Hthp Expansion - Jpk

download Hthp Expansion - Jpk

of 39

Transcript of Hthp Expansion - Jpk

  • 8/11/2019 Hthp Expansion - Jpk

    1/39

  • 8/11/2019 Hthp Expansion - Jpk

    2/39

    Design Solutions for

    Reducing End Expansion

    Use Pipe in Pipe

    Increase Spool Capacity

    Increase Axial Friction Trench and Bury

    Site specific pipe-soil Geotechnical Investigation

    Weight Coating

    Spot rock dump / mattresses Fins/ Strakes/Spiders

    Pipe Anchors

    Lateral Buckling

    Snake Lay

    Buckle Initiator

    Sleepers

    Buoyancy

  • 8/11/2019 Hthp Expansion - Jpk

    3/39

    Pipe in Pipe

    Pros:

    Proven technology

    Insulation can be included

    Provides physical protection Can be snaked laid

    Less prone to pipe walking

    Suited to deep and shallow water

    Cons:

    Increased pipe weight

    Complex field joints

    Reduced lay rate

    Cost:

    Cost of pipe in pipe is high due to cost of outer pipe andreduced lay rate.

  • 8/11/2019 Hthp Expansion - Jpk

    4/39

    Typical Expansion Movements

    For Pipe in Pipe and Single Pipe

    0

    2

    4

    6

    8

    10

    12

    100 60 30

    Operating Temperature (C)

    PipelineEnd

    Expansion(m)

    Single Pipe, 0.3 friction

    Single Pipe, 0.6 friction

    PIP, 0.3 friction

    PIP, 0.6 friction

  • 8/11/2019 Hthp Expansion - Jpk

    5/39

    Typical Anchor Lengths

    For Pipe in Pipe and Single Pipe

    0

    5

    10

    15

    20

    25

    100 60 30

    Operating Temperature (C)

    PipelineAnch

    orLength(km)

    Single Pipe, 0.3 friction

    Single Pipe, 0.6 friction

    PIP, 0.3 frictionPIP, 0.6 friction

  • 8/11/2019 Hthp Expansion - Jpk

    6/39

    Increase Spool / Jumper Expansion Capacity

    Pros:

    Proven technology

    Limit state methods can be used

    Cons:

    Connector capacities limited

    Expansion exceeds possible spool capacity

    Time needed to develop new connectors

    Cost:

    Cost of longer spools is low

    Cost of developing new connectors is high

  • 8/11/2019 Hthp Expansion - Jpk

    7/39

    Increase Axial Friction

    Trench and Bury

    Pros:

    Will reduce pipeline expansion

    Cons:

    Deep water trenching is difficult

    Cannot inspect the pipeline once it is buried

    Susceptibility to upheaval buckling

    Prohibitive cost of deep water trenching spread Increased temperature due to insulating effect of

    backfill

    Uncertainty over backfill geotechnical properties

    Cost: Cost of trenching is high due to spread costs.

  • 8/11/2019 Hthp Expansion - Jpk

    8/39

    Increase Axial Friction

    Site specific pipe-soil Geotechnical Investigation

    Pros:

    Improved confidence in friction factors

    Makes design of lateral buckling based solution

    easier

    Cons:

    Time required to collect and interpret data

    Cost:

    Cost of gathering site specific data is low due tomarginal vessel and equipment cost

  • 8/11/2019 Hthp Expansion - Jpk

    9/39

    Increase Axial Friction

    Weight Coating

    Pros:

    Will reduce end expansions Will help guarantee controlled buckles occur

    Will reduce feed-in to buckles

    Cons:

    Increased likelihood of uncontrolled lateral buckling due

    to higher axial forces Increased lateral friction factors will result in higher

    strains at buckle locations

    Difficulty in installing weight-coated pipelines

    Cost: Cost of concrete coating or clump weights is medium

  • 8/11/2019 Hthp Expansion - Jpk

    10/39

    Increase Axial Friction

    Spot rock dump / mattresses

    Pros:

    Can reduce end expansions Can help guarantee controlled buckles occur

    Can reduce feed-in to buckles

    Can eliminate potential for uncontrolled buckles

    Cons: Large quantities of rock required to counter settlement

    Increased installation time and cost (especially for

    mattresses)

    Specialist vessels required (deepwater fall pipe)Cost:

    Cost of rock dumping is high due to spread costs

  • 8/11/2019 Hthp Expansion - Jpk

    11/39

    Increase Axial Friction

    Fins/Strakes/Spiders

    Pros:

    Embedment can mobilise additional soil friction

    Cons:

    Units have to be suitable for deployment over

    lay barge stinger

    Limited track record

    Cost:

    Cost of fins is medium assuming no delay in

    pipe lay.

  • 8/11/2019 Hthp Expansion - Jpk

    12/39

    Increase Axial Friction

    Pipe Anchors

    Pros:

    Anchors are being proposed to prevent pipewalking in deepwater

    Cons:

    Limited track record

    High anchor loads

    Anchors will be large and heavy

    Subsea connection of anchor to pipeline hard toachieve

    Fishing interaction in shallow water

    Cost: Cost of anchors is high due to fabrication cost and

    installation cost

  • 8/11/2019 Hthp Expansion - Jpk

    13/39

    Lateral Buckling

    Snake Lay

    Pros:

    Proven track record in shallow water

    Cons:

    Difficult to achieve tight lay radii in deepwater

    Insufficient axial friction to guarantee buckle initiation Uncertainty over soil-pipe interaction in soft soils

    Lateral buckles may overstress pipeline

    Cost: Cost of snake lay is medium associated with

    engineering and slightly longer pipe length.

  • 8/11/2019 Hthp Expansion - Jpk

    14/39

    Pipe in Pipe Snaked Lay

    Penguin Production Line

    Shell North Sea

    34 Bends

    28 Buckle Sites

  • 8/11/2019 Hthp Expansion - Jpk

    15/39

    Pipe in Pipe Snaked Lay

    Pipeline Snake Geometry

    Penguin Production Line

    Pipelay Shape to

    Approx. Scale

  • 8/11/2019 Hthp Expansion - Jpk

    16/39

    Pipe in Pipe Snaked Lay

    Penguin Production Line

    Operational Feedback

    Feed-Back

    Operation

    First Oil 4/1/2003

    3 months - high spec survey

    All Buckle Sites Formed

    80 bara, 93 C at DC5

    2 Short Sections Buckled?

    Video Record along routeBoulders swept away

    9 months - high spec survey

    Satisfactory

    Shutdown for Brent Safety

    Late September 2003

    Started Up again last week

  • 8/11/2019 Hthp Expansion - Jpk

    17/39

    Pipe in Pipe Snaked Lay

    Penguin Production Line

    Installer Feedback

    Feedback

    InstallationSaipem - Castoro Sei

    ROV Touch down Monitoring

    ROV moved some boulders

    As-installed survey

    Buckle Sites ~ 1500m Rad+/- 2m of target laydown

    No embedded boulders

  • 8/11/2019 Hthp Expansion - Jpk

    18/39

    SPD 4

    Phase 1

    PLEM 2

    PLEM 1

    Phases 2 & 3

    SPD7

    SPD8

    SPD9

    South Pars Development

    Field Layout

    SP6-1

    &2

    SP7-

    1&2

    SP8

    -1&2

    80m

    80m

    Phase 6, 7 & 8

    pipelines

    Condensate line

    N

    SPD 3

    Phases 4 & 5

    3 identical NNM wellhead platforms

    Transporting 3-phase wet gas toshore

    Via 3, 110km long, subsea 32trunklines

    Each with a 4 MEG injectionpiggyback line.

    Single Line Snaked Lay

    South Parrs Trunklines

  • 8/11/2019 Hthp Expansion - Jpk

    19/39

    Pipeline Route Length = 110km

    Platform

    (KP 110)

    Shore

    (KP0.0)KP80

    Rough Seabed

    KP50

    Snaked Lay

    KP30

    Free Span

    Feed-in

    Below Critical

    Buckling Limit

    Pipeline Temperature Profile 4C89C

    Single Line Snaked Lay

    South Parrs

    Route Length Buckling Mitigation

  • 8/11/2019 Hthp Expansion - Jpk

    20/39

    Single Line Snaked Lay

    South Parrs

    Nested Snaked Lay Pipeline Routes and Buckle Sites

  • 8/11/2019 Hthp Expansion - Jpk

    21/39

    Single Line Snaked Lay

    South Parrs

    Snaked Lay Pre-Buckle Shapes

  • 8/11/2019 Hthp Expansion - Jpk

    22/39

    Single Line Snaked Lay

    South Parrs

    Buckle Formations Approaching Platforms

    40 x Magn i f i ca t i on o f l a te ra l d i sp lacem en ts a long the SP6 , 7 and 8 p ipe l i nes

    2,945,000

    2,950,000

    2,955,000

    2,960,000

    2,965,000

    2,970,000

    2,975,000

    618,000 620,000 622,000 624 ,000 626,000 628,000 630,000 632,000 634,000 636,000

    E a s t in g s ( m )

    Northings(m)

    50 concrete wt coat

    Extg pipeline

    70 concrete weight coat

    Platform

    Extg SP2

    pipeline

    Extg SP3

    pipeline

    SPD 9(KP110.5)

    SPD 7

    (KP95.4)

    SPD 8

    (KP101.8)

    KP80

    KP88

  • 8/11/2019 Hthp Expansion - Jpk

    23/39

    Single Line Snaked Lay

    South Parrs

    3D Image of Snaked Lay Pipeline Route

  • 8/11/2019 Hthp Expansion - Jpk

    24/39

    12 by 23km stainless steel pipeline

    Reeled installation

    Flow assurance for 95 deg C inlet

    7 lateral buckle sites

    Single layer insulation

    Friction sensitivity studies

    Ratcheting,fatigue, creep and buckle interaction code checks

    Strain based acceptance criteria

    Shell International verification

    Single Line Buckle Initiator

    Echo Yodel Flowline

    Woodside Energy - West Australia

  • 8/11/2019 Hthp Expansion - Jpk

    25/39

    Single Line Buckle Init iator

    Echo Yodel

    Pipeline Route

  • 8/11/2019 Hthp Expansion - Jpk

    26/39

    Single Line Buckle Init iator

    Echo Yodal

    Buckle Init iator Geometry

    Perodic Lateral Buc kl ing Init iat ion Feature (1000m Radius o f Curvature)

    0

    2

    4

    6

    8

    10

    12

    14

    0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800

    Distance (m)

    Amplitud

    e(m)

    1000m Radius

    IP2 (411.521, 13.700)

    2000m

    Radius

    2000m

    Radius

    375.0m IP2 to IP3375.0m IP1 to IP2

    IP1 (36.521,0.0) IP3 (786.521, 0.0)

  • 8/11/2019 Hthp Expansion - Jpk

    27/39

    Single Line Buckle Init iator

    Echo Yodel

    As Built Survey

  • 8/11/2019 Hthp Expansion - Jpk

    28/39

    Single Line Buckle Init iator

    Echo Yodel

    Operational Lateral Buckling

  • 8/11/2019 Hthp Expansion - Jpk

    29/39

    Lateral Buckling

    Lay Over Sleepers

    Pros:

    Proven technology in deepwater and shallow water

    Better control on how the pipeline buckles than snake layonly

    Hybrid designs available

    Cons:

    Bearing design of sleepers for low strength soils Insufficient axial friction to guarantee buckle initiation.

    Fatigue in spans induced by sleepers

    Buckles may overstress pipeline

    Interaction with fishing in shallow waterCost:

    Cost is high due to fabrication and deployment of sleepers

  • 8/11/2019 Hthp Expansion - Jpk

    30/39

    Lateral Buckling

    Post buckle survey profile for a 14-inch CRA pipe (long trigger)

    L l B kli

  • 8/11/2019 Hthp Expansion - Jpk

    31/39

    Lateral Buckling

    Post Buckle Survey Profile for a 24-inch CRA Pipe

    (Short Trigger)

    L t l

  • 8/11/2019 Hthp Expansion - Jpk

    32/39

    Pipe in Pipe

    Sleepers

    Lateral

    Buckling

    Sleepers

    L t l B kli

  • 8/11/2019 Hthp Expansion - Jpk

    33/39

    Lateral Buckling

    Lay Over Sleepers

    Water Injection Lateral Buckling Analysis

    Lateral Buckling

  • 8/11/2019 Hthp Expansion - Jpk

    34/39

    Lateral Buckling

    Lay Over Sleepers

    Water Injection Lateral Buckling Results

    DNV Utili ty Check for i75 Route (Sensi tivity)

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    0 5000 10000 15000 2000

    KP (m)

    DNVUtility

    High FrictionHigh Lateral Low AxialLow FrictionLow Lateral High Axial

    Lateral Buckling

  • 8/11/2019 Hthp Expansion - Jpk

    35/39

    Lateral Buckling

    Lay Over Sleepers

    Water Injection Expansion Results

    PIPELINE DESCRIPTION NO INITIATORS WITH INITIATORS

    Hot End - FLET 3.4 2.0

    ITA 0.6 0.6I65Cold End - FLET 0.6 0.6

  • 8/11/2019 Hthp Expansion - Jpk

    36/39

    Lateral Buckling

    Layover Sleeper with Trigger

  • 8/11/2019 Hthp Expansion - Jpk

    37/39

    Lateral Buckling

    Buoyancy

    Pros:

    Better control on how the pipeline buckles thansnake lay only.

    Cons: Not proven technology

    Difficulty passing buoyancy though lay bargefiring line

    Insufficient axial friction to guarantee buckle

    initiation. Fatigue in spans induced by buoyancy

    Buckles may overstress pipeline

    Interaction with fishing in shallow water

    Cost: Cost is medium due to fabrication and attachment

    of buoyancy

  • 8/11/2019 Hthp Expansion - Jpk

    38/39

    Key Findings

    A range of design solutions exist for reducing HT expansion movements

    Low cost solutions include

    Increase Spool Capacity proven Site specific pipe-soil Geotechnical Investigation proven

    Medium cost solutions include

    Snake Lay - proven

    Buckle Initiator - proven Weight Coating - proven

    Fins/Strakes/Spiders limited experience

    Buoyancy limited experience

    High cost solutions include

    Use Pipe in Pipe - proven Trench and Bury - proven

    Spot rock dump / mattresses limited experience

    Sleepers - proven

    Pipe Anchors limited experience

  • 8/11/2019 Hthp Expansion - Jpk

    39/39

    Any Questions