Hydro-Québec Utility update - PPDIUC Utility Update_Anne... · Hydro-Québec Utility update PPDIUC...

20
Hydro-Québec Utility update PPDIUC May 2017 Cordova, Alaska Anne Malenfant, ing 30 april 2017

Transcript of Hydro-Québec Utility update - PPDIUC Utility Update_Anne... · Hydro-Québec Utility update PPDIUC...

Hydro-Québec Utility updatePPDIUC May 2017Cordova, Alaska

Anne Malenfant, ing30 april 2017

Presentation plan

•Organization (Non integrated

network)

•Remote communities

•Off-grid systems

•Strategic plan 2016-2020

2

Organization (Non integrated network)

3

Organization (Non integrated network)

•Hydro-Quebec

– PDG : Éric Martel (july 2015)

•Hydro-Quebec Distribution

– President : David Murray (sept. 2016)

•VP Réseau Distribution (main distribution network)

•Direction Réseau distribution Matapédia (main network) et réseaux non reliés (non integrated network)

4

Organization (Non integrated network)

5

Section RNR (non integrated network) - Plan and Technical expertise

production and transport

- Technical support

- Plan and project

- Energy efficiency

- Installations BOR et génératrices;

- Exploitation, distribution & maintenance

- Installations IDLM

- Exploitation & maintenance

- Schefferville

Remote communities

6

Remote communities

• Population : 35 000

• Customers: 18 500

• Various autochthone communities

– Atikamekw, Cree, Innu, Inuit, Naskapi

• 24 off-grid systems

• 5 geographic regions

– Nunavik

– Schefferville

– Basse Côte-Nord

– Haute-Mauricie

– Îles-de-la-Madeleine7

Off-grid systems

8

Generation

•Installations Boréal et génératrices:– Boréal:

•Over 10 100 clients;•Maintenance and exploitation;•20 diesel power houses 56,2 MW

» Akulivik : new diesel powerhouse of 2 MW (3 units, commissioned in 2015)

– 2 Back-up plants 11,6 MW» St-Augustin Bach-up plant

dismantled in 2016•1 Hydro plant 21,6 MW

9

Generation

•Installations Boréal et génératrices:– Génératrices (BDI) :

•Maintenance and exploitation;•50 mobile units (12 to 2000 kW)

10

Generation

•IDLM Installations– Over 7 600 clients– 2 diesel power houses – 68,4 MW

•1 Heavy fuel – 67,2 MW

•Schefferville– Over 600 clients – Powered by Hydro plant 17 MW Menihek (Labrador, with NALCOR) – 1 back-up diesel powerhouse of 5,1 MW (4 units, commissioning 2017) in

Schefferville

11

Transport and Distribution

• 7 transport stations (BCN and IDLM)

– 69 to 25kV

• Distribution mostly at 4 kV;

– 25 kV in Kuujjuaq

– 600V in Île-d’Entrée and Tasiujaq

• Native Operators/linemen in Nunavik

• Transport and distribution maintenance in Basse Côte-Nord and IDLM done by other Directions

12

Environment

•August 2015 : spill at Ivujivik– Leak of 10 000 liters of diesel fuel

– Ground and water stream contaminated

– Total of 605 m³ of contaminated soil treated

– Site restauration : 2015-2016

•Sept. 2014 : spill at IDLM– Leak of 100 000 liters of diesel fuel

– Ground and water contaminated

– Site restauration : 2015-2017

13

Financial

• Cost : 230 M$ (51,6 ¢/kWh)

• Revenue : 40 M$ (9,0 ¢/kWh)

• Deficit : 190 M$ (42,6 ¢/kWh)

- Social pact : Same rates everywhere for HQ customers

- Dissuasive rates (electric heating, north of 53rd)

- Commercial programs

- Energy efficiency programs

• GHG emissions

– The Quebec cap-and-trade system

– Emission rights = 2M$ in 2016 (IDLM)

– Emission unit price scheduled to increase : 5% plus inflation every year

14

Strategic plan 2016-2020

15

Strategic plan 2016-2020

•Progressively convert off-grid systems to cleaner, lessexpensive energy sources

•Launch requests for proposals (RFPs) for all systems by 2020

•Partnerships between project proponents ans communities

•Competitive bidding

•Consideration : particularities of each system and needs of each community to choose the most appropriate technologicalsolution

16

Conversion - ongoing

• IDLM

– Phase 1•RFP – october 2015

•6MW wind power

•Commissionning – 2020

– Phase 2•RFP – 2018

•All energy source

•Commissioning – 2023

•In competition with connection to main grid

• La Romaine– Connecting to main grid

– Commissioning – 2019

• Obedjiwan– RFP – november 2016

– Energy generated by forest biomass

– Commissioning 2020

• Tasiujaq– EOI – november 2016

– RFP – third quarter of 2017

– New power plant (renewable encouraged)

– Commissioning - 202117

Conversion - planned

•Nunavik – phase 1 (Hudson Bay)– RFP – Third quarter of

2017

– All energy sources

– Aupaluk

– Kangiqsualujjuaq

– Kangiqsujuaq

– Kangirsuk

– Kuujjuaq

– Quaqtaq

•Nunavik – phase 2 (Ungava Bay)– RFP – Third quarter of

2018

– All energy sources

– Akulivik

– Inukjuaq

– Ivujivik

– Kuujjuarapik

– Puvirnituq

– Salluit

– Umiujaq18

•All other systems– RFP – second quarter of

2019

– All energy sources

– Clova

– Île-d’Entrée

– Port Menier

Energy efficiency and conservation program

• Energy efficient measures:– Compact fluorescent and LED lighting

– Roof insulation

– Water and energy conservation kits

– Block-heater timers

• Energy efficiency and conservation awareness– Load reduction

– Interruptible electricity option

– Promotion of reduced-load water heaters (3 elements)

– End-use efficiency (fuel – based space and water heating)

– Peak winter – load awareness campaign

– Private generators19

Thank you for your attention!Questions?

PPDIUC May 2017Cordova, Alaska