Transcript of expansion-to-claim-vital-Iron-Range-highway KARE 11 News Story 2.
http://www.kare11.com/news/article/1044895/391/Mine-expansion-to-claim-vital-Iron-Range-highway
KARE 11 News Story
2
Today’s TopicsToday’s Topics
3
Project Updates
Layout
Ongoing activities
Schedule
Dates
Economic Study
Draft EIS
Layouts/preliminary plans
Cost Estimates
Hydrogeology Study of Rouchleau pit
Project Delivery/Schedule Methods
Upcoming/Ongoing Activities
Dewater about 25 feet build in dry
Possible locations Virginia Lakes Enterprise Pit Magneka Creek
3 months to dewater @ 20,000 gpm
Will not affect City water supply.
Rouchleau Pit Study for E1a
Anticipated Schedule (11/07/13)
Milestone Tasks Target Dates
Draft EIS and Public Hearing April 2014
Identification of Preferred Alternative June 2014
Final EIS February 2015
FHWA Record of Decision May 2015
Start construction June 2015
Open to traffic October 31, 2016
Coffee & Conversation
Thursday, December 5
10-11 am
MnDOT
Coffee & Conversation
January 2, 2014
10-11 am
MnDOT
Upcoming Meetings