HSE Standars for Pipeline Construction Onshore WILI
-
Upload
ghazi-kallel -
Category
Documents
-
view
14 -
download
0
description
Transcript of HSE Standars for Pipeline Construction Onshore WILI
-
Doc No. HSE-S011-400-00 Page 1 of 8
0.1.1.1
C96 & C97 Document No. HSE-S011-400
HSE Standards for Pipeline Construction, onshore Libya
DOCUMENT PURPOSE
This procedure defines minimum standards to be applied in pipeline construction in order to limit the extent of obstacles on the ground surface, and the associated risk to personnel in vehicles travelling in or around the construction site, and to define suitable warnings and crossing points.
DOCUMENT REVISION HISTORY
Rev. No. Date Reason for Revision By Review Sign
A1 First draft Issued for comment HSEC
A2 09.03.06 Formatted and issued to EP for comment HSEM
00 19.04.06 First Issue HSEM
This procedure must be reviewed every year Date of next review: April 2007
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 2 of 8
1 Preparation
It is essential that the following HSE standards are communicated to potential
contractors at the earliest stage of the tendering process. The work flow for pipeline
construction and the required safety equipment all have a cost impact which must be
accurately reflected in any bid.
The Wintershall-Libya HSE Department must be represented in any negotiation with
the contractor over the scope of the construction project, either before award of
contract or after, if such negotiations could possibly impact the implementation of these
HSE standards or alter the HSE risk.
2 HSE Concerns
Trenching, the lay-out of equipment and materials, including the stringing of the
pipeline, represent a significant risk to persons driving across the route of the pipeline.
Construction and material planning should always being organized so that the size of
the construction site is minimized. The site should be adequately marked with
warning signs for both day and night and conditions of poor visibility.
Crossing points (road, sand track, pipelines) needs special set ups. The frequency and
setup of crossing points should be risk assessed for each pipeline construction. This
may involve consultation and negotiation with the community and other companies.
3 Procedure
The following minimum standards shall be applied.
Beginning / End of Site
If the construction comes close to a road, a minimum distance has to be fixed on
location. At the end position, additional floodlights need to be installed and drums have
to be used to form a funnel, (see Figure 1.).
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 3 of 8
Figure 1. Site end position close to existing sand road (Drum-way)
Sand road with Drum- way markers
Minimum Distance needs to be fixed on location
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 4 of 8
Road / Drumway and Track Crossings
Any route crossings need to be constructed in one day and need to be ready before
darkness. Routes include established roads (black-top, caliche, oil-sand), marked
drumways, and tracks without special markers but recognised as frequented routes.
Route Deviations
Deviations from the normal vehicle route have to be marked with drums, with additional
floodlights at the closing points from each direction. Behind the floodlight, a higher
bund wall has to be installed (min. 1 m). Figure 2. shows the set-up for a right-angle
crossing. The same precautions must be used for other geometries of crossings, but
with an adjusted layout.
Figure 2. Marking of deviations from existing vehicle routes.
Additional bund wall
Additional bund wall
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 5 of 8
Site Length and Marking
Depending on the expected third party vehicle movements in the area of construction,
there are two general possibilities. The more stringent control (option A, or standards
exceeding the requirements of option A) should be in place where indicated by the
project specific risk assessment.
Option A) Maximum length of whole construction site not to exceed 4 km
A.1) Maximum length between first wooden blocks and refilling is 4 km,
A.2) At a minimum distance of 10 m each side of the pipe / trench, a 0.6 m high sand
bund wall shall be constructed. A second (outer) sand bund wall of 0.4 m high to be
constructed a further 15 m out from the first bund walls. In addition, red/white drums
with a warning X marked with reflecting tape fixed to the top of the drum (see Figure
3.) should be located close to the outer bund wall and at 100 m intervals (on both sides
of the construction site),
A.3) During darkness the complete length of the construction has to be lighted with
floodlights.
A.4) Each individual pipe joint is to be marked with longitudinally fixed reflecting tape of
approximately 8 mm width. This tape should be mounted at 120 degree intervals on the
circumference of the pipe so that it is visible from all sides (see Figure 5.).
Option B) No maximum length of whole construction site BUT following a risk assessment the site length should be as short as reasonably practicable.
B.1) Forward laying of non connected pipes and wooden blocks should not exceed the
foreseen welding progress of 2 days,
B.2) Crossing points have to be installed every 3 km and need to be equipped with
floodlights and construction lighting (see Figure 4.). Crossing points are to be kept
open while surface hazards remain (strung pipe, open trench, etc.),
B.3) At a minimum distance of 10 m each side of the pipe / trench, a 0.6 m high sand
bund wall shall be constructed. A second (outer) sand bund wall of 0.4 m high to be
constructed a further 15 m out from the first bund walls. In addition, red/white drums
with a warning X marked with reflecting tape fixed to the top of the drum (see Figure
3.) should be located close to the outer bund wall and at 100 m intervals (on both sides
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 6 of 8
of the construction site). A warning light (red or yellow, flashing or constant) shall be
secured to every fourth drum (400 m intervals).
B.4) Beginning and endpoint of the site to be secured with drums standing at 10 m
intervals. Area has to be lighted with floodlights during darkness.
B.5) Each individual pipe joint is to be marked with longitudinally fixed reflecting tape of
approximately 8 mm width. This tape should be mounted at 120 degree intervals on the
circumference of the pipe so that it is visible from all sides (see Figure 5.).
Figure 3. Drum and bund wall warnings.
100
Pic 1
10m
0.6m
min. 10m
Reflecting tape
15m
0.4m
15m
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 7 of 8
Figure 4. Design and spacing of crossing points.
Figure 5. Reflecting tape fixed to pipe.
8 mm
Front view of the pipe.
-
C96 & C97 HSE Standards for Pipeline Construction,
onshore Libya
Doc No. HSE-S011-400-00 Page 8 of 8
4 Reference Documents
All construction companies should familiarise themselves with Wintershall-Libyas
general HSE requirements for contractors.