HPS SummaryCosts, Manpower, Schedule

John Jaros Searching for a New Gauge Boson at JLab Jefferson Laboratory September 20, 2010

Page 2: HPS Summary Costs, Manpower, Schedule

In Summary• HPS Setup

HPS relies on a high rate, forward spectrometer, with good acceptance. Si microstrip detectors provide precision vertexing and tracking inside a 1 Tesla dipole. A PbWO4 crystal EM calorimeter provides fast triggering and electron ID. A muon detector provides a complementary trigger, and doubles the statistics at high mass.

September 20, 2010 2

Page 3: HPS Summary Costs, Manpower, Schedule

In Summary• 100 % CEBAF duty cycle, excellent beam quality,

plus >40 MHz readout capability gives HPS access to the high luminosity data sets needed to search for heavy photons.

• The Silicon Vertex Tracker will provide 1% x p (GeV/c) momentum and ~1mm vertex resolution, continuous readout, and 2ns timing capability.

• The PbWO4/Shashlyk Ecal will provide the trigger and electron ID using 250 MHz FADCs.

• DAQ can handle a 50kHz trigger rate, 250 MB/sec data transfer rate. It’s build on Jlab FADCs and SLAC ACTA SVT readout.

3September 20, 2010

Page 4: HPS Summary Costs, Manpower, Schedule

• GEANT4 Monte Carlo has been used to determine trigger rates and establish tracking and vertexing performance for physics events in the presence of full beam backgrounds.

• Detailed estimates of the HPS physics reach show:

HPS will search a unique small coupling region of heavy photon parameter space with unparalleled sensitivity, obtained by combining invariant mass and decay vertex information.

At the same time, using invariant mass information alone, HPS will explore the region of moderate couplings over the mass range 50-1000 MeV.

Sensitivity to decay vertices gives HPS the unique opportunity to discover “true muonium”.

In Summary

September 20, 2010 4

Page 5: HPS Summary Costs, Manpower, Schedule

So, What does it Cost?Costing Assumptions

• “Donations” lower the HPS cost Fermilab ~150 Hamamatsu Si microstrip detectors SLAC 18D36 H Magnet JLab PbWO4 crystals, magnets, power supplies, DAQ infrastructure, Data Storage Collaborators Engineering and design for Ecal and Muons

• Lab Indirects have been included in Labor Rates

• Contingencies have been included SLAC 30% Labor 35% M&S 10-15% Costed items

JLab 20% Labor 25% M&S 10-15% Costed items

• HPS makes use of ongoing Jlab R&D for 12 GeV Upgrade Detectors

Engineering Designs Needed

Many Systems Already Engineered

Page 6: HPS Summary Costs, Manpower, Schedule

Costing Methodology : HPS WBS

September 20, 2010 6

Page 7: HPS Summary Costs, Manpower, Schedule

Beamline

• Items√Chicane magnets and quads (J)√Magnet power supplies (J)√Analyzing magnet (S) Girders, BPMs, Harps, Correctors Support Stands Beam Pipes and Windows Refurbish Analyzing Magnet Power Cables Installation

• Engineering and Design .4 FTE• Technician 1.6 FTE

TOTAL $590k

September 20, 2010 7

Page 8: HPS Summary Costs, Manpower, Schedule

Silicon Vertex Tracker

• Items√Si microstrip sensors (F) Sensor modules CF Support Box Vacuum Chamber Readout Cables Power, Vacuum, Temp Systems

• Engineering and Design 0.6 FTE• Technician 0.7 FTE

TOTAL $830k

September 20, 2010 8

Page 9: HPS Summary Costs, Manpower, Schedule

ECal

• Items√PbWO4 crystals/APDs/amps (J)√Shashlyk towers or Pb Glass (J) PbWO4 Connection Board & Motherboards PMTs for Shashlyk or Pb Glass Cables and Connectors Temp Enclosure Box Vacuum Box Support Stand

• Engineering and Design* 1.0 FTE• Technician (fab and test) .25 FTE

TOTAL $260k

* Engineering and Design by JLab User.

September 20, 2010 9

Page 10: HPS Summary Costs, Manpower, Schedule

Muon System

• Items√HV supplies (J) Fe Absorber Scintillator and Fibers PMTs and dividers Cables and splitters Support Stand

• Engineering and Design* 1.0 FTE• Technician 0.1 FTE

TOTAL $180k

* Engineering and design by JLab User

September 20, 2010 10

Page 11: HPS Summary Costs, Manpower, Schedule

Ecal and Muon DAQ and Trigger• Items

√Discriminators, TDCs, and crates (J) FADCs Crate Trigger Processor Board Sub System Processor Board Trigger Interface Board Signal Distribution Board CPU Board VXS Crates Cables and Misc

• Engineering and Design 0.1 FTE• Technician 0.3 FTE

TOTAL $600k

September 20, 2010 11

Page 12: HPS Summary Costs, Manpower, Schedule

SVT DAQ

• Items Hybrid and APV25s Readout Board Trigger Interface Board ATCA Crate CPU Board Server

• Engineering and Design 0.9 FTE• Technician 0.6 FTE

TOTAL $650k

September 20, 2010 12

Page 13: HPS Summary Costs, Manpower, Schedule

Total Costs

Breakdown by Sub System $ JLab SLAC Beamline & Installation 590k 405k 185k Vertex Tracker 830k 0k 830k ECal 260k 260k 0k Muon 180k 180k 0k Ecal DAQ/Trigger 600k 600k 0k SVT DAQ 650k 0k 650k

TOTAL $3110k $1445k $1665k

September 20, 2010 13

Page 14: HPS Summary Costs, Manpower, Schedule

Total Manpower Breakdown

September 20, 2010 14

Note: This is the manpower breakdown assumed in the costing. We expecta much larger contribution from physicists and grad students in the actual construction, testing, and installation phases of the experiment.

In FTE years

Page 15: HPS Summary Costs, Manpower, Schedule

Schedule before ShutdownGoal: Take beam Spring 2012

Understand beam control, trigger rates, and occupancies. Test critical assumptions and Monte Carlo simulations. Have time, before the 12 GeV data taking, to react to surprises.

Steps:• 2011 Spring (during CLAS photon calibration and running)

Test FADCs and readout Test SVT detector module and readout

• 2011 Downtime (May-November, 2011) Install major beamline items: magnet, vac chambers

• Spring 2012 Complete beamline installation Install detectors Commission DAQ Commission beam, check quality and stability Test trigger and occupancy calculations, detector performance 1 Week Test Run

September 20, 2010 15

Page 16: HPS Summary Costs, Manpower, Schedule

Schedule after Shutdown• Downtime mid 2012-end 2013|

Remove HPS beamline for CLAS decommissioning and eventual re-installation Evaluate performance; React to surprises Analyze Test Run Data

• Major Data Taking in the 12 GeV Era. Detailed plan being developed. Re-install and re-commission HPS Take HPS data for ~3 months. Run at several energies to optimize reach and mass range. Take HPS true muonium data for ~1.5 months

September 20, 2010 16

Page 17: HPS Summary Costs, Manpower, Schedule

Conclusions

• Total HPS estimated cost $3.1M. Considerable savings from Fermilab donation, use of existing Jlab and SLAC apparatus, and engineering and design by collaborators.

• Goal is to install HPS in Spring 2012 for test run. Major datataking would take place in the 12 GeV era.

• Being ready in Spring 2012 is possible, but depends on funding being ready soon to begin ED&I on long leadtime items. Hybrid design, beamline design, vac chamber construction need keep alive funds ~now.

Major funding needed ~Jan 2012

September 20, 2010 17

Page 18: HPS Summary Costs, Manpower, Schedule

• Searching for heavy photons provides Jlab with an exciting and topical research program with the potential for fundamental discoveries.

• Heavy photon searches must be pursued aggressively if this potential is to be realized.

• HPS extends the search into a unique range of heavy photon parameter space with unparalleled sensitivity, exploiting both separated vertex and invariant mass signatures.

September 20, 2010 18