I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

21
I I Larry Heil, FHWA October 15, 2003

Transcript of I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Page 1: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

II

Larry Heil, FHWA October 15, 2003

Page 2: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Environmental StreamliningEnvironmental Streamlining

Page 3: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Why integrate planning into Why integrate planning into NEPA?NEPA?

Hoosier Heartland Corridor Study – 1995Ohio River MIS (ORMIS) - 1997US 231 & SR 641 FEIS/ROD – 2000Indiana NEPA/404 Merger Agreement was

a limited success

Page 4: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Desired OutcomeDesired Outcome

ONE decision-making process that is efficient, inclusive, structured, that resolves issues as early as possible, and results in high-quality transportation decisions and NEPA documents

Page 5: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Why integrate planning into Why integrate planning into NEPA?NEPA?

Section 1308 of TEA-21 (June 9, 1997), entitled Major Investment Study (MIS) Integration – shall eliminate the MIS as a separate

requirement, and– integrate the MIS requirement into NEPA

Page 6: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Why integrate planning into Why integrate planning into NEPA?NEPA?

Section 1309 of TEA-21 (June 9, 1997), entitled Environmental Streamlining – Develop/Implement coordinated environmental

review process– Environmental reviews for all Federal permits

& approvals conducted concurrently– Establish time frames for reviews– Dispute Resolution

Page 7: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

How did Indiana integrate How did Indiana integrate planning into NEPA?planning into NEPA?

Environmental Streamlining Task Group – 1st Draft and agency expectations/issues

discussed at January 19, 2001 Meeting– 2nd Draft and response to agency comments

discussed at February26, 2001 Meeting– 3rd Draft and 30-minute presentation on each

active EISs and EA/Corridor Studies presented at March 28-29,2001 Interagency Meeting

– Final EIS Procedures issued July 6, 2001

Page 8: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Basic Elements of EIS Basic Elements of EIS ProceduresProcedures

Establish “Project Coordination Team” to provide a structured mechanism for INDOT, FHWA-IN, and the MPO to guide consultant EIS development

Eliminate the duplication of effort between planning and NEPA studies (eliminate MIS, per Section 1308 of TEA-21)

Page 9: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Basic Elements of EIS Basic Elements of EIS Procedures (cont.)Procedures (cont.)

Provide a structured interagency coordination process with deadlines and a dispute resolution process (per Section 1309 of TEA-21)

Seek agency input at key decision pointsResult in timely decisions that avoid project

delay

Page 10: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Key Coordination Points with Key Coordination Points with AgenciesAgencies

Required: NOI (early coordination), DEIS, FEIS, ROD

Three Interagency Review Meetings: – Purpose and Need/Preliminary Alternatives– Preliminary Alternatives Analysis and

Screening– Preferred Alternative and Mitigation

Page 11: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Interagency Review MeetingsInteragency Review Meetings

Face-to-face meetings with agencies held 30 days into 60-day review period

Minutes documenting issues sent 7 days after meeting.

Any remaining agency issues may be submitted in writing by the deadline

Page 12: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Purpose and Need and Purpose and Need and Preliminary AlternativesPreliminary Alternatives

Purpose and Need Package:– 2-page summary – Core objectives & evaluation criteria– Map of conceptual alternatives– Discuss study area problems/issues– Supporting documentation/details

Page 13: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Purpose and Need and Purpose and Need and Preliminary Alternatives(cont.)Preliminary Alternatives(cont.)Seeking agency feedback on:

– Statement of core project objectives– Evaluation criteria for alternatives– Additional alternatives– Modification of existing alternatives– Specific resource issues– Response to FHWA invitation to be

Cooperating Agency

Page 14: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Preliminary Alternatives Preliminary Alternatives Analysis and ScreeningAnalysis and Screening

Preliminary Alternatives Analysis and Screening Package:– Revised 2-page P&N– Alternatives Screening Summary Table– Map of alternatives retained/discarded– Preliminary alternatives analysis (GIS)– Rationale for dropping/retaining alternatives– Scope of special studies

Page 15: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Preliminary Alternatives Preliminary Alternatives Analysis and Screening Analysis and Screening

(cont.)(cont.)Seeking agency feedback on:

– Clarity of preliminary alternatives analysis– Alternatives retained– Methodologies for evaluating impacts– Scope of study needed for critical impacts

Page 16: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Preferred Alternative and Preferred Alternative and MitigationMitigation

Package:– 2-page summary with map– Summary of major public and agency issues

and responses– Recommended Selected Action with rationale– Preliminary proposed mitigation

Page 17: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Preferred Alternative and Preferred Alternative and Mitigation (cont.)Mitigation (cont.)

Seek Agency Feedback on:– Response to agency issues– Rationale for selecting Preferred Alternative

and not others

Page 18: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

EA/Corridor Study vs. EISEA/Corridor Study vs. EIS

INDOT/MPO Funding CommitmentClarity from INDOT and MPO 20-year

Transportation PlansCongressionally Mandated Feasibility

StudyNew Transit Start

Page 19: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Option 1 – Planning in Context Option 1 – Planning in Context of EISof EIS

NOI P&N Interagency

Meeting Preliminary

Alternatives Analysis and Screening Interagency Meeting

DEIS

Preferred Alternative and Mitigation Interagency Meeting

FEIS/ROD Final Design

Page 20: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Option 2 – Planning in Context Option 2 – Planning in Context of EA/Corridor Studyof EA/Corridor Study

Early Coordination Letter

P&N Interagency Meeting

Preliminary Alternatives Analysis and Screening Interagency Meeting

EA/Corridor Study

NOI DEIS Preferred Alternative

and Mitigation Interagency Meeting

FEIS/ROD Final Design

Page 21: I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.

Contacts Contacts

Janice Osadczuk

INDOT

[email protected]

317-232-5468

Virginia LaszewskiUSEPA - Region [email protected]

Larry [email protected]