HSE Standars for Pipeline Construction Onshore WILI

download HSE Standars for Pipeline Construction Onshore WILI

of 8

description

hse

Transcript of HSE Standars for Pipeline Construction Onshore WILI

  • Doc No. HSE-S011-400-00 Page 1 of 8

    0.1.1.1

    C96 & C97 Document No. HSE-S011-400

    HSE Standards for Pipeline Construction, onshore Libya

    DOCUMENT PURPOSE

    This procedure defines minimum standards to be applied in pipeline construction in order to limit the extent of obstacles on the ground surface, and the associated risk to personnel in vehicles travelling in or around the construction site, and to define suitable warnings and crossing points.

    DOCUMENT REVISION HISTORY

    Rev. No. Date Reason for Revision By Review Sign

    A1 First draft Issued for comment HSEC

    A2 09.03.06 Formatted and issued to EP for comment HSEM

    00 19.04.06 First Issue HSEM

    This procedure must be reviewed every year Date of next review: April 2007

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 2 of 8

    1 Preparation

    It is essential that the following HSE standards are communicated to potential

    contractors at the earliest stage of the tendering process. The work flow for pipeline

    construction and the required safety equipment all have a cost impact which must be

    accurately reflected in any bid.

    The Wintershall-Libya HSE Department must be represented in any negotiation with

    the contractor over the scope of the construction project, either before award of

    contract or after, if such negotiations could possibly impact the implementation of these

    HSE standards or alter the HSE risk.

    2 HSE Concerns

    Trenching, the lay-out of equipment and materials, including the stringing of the

    pipeline, represent a significant risk to persons driving across the route of the pipeline.

    Construction and material planning should always being organized so that the size of

    the construction site is minimized. The site should be adequately marked with

    warning signs for both day and night and conditions of poor visibility.

    Crossing points (road, sand track, pipelines) needs special set ups. The frequency and

    setup of crossing points should be risk assessed for each pipeline construction. This

    may involve consultation and negotiation with the community and other companies.

    3 Procedure

    The following minimum standards shall be applied.

    Beginning / End of Site

    If the construction comes close to a road, a minimum distance has to be fixed on

    location. At the end position, additional floodlights need to be installed and drums have

    to be used to form a funnel, (see Figure 1.).

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 3 of 8

    Figure 1. Site end position close to existing sand road (Drum-way)

    Sand road with Drum- way markers

    Minimum Distance needs to be fixed on location

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 4 of 8

    Road / Drumway and Track Crossings

    Any route crossings need to be constructed in one day and need to be ready before

    darkness. Routes include established roads (black-top, caliche, oil-sand), marked

    drumways, and tracks without special markers but recognised as frequented routes.

    Route Deviations

    Deviations from the normal vehicle route have to be marked with drums, with additional

    floodlights at the closing points from each direction. Behind the floodlight, a higher

    bund wall has to be installed (min. 1 m). Figure 2. shows the set-up for a right-angle

    crossing. The same precautions must be used for other geometries of crossings, but

    with an adjusted layout.

    Figure 2. Marking of deviations from existing vehicle routes.

    Additional bund wall

    Additional bund wall

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 5 of 8

    Site Length and Marking

    Depending on the expected third party vehicle movements in the area of construction,

    there are two general possibilities. The more stringent control (option A, or standards

    exceeding the requirements of option A) should be in place where indicated by the

    project specific risk assessment.

    Option A) Maximum length of whole construction site not to exceed 4 km

    A.1) Maximum length between first wooden blocks and refilling is 4 km,

    A.2) At a minimum distance of 10 m each side of the pipe / trench, a 0.6 m high sand

    bund wall shall be constructed. A second (outer) sand bund wall of 0.4 m high to be

    constructed a further 15 m out from the first bund walls. In addition, red/white drums

    with a warning X marked with reflecting tape fixed to the top of the drum (see Figure

    3.) should be located close to the outer bund wall and at 100 m intervals (on both sides

    of the construction site),

    A.3) During darkness the complete length of the construction has to be lighted with

    floodlights.

    A.4) Each individual pipe joint is to be marked with longitudinally fixed reflecting tape of

    approximately 8 mm width. This tape should be mounted at 120 degree intervals on the

    circumference of the pipe so that it is visible from all sides (see Figure 5.).

    Option B) No maximum length of whole construction site BUT following a risk assessment the site length should be as short as reasonably practicable.

    B.1) Forward laying of non connected pipes and wooden blocks should not exceed the

    foreseen welding progress of 2 days,

    B.2) Crossing points have to be installed every 3 km and need to be equipped with

    floodlights and construction lighting (see Figure 4.). Crossing points are to be kept

    open while surface hazards remain (strung pipe, open trench, etc.),

    B.3) At a minimum distance of 10 m each side of the pipe / trench, a 0.6 m high sand

    bund wall shall be constructed. A second (outer) sand bund wall of 0.4 m high to be

    constructed a further 15 m out from the first bund walls. In addition, red/white drums

    with a warning X marked with reflecting tape fixed to the top of the drum (see Figure

    3.) should be located close to the outer bund wall and at 100 m intervals (on both sides

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 6 of 8

    of the construction site). A warning light (red or yellow, flashing or constant) shall be

    secured to every fourth drum (400 m intervals).

    B.4) Beginning and endpoint of the site to be secured with drums standing at 10 m

    intervals. Area has to be lighted with floodlights during darkness.

    B.5) Each individual pipe joint is to be marked with longitudinally fixed reflecting tape of

    approximately 8 mm width. This tape should be mounted at 120 degree intervals on the

    circumference of the pipe so that it is visible from all sides (see Figure 5.).

    Figure 3. Drum and bund wall warnings.

    100

    Pic 1

    10m

    0.6m

    min. 10m

    Reflecting tape

    15m

    0.4m

    15m

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 7 of 8

    Figure 4. Design and spacing of crossing points.

    Figure 5. Reflecting tape fixed to pipe.

    8 mm

    Front view of the pipe.

  • C96 & C97 HSE Standards for Pipeline Construction,

    onshore Libya

    Doc No. HSE-S011-400-00 Page 8 of 8

    4 Reference Documents

    All construction companies should familiarise themselves with Wintershall-Libyas

    general HSE requirements for contractors.