• Bike path will run from end of Milk Street extension to Cisco Beach• Funding from the Town of Nantucket and private donations• Estimated completion date: May 2013• Implements path six years earlier than Transportation Improvement
Program funding
HPRBP –Implementation Summary
January 2012: - ConCom hearings (January 4th and 18th)- Receipt of abutter right of way comments- County public hearing for taking all easements- Utilities notified / initial design plans distributed
December 2011: - Staking of path centerline and property bounds for Stroll Weekend- Finalize Appraisals, ROW plans, and property owner notices- Conservation Commission review initiated
November 2011: - Development and review of initial design with VHB- Notice to abutters of strategy and property staking- ROW plan complete / initiate
October 2011: - BOS / County approval of implementation strategy- Finalize amendment to design contract with VHB- Wetland review with ConCom staff
HPRBP Implementation Schedule – Tasks Completed
May 2013: - Construction complete
October 2012: - Pre-Construction meetings- Construction Starts
September 2012: - Construction bid opening
July 2012: - Finalize design plans- Construction bid
May 2012: - Initiate final design of bike path
April 2012: - Construction funding ($3.2 million) approved at ATM / ballot- Taking filed at Registry if the funding is approved- Right of way damage award notifications
March 2012: - ROW secured via County taking (recorded after ATM / ballot vote in mid-April)
February 2012: - ConCom hearing – seek approval of Order of Conditions- County hearing of taking challenges