Huntly East land subsidence due to coal mining Review ...€¦ · adjacent pillars, resulting in...
Transcript of Huntly East land subsidence due to coal mining Review ...€¦ · adjacent pillars, resulting in...
Level 2 TeRenCo House 86-96 Victoria Street P.O. Box 24 147 Wellington
Phone (04) 471 1464 Facsimile (04) 471 1745
IAN R BROWN ASSOCIATES LTD
geo log i ca l e ng i ne er ing con su l t an t s
Huntly East land subsidence due to coal mining
Review following levelling survey
April 2010
Report for Waikato District Council
Project Number 1003
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 1
1. Introduction
Ian R Brown Associates Ltd (IRBA) has been engaged by Waikato District Council (WDC) to
provide advice on issues of land subsidence over underground coal mine workings in the
Huntly East area (Figure 1). A scoping report, outlining what was known about the
subsidence problems, and the range of geographical and geotechnical data which were
available in the area, was presented to WDC in October 2008 (IRBA 2008).
In this report, we present follow-up studies which address a number of the recommendations
made in the 2008 report. In particular, we present an update on the status of the survey bench
mark network as well as results from a recent levelling survey, a review a study undertaken
for Solid Energy, and an improved understanding of the extent of past underground coal
mining in the Huntly area.
2. Survey benchmark network
Lands & Survey (now LINZ) benchmarks were established in 1978 prior to mining in the area
(Figure 1). As previously discussed, survey data for the network were presented in various
reports and WDC files up until about 1993.
Mr John Taris, a former LINZ employee, has reconstructed a digital file containing
benchmark elevation data for numerous surveys of the former Lands & Survey network
undertaken between October 1981 and June 1998. Unfortunately data are absent for many of
the benchmarks within the areas of maximum subsidence as identified in our previous report,
and the full range of measurement dates appears to be absent, therefore a full description of
the subsidence history of the area based on levelling data cannot be made.
A relevelling survey of available benchmarks in was conducted in October 2009. As many
sites as could be confidently identified were resurveyed, though a number of sites were not
able to be located. The locations of some survey sites which we previously reported have
been clarified using the updated data.
For most survey stations with data extending from 1981–2009, total subsidence is < 120 mm.
Between March 1998 and October 2009, subsidence was generally between 0 and 10 mm. A
small number of sites exhibited positive ground displacements. Slight increases in elevation,
recorded during the period 1994-1996, may be related to increased rainfall resulting in higher
aquifer water pressures. Two recorded sites had higher subsidence rates: E9 (17.5 mm/yr) and
E15 (7.4 mm/yr) over the last surveyed period (1998–2009).
The location of subsidence areas discussed below is shown on Figure 1.
Subsidence Area A:
Survey data for this area were absent from the data compilation. Limited points on the
periphery suggest the area affected by subsidence has not expanded since 1986.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 2
Subsidence Area B:
Survey data for this area are generally absent from the data compilation. The only data
available for Subsidence Area B is Site E50 (up to November 1995), which shows a typical
pattern of rapid initial subsidence followed by much lower subsidence rate. This is consistent
with data depicted in Kelsey (1985/6) for sites E53 and E61. By May 1984, these sites were
going down 0.6–0.7 mm per day, declining over the last survey period (May 84-Nov 95) to
about 7 mm per year. There are no data to confirm what is happening subsequently, though
stations around the area are stable or show typical long-term subsidence rates, indicating
Subsidence Area B has not increased in size since Nov 1995.
Subsidence Area C:
Subsidence curves (Figure 2) show that subsidence in this area was ongoing prior to
recognition of problems at the ground surface in 1990. Subsidence rates were moderate until
Sept 1990, then 2 episodes of faster subsidence were recorded, namely Sept 1990-Nov 1993
(sites E42, E47, and E49), followed by more rapid subsidence (site E42, E43, and E49)
through to Nov 1995. Subsequent subsidence rates are low (indicated by E42) at 2 mm/yr.
Sites E42, E43, E47 and E49 show peripheral subsidence from Subsidence Area 2 (Sept
1983), suggesting maybe 90–230 mm of subsidence attributable to “far-field” effects, possibly
due to aquifer depressurization. New rapid subsidence from Nov 1993 was likely to have
been caused by localized pillar failure in Panel 4 workings, with the centre of subsidence near
the smallest pillar as discussed below.
Subsidence Area D:
Area D is not underlain by East Mine South Headings workings. Subsidence was noted in the
area in 1993 (Figure 3), though survey data indicate subsidence had commenced between
1981 and 1984 (23 mm at site E51). Rapid subsidence was observed between the Sept 1990
survey and the Nov 1993 survey (63 mm at site E102 and an additional 35 mm at site E51).
The likely mechanism for this subsidence is aquifer depressurization. Subsequently, typical
long-term rates of 1-2 mm/yr have been recorded in this area.
Mine roadway area:
Kelsey (1986) indicated up to 100mm subsidence above the access roadway workings.
Extensive survey data through this area (Figure 4) demonstrate moderately rapid subsidence
between Oct 1981 and July 1987, followed by typical background rates of 1-2 mm/yr. One
site, E37B, shows a long-term trend of increasing elevation, possibly as a result of tree-root
growth causing heave in the footpath at the station site.
Northern area:
We are not aware of significant subsidence-related problems reported in the north of the study
area. Survey data indicate subsidence rates of up to 5-6 mm/year were experienced until
1998, with some sites now showing typical background rates of either 1–2 mm/yr (Figure 5).
Two sites in the northern area show ongoing subsidence.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 3
Site E9 is located at the far north of the study area. Total subsidence is 248 mm over the
period 1983–2009, with a moderate rate of subsidence until 1998, and a higher rate (17.5
mm/year) recorded subsequently. Site E9 has the highest rate of subsidence presently
recorded at any site. The site is underlain by the southwest corner of the workings for the
Huntly East Mine North Headings which were developed later than the South Headings.
Site E15 is located north of the area where significant subsidence has occurred, with a total
displacement of 189 mm between Oct 81 and Oct 2009. The linear subsidence rate at site E15
is not typical of mine subsidence seen elsewhere in the area, and suggest another mechanism.
The survey data file indicates that localised settlement of a retaining wall is suspected at this
site. However, during the period 1993–1998, sites E9 and E10 had similar subsidence rates to
site E15, indicating that a mine-related subsidence mechanism is still required. Settlement
over mine roadways is likely.
3. Review of Solid Energy study
In 2003, Solid Energy North Ltd commissioned a report from Strata Control Technology
(SCT) Operations Pty Ltd to conduct a geotechnical assessment of the proposed North 6 panel
of the Huntly East Mine (SCT 2003). A significant part of this report includes assessment of
existing mine working at Huntly East, Huntly West and Taupiri Mines. SCT also undertook
an analysis of pillar stability issues in Panel 1 of the Huntly East Mine, underlying the NZED
hostel.
The SCT analysis shows that the pillar strength index (i.e. strength / load) for initial Panel 1
workings (3 m high roadway extraction) ranged from 1.7–2.3. Strength index values for 6 m
high roadway extraction decreased to 1.0–1.3 with smaller pillars having values of 0.9. These
low values are located near the axis of original surface subsidence, and the total subsidence in
the NZED hostel area is aligned parallel to these low strength pillars.
SCT conclude that the pillar system in Panel 1 has a marginal level of stability, and that,
should one pillar shed load (due to failure from overstressing) on to adjacent pillars, the
system could become unstable.
SCT also undertook a numerical model-based back analysis of the NZED hostel area. The
model demonstrated that failure of one of the smaller pillars would result in transfer of load to
adjacent pillars, resulting in yield and loss of stiffness in the system. This causes overburden
material to displace into the panel due to its inability to bridge the panel. The result is that
overburden is no longer supported, allowing subsidence to progress.
The SCT model and analysis appears to follow closely the observed subsidence events in the
NZED hostel area, both at the surface and in the mine workings. Previous interpretations of
the driving mechanism for the subsidence by Kelsey (1986, 1987, as discussed by IRBA
2008) downplayed the role of coal pillar collapse, because underground inspection showed
that the pillars were generally intact, with only minor spalling into roadways. The proposed
mechanism for the subsidence was mine roof collapse allowing dewatering and consolidation
of Tauranga Group sediments (especially pumiceous silts). The SCT study concluded that
partial collapse of smaller coal pillars was the initial driving mechanism for the mine roof
collapse and subsequent dewatering.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 4
A driving factor behind the pillar collapse is likely to be an increase in overburden loading as
the ground elevation above the mine workings increases to the east. There appears to have
been no effective change to the pillar design to accommodate variable overburden thickness.
Subsidence still occurred in later parts of the mine working where pillar design was changed
in an attempt to improve stability at roadway intersections. The presence of smaller pillars
than was optimal to maintain stability in the revised design allowed pillar collapse to continue.
4. Extent of historical mine workings
We have compiled maps showing the extent of historical underground coal mine workings
throughout the Huntly township area (Figure 6). Data have been obtained from Crown
Minerals (as digital vector data) for the area north and east of the Huntly Power Plant. For
other areas, we have georeferenced (TM2000 grid) a set of copies of historic mine plans
which were supplied by Mr Jae Bateman, Solid Energy North.
Much of the northern part of the Huntly township is underlain by workings of the former
Taupiri Extended Mine, which operated from 1888 to 1924 (Kirk et al. 1988). Brown (1981)
indicated that in the Taupiri Extended Mine, pillar stability problems were experienced when
overburden depths exceeded about 110 m. Pillars were typically 150 m2 and extracted heights
were up to c. 5 m.
One roof fall which reached the surface was recorded between Waikato River and Lake
Hakanoa in July 1915 (Mines Department, 1983). Cover above the coal seam at this point
was about 20 m. The collapse appears to be located above a fault-controlled structural high.
An area of 0.8–2.8 ha was reported to have been affected by subsidence over the deeper
workings of the Taupiri Extended Mine (Mines Department, 1984). The location of this
subsidence is not known, and does not appear to have been reported in any documents
available to us.
The southern part of the Huntly township is underlain by workings of the former Ralphs
Mine, which operated from 1890 to 1916 (Kirk et al. 1988).
While a number of historical reports indicate minor effects at the surface from these old
workings, there is no record of significant subsidence in these areas.
5. Recommendations
Our scoping study identified the following issues which required further investigation, and
which would allow a full assessment of the risks associated with future subsidence. As
indicated, some items have been addressed and others require further consideration.
• Request a copy of the recent Solid Energy study of mine related subsidence in the
Huntly East area. We have received and reviewed this report.
• Compilation of all benchmark survey data and thorough review to highlight changing
patterns of subsidence since 1979. This was completed and is discussed in the present
report.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 5
• Resurvey of monitoring network. The available points have been resurveyed.
• Compilation of WDC and Government records of property and infrastructure damage
to correlate response to subsidence with measured surface settlement patterns.
• Construction of a digital geological and geotechnical database and model.
• Compilation of existing piezometer records, collection of current piezometer data,
review of groundwater hydrology. In particular, the piezometer installed above the
Panel 4 area should be investigated to test whether dewatering occurred as predicted
during subsidence in that area.
• Analysis of geological and geotechnical data to determine whether sensitive strata
identified by Kelsey are present in areas where subsidence was recorded subsequent
to 1987.
• Preparation of a dewatering consolidation subsidence zonation map as recommended
by Kelsey (1987).
• Further assessment of the stability of the South Headings workings. We understand
this area is not flooded, and is presently used by Solid Energy for Mines Rescue
training. This task may have been undertaken by Solid Energy during their recent
study. The Solid Energy study addresses some of the issues, but only analysed Panel 1
workings, and no subsidence predictions are presented.
• Compilation of mine plan information and subsidence for historic working under other
parts of Huntly, and comparison with the Huntly East Mine workings. This is
presented in Figure 6.
• Suitable foundation designs which mitigate against subsidence damage should be
developed for the area. A draft document prepared by Ministry of Works and
Development in 1985 for Huntly Borough Council, but which does not seem to have
been finalised and adopted, provides a good starting point.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 6
6. Conclusions
Survey data, where available, show that many areas within the Huntly Mine Subsidence
zone are subject to long-term subsidence rates of 1–2 mm per year.
Limited survey data indicates rapid subsidence experienced in the period 1983–1993 has
stabilised, but many relevant survey points have not been obtained to provide a definitive
answer about this.
Survey data indicate that previously mapped subsidence areas have not expanded since
1993.
Some subsidence has been recorded in benchmarks in the northern part of the area. We
have not seen any damage records for this area. Settlement over mine roadways is the
likely mechanism for subsidence in this area, with addition subsidence at site E9 being
probably related to the extensive Huntly East Mine North Headings.
The Solid Energy report provides further indications as to the origin of the subsidence, in
particular the recognition that sub-optimally sized pillars are likely to have failed, starting
a chain reaction of roof strata failure followed by dewatering followed by subsidence.
While most of the Huntly township is underlain by historical mine working, these are low
elevation areas. It appears that the higher overburden ratios in the Huntly East Mine
South Headings area due to increasing elevation, were sufficient to initiate instability in
the mine workings beneath.
Due to gaps in the survey data, we are unable to confirm whether Subsidence Areas A and
B, where significant subsidence occurred in 1983–1984, are presently stable.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 7
7. Applicability
This report has been prepared for the benefit of Waikato District Council with respect to the
proposal submitted by Ian R Brown Associates Ltd. It may not be relied upon in other
contexts or for any other purpose without our prior review and agreement.
Opinions and recommendations contained in this report have been derived from the
information and data gathered during the course of our investigations.
No liability is accepted by Ian R Brown Associates Ltd nor by any Director, or any other
servant or agent of the company, in respect of the use of this report (or any information
contained therein) by any person for any purpose other than that specified in the brief.
8. References
IRBA (2008): Huntly East Land Subsidence Due to Coal Mining - Scoping Study.
Unpublished report for Waikato District Council, October 2008, IRBA Job 1003, 16pp.
Kelsey, P.I. (1986): An engineering geological investigation of ground subsidence above the
Huntly East Mine Area. Unpublished M.Sc. thesis, University of Canterbury.
Kelsey, P.I. (1987): An engineering geological investigation of ground subsidence above the
Huntly East Mine. NZERD Report P123.
Kirk, PA; Sherwood, AM; Edbrooke, SW (1988): Waikato Coal Region: a summary of
geology and resources. New Zealand Geological Survey Record 34, 28pp.
Mines Department, Ministry of Energy (1983): Huntly East Mine, Longwall feasibility study
Part I, Preliminary Assessment. Unpublished Coal Report CR102, Crown Minerals, Ministry
of Economic Development, 100pp.
Mines Department, Ministry of Energy (1984): Huntly East Mine, Longwall feasibility study
Part II. Unpublished Coal Report CR1488, Crown Minerals, Ministry of Economic
Development, 633pp.
Strata Control Technology Operations Pty Ltd (2003): Assessment of North 6 pillar design
issues at Huntly East Mine. SCT report CNZ2535, unpublished report for Solid Energy North
Ltd, 4 August 2003, 44pp.
Huntly subsidence – review of survey data Ian R Brown Associates Ltd 8
FIGURES
Figure 1. Location map showing survey benchmark locations.
Figure 2. Time series plot of elevation data, Subsidence Area C.
Figure 3. Time series plot of elevation data, Subsidence Area D.
Figure 4. Time series plot of elevation data, Mine roadway area.
Figure 5. Time series plot of elevation data, Northern area.
Figure 6. Map showing extent of historical underground coal working, Huntly.
1790500E 1791000E 1791500E 5842500N
5843000N
5843500N
5844000N
E12B E13
E57
E34E34L
E38
E38L E37BE37A E37C
E36
E41
E40A
E40
E51A
E44
E43
E42
E47
E49
E50
E73
E39A
E72
E37
E56
E9
E67
E16A
E16B
E15
E71
E35
E41A E45
E69
E68
E104E105
E106
E102
E8
E10
E12
E16
E16C
E48A
E51
E51C
E52
E70
E81
E94
E95E96
E97
E98
E99
E100E101
E107
E108
E109
E110
E111
E112
EE
E108A
E108BE108CE114A
E114BE114C
E114DE114EE114F
E12A
E14
E33
E46A
E46
E42A
E39
E62
E63
E53
E61
E54E60
E55 E59 E65
E66
E55A
E58
E92
E90E87
E88
E89
E64
E11A
E38A
E39BE42B
E51B
E68A
E73B
E86
E100B
Figure 1. Survey data point locations. gp1003_base5.rlg - 1 April 2010
LEGENDWDC subsidence zone
Cadastral boundaries
SCM underground mine workings
Kelsey 1987 subsidence contours (mm)
L&S/Works surveyed subsidence zones
A September 1984 subsidence
B April 1983 subsidence
C 1990-92 localised sinkhole
D 1993 localised subsidence
Survey stations with data available
Survey stations with no data available
A
B
C
D
50
50
50
100
100
200
400
600
100
200400
600
800
-440.0 -440.0
-420.0 -420.0
-400.0 -400.0
-380.0 -380.0
-360.0 -360.0
-340.0 -340.0
-320.0 -320.0
-300.0 -300.0
-280.0 -280.0
-260.0 -260.0
-240.0 -240.0
-220.0 -220.0
-200.0 -200.0
-180.0 -180.0
-160.0 -160.0
-140.0 -140.0
-120.0 -120.0
-100.0 -100.0
-80.0 -80.0
-60.0 -60.0
-40.0 -40.0
-20.0 -20.0
0.0 0.0
20.0 20.0
40.0 40.0
E42
E42
E42
E42
E42
E42
E42
E42
E42E42
E42
E42
E43
E43E43 E43
E43 E43
E43
E43
E43E43
E43
E47
E47
E47
E47
E47E47
E47E47
E47
E48A
E48A
E48A
E48AE48A E48A E48A
E48A
E49
E49
E49
E49
E49
E49
E49
E49
E49
E50
E50
E50
E50
E50
E50 E50
E50
Figure 2: Time series - Subsidence area CVertical scale = millimetres vertical movement relative to original
1981/10/01
1984/08/01
1987/07/01
1990/09/01
1992/11/01
1993/11/01
1994/11/01
1995/11/01
1996/11/01
1997/03/01
1998/03/01
2009/10/01
-150.0 -150.0
-140.0 -140.0
-130.0 -130.0
-120.0 -120.0
-110.0 -110.0
-100.0 -100.0
-90.0 -90.0
-80.0 -80.0
-70.0 -70.0
-60.0 -60.0
-50.0 -50.0
-40.0 -40.0
-30.0 -30.0
-20.0 -20.0
-10.0 -10.0
0.0 0.0
10.0 10.0
20.0 20.0
30.0 30.0
40.0 40.0
50.0 50.0
E100E100C E100CE100CE100C E100CE102 E102
E102 E102 E102 E102E102
E102
E102
E111 E111E111
E111
E111 E111 E111E51
E51E51
E51 E51
E51 E51E51 E51
E51
E99
E99 E99 E99E99E99
E99
E99
Figure 3: Time series - Subsidence area DVertical scale = millimetres vertical movement relative to original
1981/10/01
1984/08/01
1987/07/01
1990/09/01
1992/11/01
1993/11/01
1994/11/01
1995/11/01
1996/11/01
1997/03/01
1998/03/01
2009/10/01
-150.0 -150.0
-140.0 -140.0
-130.0 -130.0
-120.0 -120.0
-110.0 -110.0
-100.0 -100.0
-90.0 -90.0
-80.0 -80.0
-70.0 -70.0
-60.0 -60.0
-50.0 -50.0
-40.0 -40.0
-30.0 -30.0
-20.0 -20.0
-10.0 -10.0
0.0 0.0
10.0 10.0
20.0 20.0
30.0 30.0
40.0 40.0
50.0 50.0
E112 E112E112 E112
E112 E112
E112
E34
E34
E34
E34
E34 E34 E34E34E34 E34
E34
E34L
E34L
E34LE34L
E34L E34LE34L E34L
E34L E34LE34L
E36
E36
E36
E36
E36 E36 E36E36
E36 E36
E36
E37
E37
E37
E37
E37
E37 E37 E37 E37E37 E37
E37
E37A
E37A
E37A E37A
E37A E37A E37A E37AE37A E37A
E37A
E37B
E37B E37BE37B
E37BE37B
E37BE37BE37B E37B
E37B
E37C
E37C
E37CE37C
E37C
E37C E37C E37CE37C
E37C E37C
E38L
E38L E38L
E38L E38L E38LE38L
E38L E38L E38L
Figure 4: Time series - Mine roadway areaVertical scale = millimetres vertical movement relative to original
1981/10/01
1984/08/01
1987/07/01
1990/09/01
1992/11/01
1993/11/01
1994/11/01
1995/11/01
1996/11/01
1997/03/01
1998/03/01
2009/10/01
-250.0 -250.0
-240.0 -240.0
-230.0 -230.0
-220.0 -220.0
-210.0 -210.0
-200.0 -200.0
-190.0 -190.0
-180.0 -180.0
-170.0 -170.0
-160.0 -160.0
-150.0 -150.0
-140.0 -140.0
-130.0 -130.0
-120.0 -120.0
-110.0 -110.0
-100.0 -100.0
-90.0 -90.0
-80.0 -80.0
-70.0 -70.0
-60.0 -60.0
-50.0 -50.0
-40.0 -40.0
-30.0 -30.0
-20.0 -20.0
-10.0 -10.0
0.0 0.0
10.0 10.0
20.0 20.0
30.0 30.0
40.0 40.0
50.0 50.0
E10
E10
E10E10
E10
E10E10
E10
E12
E12
E12 E12 E12 E12E12 E12
E12
E15
E15
E15
E15E15
E15
E15E15E15
E15
E16
E16
E16 E16
E16 E16 E16E16E16
E16
E16
E8
E8 E8
E8 E8 E8E8E8
E8
E8
E9
E9
E9 E9 E9
E9E9E9
E9
Figure 5: Time series - Northern areaVertical scale = millimetres vertical movement relative to original
1981/10/01
1984/08/01
1987/07/01
1990/09/01
1992/11/01
1993/11/01
1994/11/01
1995/11/01
1996/11/01
1997/03/01
1998/03/01
2009/10/01