HVAC Technical and Qualification Issues Alain Kupferman Manufacture of sterile medicines –...
-
Upload
jonas-moody -
Category
Documents
-
view
238 -
download
8
Transcript of HVAC Technical and Qualification Issues Alain Kupferman Manufacture of sterile medicines –...
HVAC Technical and Qualification Issues
Alain Kupferman
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
2 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
• The primary objective of manufacturing in an ideal GMP environment is that this should lead to a high quality product being produced.
• Manufacturing in an ideal environment not only leads to better quality products but should also result in :
• Improved production rates.
• Operator comfort, satisfaction and safety.
GMP Manufacturing EnvironmentsGMP Manufacturing Environments
3 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Factors Contributing To Quality Products
Raw Materials
Personnel
Procedures
Validated processes
Equipment
Premises
Environment
Packing Materials
4 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Defining The EnvironmentDefining The Environment
• What is the optimal manufacturing environment ?
• How does the manufacturing environment affect quality, contamination and cross-contamination ?
• How do we arrive at an optimal environment ?
Cleanroom concept
5 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Design ConsiderationsDesign Considerations
6 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
SystemsSystems
To support pharmaceutical production activities, state-of-the-art factories include systems, which have to be conceived according to GEP and cGMP.
Some of these systems have a direct impact on product quality, some an indirect impact.
Systems with direct impact must be identified and documented in a more exhaustive way, and evaluated in relation to critical GMP parameters.
QA, Production and Engineering must agree beforehand on the scope of qualification activities, ideally right at project start.
7 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Good Engineering Practice Good Engineering Practice
Good Engineering Practice (GEP) is defined as those established engineering methods and standards that are applied throughout the lifecycle to deliver appropriate and cost effective solutions.
Generally the term is used to describe an engineering management system that is being applied in the engineering profession for delivering, operating and maintaining capital assets. While GEP is expected in a pharmaceutical enterprise, it is not mandated by GMP regulations.
Good HVAC installation: GEP + cGMP
8 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
A HVAC system conceived, installed and commissioned according to GEP should be:
– Fit for the intended purpose, reliable and economic to run.– Conceived and installed taking into account GMP norms, as
well as norms for safety, ecology, ergonomy, operation, maintenance and local industry rules and country regulations.
– Conceived, constructed, installed and commissioned by professionnal and competent people.
– Supported by appropriate documentation (conceptual documents, diagrams, as-built drawings, test reports, manuals, etc.).
Good Engineering Practice Good Engineering Practice
9 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Some DefinitionsSome Definitions
Direct impact system– System which could have a direct impact on product quality– These systems are generally to be documented more
in-depth (qualification).– Normally contain critical components.– These systems normally depend on other systems, with indirect
impact.– Interface important !
10 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Some DefinitionsSome Definitions
Indirect impact system– A system which does not have a direct impact on product
quality !– Can affect the performance of direct impact systems and thus
indirectly affects product quality.– Needs less detailed documentation (no qualification).
Must be constructed, tested and commissioned according to GEP.
– By definition, do not contain critical components.
11 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
More DefinitionsMore Definitions
Critical GMP parameter– A GMP criteria, influencing product quality (differential
pressure, airflow pattern, etc.).
Critical component– A component which maintains a GMP critical within pre-
determined limits (filter HEPA, dehumidifier, etc.).
Critical instrument– Instrument measuring a critical GMP parameter.
12 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Examples Of SystemsExamples Of Systems
Purified water WFIHVAC to clean roomsCompressed air and gasses for productionCIP/SIPEnvironmental monitoringEtc.
Heating systemsPotable waterFire systemsEffluent treatmentGeneral HVACLightingCooling waterEtc.
GMP Direct Impact No GMP Direct Impact
13 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
ExamplesExamples
AHU
Aseptic area
HEPA
Chilled water system(indirect)
AHU system(direct)
Critical component(direct)
14 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Extent Of QualificationExtent Of Qualification
Japan GMPUS GMP EU GMP
ICH Q9
ISPE Commissioning and QualificationBaseline Guide
Equipment shall be suitable, correct material,
calibrated… ,Basis for qualification
Quality risk management can be used to determinethe extent of qualification
15 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Qualification SuccessQualification Success
GEP + GMP = Qualification
GEP + GMP = Qualification
GEP + GMP = Qualification
16 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design RequirementsHVAC Design Requirements
The complexity resulting from the different requirements for air quality in the various cleanliness zones, makes it recommendable to define up-front the following criteria:
– Critical room parameters which affect product or materials (i.e. humidity)
– Process operations presenting a potential for contamination.
– Process or operations not affected by room conditions (e.g. closed systems).
– Potential sources of room contamination (process equipment / operation, HVAC components, HVAC operation type, personnel, failure of HVAC functions...).
– Equipment failure modes (fans, room / zone fail safe modes, interlocks, user action in the event of failure).
17 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design RequirementsHVAC Design Requirements
HVAC100 % fresh air versus air re-circulation
Local extraction systemsTurbulent or uni-directional flowsPosition end-filtersLow-wall returns
Targeted hygiene class
18 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design Requirements
19 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Definition Of ConditionsDefinition Of Conditions
air
As built
air air
At rest In operation
20 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC And GMPHVAC And GMP
In pharmaceutical primary as well as in secondary manufacturing, HVAC systems are a major factor for the observance of cleanliness and product purity, and thus for GMP compliance.
Qualification activities of HVAC systems with their measurement and control and computerized units are cost intensive and necessitate a great deal of time.
The key issues to keep HVAC qualification in quality, time, and costs are
– the understanding of interfaces beween product purity / characteristics, process, cleanliness zones, HVAC functions and clean rooms requirements.
– the structured identification of critical functions and operations, the objective evaluation, and the definition of appropriate measures (design, qualification, calibration, and validation activities) in a documented way.
21 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design Requirements And Process
22 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design Requirements And Process
23 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
To Start With…To Start With…
HVAC: Heating, Ventilation and Air Conditionning
« HVAC System » or « Ventilation System »?– HVAC System: Includes sub-systems (chilled water, brine, steam, etc.).
– Ventilation system: Air treatment components (AHU, ducts, flow controllers, etc.).
BMS: Building Management System– BMS: Building Management System (BMS) is a computer based control system installed in buildings that
controls and monitors the building’s mechanical and electrical equipment such as air handling and cooling plant systems, lighting, power systems, fire systems, and security systems
24 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Key Qualification AspectsKey Qualification Aspects
A HVAC system serving a production area must be considered as direct impact system
Such a system consists of sub-systems
As a consequence, it is necessary to identify sub-systems which also could have a direct impact.
Within these sub-systems, critical components and instruments have to be identified as well.
25 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC QualificationHVAC Qualification
For example, for a typical HVAC system in an aseptic area, critical components would be:
– Terminal HEPA filters.– Unidirectional airflow units.
The monitoring of the critical GMP parameters indicates whether the system operates within the pre-established criteria.
A breakdown in a fan would for instance have as consequence a drop in differential pressures, as well as changes in temperature and humidity.
The monitoring system in itself is thus critical as well.
26 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC QualificationHVAC Qualification
– IQ Tests Installation (Static verifications)• Installation of components
– OQ Tests Installation (Dynamic verifications)• Individual tests components (fans, coils, etc.)• Functional tests sub-systems• Verification control system
These tests confirm that the installation is working as a whole and must be done before the room qualification
27 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Key Qualification AspectsHVAC Key Qualification Aspects
Facility qualification tests– Air changes– Differential pressure cascade – Flow patterns (turbulent and uni-directional)– Room classification (ISO norms)– Temperature and humidity– Integrity tests HEPA filters– Exactness of readings of GMP critical parameters– Uni-directional airspeed– Laminarity at point of use
28 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HVAC Design RequirementsHVAC Design Requirements
In establishing design criteria for critical parameters, consideration should be given to operating ranges which will assist in the definition of the tightness of control range of these parameters.
Continuous ringing ofalarms to be avoided !!
Action limit
Alert limit
Range of measurement and control unit
Process range
Pro
cess
lim
its
Pro
cess
lim
its
Process tolerance
29 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
In addition to the general tests (e.g. power failure and recovery tests, verification offunctions andsequences, verifi-cation of alarmsand interlocks...)specific tests have to beperformed.
Test:
Differential pressure on filters
Turbulent / mixed airflow:
Unidirectional airflow / LAF:
Room differential pressure
Airflow velocity / uniformity
Airflow volume / rate
Parallelism
Air flow patterns
Filter leak test / challenge test
Recovery
Room classification )airborne particle(
Particle fall out
1 1
N/A 2 ,3
2 ,3 Optional
2 2
2 N/A
Optional Optional
2 2
N/A 2
2 2
Optional Optional
Temperature, humidity N/A 2 ,3
1 =: As built )ideally used to perform IQ(; 2:= At rest )ideally used to perform OQ(; 3:= Operational )ideally used to perform PQ(
30 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Physical / Technical OQ And PQ Tests Physical / Technical OQ And PQ Tests
Determination of differential pressure on filters– to detect initial defects of filters,– to verify the pressure differential (for a defined flow) meets the value specified
by the vendor,– to set the correct value of the alarm as indicated by the vendor for triggering a
filter replacement.
Differential pressure between rooms– This measurement consists in measuring with a calibrated manometer the
differential pressure existing between the inside of a clean room and the surrounding areas as defined in the specifications.
– This determination should be made under various operational conditions such as day mode, night mode, opening of doors, etc. to identify also situations when the pressure differential cannot be met and as a consequence the product may be at risk.
31 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
Determination of air flow velocity– This verification is used to determine average airflow velocity and uniformity of
velocity within a clean room, clean zone or unidirectional flow work zone.– This method is not recommended for non-unidirectional airflow cleanliness
zones; in that case the measurement of airflow volumes should be performed instead.
– The airflow velocity is measured at a distance of 15--30 cm from the supply source using an anemometer (WHO), at the working station (EU).
– The uniformity of air flow velocity is defined as being the relative standard deviation of the velocity, expressed as a percentage of the mean as follows: Uniformity = standard deviation / average velocity * 100.
32 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Measurement of air volume and uniformity – air exchange rate– This procedure / verification is used to determine average airflow volume
and uniformity of volume wihin a clean room, clean zone or unidirectional flow work zone.
– The airflow volume is measured from each terminal filter or supply diffuser by using an electronic microanemometer with an appropriate airflow hood in a manner that includes all of the air issuing from each single source.
– The uniformity should not exceed 15 %, except where otherwise specified.– Total air volume will, in turn, be used to determine the air exchange rate
(room air volume per hour) for the clean room, as defined: Air exchange rate = total airflow volume / volume of the room.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
33 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Airflow parallelism test– The purpose of the test is to verify the parallelism of air flow throuout the
work zone of a unidirectional airflow and whether the clean room is capable of limiting the dispersion of internally generated contamination.
– The measurement is made using a isokinetic smoke generator and defining the offset distance between the smoke streamline and the theoretical straight line coming from the smoke outlet and parallel to the specified unidirectional airflow.
– To be valid, such tests must be documented using video techniques.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
34 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Determination of airflow patterns– This verification is above all valuable for demonstrating the interactions of
airflow and equipment during the OQ phase, and for demonstrating the effectiviness of aerodynamic barriers.
– This test is particularly recommended for the initial qualification of cleanliness zones (HVAC or clean rooms) where aerodynamic barriers are employed instead of physical barriers (A/B areas) and where therefore acceptable differential pressures cannot be achieved.
– The test consists of a visualisation of the air flow patterns, using a smoke or other visible aerosol and is designed to show evidence that all air flows are as expected.
– In addition it is also recommended for the initial qualification in the at rest mode of all types of clean room to demonstrate absence of non desirable dead zones, backflows, leaks or turbulances which may contaminate a critical part of a clean zone. To be valid, such tests must be documented using video techniques.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
35 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Filter installation leak test (challenge test)– These verifications are performed to confirm that
HEPA and ULPA filters are properly installed by verifying there is no by-pass leakage in the installation (frame, gasket seal, and filter bank framework) and the filters are free of defects and small leaks in the filter medium and frame seal.
– These tests are required for unidirectional airflows, but have only limited value for non-unidirectional airflow systems.
– Tests are performed by introducing an aerosol challenge upstream of the filters and scanning immediatly downstream of the filters and support frame or sampling in a downstream duct.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
36 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Determination of the recovery time– This test is not recommended for unidirectional airflows.
It is performed to determine whether the clean room or clean zone is capable of returning to its specified cleanliness class within a finite time, after being expoused to a source of airborne particulate challenge in form of smoke or aerosol.
– The result of this test is an important information for correct operation of the system, because it defines also the minimum „hold“ time which should be taken into account after power failure, start (recovery), mode change, use of changing rooms, etc.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
37 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Determination of room classification (airborne particle count mapping)– This test is performed to determine that the completed clean room can meet the
cleanliness class specified.– The test consists in measuring the concentration of particles of a well defined size
in the clean room in order to prove with a defined confidence limit, that the clean room complies with the cleanliness class.
– In case of unidirectional airflows, the sample points should include test points located immediately upstream of the work activity level.
– All sample points must comply with the class limit.– In the case of class A, this test must be repeated to take into account generation
of particles by operator, equipment or process. The main purpose is then to identify worst case locations which should also be taken into account when installing probes for continuous particle monitoring.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
38 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Temperature level and uniformity test– The purpose is to demonstrate the capability of the clean room / HVAC
system to maintain air temperature wihin the specified limits and over a certain period of time.
– The result of this test can also be used to support qualification of the location of fixed installed temperature monitoring devices.
Humidity level and uniformity test– The purpose of this test is to demonstrate the capability of the clean room (HVAC system with (de)humidification units) to maintain air humidity levels within the specified limits and over a certain period of time.– The result of these tests can also be used to support qualification of the location of fixed installed humidity monitoring devices.
Physical / Technical OQ And PQ TestsPhysical / Technical OQ And PQ Tests
39 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
SummarySummary
The key factors for a successful HVAC qualification are
• the understanding of interfaces beween product purity / characteristic, process, cleanliness zones, HVAC functions and clean rooms requirements,
• the knowledge concerning general and HVAC specific tests,• the structured identification of critical functions and operations, the objective
evaluation, and the definition of appropriate measures (design, qualification, calibration, and validation activities) in a documented way.
40 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Classification And MonitoringClassification And Monitoring
EU Guidelines Annex 1 Revision 2008
Clean rooms and clean air devices should be classified in accordance with EN ISO 14644-1. Classification should be clearly differentiated from operational process environmental monitoring
For classification purposes EN/ISO 14644-1 methodology defines both the minimum number of sample locations and the sample size based on the class limit of the largest considered particle size and the method
of evaluation of the data collected .
Clean rooms and clean air devices should be routinely monitored in operation and the monitoring locations based on a formal risk analysis study and the results obtained during the classification of rooms and/or clean air devices.
41 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Monitoring in critical areas ) Room Class B and LF area = class A (
L F
Environmental control: t°C, r.H., pParticles
MeasurementMicrobial Monitoring
Air flowSpeed
(conditions different for EU and WHO )
Reference pointfor pressure
Monitoring
42 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Monitoring in non-critical areas )C, D and other classes(
Environmental control: t°C, r.H., p
Particles Measurement
Microbial Monitoring
Reference pointfor pressure
Monitoring
43 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Balinometers
Air changes measurement
44 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Differential Pressure Indicators
45 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle CountersParticle Counters
Probe Measuring device Computer, printer
Transfer of particles Transfer of data
Manifold system
INTEGRATED SYSTEM
46 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle Counters )1 Ft3/Min(Particle Counters )1 Ft3/Min(
Met One
Climet
PMS
Lighthouse
47 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
AIR MONITORING FOR PARTICLESHARDWARE - LAYOUT
48 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
The particle counter is taken from one sampling point to another, according to a fixed sampling plan (SOP)Only one sampler is neededto monitor sequentially the sampling points.
Mobile Particle Monitoring
49 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
The particle counter is installed in a fixed position and is permanently connected to its sampling probe .
The sampling is continuous, without interrruptions.
Every sampling point needs ist own sampling probe/counter
Automatic data transferLow personnel requirements.
Stationary On-line Monitoring
50 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
A-Zones -> stationary only -> continuous measurements are required
B-Zones -> continuous measurements are recommended
C/D-Zones -> mobile measurements can and should take place
No fixed rules, but logical deductions from relevant GMP Guidelines
Stationary Or Mobile?
51 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle CountersParticle Counters
Climet PMS Lighthouse
Metone
REMOTETransfer of data
INTEGRATED
52 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle Counters )Remote(Particle Counters )Remote(
53 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle CountersParticle Counters
54 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Particle MonitoringParticle Monitoring
REMOTETransfer of particles
Short extensions from the sample point to the sensor are generally acceptable,assuming that the tubing has a minimum of turns or curves and that the curves have a generous radius .
Due to the statistically low number of particles within a sample under "Class 100" conditions,it is best to limit the use of tubing, which causes some entrapment or fragmentation of particles.If the tubing must be longer than 10 feet. then the loss factor for that given tubing must be
determined and a correction factor must be used to adjust the counts obtained during filling procedures .In general, the use of manifolds for sampling in clean areas Is strongly discouraged by EU/ FDA.
55 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Docking Through „Wall Plates“Docking Through „Wall Plates“
Pos
. 1
Pos
. 2
Pos
. 3
Pos
. 4
Pos
. 5
Pos
. 6
Pos
. 7
Mobiler PartikelzählerCLIMET CI-500 mitDocking-Position-Modul
PC-Systemmit SCADA Applikation
Reinraum mitC/D-Zonen isokinetische
Probenahmestelle
BUS-Controller
56 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
HEPAHEPA
Particle counter clean air Particle counter unfiltered air
Aerosol generator
Dilution system
Supply aerosolSampling
unfiltered airSamplingclean air
Filter Integrity TestFilter Integrity Test
57 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Filter Integrity Test)Leak Testing(
Filter Integrity Test)Leak Testing(
58 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Anemometers
59 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Air Speed MonitoringAir Speed Monitoring
60 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
INTEGRATED MONITORING SYSTEMINTEGRATED MONITORING SYSTEM
61 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Microbial MonitoringActive Air Sampling
+passive air samplingwith settle plates
62 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Airflow Visualisation
63 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Light Intensity Measurement
64 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Maintaining continuous compliance
4.2.4 Where the installation is equipped with instrumentation for continuous or frequent monitoring of the airborne particle concentration, and air pressure difference, where applicable, the maximum time interval as stated in Table 1 may be extended, provided that the results of continuous or frequent monitoring remain within the specified limit(s).
4.2.5 In those installations that require additional tests, and where the installation is equipped with instrumentation for continuous or frequent monitoring of the test parameter applicable, the maximum time interval(s) as stated in Table 2 may be extended, provided that the results of continuous or frequent monitoring remain within the specified limit(s).
65 |
Manufacture of sterile medicines – Advanced workshop for SFDA GMP inspectors,
Nanjing, November 2009
Questions, please? .…Questions, please? .…