HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...
Transcript of HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...
![Page 1: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/1.jpg)
HYDROPOWER DEVELOPMENT FOR LESOTHO
LHWP PHASE II FEASIBILITY STUDIES
Mark MatchettLHDA
3rd April 2019
LESOTHO HIGHLANDS WATER PROJECT
![Page 2: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/2.jpg)
• RSA – water scarcity - growing water demand - industry and household needs
• Lesotho – abundant highland waters - economic development through external revenue & reduce energy imports
COINCIDENCE OF NEEDS
![Page 3: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/3.jpg)
LHWP – PHASE I
![Page 4: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/4.jpg)
LESOTHO ENERGY POLICY • Develop sustainable electricity generation resources• Develop robust energy framework
• regulation of IPPs• renewable energy resources• competitive market operations
• Improve energy security (reduce imports)
![Page 5: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/5.jpg)
LESOTHO GENERATION LANDSCAPE• National maximum demand = 150 MW (2018)• Installed generation capacity = 72 MW ‘Muela Power Station (LHDA)• Shortfall imports from South Africa
and Mozambique• Potential sustainable options:
• Solar 20 MW – (Private investor)• Wind (Department of Energy)• Hydropower
(LHWP II further feasibility studies)
![Page 6: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/6.jpg)
LHWP II Further Feasibility Studies
• Kobong Pumped Storage:• 1200 MW technically feasible• Bulk power for export – 1000 MW• Balance for Lesotho consumption• Project deferred - unfavourable
market study results
• Conventional Hydropower• LHWP installations – utilisation of
Environmental Flow Releases• Greenfields• Energy independence• Screening of potential sites
![Page 7: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/7.jpg)
SCREENING STUDY• 53 sites - Site selection criteria:
• Engineering • Hydrology• Access• Installed capacity• Site geology• Power transmission requirements
• Environmental and Social aspects• Project Economy• Type of generation i.e. peaking, base-load, mid-merit etc.• Energy generation capability
![Page 8: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/8.jpg)
SCREENING STUDY• 3 sites identified• Geotechnical investigations• Studies at the final phase
BANKABLE FEASIBILITY
‘MUELA HPP
![Page 9: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/9.jpg)
OXBOW SITE• 90.5 MW• 92m CFRD• Pelton turbines• 4 hours/day peaking• 187 GWh/Annum
![Page 10: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/10.jpg)
SENQU B SITE• 82 MW• 107m CFRD• Vertical Francis machines• 7 hours/day peaking• 129 GWh/Annum
![Page 11: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/11.jpg)
SENQU D SITE• 30 MW• 72m RCC dam• Vertical Francis
machines• 16 hours/day
baseload• 186 GWh/Annum
![Page 12: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/12.jpg)
• ESIA project briefs completed• Transmission network• Geotechnical investigations • Engineering studies advanced• Legal and regulatory
framework in progress• Project financing
requirements/development options analysis ongoing
• Construction completion 2025
PROGRESS TO DATE
![Page 13: HYDROPOWER DEVELOPMENT FOR LESOTHO LHWP PHASE II ...](https://reader034.fdocuments.in/reader034/viewer/2022050500/627172adecf9a60f7f31ba34/html5/thumbnails/13.jpg)