Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar...

23
http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th , 2008 Mar CAPEANS CERN This project has received funding from the European Community's Seventh Framework Programme (FP7/2007-2013) under the Grant Agreement n o 212114

Transcript of Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar...

Page 1: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

S L H C – P PManagement Tools

Kick-off MeetingApril 8th, 2008

Mar CAPEANSCERN

This project has received funding from the European Community's Seventh Framework Programme (FP7/2007-2013) under the Grant Agreement no212114

Page 2: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Outline

• Reporting to the EC– Technical Progress and Financial Periodic Reports – Financial reporting timeline for SLHC-PP

• SLHC-PP Management Tools– Overview and schedule

• Other Electronic Tools

April 8, 2008 M.C. 2

Page 3: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Reporting to the EC

• SLHC-PP has received funding from the European Community's Seventh Framework Programme (FP7/2007-2013) under the Grant Agreement no 212114. Therefore EC reporting rules apply

• The EC will monitor the project technically and financially at the end of each reporting period:

April 8, 2008 M.C. 3

• P1: from month 1 (April 2008) to month 12 (March 2009) • P2: from month 13 (April 2009) to month 24 (March 2010) • P3: from month 1 (April 2010) to last month of the project (March 2011)

• P1: from month 1 (April 2008) to month 12 (March 2009) • P2: from month 13 (April 2009) to month 24 (March 2010) • P3: from month 1 (April 2010) to last month of the project (March 2011)

Page 4: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Reporting to the EC

The beneficiaries, via the Coordinator, shall submit the following reports to the Commission:

April 8, 2008 M.C. 4

1. The deliverables identified in Annex I2. A periodic report within 60 days after the end of each

reporting period, including:• Progress of work towards the objectives of the project • Explanation of the use of the resources• Financial Statement (Form C – Annex VI of the Grant Agreement)

from each beneficiary together with a summary financial report

1. The deliverables identified in Annex I2. A periodic report within 60 days after the end of each

reporting period, including:• Progress of work towards the objectives of the project • Explanation of the use of the resources• Financial Statement (Form C – Annex VI of the Grant Agreement)

from each beneficiary together with a summary financial report

Page 5: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Financial Reporting at Institute Level

April 8, 2008 M.C. 5

Personnel

Travel

Material

TimesheetTimesheetTimesheetTimesheet Collection,Consolidation

Form CForm CForm CForm CClaimClaimClaimClaim Collection,

Consolidation

AcquisitionAcquisitionCollection,

ConsolidationCETFI-F

Keep supporting documents

(paper copies) of all costs

Page 6: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Time Sheets

April 8, 2008 M.C. 6

Timesheets record personnel working hours. EC requests a system that certifies the number of hours worked in order to declare a cost as eligible. A contract, as a document signed before the work is actually performed, would not be sufficient.

Timesheets record personnel working hours. EC requests a system that certifies the number of hours worked in order to declare a cost as eligible. A contract, as a document signed before the work is actually performed, would not be sufficient.

~ 75% SLHC-PP direct costs

are costs of Personnel

Page 7: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Form C, Institute level

April 8, 2008 M.C. 7

RTD Coordination Support Mgt

PersonnelSubcontracting

Other Direct CostsIndirect Costs

Page 8: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

SLHC-PP Financial Reporting Timeline

MONTHLY

QUARTERLY

REGULARLY

REGULARLY

YEARLY YEARLY

1st April to 31st March of next year + 60 days1st April to 31st March of next year + 60 days

Page 9: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Financial Reporting at Project Level

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

“Form C”s“Form C”s

Form CForm CForm CForm C

Form CForm CForm CForm CForm CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm C

Form CForm CForm CForm CForm CForm CForm CForm C

Form CForm CForm CForm C

YEARLY

4 weeks

Consolidation at Project Level2/3 weeks

Consolidation at Beneficiary Level

Page 10: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Summary of SLHC-PP Financial Reporting

April 8, 2008 M.C. 10

MONTHLY

Individuals submitTimesheets

QUARTERLY

Institutes submitInternal Cost Claims

YEARLY

Institutes submitForm C

+ Audit Certificates

To demonstrate that all personnel costs are directly related to the project

Effort monitoring in PM

To monitor the costs of each partner by activity and cost category (personnel, travel, materials)

To get reimbursement of the cost incurred by each partner

Page 11: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Management Tools

April 8, 2008 M.C. 11

A Management of SLHC-PPGeneral project monitoring structure for financial reporting and project progress management tool

B SLHC Implementation

Project monitoring structures and a finance management system for the SLHC implementation (accelerator and experiments)One of the main aims of SLHC-PP WP2 and possibly WP3 and WP4

Page 12: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

A: CERN PPT for EU projects

• CERN/IT-AIS has developed a Project Progress Tracking (PPT). It has been used by ATLAS, LHC, CNGS, APT

• The tool has been adapted to manage EU projects in FP6. PPT-EU has been used by EGEE (funding over 30 M€ from the EC, ~1000 members), ETICS… and it will be used for EGEE3 and ETICS2 in FP7

• Web based, accessible to all beneficiaries

April 8, 2008 M.C. 12

Functionality:– Members Database– Activities Management– Data collection (timesheets, cost claims) and reminders– Data repository for EC mandatory reporting

Functionality:– Members Database– Activities Management– Data collection (timesheets, cost claims) and reminders– Data repository for EC mandatory reporting

Page 13: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

CERN PPT-EU for SLHC

April 8, 2008 M.C. 13

SLHC-PPAdministrative Management

SLHC-PP Progress Tracking

SLHC Mgt

Phase 1 Phase 2 Phase 3

End of May 08Tool available to SLHC-PP Beneficiaries

End of May 08Tool available to SLHC-PP Beneficiaries

Page 14: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Phase 1 Preparation

ADMIN TOOL• Preparation of Timesheets

April 8, 2008 M.C. 14

Request: • Provide a list of members per WP, and their role (member,

activity supervisor, WP leader, etc)Instructions and templates will be provided

Request: • Provide a list of members per WP, and their role (member,

activity supervisor, WP leader, etc)Instructions and templates will be provided

Page 15: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Phase 2 Preparation

PROJECT PROGRESS TRACKING• Annex I contains defined dates for EC DELIVERABLES and EC

MILESTONES. Typical granularity is:

April 8, 2008 M.C. 15

WP

Task 1 Task 2

D 1.1 D 2.1

M 1 M 2

D 1.2 D 2.2

D 1.3

Request: – Produce a proper WBS of each WP (broken down in tasks and

subtasks), with a set of internal deliverables to help/ensure that EC deliverables are attainable on schedule, within budget

Request: – Produce a proper WBS of each WP (broken down in tasks and

subtasks), with a set of internal deliverables to help/ensure that EC deliverables are attainable on schedule, within budget

Page 16: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Example: WP1 deliverables and milestones

April 8, 2008 M.C. 16

WP1: SLHC Project Management

Task 1: Steering of the Consortium and project follow-up

Task 2: Dissemination

M 1.1 Kick-off meeting M01

D 2.1 SLHC-PP Web Site M03

M 1.2 Annual Meeting 1 M12

D 1.1 Periodic report M14

M 1.3 Annual Meeting 2 M24

D 1.2 Periodic report M26

M 1.4 Annual Meeting 3 M36

D 1.3 Periodic report M38

D 1.4 Final Report M38

EC Deliverables and Milestones

Internal Deliverables and MilestonesNot visible to EC

Page 17: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Phase 2 Preparation

PROJECT PROGRESS TRACKING• Members are assigned to partners• Members are assigned to tasks or subtasks• Tasks and subtasks have a defined duration

April 8, 2008 M.C. 17

Request: – Define the assignments above for each WP

Request: – Define the assignments above for each WP

Page 18: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Targets

• All the information will be collected by the WP leaders (via templates)

• Deadline: May 5th

• Target: Timesheets for April and May collected with the tool

April 8, 2008 M.C. 18

Next steps:– May 6 – 13: enter data (by SLHC-PP Admin team)

– May 26: Admin Tool (Phase 1) available to all beneficiaries

Next steps:– May 6 – 13: enter data (by SLHC-PP Admin team)

– May 26: Admin Tool (Phase 1) available to all beneficiaries

Timesheets for April and May must be filled in Excel Templateshttp://cern.ch/SLHC-PP/MANAGEMENT.htm

Target: Collect Timesheets with the tool from June

Page 19: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

SLHC-PP Admin Guide

• SLHC-PP Administration Guide being prepared by Admin team

• First draft available towards the end of the week:https://edms.cern.ch/document/904943/1

April 8, 2008 M.C. 19

Contents:– Summary of FP7 rules: EC reporting, finances, timescales– SLHC-PP internal rules for reporting and financial matters

(personnel costs, travel and materials claims, etc.)– Links to EC reporting templates and forms

Contents:– Summary of FP7 rules: EC reporting, finances, timescales– SLHC-PP internal rules for reporting and financial matters

(personnel costs, travel and materials claims, etc.)– Links to EC reporting templates and forms

Page 20: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

SLHC-PP Web• Public pages: http://cern.ch/SLHC-PP/• Internal pages, password protected, will be prepared

April 8, 2008 M.C. 20

Page 21: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

SLHC-PP Documents in EDMS• Restricted access to SLHC-PP members -member list under preparation

• Storage, approval, versioning of documents, release procedures…

April 8, 2008 M.C. 21

Page 22: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

SLHC-PP Indico

April 8, 2008 M.C. 22

• Management of conferences, public and internal meetings• Contributions and Minutes Repository• Calendar of events

Page 23: Http://cern.ch/SLHC-PP S L H C – P P Management Tools Kick-off Meeting April 8 th, 2008 Mar CAPEANS CERN This project has received funding from the European.

http://cern.ch/SLHC-PP

Questions

• Please, contact SLHC-PP management/admin team at CERN– Emails, phones of the team and expertise will be

available soon in the SLHC-PP Web Site

• EC Guides: http://cordis.europa.eu/fp7/find-doc_en.html

April 8, 2008 M.C. 23