ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992 METALLURGY AND MATERIALS ENGINEERING 1 1. Explain the concept welding design and fabrication in manufacturing steel structure. What should you do when you act as: a) Welding Engineer 1) Develops welding techniques, procedures, and application of welding equipment to problems involving fabrication of metals, utilizing knowledge of production specifications, properties and characteristics of metals and metal alloys, and engineering principles: Conducts research and development investigations to develop and test new fabrication processes and procedures, improve existing or develop new welding equipment, develop new or modify current welding methods, techniques, and procedures, discover new patterns of welding phenomena, or to correlate and substantiate hypotheses. 2) Prepares technical reports as result of research and development and preventive maintenance investigations. 3) Establishes welding procedures to guide production and welding personnel relating to specification restrictions, material processes, pre- and post-heating requirements which involve use of complex alloys, unusual fabrication methods, welding of critical joints, and complex postheating requirements. 4) Evaluates new developments in welding field for possible application to current welding problems or production processes. 5) Directs and coordinates technical personnel in performing inspections to ensure workers' compliance with established welding procedures, restrictions, and standards; in testing welds for conformance with national code requirements; or testing welding personnel for certification. 6) Contacts personnel of other agencies, engineering personnel, or clients to exchange ideas, information, or offer technical advice concerning welding matters.

description

hw

Transcript of HW-07_1206291992

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 1

    1. Explain the concept welding design and fabrication in manufacturing steel structure.

    What should you do when you act as:

    a) Welding Engineer

    1) Develops welding techniques, procedures, and application of welding equipment

    to problems involving fabrication of metals, utilizing knowledge of production

    specifications, properties and characteristics of metals and metal alloys, and

    engineering principles: Conducts research and development investigations to

    develop and test new fabrication processes and procedures, improve existing or

    develop new welding equipment, develop new or modify current welding methods,

    techniques, and procedures, discover new patterns of welding phenomena, or to

    correlate and substantiate hypotheses.

    2) Prepares technical reports as result of research and development and preventive

    maintenance investigations.

    3) Establishes welding procedures to guide production and welding personnel

    relating to specification restrictions, material processes, pre- and post-heating

    requirements which involve use of complex alloys, unusual fabrication methods,

    welding of critical joints, and complex postheating requirements.

    4) Evaluates new developments in welding field for possible application to current

    welding problems or production processes.

    5) Directs and coordinates technical personnel in performing inspections to ensure

    workers' compliance with established welding procedures, restrictions, and

    standards; in testing welds for conformance with national code requirements; or

    testing welding personnel for certification.

    6) Contacts personnel of other agencies, engineering personnel, or clients to

    exchange ideas, information, or offer technical advice concerning welding matters.

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 2

    7) May perform experimental welding to evaluate new equipment, techniques, and

    materials.

    b) Welding Supervisor

    1) Supervises and coordinates activities of workers engaged in welding and cutting

    of products and structures, such as auto, aircraft, and ship components, pipes,

    boilers, and mobile homes, applying knowledge of welding and cutting techniques,

    materials, and equipment, and fabrication requirements: Analyzes work orders and

    blueprints to determine need for supplies and sequence of operations required.

    2) Requisitions supplies, such as weld rods, gas, flux, and fixtures.

    3) Inspects work or confers with WELD INSPECTOR I and WELD INSPECTOR

    II to maintain specified standards and quality.

    4) Trains workers in operation of equipment.

    5) May set up machines or make trial welds to make test runs and experimental

    products.

    6) May supervise brazing and soldering operations.

    7) May supervise fitting and assembly of structural frames.

    8) May supervise workers engaged in making tubing from flat steel strips by

    electric-weld process and be designated Welding Supervisor, Electric-Weld Pipe

    Mill.

    9) Important variations include location of workers supervised, such as in-plant,

    job-shop, construction site, or shipyard.

    10) Performs other duties as described under SUPERVISOR Master Title.

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 3

    c) Welding inspector

    (1) Codes, standards and specifications: Interpretation of the intent and ensuring

    the requirements of codes, standards and specifications are met.

    (2) Welding procedures: Ensuring that a procedure is available, has been approved

    and is being employed in production.

    (3) Witnessing of welder and procedure approval tests: Witnessing the

    preparation of test plates and destructive tests and verifying compliance with

    appropriate standards and specifications.

    (4) Welder approvals: Verifying that adequate and valid welder approvals are

    available, and that only approved welders are used in production.

    (5) Parent material: Verifying parent material against documentation and

    markings.

    (6) Welding consumables identity: Verification of correctness of welding

    consumables (electrodes, filler wires, consumable inserts, gases, fluxes etc.)

    (7) Pre-weld inspection: Verification that dimensions, fit-up and weld

    preparations are in accordance with specifications.

    (8) Preheating: Verification that any required preheat is in accordance with the

    specified procedure.

    (9) In-process welding inspection and surveillance: Surveillance during welding

    to verify compliance with specified procedures including any preheat, interpass

    temperature control and post heat requirements.

    (10) Inspection and Test Plans: Assistance and agreement with the preparation of

    Inspection and Test Plans (ITPs)

    (11) Post-weld heat treatment: Verification, when required that post weld heat

    treatment has been conducted in accordance with specification requirements.

    (12) Post-weld visual inspection: Visual inspection and dimensional check of

    completed weldment against specification requirements and drawings.

    (13) NDT reports: The study and cognisance of NDT results on any welding work

    for which the welding inspector is responsible. Where the duties of the welding

    inspector include using NDT methods such as liquid penetrant, magnetic particle,

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 4

    radiography or ultrasonic inspection then it is suggested that he/she obtains

    certification in accordance with the related approval schemes.

    (14) Reports: Evaluation of and preparation of inspection reports for the employer

    or the client.

    (15) Records: Maintenance of records of inspections carried out

    2. Sketch drawing welded construction with reference to welding symbol below.

    (a)

    (b)

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 5

    3. Calculate the minimum fillet weld size on a welded construction as shown in the

    picture below, the known shear stress (T) which is parallel to the load of 20 MPa or

    N/mm2, while the load (P) which is 20000 N (2.5 Tons) with the length of each side of

    the weld joint (W) is 100 mm. Use the formula: T = P/(2.w.a)

    =

    2. w. a

    20 =20000

    2.100. a

    200 =20000

    20

    =500

    200

    =500

    200

    = 2.5

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 6

    4. Welding symbols

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 7

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 8

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 9

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 10

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 11

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 12

  • ASSIGNMENT-7 ENMT610029 WELDING ANDARADHI NARARYA/1206291992

    METALLURGY AND MATERIALS ENGINEERING 13