northeast portion of the Plant

Industrial Area (PIA). Within the PIA, the proposed ISFSI will encompass the footprint of the

former radwaste storage building as well as other open land areas (Figure 1). Because soils will be

inaccessible beneath the ISFSI once it is constructed :'nd radiation levels in the immediate area will

be elevated when the spent fuel is stored in the facility, PGE has elected to perform the final status

radiological survey of the ISFSI site prior to the facility's construction. In support of these activities,

PGE prepared a final status survey plan (PGE 1996) which was submitted to and approved by the

U. S. Nuclear Regulatory Commission (NRC). PGE's final status survey plan was prepared in

accordance with Draft NUREG/CR-5849 (NRC 1992). The PIA survey area was divided into an

affected area-the footprint of the former radwaste building referred to as survey unit RWA-and

the remainder classified as an unaffected area, referred to as survey unit TIA (Trojan Industrial

Area).

The NRC's, Division of Waste Management requested that the Environmental Survey and Site

Assessment Program (ESSAP) perform both an in-process review of PGE's final survey of the ISFSI

area as well as a limited confirmatory radiological survey of the area. This report describes the

procedures and results of these activities.

OBJECTIVES

The project objectives were to provide independent reviews of the PGE ISFSI survey procedures and

documentation, in-process observation of the final status survey performance, and to provide limited

independent radiological data for use by the NRC in determining the adequacy and accuracy of

PGE's final status survey data.

Trojan Nu eAt PuwcI Plant ISFS! lrny (6510) * .Scrtenict 27. 1996 hN.eS131fitll rP(%Vitku%.(j4

Page 3: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

PROCEDURES AND RESULTS

ESSAP's on-site activities included a review of the PGE final status survey procedures and

evaluation and observation of the following: survey instrumentation calibration and use, site

preparation, surface scanning, soil sampling, survey documentation, in-house quality assurance- (QA)

oversight, sample analysis, data management, and personnel qualifications. In addition, the

independent confirmatory survey activities included surface scans of the ISFSI area and the

collection of split soil samples for confirmatory analysis.

FINAL STATUS SURVFY REVIEW

ESSAP initially reviewed the ISFSI area final survey plan in order to become familiar with the

commitments made in the plan relative to procedure implementation during survey performance.

Instrument Calibration and Operational Checkout

Instrumentation used for the final status survey included NE Technology gas proportional detectors

for alpha and beta-gamma surface scans, and Eberline SPA-8 Nal scintillation detectors and a

Reuter-Stokes RSS-I 12 pressurized ionization chamber (PIC) for gamma exposure rate

measurements. The calibratiuma sources used for the gas proportional detectors were Pu-239 and

Tc-99 for alpha and beta, respectively, and were NIST-traceable. Calibrations of the PIC and the Nal

scintillation detectors were performed by the manufacturer. The Nal scintillation detectors were

calibrated with Cs-137 and the Eberlinc ESP-2 ratemeter-scalers coupled to the detectors had been

elcctronicallv adjusted to convert gamma counts per minute to pR/h, based on this calibration. The

licensee was validating the conversion factor during the course of the final status survey by

performing comparative gamma measurements between the PIC and the Nal scintillation detectors.

Operational checkouts for the instrumentation included background counts and check source

measurements three timnes per day. The acceptable operational parameter used by the licensee was

+10% of the mean.

t J,,Lk Pn.-r Mm ISI N et 1 ).* .1 27. 1in 2u.n ,. -'... . - - . .' " .. . -.. ..-. - . -- , -1-- - - . - -

Page 4: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

Site Preparation

A 10 m x 10 m reference grid had been superimposed on a site plan. The grids within the affected

survey unit were then installed and labeled alpha-numcrically within the area, resulting in a total of

ninc 100 m2 grid blocks. The grids within the TIA had not been established at the time of the sile

visit.

Surface Scan

The licensee performed 100 percent beta-gamma surface scans of each 100 m2 grid block within the

RWA by systematically moving the gas proportional detectors in close contact with the ground

surface at a rate of approximately 5 cm per second. The area was then re-scanned. Locations of

elevated direct radiation were determined by establishing an alarm set point consistent with the

scanning minimum detectable activity.

Because of the contaminants of concern at TNP-Cs-137 and Co-60-ESSAP recommended that

the licensee consider replacing beta-gamma surface scans of the soil areas with gamma scans using

Nal scintillation detectors. The recommendation was based on the reliability of gamma scans for

the detection of these contaminants and the uncertainty of the alarm setting-based on a calibration

efficiency factor determined with a standard electroplated soutce that did not account for soil

attenuation of the beta radiation.

Exposure Rate Measurements

PGE performed gamma exposure rate measurements at four locations within each grid block that

were spaced equidistance bhtween the center and the grid block corners. Measurements were

performed at I meter above the surface using a Reuter-Stokes RS-I 12 pressurized ionization

chamber. In addition, one minute integrated counts were also made at I meter above the surface with

the Nal scintillation detector at each location in order to validate the gamma count rate to pR/h

conversion factor.

Trniin NHudcar Ptw*r rnit ISUS njict (65.)*.% mcri 27.1996 3 h Vs~atnr n mffiillm U11... I.....................

Page 5: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

Soil Sampliuig

Soil samples were collected within each grid block at four locations corresponding to the exposure

rate measurement locations. A template was placed over each location and the soil contained within

the template was collected; placed into bags; and labeled with grid location, identification number,

sampler(s) name, and date. The depth of sample varied dependent upon bedrock depth but did not

exceed 15 centimeters. Samples were then transported to the laboratory undkr appropriate

chain-of-custody.

Survey Documentation

ESSAP reviewed survey documentation for each area that had been completed at the time of the site

visit. All data had been recorded on appropriate field forms. The data recorded included a daily

record of the instrumentation used and the operational checkout data for each instrument and

resolution of any occurrences of instrumentation failure, the area scanned and the surface scan results

including investigations of areas where the instrument alarm action level was exceeded. exposure

rate measurement data, soil samples collected with corresponding chain-of-custody, and raw soil

sample analysis data. The data base that will be used for data management had not been established

a: the time of the site visit; therefore, ESSAP was unable to review the adequacy and accuracy of the

proposed system.

The survey documentation also included records of the in-house quality assurance (QA) oversight.

This documentation provided a description of the QA activities performed. . hese included QA

observation of the field survey activities and a comparison to the written procedures. Any

nonconfomiances observed were then documented in a formal memorandum for resolution. ESSAP

did note that when areas were resurveyed as a result of a nonconformance, the new data sheets

generated were not specifically identified as replacements for the old data.

Tn.,an NuL.r Pi.set PIlnr ISFSI Proicet PMnte1 *.e t Th I'P)6 4 b.-I......... 1-1. . - . - � - - - - __ - - -I- . - � _- __ - __ - . - - .. - .|'11.1. -}l5lU r

Page 6: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

POrsonn 1Qualificailons

ESSAP reviewed the training program used to certify individuals to perform the final status surveys.

The program con-esed of lectures as well as practicles (i.e., instrumentation set up and use, and

mock surveys). The lecturc material consisted of presentation of all applicable procedures including

survey preparation, field data collection, sample collection, chain-of-custody, survey/sample

documentation, instrumentation set up and use. Successful completion of the training was then

formally documented.

Sample Preparation and Analysis

The system used for sample analysis is an intrinsic germanium gamma spectrometry system

calibrated to a NIST traceable mixed-gamma standard. Calibration procedures also include two-hour

background counts and daily energy calibration. The operability parameters of the counting system

are documented on control charts and include plots of background, energy resolution, full-width half

maximum, and calibration standard activity levels. If any of these parameters fall outside of the ±3

a acceptable operating parameters, the system requires recalibration or service as applicable.

Once samples were collected, they are transferred under chain-of-custody to the on-site laboratory

for preparation anC analysis by gamma spectrometry. Samples are transferred from the original

container to pans labeled with th' unique sample identification number, dried in an oven for two

hours, weighed, and then transferred to 2-liter Marinellis for counting. Samples arc counted for two

hours. The system includes a computer software library for photopeak identification. The raw data

sheets contain the sample identification number, peak search and related information, and identified

radionuclides reported in microcurics per gram (pCi/g). The system reports the minimum activity

concentration (MDC) for Cs-137, Co-60, and Ce-144. ESSAP recommended that MDCs also be

reported-if the following were not identified in the peak search-for U-238, U-235, and other

gamma emitting fission or activation products.

Currently. the laboratory QA/QC program does not include participation in an EML cross-check

program or duplicate analysis. ESSAP also suggested that the laboratory consider these two options

for the laboratory program.

T .uma N tl-n IPFSI PnIed if moli . Se,.ten1er 7. MM5 P...*ran n t .- llI.. . 'I' �. -.. ' -

Page 7: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

I

CONFIRMATORY SURVEY OF THE ISFSI AREA

The following provides the procedures and results of the limited confirmatory survey of the ISFSI

area.

Surface Scans

ESSAP performed surface scans for gamma radiation over I 0U percent of the RWA survey unit and

approximately 25 percent of the unaffected TIA survey unit. Surface scans were performed using a

Nal scintillation detector coupled to a ratemeter with an audible indicator. Surface scans did not

identify any locations of elevated direct radiation.

'soL Sampling

ESSAP obtained five split soil samples from two of the nine RWA grids. Samples were collected by

TNP personnel, homogenized in the field, and an approximately 1000 gram aliquot removed for

confirmatory analysis.

Salmple Analysis

The five split soil samples were analyzed by solid-state gamma spectrometry. The spectra were

reviewed for fission and activation products and U-238 and U-235. The radionuclide concentrations

in these soil samples are provided in Table 1. Although ESSAP has not collected area specific

background data for comparison, concentration levels in these samples do not suggest the presence

of contamination.

Tron-, W-Iewh ertMnln t ISFSI rNowtt (6 .Sn,4cmat ' 6. 19j6 6 h' ejir m rntw4ithu N4

Page 8: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

__ - - __ __ __ __ - -__ -

SUMMARY

The Environmental Survey and Site Assessment Program of the Oak Ridge Institute for Science and

Education performed an on-site review and limited confirmatory survey of the ISFSI area at the

Trojan Nuclear Plant in Ranier, Oregon. The review consisted of an on-site evaluation and

observation, during the period August 17 through 19, 1996, of TNP's final status survey, sampling.

and analytical procedures for the ISFSI area. Additionally, a limited confirmatory survey of the ISFSI

area was performed that included gamma surface scans and split soil samples for confirmatory

analysis.

The results of the on-site review indicated that overall, TNP's survey plan and procedures are

adequate for demonstrating the current radiological status of the ISFSI area. The limited-scope

confirmatory survey did not identify any areas with elevated direct radiation levels suggestive of

residual contamination. Analysis of split samples also did not identify any residual contamination.

T..,,n Nwiek Powrf Pl" ISFSI Poten t (630) . Soembet 26. 1006 7 .-t--I.__ I - - ____ - - I . cha g-d, *w ". _.

Page 9: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

I

rD50-001 (1)

1 7 1 6 1 5 1 4 13 12 1 1 10 9 8 7 6 5 4 3

. .~ .... .........

0

. 1. .. ... .. ...... . ..... . .... .

E

awSR

(J ~WAREH-OUSE RW

H

...... . AME.CA *.**.'... ... ........

FAB SHOP'

MiATER~IALS.

J WAREHOUSE TIK

. ...........

(E)

N

x X FENCE

- -- -SITE SURVEYBOU1NDARY

0 FEET 60

FIGURE 1: Trojan ISFSI Area - Plot PlanMEES2

Troizsn NulkeJ1 Power Plugt IsmS Proiect C650). -cvcm~bc 27.19% 8 Is&.ww.- -fL

- - -- - - - - - - --- - I . . . - --- - .1 .1-- - -,

Page 10: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

. . .650-002 (x)

17 16 15 14 13 12 11 10 9 8 7 6 5 4 3

... . ...... . ........ . .....

... ...........

! U TIkI ... ;- [ .- wt-ii

I . . .3I . . . i

......

MEASUREM ENT/SAMPLING i X FENCELOCATIONS

L - ____ SITE SURVEYn SURFACE SOIL BOUNDARY

F FEET 60

0METERS 20

FIGURE 2: Trojan ISFSI Area - Sampling Locations

Trojan Nuclca Powa PIug ISFSI Project (650) . ScPcnbci 27. 1996 9 h:1cssap4np rp{Wvvittnu.04

Page 11: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

TABLE 1

RADIONUCLIDE CONCENTRATIONS IN SOIL SAMPLESTROJAN NUCLEAR PLANT

RANIER, OREGON

Radionuclide Concentration (pCi/g)

Radionuclide Sample 1"j S.Imle2' Sam le 3' Sample4 Sam le 3'

Co-57 <0.0 I <0.01 <0.0 1 <0.0 1 <0.02

Co-58 <0.02 <0.02 <0.02 <0.02 <0.03

Co-60 <0.03 <0.03 <0.03 <0.03 <0.04

Cs-134 <0.03 <0.02 <0.03 <0.03 <0.04

Cs- 1 37 <0.02 <0.02 <0.03 <0.02 <0.06 4

Eu-152 <0.05 <0.04 <0.05 <0.05 <0.08

Eu-154 <0.09 <0.09 <0.08 <0.10 <0.13

Eu-155 <0.05 <0.05 <0.05 <0.05 <0.07

Mn-54 <0.02 <0.02 <0.02 <0.02 <0.03

U-23 5 <0.10 <0.09 <0.09 <0. I0 <0.15

U-238 0.45 +. 0.21 0.43 4 0.22 0.35 i 0.18 0.35 + 0.26 0.83 ± 0.26

Zn-65 <0.05 <0.05 <0.05 <0.05 <0.08

'Refer to Figure 2.bUncertainties represent the 95% confidence level, based only on counting statistics.

10TmW~ Nuclear Pow,. Plant ISFSI Pr.ojm (so) . Septembe 26,199% h "MPtnp I'"r tktn *1w

Page 12: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

I l

TABLE 1

RADIONUCLIDE CONCENTRATIONS IN SOIL SAMPLESTROJAN NUCLEAR PLANT

RANIER, OREGON

Radionuclide Concentration (pCi/g)

Radionuclide Sakmple 1V Sample 2' Sample 3' Sample 4' Sape5

Co-57 <0.01 <0.01 <0.01 <0.01 <0.02

Co-58 <0.02 <0.02 <0.02 <0.02 <0.03

Co-60 <0.03 <0.03 <0.03 <0.03 <0.04

Cs-134 <0.03 <0.02 <0.03 <0.03 <0.04

Cs-137 <0.02 <0.02 <0.03 <0.02 <0.06 ± 0.02

Eu- 152 <0.05 <0.04 <0.05 <0.05 <0.08

Eu- 154 <0.09 <0.09 <0.08 <0.10 <0.13

Eu- 155 <0.05 <0.05 <0.05 <0.05 <0.07

Nin-54 <0.02 <0.02 <0.02 <0.02 <0.03

U-23 5 <0. 1 0 <0.09 <0.09 <0. 1 0 <0. 1 5

LJ-238 0.45 .1. 0.21 0.43 i 0.22 0.35 i 0.18 0.35 i 0.26 0.83 ± 0.26

Zn-65 <0.05 <0.03 <0.05 <0.05 <0.08

'Rcfcr to Figure 2'Unccriaintics reprcscnt the 95% confidence level, based only on counting statistics.

f- 046-P Mwe~e 1 1 15t ll1 e J1.@1i. F '. 21> I10 h h - tt"r Wrm %,u . to-.... . . . . .. . .. ..... ...... .... . ..... . .

Page 13: I - - mmmm VA I o;1- 1mock surveys). The lecturc material consisted of presentation of all applicable procedures including survey preparation, field data collection, sample collection,

1.

REFERENCES

Portland General Electric (PGE). Trojan Nuclear Plant, Final Survey Plan for the ISFSI Site. RanierOregon; August 13, 1996.

U. S. Nuclear Regulatory Commission (NRC). Draft NUREG CR/CR-5849, Manual for ConductingRadiological Surveys in Support of License Termination. Washington, DC; June 1992.

[.nr;lP - ll MM P!S ... Ilect #(.Viarer~ -a1we1Ihtkt1nt1~i.. 1- . -- - - - - . .-.- .- - . � I --- . - -1 - - . . - - " .. . l.*r a d