HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI...

15
1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17 th April 2013 The Cavity Insulation Guarantee Agency Agenda What is a HTT cavity? What is the Opportunity? What is CIGA Doing? HTT Examples? Future HTT Developments?

Transcript of HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI...

Page 1: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

1

The Cavity Insulation Guarantee Agency

HTT CWI Opportunities and Challenges

Gerry Miller

17th April 2013

The Cavity Insulation Guarantee Agency

Agenda

• What is a HTT cavity?

• What is the Opportunity?

• What is CIGA Doing?

• HTT Examples?

• Future HTT Developments?

Page 2: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

2

The Cavity Insulation Guarantee Agency

WHAT IS A HTT CAVITY?

The Cavity Insulation Guarantee Agency

What is a HTT Cavity?

• Term coined by DECC to identify properties that are

more difficult to treat for technical or cost reasons.

• Higher costs means that they were not treated in

earlier Supplier Obligations.

• Extending benefits of CWI to householders in hard to

treat properties is a Particular focus of the Energy

Company Obligation (ECO) and Green Deal.

– HTT Cavities a primary measure under CERO

• Defined in “The Electricity and Gas (Energy Companies

Obligation) Order 2012” Statutory Instrument.

• Further Guidance included in the OFGEM “Energy

Companies Obligation (ECO) 2012 - 2015: Guidance for

Suppliers”

Page 3: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

3

The Cavity Insulation Guarantee Agency

The HTT Opportunity - Si

• (i) 3 or more storeys where each storey has cavity

walls;

• (ii) which a chartered surveyor has reported is not

suitable to insulate with standard insulation material or

techniques;

• (iii) which a chartered surveyor has reported is not

suitable to insulate without substantial remedial works;

• (b) a cavity within a cavity wall which is less than

50mm wide;

• (c) a cavity found in homes of prefabricated concrete

construction or with metal frame cavity walls; or

• (d) an uneven cavity formed in walls constructed of

natural stone or from natural stone outer leaf and

block or brick inner leaf;

The Cavity Insulation Guarantee Agency

WHAT IS THE OPPORTUNITY?

Page 4: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

4

The Cavity Insulation Guarantee Agency

HTT Potential (DECC IA) 3.2m

High Rise,

66,000

Other, 96,000 Random Stone,

175,000 High Exposure,

225,000

Narrow

Cavities,

535,000

Unfillable/

Timber Frame,

580,000

System Built &

Steel Frame,

663,000

Partial Fill2,

2,000,000

Remedial

Works,

1,400,000

The Cavity Insulation Guarantee Agency

HTT Challenge - Process

Industry Delivery Capability Capacity & Skills Constraints & Investment

Building Regs Compliance CP Schemes

Consumer Confidence Guarantee Availability

Finding HTT Identification, Validation and Assessment

Scoring RdSAP Savings, In Use Factors

Product Approvals Testing/Certification

Product Development Products/Techniques

Rules & Access to Funding ECO Guidance

Definition of HTT Scope/Categories

Page 5: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

5

The Cavity Insulation Guarantee Agency

Deliverable Potential 2m

High Rise,

66,000

Other, 96,000 Random Stone,

175,000 High Exposure,

225,000

Narrow

Cavities,

535,000

Unfillable/

Timber Frame,

580,000

System

Built &

Steel Frame,

663,000

Partial Fill2,

2,000,000

Remedial

Works,

1,400,000

Potentially

Treatable

Now 2m

R&D/Approvals

Challenges1.2m

The Cavity Insulation Guarantee Agency

Segmentation

GD only, 78,444

<50% ECO, 442

>50% ≤75% ECO, 39,569

>75% ≤100% ECO, 51,339 >100% ECO,

155,630

CWI Funding (2013)

Page 6: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

6

The Cavity Insulation Guarantee Agency

Segmentation

CWI Easy-to-treat , 201054

CWI Hard-to-treat Unidentifia

, 4573

CWI Hard-to-treat

Identifiable , 192351

CWI Easy/Hard to Treat (2013)

The Cavity Insulation Guarantee Agency

Market Value Opportunity

Page 7: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

7

The Cavity Insulation Guarantee Agency

WHAT IS CIGA DOING?

The Cavity Insulation Guarantee Agency

GBP Review

Page 8: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

8

The Cavity Insulation Guarantee Agency

Technical Notes

• Existing

– Internal Flues & Chimneys

– Technical Note -: drilling near flues

– Air Bricks and Ventilators.

– Safety Alert -: internal flues & chimneys.

– Flueless Gas Fires.

– Conservatories.

– Safety note : Core drilling.

• Proposed Drafts for review by Technical Committee

– Non Standard Buildings

• Narrow

• Partially filled

• 3 or more storeys up to 12m

– High Rise Buildings (above 12m)

– Commercial Buildings.

– Properties requiring remedial works

The Cavity Insulation Guarantee Agency

HTT Training

• Installation may require up skilling of existing

employees

– Assessors – competence to assess HTT cavities

– Technicians – ie non standard techniques

– Supervisors / technical moniters

– Sales/Customer Care.

• System Designer CWI Training Course -:

– Classroom.

– On Site.

• CIGA Training

– Working with System Designer’s

– Delivery to Installer Companies in association with

System Designers

Page 9: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

9

The Cavity Insulation Guarantee Agency

Website

The Cavity Insulation Guarantee Agency

HTT EXAMPLES?

Page 10: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

10

The Cavity Insulation Guarantee Agency

HTT - Examples

• 3 or More Storeys

• Requiring substantial Remedials (4 hours)

• <50mm cavities

• Cannot treat with Standard Products or Techniques

– High Exposure/WP risks

– Timber Framed

– Partial Fill

• Steel or Concrete Frame

• Random Stone.

The Cavity Insulation Guarantee Agency

Identification -GD Assessment

• RdSAP covers 3 issues in relation to hard-to-treat

flaged on EPC – access, narrow cavity and exposure:

– Access issue is indicated for any façade where it is

not possible to safely pitch a 5 metre.

– A narrow cavity is indicated by a stretcher bond

brick pattern with wall thickness 220 to 250 mm.

– Exposure zones 3 or 4.

• Includes cases where at least 1 elevation is HTT.

• BUT:

– Does not map to ECO HTT definitions.

– Does not capture main addressable markets ie

remedials & Non Standard Techniques and Materials

Page 11: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

11

The Cavity Insulation Guarantee Agency

High Rise

Suitability Assessment of High Rise Buildings.

Building Report: (System Designer). (single page)

Suitability Assessment Form. (3x Pages)

High Rise Building - Additional Notes. (2x pages)

High Rise Building Assessment Version 4 RJS 04/04/2013

The Cavity Insulation Guarantee Agency

3 or More Storeys

• A building of 3 or more storeys of cavity wall is HTT.

• Includes basement with external wall exposed to the

air but excludes Lofts.

• Buildings up to 12m can filled under current approvals.

• In the case of buildings over 12m System Designer must

have a BBA approved procedure to issue height waivers

and additional CIGA requirements apply for issue of

CIGA HTT Guarantee.

• Can be notified under CWISC CP scheme.

Page 12: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

12

The Cavity Insulation Guarantee Agency

Building Defects

• A building that a Chartered Surveyor reports

is not suitable to treat without substantial

remedials works is HTT

• Covers a wide range of defects and

structural issues.

• Standard construction and cavities, but CWI

cannot be installed until defects rectified.

• Includes removal of failed cavity or solid

wall insulation - but if covered by a

guarantee then savings from its

replacement cannot be claimed under ECO

• Additional requirements for sign off for

remedials - but standard assessment and

installation.

– Proposed to categorise by type or works.

The Cavity Insulation Guarantee Agency

Published by:Cavity wall Insulation Guarantee Agency, CIGA House, 3, Vimy Court,

Vimy Road, Leighton Buzzard LU7 1FG Tel: 01525 85300 FAX: 01525 385926

April 2013.

Assessment form to confirm the Suitability for Cavity Wall Insulation

For: Non-Standard Buildings up to 12m in height.

Balanced Flue.

Cracked Facings

Render

Check guttering and

leaking downpipes Chimney /

Flue Routes

Combustion

air vents

ALL - Sub floor vents -

must be maintained.

Sloping Roof

Extension Roof.

Construction type ;

o Timber

o Felt,

o Perspex,

o Others

as

Garage Roof

construction

Assessing the Suitability of Buildings:

Some of the things we need to know.

Hedges preventing

safe working access

Ridge tile vent’s

Check connecting

Flue Routes

Internal and External leaf

construction +

Residual cavity width

Radon Vent’s ?

Non Standard Buildings

Page 13: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

13

The Cavity Insulation Guarantee Agency

Narrow Cavities

• A wall that has a section of cavity which is <

50mm wide is a hard-to-treat cavity wall.

• HTT Guarantee available where an approved

System used and can be notified under CWISC

CP Scheme.

• Currently some systems are approved down to

nominal minimum of 40mm.

• Each wall must be considered separately.

• CS report not required, but OFGEM looking at

evidence required to show that each elevation

claimed was <50mm.

– Assessment record with photographic

evidence?

– Monitoring through physical inspection?

The Cavity Insulation Guarantee Agency

Unsuitable for Std Prod.

• A Cavity that a Chartered Surveyor reports

is not suitable to be treated with standard

products is a HTT Cavity.

• Can be determined by whether a CIGA

Guarantee was available at 31/12/12

• Includes Partial Fill

• Includes Non Standard Constructions

– Steel Frame

– System Built

– Random Stone

• Cannot currently be treated or awarded a

CIGA HTT Guarantee.

• Not notifiable under the CWISC CP scheme.

Page 14: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

14

The Cavity Insulation Guarantee Agency

Unsuitable for Std Tech

• A Cavity that a Chartered Surveyor reports is not

suitable to be treated with standard techniques is

a HTT Cavity.

• Can be determined by whether a CIGA Guarantee

was available at 31/12/12

• Includes Non Standard Techniques such as Lance

System

• CIGA HTT Guarantee available where:

– System approvals exist for technique

– Assessors and Technicians are trained by the

System by the System Supplier;

– Appropriate controls are in place to allow

identify properties to aid investigation if any

problems are reported.

The Cavity Insulation Guarantee Agency

FUTURE HTT DEVELOPMENTS?

Page 15: HTT CWI Opportunities and · PDF file1 The Cavity Insulation Guarantee Agency HTT CWI Opportunities and Challenges Gerry Miller 17th April 2013 The Cavity Insulation Guarantee Agency

15

The Cavity Insulation Guarantee Agency

Future Developments

• ECO Statutory Instrument imposes onerous requirements for claiming HTT cavities.

• In some cases includes report by a Chartered Surveyor and specific recommendation of a treatment

• Unproven, and work ongoing to develop alternative approaches that will provide greater safeguards.

• Centred on proposed BBA policy to assess and card HTT Assessors coupled with CIGA guidance and provision of CIGA HTT Guarantee.

• Requirement for CS hard wired in Si - so will require DECC change to legislation.

• Additional Issues:

– Monthly reporting by end of month following works.

– Uncertain monitoring requirements of Suppliers – evidence that Guarantee applied for etc.

The Cavity Insulation Guarantee Agency

Conclusion

• HTT cavities now defined

• OFGEM Guidance imposes some challenges but still

represents a significant opportunity

• Addressing all of the HTT markets will depend on R&D,

testing/approvals of systems and availability of

guarantees.

• CIGA HTT Guarantee now “live”

• Ongoing development of CIGA assessment and

installation templates and Technical notes.

• CIGA training being rolled out.

• Ongoing work to simplify ECO HTT requirements

• Updates will continue to be provided through member

communications and via the website:

www.ciga.co.uk