Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM...

14
HYPERLOOP TUBE BREACH CONTINGENCY (HTBC) SYSTEM PROJECT REPORT Version 1.1 10/27/2015 ENG 2001 E Prof. Regina Lee Project Manager: Simin Lin Budget Lead: Cameron Boyce Technical Lead #1: Mohammad Afaneh Technical Lead #2: Tai Dinh

Transcript of Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM...

Page 1: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY (HTBC)

SYSTEM PROJECT REPORT

Version 1.1

10/27/2015

ENG 2001 E

Prof. Regina Lee

Project Manager: Simin Lin

Budget Lead: Cameron Boyce

Technical Lead #1: Mohammad Afaneh

Technical Lead #2: Tai Dinh

Page 2: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

2

Contents

1.0 Overview .......................................................................................................................................................... 3

1.1 Project Summary ......................................................................................................................................... 3

1.2 Purpose, Objectives, and Scope .................................................................................................................. 3

1.3 Assumptions and Constraints ...................................................................................................................... 4

1.4 Project Deliverables ..................................................................................................................................... 5

1.5 Schedule ...................................................................................................................................................... 5

1.6 Evolution of the Plan ................................................................................................................................... 5

2. References ......................................................................................................................................................... 6

3. Definitions.......................................................................................................................................................... 6

4. Project Work Plan .............................................................................................................................................. 6

4.1 Measure of Success and Future Plans ......................................................................................................... 6

4.2 Roles and Responsibilities ........................................................................................................................... 7

4.3 Project Charter ............................................................................................................................................ 8

4.4 Risk Management Plan ................................................................................................................................ 9

4.5 Communications & Reporting Plan ........................................................................................................... 10

4.6 Work Breakdown Structure ....................................................................................................................... 11

4.7 AON Diagram & Gantt Chart ..................................................................................................................... 12

4.8 Master Budget ........................................................................................................................................... 13

4.9 Task Responsibility .................................................................................................................................... 13

Page 3: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

3

1.0 Overview

In 2013, entrepreneur Elon Musk proposed a Hyperloop transportation system to replace the high speed rail

project proposed in the state of California. The Hyperloop system is a transportation system in which a pod

(‘capsule’ used interchangeably) travels in a low pressure environment within a steel tube near the speed of

sound.

This is a proposal for the tube breach contingency response system for the Hyperloop transportation system. We define a breach in the Hyperloop system as a physical rupture of the tube resulting in an immediate

increase in pressure. The causes of such a breach may include the following:

Natural disaster (earthquake, hurricane, etc.)

External stimuli

Internal stimuli (i.e., electrical fire)

Pod-pod/pod-tube collision

The HTBC System must implement a response mechanism for pods greater than 37 km away from the breach

zone (defined as area of affected pressure loss) at time of breach in accordance with the requirements of

SpaceX Corporation.

1.1 Project Summary

This section of the HTBC Project presents an overview of project’s purpose, scope, and objectives. It also outlines our assumptions, constraints, project deliverables, and budget summary.

1.2 Purpose, Objectives, and Scope

The purpose of this proposal is to outline the processes that will be implemented throughout the evolution of

the project to ensure that its requirements are satisfied in alignment with those stipulated by design entities,

SpaceX Corporation and Tesla Motors. The HTBC project will also detail the activities, resources, schedules, and management strategies needed for maintaining the safety of passengers and any existing infrastructure

within the Hyperloop transportation system during a tube breach scenario.

Our principal design objectives are outlined below:

Ensure safety of all on-board passengers

Minimize or eliminate damage to Hyperloop components (pods/tube)

Maintain uninterrupted operation of unaffected pods

Minimize cost of system implementation

Page 4: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

4

Table 1: Matrix of upper level objectives.

Safety Damage Operation Cost Score

Ensure safety of all on-board

passengers - 1 1 1 3

Minimize or eliminate damage to

Hyperloop components (pods/tube) 0 - 1 1 2

Maintain uninterrupted operation of

unaffected pods 0 0 - 0 0

Minimize cost of system

implementation 0 0 1 - 1

A “1” denotes that the objective in the row is perceived to be of greater importance that the objective in the

column. A “0” represents an objective in the row that is of lesser importance than the objective in the column.

The scope of the HTBC system is exclusively limited to tube breach scenarios which do not involve the following:

Pod malfunction (i.e., loss of power etc.)

Vehicles within 37 km of breach zone (defined as area of affected pressure loss) at time of breach

1.3 Assumptions and Constraints

These quantitative limitations serve to guide our design process toward the most suitable solution for our

target user.

Table 2: Quantitative Design Constraints

Objective Weight Measurement or Estimation Constraint

Ensure safety of all onboard

passengers, bring capsules to a

safe stop

10% Stopping distance calculated as the distance

separating capsules in km, D

D < 37 km

Maintain uninterrupted

operation of unaffected pods

20% Air pressure environment in tube to ensure pod

lift is sustained measured by air pressure

sensors in kPa, P

P < 5.6 kPa

Ensure safety of all onboard

passengers

35% G-force acting on passengers estimated by rate

of deceleration, G

G < 5g

Page 5: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

5

Minimize or eliminate

damage to Hyperloop

components (pods/tube)

5% Measured distance between Hyperloop capsule

and enclosing tube to deploy braking

mechanism, X

X < 0.70 m

Minimize or eliminate

damage to Hyperloop

components (pods/tube)

5% Weight of pod braking mechanism, W W < 600 kg

Minimize cost of system

implementation

20% Estimated budget comprised from the sum of

component parts for entire fleet of Hyperloop

pods, B

B < $5.3 million

Minimize or eliminate

damage to Hyperloop

components (pods/tube)

5% Speed of pod at breaking mechanism

deployment, S

S < 160km/h

1.4 Project Deliverables

The HTBC team will produce a finalized concept design of the Hyperloop tube breach contingency system that

satisfies the design and budget specifications of the client, SpaceX Corporation. The design report will be

delivered to the client no later than October 27, 2015 and a final report/presentation will be given to ENG2001 audience on October 15, 2015.

1.5 Schedule

Table 3: HTBC project milestones and due dates:

Project Milestone Due date

Project start September 10, 2015

Project proposal September 22, 2015

Phase 1 completion September 29, 2015

Phase 2 completion October 06, 2015

Phase 3 completion October 13, 2015

Phase 4 completion and final presentation October 15, 2015

Project Final report October 27,2015

1.6 Evolution of the Plan

Any modifications to the HTBC project plan will be under version control. The updated document will be made available to all project members and interested stakeholders. The most recently modified version of the document will be made available on the HTBC project web page.

Page 6: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

6

2. References

Musk, Elon. “Hyperloop Preliminary Design Study.” SpaceX Corporation, 12 Aug. 2013. 10 Sep. 2015.

3. Definitions HTBC - Hyperloop Tube Breach Contingency System

4. Project Work Plan

4.1 Measure of Success and Future Plans

The HTBC project is considered complete and successful when final modifications to the concept design of

the HTBC system have met all the design specifications, objectives, and constraints stipulated by SpaceX

Corporation. Passengers’ safety are to be ensured; damage to the Hyperloop system is to be minimized.

Additionally, the team will be successful when submission of the final report takes place within the target

period: on or prior to the final deadline of October 27, 2015.

As stated in the overview, the HTBC system is designed specifically for tube breach incidents caused by

natural disasters, external and internal stimuli, and pod/tube collision. However, there are other scenarios

where passengers’ safety could be comprised while onboard a Hyperloop capsule. In the future, Team

Hyperloop plans to develop a Loss of Power Contingency system for Hyperloop in the same manner it has

developed the HTBC. The new system will feature secondary power-generation devices and emergency cabin

pressurization system to ensure the passengers’ safety when the pod stops unintendedly.

Page 7: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

7

4.2 Roles and Responsibilities

Table 4: Team member roles and responsibilities

Roles List of Responsibilities

Project Manager Help the team divide the tasks and resolve issues.

Liaison between clients and team members.

Allocate available resources to maximize group efficiency.

Ensure deliverables are completed by project deadline.

Motivate the team members to perform their tasks.

Budget Lead

Develop breakdown of component costs.

Appropriate budget for each component/subsystem

Communicate with Technical Leads to ensure subsystem design specifications are met within financial resources

Communicate with Project Manager to ensure the team is meeting

the budget guidelines.

Technical Lead #1 (Design)

Develop component designs to satisfy objectives/constraints of

project.

Plan and design subsystems of HTBC

Prioritize relative importance of components and communicate information with Budget Lead.

Communicate with Project Manager to ensure they are meeting

project guidelines.

Technical Lead #2

(Testing & Implementation)

Perform calculations on components to satisfy the objectives / constraints of project.

Communicate with Technical Lead#1 by providing numerical details required for implementation.

Perform simulation and software testing.

Communicate with Project Manager to ensure they are meeting

project guidelines.

Page 8: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

8

4.3 Project Charter

Goals

Ensure safety of all on-board passengers Minimize or eliminate damage to Hyperloop components (Pod/Tube)

Maintain uninterrupted operation of unaffected pods

Scope Management Plan The scope of our project includes:

Outline the processes that will be implemented throughout the evolution of the project to ensure that its requirements are satisfied in alignment with those stipulated by design entity, SpaceX Corporation.

The HTBC project will also detail the activities, resources, schedules, and management strategies needed for maintaining the safety of passengers and any existing infrastructure within the Hyperloop transportation system during a tube breach scenario.

The scope of the HTBC system is exclusively limited to tube breach scenarios which do not involve the following:

Pod malfunction (i.e., loss of power etc.)

Vehicles within 37 km of breach zone (defined as area of affected pressure loss) at time of breach.

Key Stakeholders

Client SpaceX Corporation

Project manager Simin Lin

Project team members Cameron Boyce , Mohammad Afaneh, Tai Dinh

Project Milestones Start date of the project: September 10, 2015

Completion of technical design: September 27, 2015

Completion of tube breach response plan: October 6, 2015

Completion of system testing: October 26, 2015

End date of the project: October 27, 2015

Project Budget Estimated Budget of our project is $ 5.3 million.

Constraints, Assumptions, Risks and Dependencies

Constraints Stopping distance, Air pressure, G-force on passengers, Weight of the pod

Assumptions The project is based on the following assumption: The Hyperloop is working in the ideal condition.

Risks and Dependencies Pressure sensor malfunction, Natural disasters, Staff mismanagement

Page 9: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

9

Approval Signatures

SpaceX corporation Simin Lin

Project Client Project Manager

4.4 Risk Management Plan

Team Hyperloop has identified five principal aspects of risk associated with this project: project staffing,

environment, definition, management and the nature of the project.

As a conceptual design for Hyperloop, the HTBC system design is not defined by the client, SpaceX

Corporation. What is defined are the specifications and associated constraints. Additionally, such a system has

yet to be designed and implemented elsewhere. Thus, Team Hyperloop, faces the same challenge associated

with any inaugural project such as a lack of research data and prior experience of team members. The

resources and support associated with the project are therefore limited, making it more risky than working on

a subsystem of a well-established system. Furthermore, as Hyperloop will be built in California, USA, Team Hyperloop must also comply with international laws regarding transportation safety.

Project staffing also poses significant risk. As it is only Mr. Lin’s second project as manager, he is

inexperienced at managing a team. While the team members have worked on a prior design projects in ENG

1102, they did not address aspects of formal project management.

Project environment, definition, and management constitute the remaining 40% of project risk. Team Hyperloop recognizes that this project lacks the support of a feasibility study, thus the basis of the project may be unreliable.

Figure 1: Project Risk Management category percentage breakdown.

Page 10: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

10

Table 4: Risk Assessment Form

Risk event Likelihood Impact Detection Difficulty When

Breach Detection failure 4 5 3 airflow into the tube

Server failure 3 4 3 Software freeze

Decelerator 4 4 2 Pod in motion

Levitation failure 5 3 3 Pod in motion

Table 5: Risk Response Matrix

Risk Event Response Contingency Plan Trigger Who is responsible

Breach Detection

failure

Reduce Install backup

sensors

Not solved within

24h hours

Tai Dinh

Server failure Reduce Reinstall OS Still frozen after

one hour

Server controls

Decelerator Increase Install backup

decelerator

Not solved within

24h hours

Mohammad

Levitation failure Increase Install backup down

force airflow under

the pod

Not solved within

24h hours

Tai Dinh

4.5 Communications & Reporting Plan

The Communications & Reporting plan discloses the interactions between team members, project manager,

the client, and project stakeholders. Internally, the HTBC team follows a proposed meeting schedule so that

the progress of current tasks can be evaluated to ensure the team is on pace to produce project deliverables by milestone deadlines. Any modifications to the HTBC project plan are placed under version control. The

updated document will be made available to all project members and interested stakeholders. The most

recently modified version of the document will be made available on the HTBC project web page.

Page 11: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

11

Table 4: Communications & Reporting Plan

When What Who Comments

September 10, 2015 Defining project and determining objectives Simin Completed

September 11, 2015 Assigning Tasks Simin Completed

September 14, 2015 Obtaining Quantitative Data Mohammad,Tai Completed

September 27, 2015 Designing Decelerator Cameron, Mohammad, Tai Completed

September 27, 2015 Designing Levitation System Cameron, Mohammad, Tai Completed

September 27, 2015 Designing Braking Mechanism Cameron, Mohammad, Tai Completed

October 6, 2015 Breach Detection Response Cameron, Mohammad, Tai Completed

October 14, 2015 Server Acquisition & Implementation Simin, Cameron, Mohammad, Tai Completed

October 26, 2015 System testing Cameron, Simin, Mohammad, Tai Completed

October 27, 2015 Project delivery and team reassignment Simin, Cameron Completed

4.6 Work Breakdown Structure

The project Work Breakdown Structure (WBS) describes the actual work to be done. The hierarchical structure

provides a framework for managing the project, and facilitates evaluation of the time, cost, resources and

technical performance at all levels. Our project is broken down into main deliverables: the final design

concept of the HTBC System and the final design report and presentation. Project subdeliverables include the

Pod, Tube, and Control subsystems of the Hyperloop transportation system. The lowest level subdeliverables

are the pressure sensor array, pressure control, sensor control of the Beach Detection Response subsystem. Work packages are identified at the bottom of the diagram.

Figure 2: WBS for HTBC Project

Page 12: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

12

4.7 AON Diagram & Gantt Chart

From the WBS, project task dependencies were identified allowing for the construction of the AON diagram.

The critical path highlighted in figure 3 help and identifies project tasks with a slack of zero days. The final

output of the AON diagram is the Gantt chart (shown in figure 4).

Figure 3: AON Diagram and critical path identified by shaded path.

Figure 4: HTBC Project Gantt Chart

Page 13: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

13

4.8 Master Budget

The budget for the HTBC Project was allocated to be $5.3 million USD as stipulated by the client, SpaceX

Corporation. The subdeliverable component costs were summed at each level of the budget diagram to ensure that proposed HTBC design was feasible and within proposed constraints.

Figure 3: Budget Diagram outlining component costs of all deliverables.

4.9 Task Responsibility

The task responsibility matrix is a visual representation of team members’ project task responsibilities. Tasks

were distributed equitably to ensure that the team functioned at a high-level of efficiency throughout all stages of the project.

Page 14: Hyperloop tube breach contingency system (HTBC) pRoject ...HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT 10/27/2015 3 1.0 Overview In 2013, entrepreneur Elon Musk

HYPERLOOP TUBE BREACH CONTINGENCY SYSTEM (HTBC) PROJECT REPORT

10/27/2015

14

Table 5: Team member Responsibility Matrix

Resource Responsibility R - Primary Responsibility C - Contributes A - Advises

Sim

in L

in

Cam

ero

n B

oyc

e

Mo

ham

mad

Afa

neh

Tai

Din

h

Define Objectives R C C C

Assigning Tasks R A A A

Obtain Quantitative Data A C R

Decelerator

Decelerator Design A R A

Decelerator Testing A A R

Decelerator Budget R

Levitation

Levitation Design C R A

Levitation Testing A C A R

Levitation Budget R

Braking Mechanism

Braking Mechanism Design A R

Braking Mechanism Testing C A A R

Braking Mechanism Budget R A

Breach Detection Response

Pressure Sensor/Control Design C R C

Pressure Sensor/Control Testing A A R

Pressure Sensor/Control Budget C R

Server Acquisition & Implementation

Acquisition C R

Server Testing A C C R

Server Setup R C A

Testing A C R

Project Delivery & Team Re-assignment

R C