(HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc....
Transcript of (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc....
![Page 1: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/1.jpg)
HTGR APPLICATION FOR SHALE OIL RECOVERY
R. N. Quade and R. Rao
GA Technologies Inc.
P. 0. Box 85608
San Diego, CA 92138
ABSTRACT
The High-Temperature Gas-Cooled Reactor (HTGR)
utilizes a graphite-moderated core and helium as pri
mary coolant. Developed for electric power produc
tion, the 842-MW(t) [330-MW(e)] Fort St. Vrain plant
is currently operating at Platteville, Colorado.
Studies have been performed that couple steam pro
duced at 540C (1000F) and 17 MPa (2500 psia) to two
oil shale processes: the Paraho indirect retorting
and the Marathon direct steam retorting. The plant,
consisting of two 1170-MW(t) HTGR's, would also pro
duce electric power for other shale operations.
Results show economic and environmental advantages
for the coupling.
INTRODUCTION
The HTGR is an advanced, high-efficiency reactor
system that can play a vital role in meeting the
future energy needs of the nation by contributing not
only to the generation of electric power but also to
the industrial and commercial energy sectors tradi
tionally served by fossil fuels.
Designed and developed by GA Technologies Inc. ,
the HTGR is a refinement of the gas-cooled reactor
approach developed in Europe beginning in 1956.
Thirty-nine gas-cooled reactors in eight countries
have accumulated operating experience that accounts
for a quarter of worldwide nuclear-generated elec
tricity. While these reactors differ in many
respects from the HTGR, they have proved thegas-
cooling concept as well as major components similar
to those used in the HTGR.
In the U.S., the 40-MW(e) Peach Bottom 1 proto
type reactor successfully demonstrated the basic
characteristics of the HTGR with over seven years of
commercial operation on the system of Philadelphia
Electric (1967-1974) (Ref. 1). The 330-MW(e) Fort
St. Vrain demonstration reactor at Platteville, Colo
rado, 35 miles northwest of Denver, has been generat
ing electric power on the Public Service of Colorado
system since 1976. In November 1981 it achieved suc
cessful full-power operation with all plant systems
and components performing at or near design condi
tions. This reactor produces steam at 538C (1000F)
and 17 MPa (2500 psia) with reheat to 538C (1000F)
and 4 MPa (600 psia) (Ref. 2). Based upon the fea
tures of the Fort St. Vrain design, larger plants for
electric power production were designed. More
recently other applications where electricity is not
the prime product have been examined. In many of
these areas,the light water reactors cannot compete
because they cannot provide energy at the required
temperature.
Most energy-intensive industrial processes
require considerable process steam and electric
power. Cogeneration of electric power and process
steam is an advantageous blending of twowell-
developed technologies, with a resultant increase in
overall energy utilization. The cogenerating HTGR
steam cycle system (HTGR-SC/C) is well suited to per
form this service.
The energy requirements for a complete inte
grated oil shale facility include heat to retort the
shale, hydrogen to upgrade the kerogen, and steam and
electricity for overall plant operation. The higher-
temperature process heat version of the HTGR can pro
vide all of these functions, but it must be recog
nized that considerable development effort will be
required before commercial versions of this system
can be offered. Another paper presented at this con
ference (Ref. 3) discusses a method of coupling the
process heat HTGR to an oil shale facility.
This paper shows how the steam cycle HTGR can be
used with an indirect retorting process and a direct
steam retorting process. If there is large scale
expansion of the oil shale industry in the tri-state
area, large amounts of electricity will also be
needed. In addition to the process energy, the HTGR
can provide electricity for other oil shale opera
tions without adding fossil pollutants to the atmos
phere. This concept will add a very economical
source of electricity to power the industry while
minimizing the on-site use of product fuel.
HTGR DESCRIPTION
To maximize the advantage of scale while also
325
![Page 2: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/2.jpg)
providing a range of plant sizes, a modular design
approach has been adopted for the HTGR-SC/C. An
1170-MW(t) plant has two steam generator/helium cir
culator loops, a 2240-MW(t) plant has four loops, and
a 3360-MW(t) plant has six loops.
The arrangement of an HTGR is shown in Figure 1.
The helium coolant flows downward through the central
core region, where it is heated to about 700C
(1290F). It passes radially outward to the primary
loop lower cross ducts and then flows through the
once-through steam generators, each consisting of a
helical coil economizer-evaporator-superheater region
and a straight tube superheater, where 17.3 MPa,
541C (2515 psia, 1005F) steam is produced. The gas
then is compressed in vertically mounted,single-
stage centrifugal circulators driven by synchronous
variable speed electric motors and returned through
the primary loop upper cross ducts to the inlet
plenum at about 320C (608F).
LINEAR
PRESTRESSING
SYSTEM
CONTROL ROD DRIVE
AND REFUELING
PENETRATION
Fig. 1. 2240-MW(t) HTGR arrangement
The entire helium circuit is enclosed in a
thick-walled, multicavity pres tressed concrete reac
tor vessel (PCRV), which functions as the primary
containment and biological shielding for the reactor
core and primary coolant system. The PCRV is con
structed of high-strength reinforced concretepre-
stressed by linear and circumferential prestressing
systems. A separate core auxiliary cooling system
(CACS) with its own heat exchangers and helium circu
lators is also located in the PCRV wall. The PCRV
and ancillary systems are housed inside a reactor
containment building, which is a conventional steel-
lined reinforced concrete structure.
HTGR fuel is made up of tiny spheres of uranium
and thorium in the form of UCO and Th02, each of
which is coated with pyrolytic carbon and silicon
carbide, which serve to retain fission products.
These particles are mixed and cast into small com
pacts, which are sealed into fuel cavities running
vertically through prismatic hexagonal graphite fuel
elements. The active core consists of stacks of
graphite fuel elements with holes for coolant chan
nels, fuel rods, and control rods. More detailed
information on the HTGR can be found in Ref. 4.
Flexibility in the process steam temperature and
pressure conditions from an HTGR used in a cogenerat-
ing mode is provided by several possible combinations
of turbine arrangements. If medium-temperature,
medium-pressure steam is required for the process,
the steam from the HTGR can be expanded through a
topping turbine and then sent to the process. If
more electricity is needed, some of steam can be
further expanded and condensed. If high-temperature
steam is needed for the process, steam can be taken
first to the process and then put through the turbine
for electric power production. Each coupling to oil
shale processes would involve a different balance of
plant arrangement, as described later.
APPLICATION OF HTGR TO OIL SHALE PROCESSES
Although many oil shale processes are under
development, evaluation of the state-of-the-art can
didates has shown two types that are suitable for
coupling to a steam cycle HTGR. One is the indirect
retorting process, such as Paraho, Union B, Petrosix,
or Superior, where heat is transferred to a recycle
gas that is used to directly contact and pyrolyze the
shale. The steam temperature normally provided by
the HTGR [538C (1000F)] is lower than current recy
cle gas temperatures, and some modification to the
retort kinetics would be expected. The second type
of process is direct contact with shale where steam
is the heating medium. In this case retort kinetics
are not compromised since retorting temperatures of
482C (900F) can be realized. With the help of
process developers, studies have been performed by GA
Technologies that investigate technical coupling,
economic comparisons, and environmental effects for
the two types of processes. For these studies the
Paraho indirect and Marathon steam retorting proc
esses were chosen as representative. The studies
326
![Page 3: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/3.jpg)
assume that upgrading of the kerogen to syncrude will
take place at the oil shale site by hydrogen addi
tion. Hydrogen for this upgrading would be produced
by steam methane reforming of the product off -gas.
The energy for this reforming is assumed to come from
product oil or gas. The actual development in the
tri-state area may show that the kerogen upgrading
function should be centralized, perhaps a long dis
tance from the site. In this case, all the onsite
energy could be supplied by the steam cycle HTGR,
with a resulting decrease in site environmental
effects.
HTGR INTEGRATION WITH SELECTED SHALE RETORTING
PROCESSES
Indirect Shale Retorting with Hot Recycle Gas
In the indirect shale retorting process as
developed by Paraho Development Corporation (Ref. 5),
hot recycle gas is used to pyrolyze the shale. The
recycle gas is circulated in a closed loop. The gas
is heated in a gas heater or heat exchanger by an
external heat source, or in the case of an HTGR-SC/C
plant by its steam to approximately 510C (950F).
During pyrolysis, the kerogen within the oil shale
decomposes into shale oil. At the same time, large
quantities of hydrocarbon-rich off-gases are liber
ated. As the gases ascend in the retort vessel, the
moving bed of crushed shale flowing downward is con
tacted and gets preheated before reaching the retort
zone in the vessel. The retort off-gas, containing
entrained oil mist, flows from the top of the retort
and passes through the oil recovery system. The oil
recovery system consists of a coalescer for initial
recovery, an electrostatic precipitator for second
stage recovery, and a knock-out drum at the recycle
gas compressor discharge for removal of heavy oil
carry-over.
Figure 2 shows the overall process plant
arrangement for a commercial operation of the indi
rect shale retorting, including recycle gas heating
by HTGR steam and crude shale oil upgrading. The
shale feed rate for the commercial operation was
selected to match the use of an 1170-MW(t) HTGR-SC/C
plant. Approximately 2.72 x106 kg/h (72,000 T/D) of
sized shale enters 10 parallel trains of indirect
heated retorts. Each retort is a refractory-lined
vertical kiln that acts as a countercurrentgas-
to-solids heat exchanger. Hot recycle gas is circu
lated at a rate of 1.2 x106
m3/h (42.56 x106
SCFH)
and at a pressure/temperature of 0.10 MPa (15 psia)/
510C (950F) in each retort.
SHALE
FINES
MINING
86,320 kg/h
(190,300 LB/HR)
240MW(e) PROCESS STEAM
PLANT POWER ,
C02VENT
2.86 MMkg/h (75,604 T/D)
SECONDARY
CRUSHING.
SCREENING,AND STORAGE
2.72 MMkg/h
(71,867 T/D)
INDIRECT
HEATED
RETORTS
(10)
510C
(950F)
2.32 MMkg/h
(61,490 T/D)
SPENT
SHALE
DISPOSAL
FUEL GAS
0.47 MMm3/d (16.74 MMSCFD)
VENT
CLAUS SULFUR
PLANT AND
TAIL GAS
CLEANUP
SULFUR
AMMONIA
STRETF0RD
SULFUR
RECOVERY
SULFUR
Fig. 2. Process block diagram for a commercial shale surface retorting operation with 510C (950F)
recycle gas using an 1170-MW(t) HTGR-SC/C plant
327
![Page 4: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/4.jpg)
About 99% of the oil in gas is recovered to
yield approximately 6680 m3/d (42,000 B/D) of crude
shale oil. The Fischer Assay characteristics of the
shale pyrolysis depend on the retort operating param
eters, and for the selected pressure/ temperature
parameters in the present indirect process, a Fischer
Assay value of approximately 87% was estimated. The
upgrading facilities included a product gas cleanup
system, a hydrogen production plant, and ahydro-
treater. Acid gases, such as CO2 and H2S, were
stripped from the off-gases, and a portion of the
resulting product gas was used as feed to the hydro
gen plant and the balance as high-Btu fuel gas.
Hydrotreating of the synthetic crude removes nitro
gen, sulfur, and oxygen by turning them into ammonia,
hydrogen sulfide, and water, respectively.
The energy demand at various stages of the com
mercial indirect shale retorting process is shown in
Table 1. The single largest energy demand occurs in
the retorting phase. Figure 3 shows thetemperature-
heat diagram for the indirect shale retorting process
using recycle gas. The HTGR-SC/C plant can supply
all the process thermal and electrical energy
requirements except for the hydrogen (H2) production
plant. The H2 plant requires energy at a higher tem
perature [>538C (1000F)], and therefore it is sup
plied by product oil and gas. The 1170-MW(t)HTGR-
SC/C provides about 66% of the process thermal energy
demand and 100% of the process electric power demand.
TABLE 1
ENERGY REQUIREMENTS FOR SHALE RETORTING OPERATIONS
6,680 m3/d 7,950 m3/d
(42,000 B/D) (50,000 B/D)
Crude Crude
Indirect Gas Direct Steam
Retorting Retorting
Shale retorting, MW(t) 320 372
Process steam, MW(t) 64 67
Hydrotreater, MW(t) 10 13
Hydrogen plant, MW(t) 204(a) 205<a)
Process electric power, 157 241
MW(e)
(^Energy is required at high temperature [>538C
(>1000F)] and is supplied by product oil and gas.
Figure 4 shows the integration of an 1170-MW(t)
HTGR-SC/C plant with a commercial 6680 m3/d (42,000
B/D) indirect shale retorting operation. About 75%
of the primary steam exiting the HTGR-SC/C plant is
used for heating the recycle gas and is then expanded
through power turbines, cogenerating electric power.
PROCESS HEAT LOAD [MW]
Fig. 3. Temperature versus heat load diagram for
direct and indirect shale retorting
operations
The remaining 25% of the primary steam is expanded
through a condensing turbine-generator unit to
enhance electric power production.
Also shown in Figure 4 is the extraction of 24
kg/s (192,100 lb/hr) of steam at 1.1 MPa (160 psi)
from turbogenerator T-G 2 for process use.Addition-
ally, some steam from the heat exchanger HX 2 outlet
is used in the hydrotreating process, having a heat
load of 10.3 MW(t), to heat fluid from 368C to 396C
(695F to 745F).
An 1170-MW(t) variable cogeneration HTGR plant
was added as a backup power plant. A backup power
plant is required since the process plant annual
capacity requirement (90%) is higher than the design
capacity factor (80%) of the HTGR-SC/C plant. The
variable cogeneration HTGR can function either as the
base HTGR-SC/C plant or as a full electric plant by
the use of its turbogenerator units. The variable
cogeneration HTGR plant has a capacity factor of 75%
in an all-electric mode. As a backup, it functions
as a steam cycle/cogeneration plant for 10% capacity.
For the remaining 65% capacity, it operates as an
electric plant, generating a net 428 MW(e). Figure 5
schematically shows the operation of the two HTGR
plants relative to the process plant energy demand.
Figure 5 also includes a table showing the salable
electric power from the two HTGR plants at various
process plant operating periods. The salable elec
tric power can be classified as "firmpower"
and
credited accordingly (see Economics Section) if this
power is made available for sale for a minimum of 75%
of a specified period (usually one year); otherwise
it will be considered as "non-firmpower."
328
![Page 5: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/5.jpg)
? 0.10 (15) P | TO RETORT
510 (950)T
HX2
HX1
0.1 (15) P
138 (280) T
1.21 x10em3/h (42.56 x10bSCFH)
RECYCLE GAS
ALLOCATION OF REACTOR POWER OUTPUT MW %
PROCESS USES
STEAM POWER TO PROCESS 394 34
ELECTRIC POWER 157 13
AUX POWER 35 3
OTHER USES
ELECTRIC POWER 83 7
LOSSES 501 43
TOTAL REACTOR POWER OUTPUT 1170 100
LEGEND
W = FLOWKG/SUO6
LB/HR)
P = PRESSURE MPa (PSIA)
T = TEMPERATURE C (F)
Fig. 4. Integration of an 1170-MW(t) HTGR-SC/C plant with a commercial indirect shale retorting
operation using recycle gas
i
345
LE
MWe
SA83
MWe
83<
MWe
i 157
MWe
394
MWt
PROl ESSPROC
HEAT
+
STEAM
204
MWt
H2PLANT
rV11 70 MWt HTGR
VARIABLE COGEN. PLANT(NON-FIRM)
NBACKUP (UNIT 2)
(FIRM)
FN
1170 MWt HTGR-SC/C
UNIT1
V
1170
MWt
HTGR
BACK
UP
(UNIT 2)
ENERGY SUPPLIED BY PROD OIL + PROD GAS
LNr50 60 70 80
90*
100
DUTY CYCLE (%)
(#PROCESS PLANT REQUIREMENT)
HTGR CAPACITIES
0-65% 65%-80% 80%-90%
DUTY CYCLE,%'
BASE HTGR-SC/C PLANT, MWt
BACKUP HTGR PLANT, MWt
ELECTRIC POWER FOR SALE
65
1170
1170
511
15
1170
83
10
1170
83
Fig. 5. Operation of two 1170-MW(t) HTGR plants for
a commercial indirect shale retorting plant
DIRECT SHALE RETORTING PROCESS WITH SUPERHEATED STEAM
In the direct shale retorting process with
superheated steam, shale is pyrolyzed in a vertical
kiln by passing superheated steam vapor at superfic
ial velocities ranging from 0.50 to 1.0 m/s (100 to
200 ft/min) and at a temperature of 510C (950F) or
higher. This process was developed by the Marathon
Oil Company (Research Division) of Denver, Colorado.
In the upper portion of the retort vessel where the
feed enters,shale is preheated by contact with a mix
of ascending hot steam and gases. The retorting
steam and off-gases released carry the shale oil mist
from the retort. Fischer Assay values in excess of
100% are predicted in the direct shale retorting
process with superheated steam and with several com
binations of pressure/ temperature parameters
(Ref. 6). Figure 6 shows the process arrangement for
commercial direct steam retorting of shale. The lib
erated off-gases and steam carrying droplets of shale
oil flow through an evaporator/condenser unit in
which steam is condensed. The condensate (water) is
then separated from oil and is circulated as the
cooling medium in the evaporator. The evaporator
exit steam (dry, saturated) is compressed to the
desired pressure by a steam compressor for injection
into the retort prior to heating by the HTGR steam.
The off -gases, after treatment and cleanup, are used
329
![Page 6: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/6.jpg)
as fuel gases in a hydrogen plant and partially as
feed in the hydrogen plant.
Approximately 2.66 MMkg/h (70,000 T/D) of sized
shale is retorted in 10 parallel retorts. A total of
53 kg/s (422,400 lb/hr) of superheated steam vapor
required for retorting the shale is injected into the
retorting zone of each unit at a relatively low pres
sure [0.17 MPa (25 psia)]. The steam exiting the
evaporator/ condenser unit is heated to the required
temperature [513C (955F)] by the high-temperature
steam from the HTGR plant via heat exchangers.
The shale oil upgrading facilities are similar
to those employed in the indirect shale retorting
process described earlier. About 8590 m3/d (54,030
B/D) of hydrogenated shale oil is estimated as the
gross plant yield from the upgrading plant.
Table 1 shows the process energy demand at vari
ous stages of the commercial direct steam shale
retorting operation. As in the indirect process, the
single largest energy demand occurs in the shale
retorting phase. The increased electric power demand
occurs in the direct retorting process owing to the
requirement of considerable steam compressive power
[-96 MW(e)].
The integration of the 1170-MW(t) HTGR-SC/C
plant with the direct shale retorting process is very
similar to that described earlier for the indirect
retorting process with the exception that all the
primary HTGR steam is circulated through heat
exchanger HX 2 for heating the low-pressure retorting
steam, thus eliminating the additional HP/LP turbo
generators. Table 2 shows the HTGR-SC/C plant heat
balance from the direct steam retorting operation.
TABLE 2
1170-MW(t) HTGR-SC/C PLANT HEAT BALANCE FOR A
7,950 m3/d (50,000 B/D) CRUDE SHALE OIL PLANT USING
DIRECT STEAM RETORTING
Allocation of Reactor Power Output MW %
Process uses
Steam power to process 432 37
Electric power 222 19
Condenser/ losses 516 44
Total reactor power output 1170 100
One 1170-MW(t) HTGR-SC/C plant is suited for the
8590 m3/d (54,030 B/D) direct shale retorting process
with steam. The HTGR-SC/C plant primary steam, which
is delivered at 17.3 MPa (2515 psia) and 540C
(1005F), provides the heat for the retorting steam
and for hydrotreating and also supplies steam at var
ious stages of the process. Surplus steam from the
HTGR-SC/C is expanded through power turbines ,
cogen-
erating electricity. In addition, the HTGR-SC/C
plant delivers 25 kg/s (202,000 lb/hr) of 1.1-MPa
(160-psia) saturated steam for the process.
Figure 3 shows the temperature-heat diagram for
P = 0.18(26)
T = 513(955)
W = 191,600(422,398)
P =
T '
W =
TO HTGR <H_
PLANT
W = 10,767 (23,737)
DATA SHOWN FOR ONE MODULE;
NO. OF MODULES: 10
GAS, OIL, AND
STEAM MIX
SHALE FEED
0.26 MM kg/h
(7000 T/D)
T = 25 (77)
0.19 (27)
189 (372)
191,600(422,398)9.6 MWe
P = 0.16 (23.2)
T = 113(235.5)
W = 215,347 (474,751) STEA
j -(C^) C\ fOFF-GAS 10,510 m3/h
\ ^y \ ( I (375,340)
RETORT
P = 0.09(12.5)
T = 96 (204)
P = 0.01 (14)
T = 51.6(125)
W = 204,579(451,014)
\J
SCFH
P = 0.21 (30)
T = 96 (204)
W = 23,747
(52,353)
SPENT
SHALE
P = 0.17(25)
T = 510 (950)
W = 23,747 (52,353)
BLOW
DOWN
?mum niunr
795 m3/d (5,000 B/D) RAW OIL
SPENT SHALE
0.23 MM kg/h (6010 T/D)
T = 149(300)
MAKE-UP
FROM HTGR PLANT
MAKE-UP (IF REQD)
LEGEND
P = MPa (PSIA)
T = C(F)
W = kg/h (LB/HR)
Fig. 6. Process arrangement for a 7950 m3/d (50,000 B/D) direct steam retorting of oil shale
330
![Page 7: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/7.jpg)
the direct shale retorting process with steam. As in
the indirect process, heat to the hydrogen production
plant is provided by product oil and gas. About 69%
of the process thermal energy requirement and 92% of
the electric power demand are provided by an1170-
MW(t) HTGR-SC/C plant.
For the same reasons stated for the indirect
process plant operation, an additional 1170-MW(t)
variable cogeneration plant was provided in the
direct steam retorting process as backup. Figure 7
shows the operation of the two 1170-MW(t) HTGR plants
relative to the process plant energy demand and the
salable electric power resulting from the backup HTGR
plant .
SALE408
MWe
MWe
452
MWt
PROC ;ss
PROC
HEAT
+
STEAM
205
MWt
H2PLANT
rNr
20
MWe
BACKUP 1170 MWt HTGR
VARIABLE COGEN.
HTGR PLANT (UNIT 2)
BASE 1170 MWt HTGR-SC/C
PLANT (UNIT 1)
Nr
BACK
UP
HTGR
PLANT
(UNIT 2)
ENERGY SUPPLIED BY PROD OIL + PROD GAS
LV
the energy plants covered the HTGR plant and the com
peting standard oil/gas-fired plant. The capital
costs included plant investment, engineering ser
vices, construction expenses, contingency, and work
ing capital. A preliminary capital cost was devel
oped based on such information as process flow dia
grams, major equipment sizes, in-house pricing for
process packages, budget prices based on similar pro
jects, and published cost data.
It was assumed that the HTGR was an"nth"
plant
and that commercial shale recovery operations in the
U.S. would be on-stream around the year 2005. A sum
mary of the financial assumptions and ground rules
used for the cost development and for subsequent eco
nomic analysis is shown in Table 3. Power plant cost
for the 1170-MW(t) HTGR-SC/C plant was developed by
GA Technologies in cooperation with United Engineers
and Constructors. Table 4 shows the capital costs of
HTGR power plant and process plants (direct and indi
rect processes). The standard indirect shale retort
ing process with hot recycle gas integrates a product
oil/gas-fired power plant to provide the process
thermal and electric power needs.
DUTY CYCLE (%)
(*PROCESS PLANT REQUIREMENT)
TABLE 3
SUMMARY OF FINANCIAL ASSUMPTIONS
HTGR CAPACITIES
0-65% 65%-80% 80%-90%
DUTY CYCLE, % 65 15 10
BASE HTGR-SC/C PLANT, MWt 1170 1170 -
BACKUP HTGR PLANT, MWt 1170 - 1170
ELECTRIC POWER
-SALE 408 - -
-PURCHASED- 20 20
Fig. 7. Operation of two 1170-MW(t) HTGR plants for
a commercial direct steam shale retorting
plant
CAPITAL COST AND ECONOMIC CONSIDERATIONS
Preliminary cost estimates of the process and
energy plants were made for the commercial direct and
indirect shale retorting operations. The process
plant cost estimates were based on an earlier study
performed by Davy McKee Engineers (Ref. 3) for GA
Technologies. Suitable allowances were made in the
base case equipment costs to reflect changes in shale
feed rate and crude oil processing rate in the
respective process. The capital costs developed for
Base data of all costs
Date of operation for all plants
Investment life for all plants, yr
Credit value for electric power,
mills/kW(e)-hr
2005 fuel cost projections, $/GJ($/106
Btu) (January 1983$)
Nuclear
Oil/gas
Common cost factors, %
Weighted cost of capital
Levelized fixed charge rate
(utility /industry)
Allowance for funds duringconstruction (utility/industry)
Real escalation rates, %
General
Electric power
Natural gas/oil
Mined shale
(a)Sale - firm.
(b)purchased.
(c)Sale -
nonfirm.
January 1983
January 2005
30
53(a), 84(b)]
33(c)
1.30 (1.37)
8.82 (9.30)
5.4
8.3/13.7
4.4/8.5
0.0
0.5(a,b)/i.o(c)
1.5
2.0
331
![Page 8: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/8.jpg)
TABLE 4
ECONOMIC ANALYSIS FOR DIRECT AND INDIRECT
RETORTING OF OIL SHALE
Standi
Indirect
Retort:
ltd
Shale
Ing
Assist
Indirect
Retort:
ted
Shale
Ing
Assisted
Direct Shale
Retorting
Plane Parameters
Input
Shale feed, MMkg/h (T/D) 2.46 (65 ,600) 2.72 (71 ,900) 2.65 (70,000)
Energy plant, MW(t) 1155 2 x 1170 2 x 1170
Output
Product/3) MMBBL/yr 10.238 14.578 16.836
Salable electric power 511(b) 408(b)
Process thermal efficiency, X 60 59 67
Capital Cost
Energy plants 174 2023 2036
Process plant 1637 1749 1880
Total Capital Requirement 1811 3772 3916
Annual Cost (1983 MM$, 30-yr
Levelized)
Fixed
Energy plant (utility rate) 15 172 173
Process plant (industry rate]1 224 240 258
Fuel (nuclear) 74 74
Scarcity of mined shale 127 139 135
O&M
Energy 7 64 64
Process 168 182 182
Electric power (credit) ~
(137) (83)
Total Annual Cost 541 734 803
Product Cost, S/B (1983$) 52.84
fuel use.
rtions.
50.35 47.70
(a'Net output excluding process i
'"'Includes firm and non-firm poi
The economic analysis was performed using the
revenue requirement method. The revenue requirement
method (Ref. 7) is commonly accepted by the electric
utility industry for evaluating long-lived power
plant projects, and it determines the revenue needed
by the owner as compensation for all expenditures
fixed and variable. Hence, the revenue requirements
of the owner are the costs to the consumer of the
process steam cogenerated. Base year capital costs
are escalated through plant construction, and inter
est during construction is added to arrive at a total
capital cost in constant base year (1983) dollars. A
fixed charge rate is applied to the total capital
cost to arrive at an annual fixed charge to which are
added the levelized annual fuel costs, levelized ann
ual operation and maintenance (O&M) costs, and a cre
dit for the levelized value of cogenerated power to
arrive at a total levelized annual cost.
Table 4 also shows the economic results of the
direct and indirect shale retorting operations in
constant 1983 dollars. A 30-year levelization per
iod, commensurate with the plant life, was assumed.
For comparison, the economic results of the standard
indirect shale retorting process using oil/gas as
fuel are included in Table 4. In the standard indi
rect retorting process, approximately one-third of
the produced oil is consumed as fuel. The annual
shale oil output shown in Table 4 is the net after
accounting for the in-house use of the product oil as
fuel. The annual cost shown in Table 4 includes a
levelized charge due to progressively higher mining
costs associated with the thinning of the shale seams
in the mine and the greater difficulty involved in
mining. The standard indirect process has a higher
product price (S52.84/B) than either of the two HTGR
assisted processes because of its considerably lower
net product output. The HTGR assisted direct steam
shale retorting process has an 11% economic advantage
and the HTGR assisted indirect retorting process has
a 5% economic edge over the standard indirect shale
retorting process based on product price. The HTGR
assisted indirect process has a lower process plant
cost (7%) and has increased revenues (65%) from the
sale of electric power as compared with the direct
retorting process. The HTGR-SC/C backup plants were
found to be economically advantageous over the
oil/gas-fired backup plants because of lower nuclear
fuel cost and additional revenues from surplus elec
tric power sale.
The development of the shale industry primarily
depends on other competing liquid fuels under devel
opment and, in particular, the world oil price.
Assuming a current (1983) world oil price of $30/B
and a real escalation rate of 1.5% per year (see
Table 3), the world oil price is estimated as $49/B
in the year 2005 (30-year levelized). Therefore, in
order for the shale oil to be competitive in the year
2005 and beyond and for the shale industry, in gen
eral, to receive any encouraging signs for continued
development, the projected real escalation rate for
the conventional oil would have to be in excess of
1.55 per year.
ENVIRONMENTAL CONSIDERATIONS
The environmental effluents from a commercial
surface shale retorting operation primarily extend to
three areas: air, water, and solid waste. Both
state and federal guidelines or regulations must be
satisfied In order to secure the operating permits.
At present, there are no federal emission standards
specifically covering oil shale production. However,
the State of Colorado has enacted some regulations on
air emissions directed to the shale oil industry
(Ref. 5). One requires commercial operations [pro
ducing more than 6.7 m3/h (1000 B/D)] to restrict
332
![Page 9: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/9.jpg)
themselves to 0.85 kgS02/m3 (0.3 lb SO2/BBL) of oil
production plus an equal amount of the refining oper
ation. Similarly, hydrogen sulfide emission is lim
ited to 10 ppm based on a 1-hour average ambient air
concentration. The major source of sulfur dioxide
(SO2), nitrogen oxides (N0X), and carbon monoxide
(CO) will be fuel combustion for process heat, pre
dominantly at the reforming furnace. SO2 will also
be emitted in the sulfur recovery and tailgas cleanup
operations. Particulate matter emissions will occur
from fuel combustion, raw and spent shale dust in
process streams, raw and spent shale handling and
disposal, mining and blasting, and other site activi
ties that generate fugitive dust.
Table 5 presents an overall emission summary for
three commercial shale operations: (1) the standard
indirect shale retorting process using gas/oil fuels,
(2) the HTGR-SC/C assisted indirect shale retorting
process, and (3) HTGR-SC/C assisted direct steam
retorting of oil shale. Substantial reductions in
SO2 and N0X emissions occur in HTGR-SC/C assisted
shale operations, since the use of the prime source
of these effluents, i.e., oil and gas fuel, is mini
mized. The commercial oil shale plant may be assumed
to be located in an "attainmentarea,"
meaning that
the air quality is cleaner than defined by National
Ambient Air Quality Standards. Otherwise, regulatory
requirements will be applied to the allowable emis
sions.
TABLE 5
AIR EMISSION SUMMARY FOR THREE COMMERCIAL SHALE
RETORTING OPERATIONS [kg/h (lb/day) J
Standard
Indirect
Recycle Gas
Retorting2.46 x
106kg/h
(65,600 T/D)
Indirect
Recycle
Gas Retorting(HTGR-SC/C
Assisted)
2.72 x106 kg/h
(71,900 T/D)
Direct Steam
Gas Retorting(HTGR-SC/C
Assisted)
2.65 x106 kg/h
(70,000 T/D)
Particulates 102 (5,434) 78 (4,130) 77 (4,077)
S02 38 (2,071) 26 (1,400) 26 (1,400)
N0X 424 (22,880) 226 (11,970) 224 (11,864)
HC 64 (3,470) 62 (3,266) 73 (3,846)
CO 1,346 (72,680) 1,329 (71,757) 1,600 (86,390)
C02 0.3 x106
(17 x 106)
0.2 x106
(12.4 x 106)
0.2 x106
(12.4 x 106)
H2S 4.0 (212.0) 4.4 (233.0) 4.2 (222.0)
of a standard fossil plant nearly halves the overall
emission with on-site crude upgrading included. A
further reduction of approximately 30% in the emis
sion occurs if on-site upgrading is excluded. The
emission of N0X is a major contribution to the
environment from a surface shale retorting process.
Based on environmental considerations, contami
nated wastewater streams from shale surface retorting
facilities could have access to aquifers and ground
water, resulting in fouling. The USEPA has estab
lished national effluent limitations on what a point
source can discharge into the aquifers or ground
water.
PARTICULATES
_
,75X1B5
PARTICULATES
^1
i| |PAIPARTICULATES
STANDARD
INDIRECT -
FOSSIL FUEL
(WITH UPGRADING)
INDIRECT -
HTGR-SC/C
ASSISTED
(WITH UPGRADING)
INDIRECT -
HTGR - SC/C
ASSISTED
(WITHOUT UPGRADING)
Fig. 8. Air emission comparison for a 7950 m3/d
(50,000 B/D net) surface shale oil recoverywith fossil and nuclear fuels
Solid waste disposal from oil shale processing
presents one of the major problems associated with
commercial development of the oil shale industry.
The predominant source of solid waste will be shale-
derived, including spent shale, raw shale fines, and
mined raw shale. At present, no solid waste result
ing from shale surface retorting facilities has been
classified as hazardous by federal or state agencies.
However, the management of solid waste disposal will
need to incorporate the preparation of the disposal
site, transport of the waste, and assurance of the
stability of the waste pile.
Table 6 shows the environmental effluents-
gaseous, solid and liquid - from an 1170-MW(t) HTGR-
SC/C plant. These effluents are within the limits
set by the Nuclear Regulatory Commission.
Figure 8 schematically shows the impact of over
all air emission from a large commercial indirect
shale retorting process using hot recycle gas and
energy provided by a fossil plant and a 1170-MW(t)
HTGR-SC/C plant. Use of an HTGR-SC/C plant in place
CONCLUSIONS
1. The HTGR has an excellent technical fit with many
of the oil shale processes, since the temperature
capability of the reactor is high enough to
retort oil shale.
333
![Page 10: (HTGR) [330-MW(e)]€¦ · HTGRAPPLICATIONFORSHALEOILRECOVERY R.N. QuadeandR.Rao GATechnologiesInc. P.0.Box85608 SanDiego,CA 92138 ABSTRACT TheHigh-TemperatureGas-CooledReactor(HTGR](https://reader034.fdocuments.in/reader034/viewer/2022042209/5ead7d43e997f37a39150759/html5/thumbnails/10.jpg)
TABLE 6
ENVIRONMENTAL EFFLUENTS FROM AN 1170-MW(t) HTGR PLANT
Air emissions
Noble gases, Ci/yr
Iodine and particulates, Ci/yr
Solid wastes
Miscellaneous radioactive material,
Ci/yr
Liquid effluents
Mixed fission products (no
tritium), Ci/yr
99(a)
0.01
7570(b)
0.0021
(^Includes 0.09 Ci/yr of tritium.
^"'Includes tritium contained in solidifiedhigh-
specific-activity liquids.
2. The current steam cycle HTGR design based upon
the Fort St. Vrain reactor at Platteville can
produce retorting heat and plant energy for some
processes. In addition, it can provide economic
electricity for any oil shale process in the wes
tern Colorado-Utah area as early as 1995. Elec
tricity costs are estimated at 50 mills/kW-hr for
firm power and 30 mills /kW-hr for interruptible
power for 1995 startup (1983 dollars).
3. The HTGR versions can provide large environmental
benefits in terms of reduced air pollution in the
tri-state area. With on-site upgrading, approxi
mate reductions of 32% in SO2 emissions, 47% in
N0X, and 24% in particulates could be achieved.
4. Firm economic comparisons are difficult to make
at this time. Nuclear energy is at least compet
itive with other options. Depending on the value
of the salable electricity and the market value
of the displaced oil, there may be considerable
savings over the long term associated with the
nuclear option.
5. The application of the HTGR as an energy source
conserves the shale resource and enhances shale
oil production in the western U.S.
ACKNOWLEDGMENT
This work was supported by the U.S. Department
of Energy under Contract DE-AT03-76SF70046.
REFERENCES
1. Birely, W. C, "Operating Experience of the Peach
Bottom PowerStation,"
Nuclear Engineering and
Design, 26, 9-15, (1974).
2. Brey, H. L. ,and W. A. Graul, "Operation of the
Fort St. Vrain High-Temperature Gas-Cooled Reac
torPlant,"
Proceedings of the American Power
Conference, Vol. 44, 1982, pp. 795-800.
3. Wadekamper, D. C, et al., "Application of the
High Temperature Gas Cooled Reactor to Oil Shale
Recovery,"
General Electric Company, Sunnyvale,
California.
4. Boland, C. R.,et al.
,"The High-Temperature Gas-
Cooled Reactor - A Needed Option for Future
EnergyRequirements,"
Second Joint ASME/ANS
Nuclear Engineering Conference, July 26-28, 1982,
Portland, Oregon.
5. "Paraho Retorting of Oil Shale Using a Very High
TemperatureReactor,"
Davy McKee Engineers and
Constructors.
334