HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif...

74
HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power Generation Corporation Limited Urja Bhawan, Sector-6, Panchkula, Haryana

Transcript of HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif...

Page 1: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

HPGCL Tariff Petition for the FY 2012-13

November 30, 2011

Haryana Power Generation Corporation Limited

Urja Bhawan, Sector-6, Panchkula, Haryana

Page 2: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power
Page 3: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

1

Table of Contents

1. Background ______________________________________________________________________________ 4

1.1. Introduction _________________________________________________________________________ 4

1.2. Brief Company Profile _________________________________________________________________ 5

1.3. Key achievements of HPGCL: ____________________________________________________________ 6

2. Performance of HPGCL Stations over the years and current operational constraints ___________________ 9

2.1. Historical performance of HPGCL stations _________________________________________________ 9

2.2. Operational constraints of HPGCL Power plants ___________________________________________ 19

2.3. Coal transit loss ______________________________________________________________________ 26

2.4. R&M of HPGCL power plant: PTPS Panipat _______________________________________________ 34

2.5. Loss of Generation due to Backing Down _________________________________________________ 39

2.6. Force Majeure _______________________________________________________________________ 40

3. Submission ______________________________________________________________________________ 43

3.1. Brief of Submissions __________________________________________________________________ 43

3.2. Prayer _____________________________________________________________________________ 46

4. Projections of the Technical Parameters ______________________________________________________ 47

4.1. Plant Load Factor ____________________________________________________________________ 47

4.2. Plant Availability Factor (PAF) __________________________________________________________ 51

4.3. Station Heat Rate ____________________________________________________________________ 52

4.4. Auxiliary Consumption ________________________________________________________________ 59

4.5. Fuel Price and Calorific Value __________________________________________________________ 62

4.6. Specific Oil Consumption ______________________________________________________________ 62

4.7. Coal Transit Loss _____________________________________________________________________ 63

4.8. Moisture Loss: _______________________________________________________________________ 63

5. Estimated expenses for FY 2012-13 __________________________________________________________ 65

5.1. Return on Equity _____________________________________________________________________ 65

5.2. Income-tax _________________________________________________________________________ 65

5.3. Interest on Loan Capital and Finance Charges _____________________________________________ 65

Page 4: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

2

5.4. Depreciation ________________________________________________________________________ 66

5.5. Interest on Working Capital (IoWC) _____________________________________________________ 67

5.6. Operation and Maintenance Expenses ___________________________________________________ 67

6. Other Considerations ______________________________________________________________________ 70

6.1. Two Part tariff _______________________________________________________________________ 70

6.2. Recovery of Capacity (Fixed) Charges ____________________________________________________ 70

6.3. Third party sell in case of payment default by distribution licensee ___________________________ 70

6.4. Terms of payment and adjustment of receipts towards outstanding dues ______________________ 70

6.5. Application Fees and Publication Expenses _______________________________________________ 71

7. Annexures_______________________________________________________________________________ 72

7.1. Audited Annual Accounts for FY 2010-11 _________________________________________________ 72

7.2. Cost Accounting record along with Cost Audit report for FY 2009-10 __________________________ 72

7.3. Minutes of meeting of “Steering Committee for Power Planning” under the Chairmanship of Financial

Commissioner and Principal Secretary (Power), Govt. of Haryana dated 20th

September 2011 ____________ 72

7.4. Appellate Order on Appeal No. 81 of 2007 dated 10th

January, 2008 __________________________ 72

7.5. Appellate Order on Appeal No. 26 of 2008 dated 7th

April, 2011 ______________________________ 72

7.6. CERC (Terms and Conditions of Tariff) Regulations, 2009, Statement of Objects & Reasons ________ 72

7.7. Cost benefit of Imported Coal __________________________________________________________ 72

7.8. Unit wise depreciation ________________________________________________________________ 72

Page 5: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

3

BEFORE THE HON’BLE HARYANA ELECTRICITY REGULATORY COMMISSION, HARYANA

FILING NO. ………………………………………………………….

CASE NO. ………………………………………………………….

IN THE MATTER OF PETITION FOR APPROVAL OF GENERATION TARIFF

FOR THE YEAR FY 2012-13 FOR HARYANA POWER

GENERATION CORPORATION LIMITED UNDER

SECTION 61 & 62 OF THE ELECTRICITY ACT 2003

AND

IN THE MATTER OF THE APPLICANT: HARYANA POWER GENERATION CORPORATION

LIMITED

URJA BHAWAN, C-7, SECTOR-6

PANCHKULA, HARYANA

PETITIONER

THE APPLICANT ABOVE NAMED RESPECTFULLY SUBMITS

Page 6: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

4

1. BACKGROUND

1.1. Introduction

The Govt. of India notified the Electricity Act, 2003 on 10th

June, 2003 repealing the Indian Electricity

Act-1910, the Electricity (Supply) Act 1948 and the E.R.C. Act, 1998. Among the tariff related provisions,

the State Electricity Regulatory Commission (SERC) has to be guided by National Electricity Policy and

National Tariff Policy. Also, as per the national tariff Policy, the Central Commission would, in

consultation with the Central Electricity Authority, notify operating norms from time to time for

generation and transmission which would be adopted by the SERC. Further in case of power plants/

generating units, whose performance has been below normative level for quite some time, relaxed

norms relatable to past performance and vintage of the plants shall be fixed.

The petitioner, Haryana Power Generation Corporation Limited (HPGCL) is a Company incorporated

under the provisions of the Companies Act, 1956 and is wholly owned by the Government of Haryana.

The business of Generation of Power of erstwhile HSEB was transferred to HPGCL on 14th

August 1998

for generation of power from state owned Generating stations. The Company, having its registered

office at Urja Bhawan, C-7, Sector 6, Panchkula, Haryana is filing this application seeking Approval of

Generation tariff for the financial year FY 2012-13.

The Regulation 7(1) of HERC (Terms & Conditions for Determination of Generation Tariff) Regulations,

2008 requires the revenue requirement details for determination of Generation tariff for the ensuing

year should be filed each year by 31st

October. The HPGCL, vide memo no. HPGC/FIN/Reg.-403/236

dated 19/10/2011, requested the Hon’ble Commission for extension in filing of Tariff

Petition/Application for FY 2012-13 by 30th

November 2011. The Hon’ble Commission accepted the

request and the extension were granted to HPGCL vide letter No. 2385/HERC/Tariff/HPGCL/Generation

tariff/FY 12-13/2011 dated 28/10/2011.

In accordance with the statuary requirements under the provisions of Section 61 and 62 of Electricity

Act, 2003, HPGCL is submitting this application for approval of the Generation tariff for FY 2012-13

based on the CERC “Terms & Condition of Tariff Regulation 2009-14” and tariff principles as considered

by the Hon’ble Haryana Electricity Regulatory Commission in its past orders/ Regulations.

Page 7: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

5

1.2. Brief Company Profile

Haryana Power Generation Corporation Ltd. (HPGCL), hereinafter referred to as the ‘Petitioner, is a

company registered under the Indian Companies Act, 1956 and is wholly owned by the Government of

Haryana. HPGCL was incorporated as a company on 17th

March, 1997 and was given the responsibility of

operating and maintaining State’s own generation projects. The business of Generation of Power of

erstwhile HSEB was transferred to HPGCL on 14th

August 1998. In addition, it has been entrusted with

the responsibility of setting up of new generating stations in order to keep pace with the ever –

increasing demand of power. The Company, having its registered office at Urja Bhawan, C-7, Sector 6,

Panchkula, Haryana is filing this application seeking Approval of Generation tariff for the financial year

FY 2012-13.

The Petitioner is engaged in the business of generation of power in the state through its medium and

large thermal generating stations which are located at Panipat, Yamuna Nagar, Hisar and small hydro

stations located at the Western Yamuna Canal (WYC) Bhudkalan, Yamiuna Nagar and One Hydal project

at Kakroi in Sonipat district. HPGCL, which started with a modest installed generation capacity of

863.3MW, has presently an installed generation capacity of 3230.50 MW. The electricity generated at

these power stations is evacuated and transmitted through the transmission network of Haryana Vidyut

Prasaran Nigam Ltd. (HVPNL) to the Distribution Companies i.e. Uttar Haryana Bijli Vitran

Nigam(UHBVNL) and Dakshin Haryana Bijli Vitran Nigam (DHBVNL) who are the distribution licensee(s)

for the entire state of Haryana with geographical division amongst them. HPGCL also exercised the rights

relating to procurement of power & bulk supply of electricity / trading of power for some time ( w.e.f.

9.06.2005) but the same was ultimately transferred from HPGCL to UHBVNL & DHBVNL w.e.f.

01.04.2008 vide State Govt. Notification No. 1/1/2008-1 dated 11.04.2008.

HPGCL owns & operates the following power plants in the state:

1) Panipat Thermal Power Station, Panipat - 1367.8MW.

2) Rajiv Gandhi Thermal Power Project, Khedar, Hisar. – 1200 MW

3) Deen Bandhu Chhotu Ram Thermal Power Project, Yamuna Nagar - 600MW

4) WYC Hydro Electric Station, Yamuna Nagar – 62.4 MW

5) Micro Hydro Power Station,Kakroi-0.3 MW

Page 8: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

6

HPGCL is also coordinating the activities of following power project:

1) 1500MW Indira Gandhi Super Thermal Power (IGSTPP) Project, Jhajjar – The Project is being

executed by NTPC from concept to commissioning in Joint Venture with Government of Delhi and

Government of Haryana having HPGCL’s equity share of 25%;

2) 1320 MW Mahatma Gandhi Thermal Power Project (MGTPP) in Jhajjar under Case-2 mechanism of

Government of India.

Apart from the above power projects which are being undertaken by HPGCL for commissioning in 11th

Plan the State Govt./ Govt. of India has also sanctioned following new projects to be set-up in 12th

Plan:

1) 1x660 MW Thermal Unit based on Super Critical Technology at Yamunanagar as an extension

project.

2) 1500 MW Gas based Project planned at Faridabad.

3) Coal block at Mara-to-Mahan in MP with estimated coal reserves of 956 Million Tonnes allocated

jointly to HPGCL and Delhi Govt.

Apart from above HPGCL had been involved in procurement of 2013 MW power under Case-I mode.

HPGCL is also facilitating NPCL in getting all necessary clearance from Govt. of Haryana for setting up

2800MW Nuclear Power plant in the State of Haryana in district Fathehabad.

1.3. Key achievements of HPGCL:

Some of the key achievement of HPGCL during it’s operational regime are mentioned below:

a) 2x300 MW DCRTPP Yamuna Nagar commissioned in record time. First Unit was commissioned in a

record period of 27 months which is the lowest for any coal based green field project in the

country.

b) HPGCL commissioned in quickest possible time India’s first and second 600 MW capacity thermal

Units of RGTPP, Khedar during August 2010 and March 2011 respectively, in a record period of 43

and 49 months as compared to the norms of 44 and 50 months as stipulated by CEA. 600 MW is

the largest sub-critical Unit capacity in the country.

c) 2x660 MW power project at Jhajjar awarded to IPP- first power generation project in Haryana

based on super critical technology.

Page 9: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

7

d) Supply of 1724 MW (out of 2013 MW) power through tariff based competitive bidding under

Case-I guidelines is expected to flow in 2012-13. For balance 389 MW power M/s Lanco had not

come forward for signing of RFP Project documents. Hon’ble Commission has held that it has

jurisdiction in the matter. Hon’ble Appellate Tribunal has also held that Hon’ble HERC has

jurisdiction in the matter. It has also held that the contract has been concluded on issuance of LoI

and accordingly signing of the RFP documents including PPA is just a ministerial act. Presently M/s

Lanco’s appeal is pending before Supreme Court against the judgment of the Appellate Tribunal.

Some of the key achievements of HPGCL as relating to existing Projects are as below:

a) Generation capacity of 2367.2MW added since creation of HPGCL - an increase of around 274%.

b) HPGCL was awarded Gold Shield by Ministry of Power in January 2010 for meritorious

performance relating to early completion of 2x300 MW DCRTPP, Yamunanagar.

c) Central Electricity Authority, New Delhi selected 250 MW Unit-8 of PTPS, Panipat for the award of

“Best Executed 250 MW Thermal Power Project” of Year 2004-05.

d) The Ministry of Power, Govt. of India awarded Meritorious Productivity award to PTPS for good

performance during the year 2003-04 as the power station achieved highest ever PLF of 78.75%

during the year.

e) The 210/250 MW Units (2x210MW+2x250MW) of PTPS, Panipat have performed very well during

2007-08 and achieved a Plant Load Factor of 93.61% which is comparable to the best performing

Power Plants in the Country.

f) The Overall Oil Consumption of 1.66 ml/Unit achieved in 2007-08 is the lowest since formation of

HPGCL.

g) An overall PLF of 82.93% achieved by HPGCL plants in 2009-10 highest since formation of HPGCL.

HPGCL is presently operating three (3) thermal power generation plants, viz. PTPS, Panipat (Unit 1 -

117.8 MW, Unit-2 to 4 - 110 MW each, Unit-6&7 - 210 MW each, Unit-7&8- 250MW each), DCRTPP,

Yamuna Nagar (Unit-1&2 - 300MW each) and RGTPS, Hisar (Unit-1&2 - 600MW each). The Company also

operates a hydro power plant Western Yamuna Canal Hydro Project (62.4 MW) and a Micro Hydro

Power Station in Kakroi (0.3MW). The Unit-wise details of present installed generation capacity of

HPGCL are as given below:

Page 10: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

8

Table 1: Unit-wise installed capacity of HPGCL Plants

Particulars Installed Capacity as on 31.03.2011 Date of Commissioning / COD

Panipat Thermal Power

Station, Panipat

Unit No-1: 117.8 MW

Unit No-2: 110 MW

Unit No-3: 110 MW

Unit No-4: 110 MW

Unit No-5: 210 MW

Unit No-6: 210 MW

Unit No-7: 250 MW

Unit No-8: 250 MW

01/11/1979

27/03/1980

01/11/1985

11/01/1987

28/03/1989

31/03/2001

28/09/2004

28/01/2005

DCRTPS,Yamuna Nagar Unit No-1: 300 MW

Unit No-2: 300 MW

14/04/2008

24/06/2008

RGTPS, Hisar Unit No-1: 600 MW

Unit No-2: 600 MW

24/08/2010

01/03/2011

Western Yamuna Canal

Hydro Project (Yamuna

Nagar)

Power House A

Unit No-1: 8 MW

Unit No-2: 8 MW

Power House B

Unit No-1: 8 MW

Unit No-2: 8 MW

Power House C

Unit No-1: 8 MW

Unit No-2: 8 MW

Power House D

Unit No-1: 7.2 MW

Unit No-2: 7.2 MW

29/05/1986

13/06/1986

15/05/1987

01/06/1987

27/03/1989

18/04/1989

16/04/2004

12/05/2004

Micro Hydro Power

Station, Kakroi

0.30 MW

Total Capacity 3230.5 MW

Page 11: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

9

2. Performance of HPGCL Stations over the years and current operational

constraints

2.1. Historical performance of HPGCL stations

The performance of thermal generating stations of HPGCL (formerly HSEB) has significantly improved in

the post reform era. Following graph show the overall performance of the operation parameters since

FY 1988-89:

Figure 1: Pre and Post-reform performance of the power plants of HPGCL (formerly HSEB)

HPGCL, which started with a modest installed generation capacity of 863.3MW of HSEB at the time of

unbundling. Thereafter, during the past 12 years HPGCL has added capacity more than 3 times that it

had as on FY 1998-99. The current installed capacity of HPGCL is 3230.5 MW. In the post reform era, the

plant load factor has also improved significantly. The average PLF between FY 1988-89 to FY 1998-99

was 43.97% which increased to an average value of 67.90% post reform. In FY 2009-10 HPGCL achieved

the highest ever PLF of 82.93%. In the similar way HPGCL has recorded improvement in the other

parameters as given in the following graphs.

0

2000

4000

6000

8000

10000

12000

14000

16000

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

Generation (MU) PLF(%) Installed Capacity (MW) Station Heat Rate (kcal /kwh)

Pre-reform Period (HSEB) Post-reform Period (HPGCL)

Page 12: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

10

Figure 2: Pre and Post-reform performance of the power plants of HPGCL (formerly HSEB)

The auxiliary consumption has decreased by 2.47% from 12.24% in FY 1997-98 to 9.77% in FY 2009-10. It

also can be seen from the graph there is improvement in the oil consumption also. The Unit wise and

plant wise individual performance since the commissioning of the Unit is given in the annexure- .

The performance of HPGCL stations has significantly improved over the past years in comparison to the

performance parameters achieved prior to re-organization of erstwhile HSEB. However, there are

certain reasons for non-achievement of optimum performance parameter mainly during the last two

financial years because of uncontrollable circumstances which has been discussed in the subsequent

sections.

0%

2%

4%

6%

8%

10%

12%

14%

0

5

10

15

20

25

30

Oil Consumption (ml/kwh) Aux.Consumption (%)

Pre-reform period (HSEB) Post-reform period (HPGCL)

Page 13: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

11

Figure 3: Unit wise life of HPGCL Plants (in year)

The PTPS plant of HPGCL is very old and most of the Units have completed their designed useful life of

25 (as shown in red dotted line) years as obvious from the following figure No 3 .Unit-4&5 of PTPS are

older than 20 (as shown in green dotted line) years. Similarly the Units of Hydel stations of WYC Hydel

Yamunanagar are also nearing completion of their design life of 30-35 years, as obvious from the chart

shown above.

0 3 5 8 10 13 15 18 20 23 25 28 30 33 35

PTPS (1) 117.8 MW

PTPS (2) 110 MW

PTPS (3) 110 MW

PTPS (4) 110 MW

PTPS (5) 210 MW

PTPS (6) 210 MW

PTPS (7) 250 MW

PTPS (8) 250 MW

DCRTPS (1) 300 MW

DCRTPS (2) 300 MW

RGTPS (1) 600 MW

RGTPS (2) 600 MW

WYCHP (A-1) 8 MW

WYCHP (A-2) 8 MW

WYCHP (B-1) 8 MW

WYCHP (B-2) 8 MW

WYCHP (C-1) 8 MW

WYCHP (C-2) 8 MW

WYCHP (D-1) 7.2 MW

WYCHP (D-1) 7.2 MW

Unit-wise life of HPGCL Plants (In Year)

Page 14: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

12

2.1

.1.

Pa

nip

at

Th

erm

al

Po

we

r S

tati

on

(P

TP

S),

Pa

nip

at

(13

67

.8 M

W)

Ta

ble

2:

His

tori

cal

Op

era

tio

na

l p

ara

me

ters

of

PT

PS

, P

an

ipa

t (P

ost

-re

form

)

De

scri

pti

on

F

Y –

98

(pre

-re

form

) F

Y -

99

F

Y -

00

F

Y -

01

F

Y -

02

F

Y -

03

F

Y -

04

F

Y -

05

F

Y -

06

F

Y -

07

F

Y -

08

F

Y -

09

F

Y –

10

F

Y -

11

FY

- 1

2

(up

to

Oct

’11

)

PT

PS

-1 (

Un

its

I-IV

)

Pla

nt

Loa

d F

act

or

(%)

34

.39

3

4.7

4

32

.02

3

6.3

2

41

.61

4

4.7

3

72

.45

6

1.6

9

57

.77

6

6.5

9

59

.41

5

7.8

9

68

.38

5

3.3

7

69

.51

Au

x. C

on

sum

pti

on

(%

) 1

2.5

6

12

.86

1

2.9

1

2.6

9

12

.39

1

1.6

6

11

.05

1

2.1

3

11

.75

1

1.5

9

12

.13

1

1.4

8

11

.4

12

1

2.3

5

Ge

ne

rati

on

(M

U)

13

25

.67

1

33

8.8

5

12

37

.40

1

40

0.0

6

16

03

.91

1

72

4.1

8

28

00

.20

2

37

7.6

5

22

26

.76

2

56

6.6

2

22

96

.32

2

23

1.4

4

26

81

.4

20

93

.69

1

59

8.7

6

SH

R (

kca

l/k

wh

) 3

86

0

38

60

3

69

5

36

57

3

79

0

37

13

3

49

8

35

67

3

66

5

33

41

3

47

0

34

25

3

22

5

33

49

3

23

0

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

26

.71

2

5.8

9

13

.66

1

0.1

8

5.0

3

6.5

5

4.5

8

5.4

3

5.2

6

2.9

2

2.9

3

3.3

3

2.4

4

5.8

4

.86

GC

V o

f C

oa

l (K

cal/

kg

) 3

90

2

39

02

3

97

9

40

53

4

19

3

42

37

4

25

2

40

91

4

10

9

39

95

3

93

4

39

00

3

80

1

36

53

3

46

7

PT

PS

-2 (

Un

its

V-V

III)

Pla

nt

Loa

d F

act

or

(%)

83

.89

7

1.6

0

87

.75

7

2.1

9

87

.79

8

8.8

3

85

.36

9

1.8

4

73

.7

91

.09

9

3.6

1

91

.29

9

3.3

8

89

.09

8

8.7

7

Au

x. C

on

sum

pti

on

(%

) 1

1.1

5

10

.62

1

0.2

7

10

.11

9

.40

9

.36

9

.24

9

.8

9.0

6

8.7

4

8.8

1

8.8

9

.13

9

.66

1

0

Ge

ne

rati

on

(M

U)

15

43

.17

1

31

7.1

9

16

18

.64

1

32

7.9

4

26

69

.83

3

26

8.0

7

31

49

.06

3

37

9.3

7

59

08

.94

7

34

1.5

1

75

64

.94

7

35

6.9

8

75

25

.43

7

17

9.6

0

41

94

.64

SH

R (

kca

l/k

wh

) 2

81

5

28

15

2

78

6

28

46

2

89

9

29

07

2

93

5

28

58

2

70

3

26

20

2

57

1

25

74

2

56

1

26

79

2

74

0

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

2.5

6

2.3

5

1.7

1

2.0

6

2.1

7

1.8

8

2.0

2

2.8

2

2.9

2

0.8

6

0.5

9

0.8

1

.05

2

.68

1

.52

GC

V o

f C

oa

l (K

cal/

kg

) 3

90

2

39

02

3

97

9

40

53

4

19

3

42

37

4

25

2

40

91

4

10

9

39

95

3

93

4

39

00

3

80

1

36

28

3

44

0

Pa

nip

at

Th

erm

al P

ow

er

Sta

tio

n (

PT

PS

) ,

Pa

nip

at

(13

67

.8 M

W)

Pla

nt

Loa

d F

act

or

(%)

50

.38

4

6.6

5

50

.02

4

7.9

1

61

.86

6

6.2

6

78

.75

7

1.1

4

68

.53

8

3.1

7

82

.55

8

0.4

8

85

.19

7

7.3

9

82

.47

Au

x. C

on

sum

pti

on

(%

) 1

1.8

0

11

.75

1

1.4

1

11

.43

1

0.6

7

10

.14

1

0.0

8

10

.76

9

.79

9

.48

9

.58

9

.42

9

.73

1

0.1

9

10

.65

Ge

ne

rati

on

(M

U)

28

68

.84

2

65

6.0

4

28

56

.04

2

72

7.9

9

42

73

.74

4

99

2.2

5

59

49

.26

5

75

6.6

0

81

35

.70

9

90

8.1

3

98

61

.26

9

58

8.4

2

10

20

6.8

3

92

73

.29

5

79

3.4

0

SH

R (

kca

l/k

wh

) 3

34

2

33

42

3

97

0

32

62

3

25

1

31

87

3

19

1

31

51

2

96

6

28

05

2

78

0

27

72

2

73

6

28

31

2

87

6

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

13

.72

1

4.2

2

6.8

9

6.2

3

3.0

4

3.4

9

3.2

1

3.9

3

.56

1

.39

1

.14

1

.39

1

.41

3

.38

2

.44

GC

V o

f C

oa

l (K

cal/

kg

) 3

90

2

39

02

3

97

9

40

53

4

19

3

42

37

4

25

2

40

91

4

10

9

39

95

3

93

4

39

00

3

80

1

36

36

3

44

9

Page 15: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

13

Th

e p

erf

orm

an

ce o

f P

TP

S P

an

ipa

t h

as

imp

rov

ed

sig

nif

ica

ntl

y d

uri

ng

FY

Po

st r

efo

rm p

eri

od

til

l F

Y 2

00

9-1

0.

Th

e a

ve

rag

e P

LF f

or

PT

PS

mo

ve

d u

p

fro

m b

are

ly 5

0.8

3%

in

FY

19

97

-98

(P

re-

HP

GC

L p

eri

od

) to

aro

un

d 8

5%

in

20

09

-10

. S

imil

arl

y t

he

av

era

ge

au

xili

ary

co

nsu

mp

tio

n h

ad

re

du

ced

to

aro

un

d

9.4

2%

fr

om

1

1.8

0%

in

F

Y

19

97

-98

. S

ign

ific

an

t im

pro

vem

en

t in

sp

eci

fic

oil

co

nsu

mp

tio

n

ha

s b

ee

n

ach

iev

ed

w

he

rein

th

e

ave

rag

e

con

sum

pti

on

wa

s b

are

ly 1

.41

ml/

kWh

as

com

pa

red

to

a n

orm

ati

ve

co

nsu

mp

tio

n o

f 2

ml/

kW

h.

Th

e i

mp

rov

em

en

t is

mo

re a

pp

are

nt

wh

en

com

pa

red

to

th

e c

on

sum

pti

on

le

ve

l in

FY

19

97

-98

wh

ich

wa

s a

t 1

3.7

2 m

l/kW

h.

Ho

we

ve

r, b

eca

use

of

the

qu

ali

ty o

f co

al

in t

erm

s o

f G

CV

wh

ich

HP

GC

L re

ceiv

ed

at

the

ir p

lan

t th

ere

is

flu

ctu

ati

on

in

th

e p

erf

orm

an

ce p

ara

me

ter

of

the

pla

nts

. H

ow

eve

r, b

eca

use

of

the

qu

ali

ty o

f co

al

in t

erm

s

of

GC

V w

hic

h P

TP

S r

ece

ive

d a

t th

eir

pla

nt

the

re i

s fl

uct

ua

tio

n i

n t

he

pe

rfo

rma

nce

pa

ram

ete

r o

f P

TP

S,

Pa

nip

at

aft

er

FY

20

09

-10

. T

he

oth

er

mo

st

crit

ica

l fa

cto

rs w

hic

h im

pa

ct t

he

ov

era

ll o

pe

rati

ng

no

rms

of

the

pla

nt

are

re

late

d t

o t

he

lif

e o

f it

s re

spe

ctiv

e U

nit

s. U

nit

-1 t

o 4

of

PT

PS

ha

s b

ee

n i

n

use

fo

r q

uit

e lo

ng

an

d i

t is

be

com

ing

in

cre

asi

ng

ly d

iffi

cult

to

ru

n t

he

se U

nit

s o

n o

pe

rati

ng

no

rms

spe

cifi

ed

by

Ho

n’b

le C

om

mis

sio

n.

Th

e r

ea

son

s fo

r sh

ort

fa

ll i

n p

erf

orm

an

ce l

ev

el

of

PT

PS

Pa

nip

at

are

as

un

de

r:

·

Th

e p

oo

r p

erf

orm

an

ce o

f P

TP

S c

an

be

att

rib

ute

d m

ain

ly t

o o

ld U

nit

s (U

nit

- 1

to

4)

of

the

pla

nt

incl

ud

ing

th

e p

erf

orm

an

ce o

f U

nit

– 1

& 2

be

low

th

e e

xpe

cte

d p

erf

orm

an

ce l

ev

el e

ven

aft

er

the

R&

M a

ctiv

itie

s;

·

Fo

r U

nit

-3 &

4,

the

R&

M i

s p

rop

ose

d t

o b

e c

arr

ied

ou

t th

rou

gh

Wo

rld

Ba

nk

fu

nd

ing

wh

ich

is

to b

e s

tart

ed

in

FY

20

13

-14

. T

he

re

po

rt o

f

the

Te

chn

ica

l co

nsu

lta

nt

on

R&

M o

f U

nit

-3 &

4 i

s st

ill

aw

ait

ed

. A

s th

e i

nv

est

me

nts

are

pro

po

sed

un

de

r W

orl

d B

an

k f

un

din

g s

che

me

,

HP

GC

L is

no

t m

ak

ing

an

y a

dd

itio

na

l in

ve

stm

en

t o

n t

he

se t

wo

un

its.

Ho

we

ver,

it

is a

lso

to

be

me

nti

on

ed

he

re t

ha

t, H

PG

CL

is f

ind

ing

it

ve

ry d

iffi

cult

to

ma

inta

in e

ve

n a

t e

xist

ing

pe

rfo

rma

nce

pa

ram

ete

rs f

or

Un

it -

3 &

4 w

ith

ou

t a

ny

in

ve

stm

en

t;

·

Th

e l

ow

PLF

wa

s a

lso

du

e t

o t

he

fo

rce

d o

uta

ge

s o

f U

nit

-1 f

rom

01

.03

.20

10

to

23

.08

.10

du

e t

o t

he

da

ma

ge

of

all

th

e b

ea

rin

gs

of

Tu

rbin

e

& G

en

era

tor

& U

nit

-4 f

rom

20

.04

.20

10

to

27

.5.2

01

0 d

ue

to

hig

h v

ibra

tio

ns

in G

en

era

tor

be

ari

ng

. A

lso

, th

e a

nn

ua

l o

ve

rha

uli

ng

of

Un

it-2

wh

ich

co

mm

en

ced

on

25

.10

.20

10

fo

r 4

5d

ay

s h

as

be

en

ext

en

de

d d

ue

to

un

fore

see

n f

au

lt i

n A

BB

mo

dif

ied

tu

rbin

e;

·

Th

e p

erf

orm

an

ce p

ara

me

ters

ha

ve a

lso

de

teri

ora

ted

as

Un

it-6

, U

nit

-7 &

Un

it-8

we

re u

nd

er

pla

nn

ed

sh

ut

do

wn

as

pe

r th

e l

ow

er

po

we

r

req

uir

em

en

t in

th

e S

tate

. B

ack

ing

do

wn

of

PT

PS

-2 U

nit

s a

lso

co

ntr

ibu

ted

a h

ug

e l

oss

of

40

2.9

8 M

U i

n F

Y 2

01

0-1

1 a

nd

22

8.6

6 M

U i

n F

Y

20

11

-12

up

to S

et’

11

.

Page 16: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

14

·

Als

o i

t is

a f

act

th

at

as

far

as

PLF

an

d S

HR

is

con

cern

ed

PT

PS

Un

it 1

-4 c

om

pa

res

po

orl

y w

ith

oth

er

such

Un

its

of

sam

e v

inta

ge

;

·

Th

e r

ea

son

of

po

or

pe

rfo

rma

nce

is

als

o d

ue

to

lo

ss o

f g

en

era

tio

n d

ue

to

ba

ckin

g d

ow

n o

f u

nit

s, p

art

ial

loa

d o

pe

rati

on

of

PT

PS

-1

(U

nit

-1

to 4

);

·

Re

ceip

t o

f p

oo

r q

ua

lity

of

coa

l h

av

ing

wit

h l

ow

Ca

lori

fic

va

lue

of

36

36

Kca

l/K

g a

nd

hig

h a

sh c

on

ten

t a

s co

mp

are

d t

o 3

80

1 K

cal/

Kg

in

FY

20

09

-10

. D

ue

to

po

or

qu

alit

y o

f co

al,

oil

su

pp

ort

wa

s fr

eq

ue

ntl

y r

eq

uir

ed

fo

r st

ab

ilit

y o

f th

e f

urn

ace

an

d t

o s

av

e t

he

Un

its

fro

m t

rip

pin

g;

·

Th

e q

ua

nti

ty o

f co

al

po

st s

ign

ing

of

FS

A o

n 1

st A

pri

l 2

00

9 f

or

PT

PS

, P

an

ipa

t w

as

red

uce

d t

o 6

6.0

0 L

ak

h M

T p

er

an

nu

m (

AC

Q)

an

d a

s

com

pa

red

to

85

.35

La

kh

MT

;

·

Exc

ess

ive

no

s. o

f tr

ipp

ing

s o

f th

e U

nit

s 1

to

4 d

uri

ng

FY

20

10

-11

du

e t

o v

ari

ou

s re

aso

ns

such

as

bla

de

s o

f th

e t

urb

ine

we

re f

ou

nd

to

be

da

ma

ge

d r

esu

ltin

g i

nto

ve

ry l

on

g f

orc

ed

sh

ut

do

wn

s. A

to

tal

of

90

no

s o

f fo

rce

d o

uta

ge

s o

n P

TP

S u

nit

s- 1

to

4 a

nd

54

no

s o

f o

n P

TP

S

un

its-

5 &

6 u

p t

o O

cto

be

r, 2

01

0 d

uri

ng

FY

20

10

-11

fo

rce

d h

igh

er

no

. o

f st

art

up

an

d p

art

ial

loa

d r

un

nin

g n

ece

ssit

ate

s o

il s

up

po

rt f

or

sta

bil

ity

of

the

fu

rna

ce t

he

reb

y i

ncr

ea

sin

g o

il c

on

sum

pti

on

;

·

It i

s a

lso

to

be

no

ted

th

at

the

En

erg

y A

ud

its

of

PT

PS

un

its

2 t

o 6

we

re g

ot

do

ne

du

rin

g A

pri

l, 2

01

0 a

nd

th

at

of

PT

PS

un

it-1

du

rin

g

Se

pte

mb

er,

20

10

fro

m M

/s.

Ev

on

ik E

ne

rgy

Se

rvic

es

Pv

t. L

td.

No

ida

. M

/s E

von

ik h

av

e p

oin

ted

ou

t a

nu

mb

er

of

sho

rtco

min

gs

rela

tin

g t

o

ine

ffic

ien

cy a

nd

wa

sta

ge

of

he

at

/ e

ne

rgy

in v

ari

ou

s e

qu

ipm

en

t’s.

Th

ey

ha

ve a

lso

giv

en

a s

eri

es

of

sho

rt /

me

diu

m /

lo

ng

te

rm

reco

mm

en

da

tio

ns

wh

ich

if

imp

lem

en

ted

wo

uld

re

du

ce t

he

he

at

rate

, o

il co

nsu

mp

tio

n &

au

xili

ary

po

we

r co

nsu

mp

tio

n c

on

sid

era

bly

an

d

imp

rov

e t

he

eff

icie

ncy

& P

LF o

f th

ese

un

its.

Ho

we

ve

r, H

PG

CL

pe

titi

on

wit

h r

eg

ard

to

ad

dit

ion

al

cap

ex

is s

till

pe

nd

ing

wit

h t

he

Ho

n’b

le

com

mis

sio

n;

·

Du

rin

g o

uta

ge

/ p

art

ial

run

nin

g l

oa

d r

un

nin

g o

f th

e U

nit

s, t

he

va

rio

us

Au

xili

ari

es

of

the

Pla

nt

ha

ve t

o b

e k

ep

t ru

nn

ing

at

full

lo

ad

th

ere

by

incr

ea

sin

g t

he

pe

rce

nta

ge

Au

xili

ary

Co

nsu

mp

tio

n;

Wh

ile

th

e p

erf

orm

an

ce o

f P

TP

S P

an

ipa

t h

as

rem

ain

ed

fa

irly

co

nsi

ste

nt

till

FY

20

09

-10

an

d d

eto

ria

ted

th

ere

aft

er

in l

igh

t o

f th

e i

ssu

e m

en

tio

ne

d

ab

ove

. H

PG

CL

pra

ys

to t

he

Ho

n’b

le H

ER

C t

o t

hin

k t

hro

ug

h t

he

se i

ssu

es

wh

ile d

ete

rmin

ing

th

e G

en

era

tio

n T

ari

ff f

or

HP

GC

L.

Page 17: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

15

2.1

.2.

Fa

rid

ab

ad

Th

erm

al

Po

we

r P

lan

t (1

65

MW

)

Ta

ble

3:

His

tori

cal

Op

era

tio

na

l p

ara

me

ters

of

Fa

rid

ab

ad

Th

erm

al

Po

we

r P

lan

t (1

65

MW

)

De

scri

pti

on

FY

– 9

8

(pre

-

refo

rm)

FY

- 9

9

FY

- 0

0

FY

– 0

1

FY

- 0

2

FY

- 0

3

FY

- 0

4

FY

- 0

5

FY

- 0

6

FY

- 0

7

FY

- 0

8

FY

- 0

9

FY

– 1

0

Pla

nt

Loa

d F

act

or

(%)

44

.41

5

9.4

6

65

.91

5

6.9

1

55

.90

6

7.3

2

54

.88

6

0.0

4

54

.47

4

2.6

4

49

.25

4

2.6

1

55

.7

Au

x. C

on

sum

pti

on

(%

) 1

4.1

8

12

.91

1

2.5

6

13

.02

1

3.3

7

12

.69

1

3.3

9

12

.94

1

3.1

1

4.9

6

14

.82

1

6.3

2

16

.07

Ge

ne

rati

on

(M

U)

64

1.9

8

59

.38

9

55

.34

8

22

.61

8

08

.05

9

73

.13

7

95

.38

8

67

.88

7

87

.31

6

16

.36

7

13

.81

5

01

.19

3

83

.77

Sta

tio

n H

ea

t R

ate

(k

cal/

kw

h)

40

79

4

07

9

39

70

4

31

0

43

54

4

27

6

42

71

4

18

6

41

95

4

32

5

48

01

4

51

8

46

04

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

9.7

7

8.0

1

4.8

5

5.1

2

4.5

5

3.1

2

4.3

9

4.4

5

5.5

6

9.2

7

8.8

6

9.6

2

6.0

1

GC

V o

f co

al

(Kca

l/k

g)

45

29

4

52

9

45

49

4

73

2

48

29

4

72

1

46

04

4

43

2

40

83

3

93

2

40

42

4

08

6

38

94

Go

vt.

of

Ha

rya

na

du

rin

g A

ug

ust

, 2

00

5 a

cco

rde

d a

dm

inis

tra

tive

ap

pro

va

l fo

r p

ha

sin

g o

ut

the

old

Un

its

of

FTP

S,

Fa

rid

ab

ad

. T

he

Bo

ard

of

Dir

ect

or

of

HP

GC

L a

lso

co

ncu

rre

d w

ith

th

e d

eci

sio

n o

f th

e G

ove

rnm

en

t d

uri

ng

Oct

ob

er

20

05

. D

ue

to

de

teri

ora

tin

g p

erf

orm

an

ce,

hig

h c

ost

of

ge

ne

rati

on

,

safe

ty a

nd

en

vir

on

me

nta

l co

nce

rns,

Ce

ntr

al

Ele

ctri

city

Au

tho

rity

, N

ew

De

lhi

ha

s a

pp

rov

ed

th

e p

ha

sin

g o

ut

of

the

55

MW

Un

it-2

of

FT

PS,

Fa

rid

ab

ad

. A

cco

rdin

gly

, th

e U

nit

ha

s b

ee

n p

ha

sed

ou

t w

.e.f

. 0

8.0

9.2

00

8.

Th

e o

the

r tw

o U

nit

s a

re a

lso

pla

nn

ed

to

be

ph

ase

d o

ut

by

Ma

rch

20

10

.

2.1

.3.

De

en

ba

nd

hu

Ch

ho

tu R

am

Th

erm

al

Po

we

r P

lan

t, Y

am

un

a N

ag

ar

(DC

RT

PP

) (6

00

MW

)

Ta

ble

4:

His

tori

cal

Op

era

tio

na

l p

ara

me

ters

of

DC

RT

PP

, Y

am

un

a N

ag

ar

De

scri

pti

on

2

00

8-0

9

20

09

-10

2

01

0-1

1

20

11

-12

(u

pto

Oct

’11

)

De

en

ba

nd

hu

Ch

ho

tu R

am

Th

erm

al

Po

we

r P

lan

t ,

Ya

mu

na

Na

ga

r (D

CR

TP

P)

(60

0 M

W)

Pla

nt

Loa

d F

act

or

(%)

69

.05

8

1.3

5

73

.85

7

2.6

3

Au

x.

Co

nsu

mp

tio

n (

%)

9.3

3

9.2

9

9.7

3

9.4

9

Ge

ne

rati

on

(M

U)

31

46

.97

4

27

5.9

1

38

81

.18

2

23

8.0

8

Sta

tio

n H

ea

t R

ate

(k

cal/

kw

h)

24

50

2

38

7

24

79

2

40

6

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

6.3

2

1.7

2

.35

2

.92

Gro

ss C

alo

rifi

c V

alu

e o

f co

al(

Kca

l/k

g)

36

70

3

72

5

35

89

3

59

7

Page 18: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

16

Th

e r

ea

son

s fo

r sh

ort

fa

ll i

n p

erf

orm

an

ce l

ev

el o

f D

CR

TP

P Y

am

un

an

ag

ar

du

rin

g t

he

pa

st t

wo

ye

ars

are

as

un

de

r:

·

Th

e 3

00

MW

Un

it-2

of

DC

RT

PP

¡s

op

era

tin

g a

t p

art

ial

loa

d o

f a

rou

nd

60

% d

ue

to

th

e s

tru

ctu

ral d

am

ag

e o

f E

SP P

ath

-A h

op

pe

rs;

·

Re

ceip

t o

f p

oo

r q

ua

lity

of

Ru

n-o

f-M

ine

(R

OM

) co

al

fro

m C

CL

ha

vin

g l

ow

Ca

lori

fic

va

lue

of

35

89

Kca

l/K

g a

nd

hig

h a

sh c

on

ten

t a

s

com

pa

red

to

37

25

Kca

l/K

g i

n F

Y 2

00

9-1

0.

Du

e t

o p

oo

r q

ua

lity

of

coa

l th

e S

tati

on

He

at

Ra

te w

as

red

uce

d a

nd

oil

su

pp

ort

wa

s fr

eq

ue

ntl

y

req

uir

ed

fo

r st

ab

ilit

y o

f th

e f

urn

ace

an

d t

o s

av

e t

he

Un

its

fro

m t

rip

pin

g;

·

Be

cau

se o

f in

ten

se &

pro

lon

ge

d m

on

soo

n t

his

ye

ar,

th

e B

ack

ing

do

wn

of

DC

RT

PP

Ya

mu

na

na

ga

r co

ntr

ibu

tes

a h

ug

e g

en

era

tio

n l

oss

of

15

6.5

0 M

U d

uri

ng

FY

20

10

-11

an

d 6

9.5

0 M

U u

pto

Se

p’1

1 d

uri

ng

FY

20

11

-12

;

·

Exc

ess

ive

no

s. o

f tr

ipp

ing

s o

f th

e U

nit

s 1

to

2 d

uri

ng

FY

20

10

-11

; m

ain

ly d

ue

to

re

aso

ns

such

as

coll

ap

se o

f E

SP

ho

pp

er

an

d o

the

r

em

erg

en

cy w

ork

s in

Un

it-2

, tu

rbin

e v

ibra

tio

n h

igh

at

be

ari

ng

No

.-7

an

d F

au

lt i

n C

&I

con

tro

l ca

ble

, lo

ss o

f fl

am

e,

bo

ile

r tu

be

le

ak

ag

e e

tc;

A t

ota

l o

f 2

2 n

os

of

trip

pin

g D

CR

TP

P u

nit

s- 1

an

d 2

9 n

os

of

trip

pin

g i

n U

nit

-2

we

re o

bse

rve

d d

uri

ng

Ap

ril 2

01

0 t

o J

an

’ 1

1 w

he

rea

s 1

7 n

os.

of

trip

pin

g w

ere

exp

eri

en

ce o

n U

nit

-2 d

uri

ng

FY

20

11

-12

up

to s

ep

’11

. T

his

ha

s re

sult

ed

in

to h

igh

er

no

. o

f st

art

up

wh

ich

ne

cess

ita

ted

oil

sup

po

rt f

or

sta

bil

ity

of

the

fu

rna

ce t

he

reb

y i

ncr

ea

sin

g o

il c

on

sum

pti

on

;

·

Th

e 3

00

MW

Un

it-2

of

DC

RT

PP

Ya

mu

na

na

ga

r a

chie

ve

d a

PLF

of

70

% d

uri

ng

FY

20

08

-09

, 7

7%

du

rin

g F

Y 2

00

9-1

0 a

nd

62

% d

uri

ng

FY

20

10

-

11

. A

s p

er

con

tra

ct,

the

pro

vis

ion

al

Ta

kin

g o

ver

(PT

O)

of

Un

it-2

wa

s d

on

e b

y H

PG

CL

on

Au

gu

st 3

1,

20

09

, w

he

rea

s th

e F

ina

l T

ak

ing

Ove

r

(FT

O)

ha

s n

ot

be

en

ach

ieve

d.

·

On

Se

pte

mb

er

25

, 2

01

1 w

hil

e t

he

ma

chin

e w

as

be

ing

re

-ta

ke

n a

fte

r tr

ipp

ing

of

sta

tio

n t

ran

sfo

rme

r o

n e

art

h f

au

lt,

the

ba

rrin

g g

ea

r

mo

tor

trip

pe

d o

n o

ve

rlo

ad

an

d t

he

Tu

rbin

e r

oto

r ca

me

to

sta

nd

sti

ll.

Aft

er

con

sult

ati

on

wit

h R

Infr

a,

SEC

Ch

ina

an

d v

ari

ou

s o

the

r

exp

eri

en

ced

pe

rso

nn

el,

att

em

pts

we

re m

ad

e t

o i

ncr

ea

se t

he

sp

ee

d o

f th

e m

ach

ine

be

yo

nd

60

0 R

PM

bu

t in

all

att

em

pts

, th

e m

ach

ine

go

t

trip

pe

d a

t a

rou

nd

th

e s

pe

ed

of

13

00

RP

M o

n h

igh

vib

rati

on

at

be

ari

ng

No

. 1

, a

fte

rwa

rd U

nit

-2 i

s u

nd

er

forc

ed

bre

ak

-do

wn

co

nd

itio

n ;

In l

igh

t o

f th

e i

ssu

e m

en

tio

ne

d a

bo

ve.

HP

GC

L p

ray

s to

th

e H

on

’ble

HE

RC

to

th

ink

th

rou

gh

th

ese

iss

ue

s w

hile

de

term

inin

g t

he

Ge

ne

rati

on

Ta

riff

for

HP

GC

L.

Page 19: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

17

2.1

.4.

Ra

jiv

Ga

nd

hi

Th

erm

al

Po

we

r P

roje

ct (

RG

TP

P),

His

ar

(12

00

MW

)

Ta

ble

5:

His

tori

cal

Op

era

tio

na

l p

ara

me

ters

of

RG

TP

P,

His

ar

De

scri

pti

on

2

00

8-0

9

20

09

-10

2

01

0-1

1

20

11

-12

(u

pto

Oct

’11

)

Ra

jiv

Ga

nd

hi

Th

erm

al

Po

we

r P

roje

ct (

RG

TP

P),

His

ar

(12

00

MW

)

Pla

nt

Loa

d F

act

or

(%)

- -

- 4

8.0

8

Au

x.

Co

nsu

mp

tio

n (

%)

- -

- 7

.05

Ge

ne

rati

on

(M

U)

- -

- 2

96

3.3

6

Sta

tio

n H

ea

t R

ate

(k

cal/

kw

h)

- -

- 2

84

6

Oil

Co

nsu

mp

tio

n (

ml/

kw

h)

- -

- 3

.61

Gro

ss C

alo

rifi

c V

alu

e o

f co

al

(Kca

l/k

g)

- -

- 3

30

8

Th

e r

ea

son

s o

f u

nd

er-

pe

rfo

rma

nce

of

RG

TP

P,

His

ar

sin

ce i

ts C

OD

are

as

un

de

r:

·

Th

e c

oa

l is

su

pp

lie

d t

o a

ll t

he

th

erm

al

ge

ne

rati

ng

sta

tio

ns

of

HP

GC

L b

ase

d o

n F

ue

l su

pp

ly a

gre

em

en

t (F

SA

) e

xce

pt

for

RG

TP

P,

wh

ere

co

al

is b

ein

g p

rocu

red

on

Mo

U r

ou

te.

In c

ase

of

RG

TP

P,

the

pe

rce

nta

ge

of

coa

l re

ceip

t w

as

57

.41

% d

uri

ng

FY

20

10

-11

an

d 7

8.7

0%

du

rin

g F

Y

20

11

-12

til

l S

ep

’11

;

·

RG

TP

P,

His

ar

is g

ett

ing

sig

nif

ica

nt

qu

an

tum

of

coa

l fro

m M

CL

are

a w

hic

h i

s o

f p

oo

r q

ua

lity

an

d h

as

ab

ou

t 4

0-4

2 p

er

cen

t a

sh c

on

ten

t;

·

Th

e p

erf

orm

an

ce p

ara

me

ter

of

RG

TP

P i

s a

lso

low

on

acc

ou

nt

of

sta

bil

iza

tio

n i

ssu

es

an

d i

na

de

qu

acy

an

d l

ow

qu

ali

ty o

f co

al;

·

Th

e R

GT

PP

, H

isa

r w

hic

h i

s a

su

b-c

riti

cal

pla

nt

ha

vin

g d

esi

gn

ca

lori

fic

va

lue

of

40

00

kca

l/k

g i

s b

are

ly r

ece

ivin

g c

oa

l h

av

ing

ca

lori

fic

va

lue

in

the

ra

ng

e o

f 3

50

0 k

cal/

kg

to

37

00

kca

l/ k

g.

Ta

ble

6:

His

tori

cal

Op

era

tio

na

l p

ara

me

ters

of

HP

GC

L

HP

GC

L T

he

rma

l

FY

– 9

8

(pre

-

refo

rm)

FY

- 9

9

FY

- 0

0

FY

- 0

1

FY

- 0

2

FY

- 0

3

FY

- 0

4

FY

- 0

5

FY

- 0

6

FY

- 0

7

FY

- 0

8

FY

- 0

9

FY

– 1

0

FY

- 1

1

FY

- 1

2

(up

to

Oct

’11

)

Page 20: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Pet

itio

n f

or A

pp

rov

al o

f T

arif

f fo

r th

e y

ear

FY

20

12

-13

18

HP

GC

L T

he

rma

l

Ge

ne

rati

on

(M

U)

35

10

.74

3

51

5.4

1

38

11

.38

3

55

0.6

0

50

81

.79

5

96

5.4

0

67

44

.64

6

62

4.4

8

89

23

.01

1

05

24

.49

1

05

75

.07

1

32

36

.58

1

48

66

.51

1

31

54

.47

1

09

94

.84

Pla

nt

Loa

d F

act

or

(%)

49

.17

4

9.2

4

53

.24

4

9.7

3

60

.80

6

6.4

4

74

.91

6

9.4

6

67

.00

7

8.7

8

78

.94

7

5.0

1

82

.93

7

6.2

8

67

.58

Au

x. C

on

sum

pti

on

(%

) 1

2.2

4

12

.04

1

1.7

0

11

.80

1

1.1

1

10

.56

1

0.4

7

11

.04

1

0.0

8

9.8

0

9.9

3

9.6

6

9.7

7

10

.06

9

.44

Oil

Co

nsu

mp

tio

n

(ml/

kw

h)

12

.99

1

2.7

0

6.3

8

5.9

7

3.2

9

3.4

3

3.3

5

3.9

7

3.7

4

1.8

5

1.6

6

2.8

7

1.6

1

3.0

8

2.8

5

SH

R (

kca

l/kw

h)

35

22

3

52

2

37

72

3

50

5

34

32

3

36

5

33

18

3

28

7

30

74

2

89

4

29

16

2

76

2

26

84

2

72

8

27

72

We

ste

rn Y

am

un

a C

an

al

Hyd

el (6

2.4

MW

)

Ge

ne

rati

on

(M

U)

24

6.5

5

26

8.1

3

23

9.6

0

24

1.8

1

22

9.1

5

24

6.6

9

25

2.8

9

29

0.4

8

25

8.3

3

25

5.7

2

27

0.3

1

28

2.3

9

23

5.4

2

27

2.7

0

18

3.6

6

HP

GC

L T

ota

l (T

he

rma

l an

d H

yd

ro =

32

30

.5 M

W)

Ge

ne

rati

on

(M

U)

37

57

.29

3

78

3.5

4

40

50

.98

3

79

2.4

1

53

10

.94

6

21

2.0

0

69

97

.53

6

91

4.9

6

91

81

.33

1

07

80

.21

1

08

45

.38

1

35

18

.97

1

51

01

.93

1

34

27

.17

1

11

78

.50

Wh

ile

th

e p

erf

orm

an

ce h

as

rem

ain

ed

fa

irly

co

nsi

ste

nt

till

FY

20

09

-10

fo

r H

PG

CL,

th

e p

erf

orm

an

ce p

ara

me

ter

ha

s sl

ipp

ed

do

wn

wa

rd d

ue

to

th

e

un

fore

see

n a

nd

un

con

tro

llab

le c

ircu

mst

an

ces.

In

th

is r

eg

ard

HP

GC

L e

xpe

ct f

rom

th

e H

on

’ble

Co

mm

issi

on

to

lo

ok

at

the

ab

ove

me

nti

on

ed

spe

cifi

c is

sue

s w

hil

e d

ete

rmin

ing

th

e G

en

era

tio

n T

ari

ff f

or

HP

GC

L fo

r th

e F

Y2

01

2-1

3.

Th

e p

eti

tio

ne

r h

um

bly

su

bm

its

the

se i

ssu

es

in t

he

sub

seq

ue

nt

sect

ion

of

the

pe

titi

on

.

Page 21: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

19

2.2. Operational constraints of HPGCL Power plants

2.2.1 Issues related to Quantity of coal

Presently HPGCL has linkage with CCL, BCCL, NCL and WCL effective from 1st April, 2009. Besides this

HPGCL is importing 10% coal as mandated by Govt. of India. HPGCL would like to put forth to the

Hon’ble Commission that the domestic supply of coal does not suffice the annual requirements of

coal as is evident from the table below:

Table 7: Raw Coal linkages of HPGCL for FY 11-12

Name of the Company Actual contracted Quantity(In Lakh MT) Percentage

Contribution PTPS DCRTPP RGTPP

CCL 22.90 28.00 - 35.8%

BCCL 18.50 - - 13.0%

NCL 16.00 - - 11.2%

WCL 8.60 - - 6.0%

MCL (Raw) - - 33.83 23.8%

MCL (Washed) - - - 0.0%

Import 6.00 2.00 6.50 10.2%

Total Tie-up of Indian Coal 66 28 33.83 100%

Coal Transit Loss upto Sep’11(%) 5.26% 9.09% 6.96%

Receipt of coal after Transit loss 62.52 25.45 31.47

Annual Requirement of Indian coal 68.67 28.33 67.45

Shortage of Indian coal 6.14 2.87 35.97

It is also pertinent to note that the coal received from the indigenous coal block consists of huge

amount of stones and boulders which has a significant impact on achievement of specified Technical

parameters.

The coal shortage position is further aggravated on account of very poor coal realization from some

coal companies as can be seen from the table given below. This results in payment of huge

performance incentive to some coal companies in terms of FSA for delivery of coal over and above

90% of Actual Contracted Quantity (ACQ). The overall realization of coal from domestic sources is

provided in the table below. As may be observed from the table that there is a significant shortfall in

receipt of coal from most of the domestic sources forcing HPGCL to depend upon the usage of

imported coal.

Table 8: Coal supply position of HPGCL Thermal power Plants

Plant PTPS Panipat (In lac MT) RGTPP Hisar (In lac MT) DCRTPP Yamunanagar (In lac

MT)

Year Linkage Receipt Realizati

on (%) Linkage Receipt

Realizati

on (%) Linkage Receipt

Realizati

on (%)

Page 22: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

20

Plant PTPS Panipat (In lac MT) RGTPP Hisar (In lac MT) DCRTPP Yamunanagar (In lac

MT)

2005-06 75.90 59.02 77.76 - - - - - -

2006-07 83.00 67.93 81.84 - - - - - -

2007-08 83.70 66.67 79.65 - - - - - -

2008-09 85.35 68.74 80.54 - - - 33.45 22.60 67.57

2009-10 66.00 74.71 113.20 - - - 27.96 25.25 90.29

2010-11 66.00 71.31 107.77 37.71 21.65 57.41 27.96 27.13 97.03

2011-12

(upto

Sep’11)

31.02 37.82 121.92 23.43 18.44 78.70 13.14 11.63 88.51

Further the coal is supplied to all the thermal generating stations of HPGCL based on Fuel supply

agreement (FSA) except for RGTPP, where coal is being procured on MoU route. In case of RGTPP,

the percentage of coal receipt was 57.41% during FY 2010-11 and 78.70% during FY 2011-12 till

Sep’11. Even in case of DCRTPP, Yamuna Nagar where the coal is procured through FSA route, the

quantity of coal received was 67.57% and 90.29% during the FY2008-09 and 2009-10 respectively.

During FY201-12 till Sep’11, the quantity received was 88.51%. The case highlights the events where

coal quantity received is less than the linkage. It is submitted that the shortage of coal supply is

appreciated as a national constraint across all utilities and MoP itself is suggesting the import of coal

in order to meet the shortfall.

As evident from the tables above that post signing of FSA on 1st

April 2009, the coal linkages for

PTPS, Panipat was reduced to 66.00 Lakh Tons per annum (ACQ) and that for DCRTPP, Yamunanagar

was reduced to 28 Lakh Tons per annum (ACQ). Here it also to be noted that there is no FSA for coal

supply at RGTPP, Hisar and the supply of coal is through MoU. Apart from that RGTPP, Hisar is also

getting coal through diversion from NCL which was earlier supplying coal to PTPS plants. Post

diversion PTPS is getting equivalent quantum of coal from BCCL.

Further, there are also Infrastructure constraints at coalfield under the command area of Mahanadi

Coalfields Limited (MCL) that has significant impact on the evacuation and supplies of coal. Millions

of tonnes of coal stocked at various pit heads could not be evacuated despite the best efforts of the

coal mining company due to poor and narrow roads which have not been renovated for years. It is to

be noted that RGTPP, Hisar is getting significant quantum of coal from MCL area. The table below

shows the Coal company-wise status of shortage during FY 2010-11 and FY 2011-12.

Table 9: Number of coal Rakes received at HPGCL power stations during FY 2010-11 and FY 2011-12

Coal Company Linkage/Mo

U Received

Shortag

e

Linkage/Mo

U Received Shortage

PTPS, Panipat FY 2010-11 FY 2011-12 (upto Oct’11)

Page 23: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

21

Coal Company Linkage/Mo

U Received

Shortag

e

Linkage/Mo

U Received Shortage

CCL 600 303 297 332 386 -54

BCCL 516 1273 -757 386 733 -347

NCL 432 342 90 140 116 24

WCL 231 131 100 127 47 80

Unknown / diverted 0 66 -66 0 12 0

Total PTPS* 1779 2115 -336 985 1294 -309

RGTPP, Hisar FY 2010-11 FY 2011-12 (upto Oct’11)

MCL 931 614 317 673 399 274

SCCL 52 5 47 191 144 47

Total RGTPP 983 619 364 864 543 321

DCRTPP, Yamuna Nagar FY 2010-11 FY 2011-12 (upto Oct’11)

CCL 729 746 -17 403 325 78

HPGCL(Indigenous

sources) FY 2010-11 FY 2011-12 (upto Oct’11)

Total 3,491 3,480 11 2,252 2,162 90

In spite of receiving more than 100% coal as compared to the ACQ, the coal stock at Panipat

remained low and insufficient. At times the power plant operated on hand to mouth basis. This

clearly indicate that the current ACQ is insufficient and the same will have to be augmented to

atleast 72 lakh tonnes per annum from 66 lakh tonnes per annum. Apart from this, HPGCL has to pay

additional amount as incentive to coal company in case of additional supply of coal over and above

ACQ. The table shows the month-wise coal linkage and receipt at PGCL plants.

Table 10: Month-wise Receipt of Coal at HPGC Power Stations during FY 2010-11 (upto 10.03.2011)

Month

Coal

Linkage (as

per FSA)

Coal receipt

during the

month (MT)

Coal Linkage

(as per FSA)

Coal receipt

during the

month (MT)

Coal Linkage

(as per FSA)

Coal receipt

during the

month (MT)

PTPS Panipat RGTPP, Hisar DCRTPP, Yamunanagar

April,10 550000 570316 462500 129220 233000 249930

May,10 550000 666538 462500 103090 233000 210678

June,10 550000 568604 462500 149630 233000 240553

July,10 484000 470445 462500 79495 205000 268738

August, 10 484000 540972 462500 145145 205000 222662

Sept. 10 484000 517867 462500 170495 205000 261148

Oct. 10 550000 623288 462500 226660 233000 147264

Nov. 10 550000 578069 462500 280973 233000 177473

Dec. 10 550000 649377 462500 233352 233000 188415

Jan, 11 616000 664411 462500 222700 261000 204657

Feb, 11 616000 608132 462500 321210 261000 199305

Mar, 11 (upto

10.03.2011) 198710 174707 149194 89560 84194 82729

Total 6182710 6632726 5236694 2151530 2619194 2453552

Page 24: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

22

To sort-out the issue of quantity of coal in HPGCL a committee was formed to explore the possibility

of the additional coal quantity in HPGCL Thermal Power Plant for the Financial Year 2011-12 and was

assigned to perform the following functions:

a) To explore availability of additional coal from existing subsidiaries of Coal India Ltd to meet

with the shortfall of coal for Thermal Power Plants of HPGCL;

b) To ensure the supply of good quality coal free from stones, boulders as per FSA already in

force for HPGCL thermal power plants.

c) To suggest additional measures to be taken for procurement of indigenous/ imported coal

by taking into account the projected receipt vis-a-vis the projected consumption of coal for

the year 2011-12;

Based on the recommendation of the committee, MoU was signed between SCCL and HPGCL for

supply of 5.0 Lac Tonne ‘D’/ ‘E’ grade coal from e-auction basket for the period from Feb’11 to

June’11. SCCL could supply approx. 44,000 MT coal and further suspended the movement of coal

rakes due to non-availability of spare coal. Accordingly, SCCL has been requested to extend the

period of MoU for another 6 months vide letter dated 17.06.2011. So, despite best efforts including

the possibility of e-auction, however, the quantity of coal received by the Units is not sufficient to

achieve full load and hence it will have an impact on the performance also. It is also to be noted that

the scarcity of coal has resulted into PLF reduction, Plant availability factor reduction, partial

operation of Units leading to higher auxiliary consumption etc.

2.2.2 Issues related to Quality of coal

Besides the hitches in shortage in supply of coal, HPGCL is plagued with the supply of inferior quality

of coal. The gross calorific value of coal supplied by the collieries is deteriorating over the years and

is much lower than the design calorific value of the boilers. The table below shows the design

calorific value for the HPGCL power plants:

Table 11: Design calorific value of HPGCL thermal Power Plants

Power Station PTPS,Panipat RGTPP,Hisar DCRTPP,Yamunanagar

Unit Unit-1 to 5 Unit-6 to 8 Unit-1&2 Unit-1&2

Design Calorific value (Kcal/kg) 4800 4000 4000 4000

However, the coal received by HPGCL in its Plants has witnessed a gradual decline in the quality with

year on year decline in GCV. The table below presents the annual average GCV of coal received by

HPGCL for its various plants.

Page 25: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

23

Table 12: Calorific value of coal received at HPGCL Plants

Year PTPS, Panipat(kCal/Kg) RGTPP, Hisar(kCal/Kg) DCRTPP, Yamuna Nagar (kCal/Kg)

1998-99 3,902 - -

1999-00 3,979 - -

2000-01 4,053 - -

2001-02 4,193 - -

2002-03 4,237 - -

2003-04 4,252 - -

2004-05 4,091 - -

2005-06 4,109 - -

2006-07 3,995 - -

2007-08 3,934 - -

2008-09 3,900 - 3,670

2009-10 3,801 - 3,725

2010-11 3,636 3,034 3,589

2011-12* 3,506 3,117 3,606

2011-12

(post-

blending)*

3,707 3,742 4,000

* GCV for 6 months ending September 2011.

The trend of deteriorating GCV can be seen in the table above, where the GCV of coal received for

PTPS has declined from 3,934kCal/Kg in 2007-08 to 3,506kCal/Kg, during the ensuing year. The GCV

of coal received for RGTPP during the year FY 2010-11 and current year FY 2011-12 has been

extremely poor. As despite blending upto10% of the imported coal (GCV of 6200kCal/Kg) the

average GCV achieved is around 3,742kCal/Kg.

High percentage of ash content in coal:

The real condition of raw coal received at HPGCL plants is that the percentage of ash content in coal

is in the range of 31% - 52%. Such high ash percentage results in faster erosion of boiler parts and

frequent breakdown of HPGCL Units.

The quality of coal plays an important role to deliver optimal operations of a thermal power project.

It also has impact on the operations and maintenance (O&M) cost, Station Heat Rate (SHR), auxiliary

consumption and secondary fuel oil consumption. It may be noted that deteriorating coal quality

results in:

a. Higher ash content leads to higher fuel consumption thereby having a detrimental effect on

SHR;

Page 26: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

24

b. Chokage of pulverisers causes either partial loading of mills or forced outage thereby affecting

the plant PLF or Availability;

c. Increased erosion in the boiler tubes causing frequent tube leakages and forced shutdowns

thereby reducing the PLF;

d. Increased auxiliary consumption on account of increased fuel consumption to maintain the

required thermodynamic parameters;

e. Increased specific fuel oil consumption to address flame stability and required furnace

temperature;

f. lowering boiler efficiency and erosion of boiler tubes leading to high outages and high wear

and tear of milling and coal carrying system;

g. Increased usage of auxiliaries of Coal Handling Plant and Ash Handling Plant on account of

poor coal quality and high ash content respectively;

The quality of coal impacts the coal handling systems, feeders, pulverizers and burners. The largest

impact will be on the pulverizer, where an increased throughput can not only lead to increased

auxiliary consumption, higher maintenance and potential limitations on the maximum achievable

load, but will also reduce the availability of the Unit through more failures and a decrease in the

maximum generation capability of the Unit.

As the quality of coal decreases and the fuel burn rate increases, the quantity of flue gas traveling

through the steam generator increases. Coupled with the increase in ash content, this causes an

increase in tube failures, impacting both maintenance and availability.

It is also pertinent to note that the coal received from the indigenous coal block consists of huge

amount of stones and boulders which sometimes lead to choking and/or damages the coal handling

equipment. The same ultimately impacts the overall technical performance of the Units. HPGCL is

making efforts and is pursuing the matter with the coal companies to check the quality of coal being

supplied to the stations.

Although HPGCL is making all effort to overcome the coal related issues but the issues related to the

colliery side are beyond the control of HPGCL.

2.2.3 Washing of coal

Like most of the power generating companies, HPGCL is also in a process of arranging handsome

quantity of washed coal which is billed on delivered at destination basis. For this, HPGCL has

Page 27: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

25

initiated the efforts for improving the quality of coal at RGTPS, Khedar, Hisar and issued work order

for washing and supply of washed coal to RGTPP, Khedar, Hisar. HPGCL has taken these steps with

the following objectives:

• Washing of indigenous Coal supplied by MCL to improve GCV and to reduce ash content.

• Washing of coal reduces cost of generation and wear and tear of equipment due to better

GCV and reduced ash content.

RGTPP, Hisar is having coal linkage of 5.55 MTPA (Million tonne per annum) of ‘F’ grade coal with

MCL which is being washed by four (4) washery operators. The details are given in the table below:-

Table 13: Details coal of Washery Operators in HPGCL

Sl. Name of Washery Operators Ordered

quantity (MTPA) Location

1. M/s ACB (India) Pvt. Ltd., 1.39 Himgir Coal Washery, Distt. Sundargarh. Orissa

2. M/s Bhatia International Ltd., 1.39 Chhualiberna, Belphar, Jharsughda (Orissa)

3. M/s Global Coal & Mining Pvt.

Ltd., 0.92

Near Lakhanpur OCO, P.O. Ubuda via Belphar, Distt.

Jharsughda (Orissa)

4. M/s Gupta Coalfields

&Washeries Ltd., 1.85

Earth Mineral Co. Ltd.(Subsidiary Gupta Coalfields

&Washeries), Plot No. 38(p), Village: Kirarama, Post-

Bandhbahal, Distt. Jharsughda, Orissa-768211

HPGCL is also exploring the possibility of appointing washery operators for their other Thermal

power stations.

2.2.4 Dependence on imported coal

Looking at the unique characteristics of the coal in terms of quality and availability for the HPGCL

plant from indigenous sources, the dependence of HPGCL has increased on the imported coal. On

the other hand HPGCL based on its internal observations is of the view that the cost of procurement

of coal through e-auction is more expensive than imported coal. Accordingly, HPGCL has placed an

order with PEC for import of 14.5 Lac MT coal at fixed FOB of USD 83.75/MT & USD 85.75 / MT for

PTPS, DCR TPS & RGTPS respectively for FY 2011-12. The landed cost of the same is estimated at Rs.

5294.14/MT, Rs. 5378.74 / MT and Rs. 5346.42 / MT for PTPS, DCRTPS and RGTPS for FY 2011-12.

Further, based on the order placed to M/s PEC for FY 2011-12, the cost per GCV of indigenous coal

and imported coal has minor differences which are proposed to be recovered through FPA. The cost-

benefit of the imported coal is also attached as the annexure with this petition which indicates that

overall there is negligible difference in cost per GCV of coal after blending vis-à-vis cost per GCV of

Indigenous coal. Hence under the given circumstances, procurement of imported coal is a forced

Page 28: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

26

alternative on account of poor quality of indigenous coal. Accordingly, HPGCL hereby prays to the

Hon’ble Commission to allow coal import beyond 10% as mandated by Govt. of India and also to

procure coal through e-auction process as well as from private sources to meet the coal shortage in

HPGCL.

2.2.5 Moisture Loss:

One of the reasons of Transit loss in coal arises due to the difference in the quantum of coal loaded

at the loading point by the Coal Company and the coal received at the unloading point in the Power

plant. Such losses generally arise on account of

· Superficial Surface Moisture in the washed coal

· Evaporation of moisture as well as powdered coal during transportation of coal;

HPGCL for its RGTPP, Khedar, Hisar power plant IPGCL is getting washed coal to the extent of 5.5

MTPA in FY 2011-12 pursuant to the contract with four (4) washery operators. During benefaction of

coal through washing technique, coal absorbs water resulting in higher weight at the time of loading.

The extra moisture evaporates during transit and storage. Therefore, usage of Washed coal leads to

higher moisture content and results into higher losses during transit. The loss of approx. 3% is due to

extra moisture in washed coal used in the RGTPP, Hisar power Stations. It is submitted that the

higher coal transit loss in terms of moisture loss is beyond the control of the petitioner.

2.3. Coal transit loss

During the process of extraction from the mine upto loading to the boiler, the coal passes through

various stages of stacking, reclaiming, loading, transportation, un-loading, crushing, etc. At various

stages water is sprayed to prevent spontaneous combustion and minimize coal dust pollution. This

results in increased moisture content in coal and corresponding deterioration in its quality and also

adds to the weight of coal at the loading point. Thus, the coal when weighed at the loading point

contains water whereas when weighted at the unloading point, there is a loss in weight due to

evaporation of moisture/volatile matter during transportation and due to pilferage loss. The key

factors attributing to transit loss of coal are:

i. Evaporation of surface moisture in transit,

ii. Error/Deviations in Weighbridges,

iii. Coal theft in transit,

Page 29: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

27

iv. Long distances involved in coal transport also contributes to transit loss,

In this section, the Petitioner hereby requests the Hon’ble Commission to allow the actual transit

losses as the same is largely an uncontrollable factor. The following section highlights the regulatory

provision related to Transit loss which is enforced by different regulatory commissions.

2.3.1. Regulatory provisions for transit loss

CERC (Terms and condition of Tariff) Regulation for FY 2009-14

As per clause 21 (7) of the regulation, CERC notified that in case of coal/ lignite the landed cost of

fuel shall be after considering normative transit and handling losses as percentage of the quantity of

coal or lignite dispatched by the coal or lignite supply company during the month as given below:

· Pithead generating stations : 0.2%

· Non-pithead generating stations : 0.8%

CERC (Terms and Conditions of Tariff) Regulations, 2009, Statement of Objects and Reasons

In the statements of objects and reasons for the terms and conditions of Tariff regulation 2009 the

CERC has clarified that the norms for transit losses has been specified based on the actual transit and

handling losses of the NTPC stations for the year 2004-05 to 2007-08.

“Transit and Handling losses {Regulation 21(7)}”

25.1 The Commission proposed the norms for the transit and handling losses of coal/lignite in the

draft regulation as under:

· Pit Head Station - 0.2%

· Non Pit Head Station - 0.6%

25.2 Most of the beneficiaries and state utilities have submitted during the hearing and in their

written submissions that the above norms of transit and handling losses are too stringent

and cannot be achieved by them. They have further, submitted that the transit and handling

losses in respect of their stations are in excess of 2%. They have serious concerns that the

norms as per CERC if adopted by the SERCs would lead to irreparable losses for them. They

sought to specify norms for the state utilities as well as in this regard.

Page 30: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

28

25.3 It needs to be appreciated that the CERC is specifying norms based on the data of NTPC

stations available with them. The actual transit and handling losses for the year 2004-05 and

2007-08 of NTPC stations are as follows:

Table 14: NTPC Thermal Power Plants details

Sl. Stations Capacity

(MW)

COD of

last Unit FY-05 FY-06 FY-07 FY-08

Average

(%)

Non Pit-Head Stations

1 Dadri (4x210) 840 1.12.1995 0.52 0.66 0.6 0.78 0.64

2 Unchahar (2x210+2x210+210) 1050 1.1.2007 0.6 0.6 0.6 0.64 0.61

3 Simhadri (2x500) 1000 1.3.2003 0.17 0.54 0.72 0.71 0.54

4 Badarpur (3x95 +2x210) 705 1.4.1982 0.56 0.57 0.69 0.77 0.65

5 Tanda (4x110) 440 20.2.1998 0.49 0.52 0.4 0.25 0.42

6 Kahalgaon (4x210) 840 1.8.1996 0.15 0.21 0.26 0.25 0.22

7 Farrakka (3x200+2x500) 1600 1.7.1996 0.33 0.34 0.28 0.2 0.29

Average 0.48

Pit-Head Stations

1 Talchar (2x500 + 4x500) 3000 1.8.2005 0.02 0.07 0.12 0.2 0.10

2 Rihand (2x500 + 2x500) 2000 1.4.2006 0.08 0.05 0.18 0.25 0.14

3 Korba (3x200+3x500) 2100 1.6.1990 0.02 0.12 0.28 0.23 0.16

4 Singrauli (5x200+2x500) 2000 1.5.1998 0.09 0.1 0.1 0.1 0.10

5 Ramagundam

(3x200+3x500+1x500) 2600 25.3.2005 0.21 0.23 0.23 0.24 0.23

6 Vindhyachal

(6x210+2x500+2x500) 3260 15.7.2007 0.18 0.15 0.22 0.23 0.19

7 Talchar taken over (4x60+2x110) 460 3.6.1995 0.16 0.26 0.24 0.25 0.23

Average 0.16

25.4 It can be seen that average transit and handling losses of pit head stations are of the order of

0.16%. In case of non-pit head stations, namely Dadri, Unchahar, Simhadri and Badarpur, the

transit and handling losses are of the order of 0.54% in Simhadari to 0.6% in Badarpur. In

case of Tanda, Kahalgaon, Farakka, these are much less than other non-pit stations. In case

of Kahalgaon & Farakka, the reason for low losses is that these are supplied coal through

MGR system but a substantial quantity is also supplied through distant mines. As such, it

would not be reasonable to treat these stations at non-pit head stations. The transit and

handling losses for non-pit stations like Dadri, Unchahar, Simhadri, and Badarpur in the year

2007-08 ranges between 0.64% to 0.78%.

25.5 In view of this, we are of the opinion that the norms of 0.6% for non-pit head station would

not suffice and hence we are retaining the existing norm of 0.8%. In respect of pit head

stations, norms of 0.2% appear to be in order.

Page 31: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

29

However the CERC has also clarified in point no 25.6 that

25.6 As regards norms for the state sector projects, the Commission expects the State

Commissions to specify suitable norms after due regard to the actual situation and

distance involved in the transportation of coal in respect of stations being regulated by

them.

Keeping in mind the fact that transit loss depends upon uncontrollable factors like long distance of

transit from coalfields to the generating station and its effect on evaporation, wind, seepage, theft

and pilferage in transit; HPGCL prays to the Hon’ble HERC to revise the norms in due consideration

the approach taken by other SERCs and the actual situation in case of the HPGCL as explained below:

HERC (Terms and condition for determination of Generation Tariff) Regulations, 2008

Even the Hon’ble HERC in its Generation tariff regulation has talked about relaxation of norms as

state below:

As per HERC regulation, the landed cost of coal for the purpose of computation of energy charges

shall be arrived at after considering 0.8% normative transit and handling losses of the quantity of

coal dispatched by the coal supply company. The cost shall be considered as per the notifications of

the central government or coal companies. In the absence of any recent notification, the weighted

annual average cost of the current year adjusted for known changes shall be considered as the cost

while computing generation tariff. The commission may relax the norm in the light of achievability

of the norm and circumstances specific to the generating stations.

2.3.2. Experience from other states

Gujarat Electricity Regulatory Commission

In Gujarat, GERC approved the coal transit loss of 1.4% for generating stations at Gandhinagar and

Wanakbori Power stations. Torrent Power appealed before APTEL that this cannot be the basis for

the comparison with the transit losses as Torrent procures coal directly from the mines and

Gandhinagar and Wanakbori power stations are using washed coal. After analysis in the matter

APTEL found that the transit losses in the Railway transportation do occur as there is no control of

the generators. Coal transportation in open wagons of unwashed coal procured directly from the

mines which has larger lumps of coal are more prone to pilferage unlike the washed coal. Thus,

APTEL in its judgment dated 23rd

March 2010 ordered the Hon’ble GERC to give consideration to

Page 32: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

30

washed and unwashed coal and told GERC to decide the increase percentage of allowable coal

transit losses for Torrent Power Plants.

Punjab Electricity Regulatory Commission

In PSPCL Tariff order for FY2011-12, in case of coal other than PANAM Coal (Board’s Captive Coal

Mine), transit loss of 2% has been allowed by the Hon’ble PSERC. The table below gives the plant

wise details of transit loss approved by the commission:

Table 15: Transit loss (%) approved by PSERC

Name of

Power Station

Approved by PSERC

in TO for FY-10

Approved by PSERC in

True up for FY2009-10

Approved by PSERC

for FY2010-11

Approved by

PSERC for FY-12

GNDTP 0.66% 2% 2% 2%

GGSSTP 1.14% 2% 2% 2%

GHTP 1.16% 2% 2% 2%

Bihar Electricity Regulatory Commission

For Barauni Thermal Power Station (BTPS) of Bihar State Electricity Board (BSEB) the transit loss of

3.8% has been approved by Hon’ble BERC in its Tariff order for FY 2011-12.

Appellate Tribunal for Electricity Judgment on Appeal No 26 of 2008 dated 07.04.2011:

Indraprastha Power Generation Company Limited Versus Delhi Electricity Regulatory Commission

(DERC)

Coal Transit loss for IPGCL has been estimated to be 3.80% during the control period as well as

during FY 2011-12 as against the approved transit loss of 0.80%. IPGCL appealed against the DERC’s

order before the Hon’ble Appellate Tribunal of Electricity. On which APTEL gave the ruling on

07.04.2011 that

“According to the Appellant, the State Commission has allowed a normative coal transit loss of 0.8%

by holding that the same is nationally accepted loss level as prescribed in the Tariff Regulations of the

Central Commission. It is noticed that the State Commission has rejected the claim of the Appellant

merely on the ground that NTPC had not challenged the coat transit loss for the Dadri and Badarpur

Stations which requires the same washing of coal. As pointed out by the Learned Counsel for the

Appellant, the ground that NTPC had been allowed only 0.8% coal transit loss and the same had not

been challenged by the NTPC cannot be the valid ground to deny the claim of the Appellant. The

important aspect that the State Commission has failed to consider is that the transit loss cannot be

the same both for unwashed and washed coal. The weight of the coal at the time of loading is

Page 33: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

31

significantly increased due to higher moisture content which evaporates during transit and storage.

We notice that the State Commission has not given a reasoned order regarding transit loss. Instead

of examining the transit loss in case of the Appellant’s power station the State Commission has

noticed that the use of washed coal is likely to improve the functioning of the plant. This matter,

therefore, needs re-examination. Therefore, the State Commission is required to determine the actual

coal transit loss in respect of the Appellant’s Power Station without comparing the coal transit loss

with the NTPC. This point is answered accordingly”.

Accordingly the Commission was requested by IPGCL to true up the transit and moisture loss @ 3.8%

for coal based stations of IPGCL for FY 2007-08 to FY 2010-11 and to approve the same for FY 2011-

12 for Rajghat Power House.

The table below provides the comparison of transit loss approved by the respective SERCs with that

provided in the respective state regulations:

Table 16: Comparison of State regulation with actual transit loss approved by SERC for FY12

State As per State

regulation

Approved

by SERC Remarks

Gujarat – Torrent

Power* 0.8% 1.4%

APTEL ordered GERC to decide the increase percentage of

allowable coal transit losses for Torrent Power Plants on

the basis of differentiation between washed and

unwashed coal

Bihar 0.8% 3.8% -

Punjab 2% 2%

No transit loss is allowed for PANAM Coal (Board’s Captive

Coal Mine), for other coal transit loss of 2% has been

allowed by the PSERC

Delhi – IPGCL 0.8% 0.8%

APTEL after examination of plea by IPGCL requested DERC

true up the transit and moisture loss @ 3.8% for coal based

stations of IPGCL for FY 2007-08 to FY 2010-11 and to

approve the same for FY 2011-12.

* Appeal against GERC order for control period FY09 to FY11.

2.3.3. Impact of distance on the transit loss:

As stated in Hon’ble CERC in Statement of Objects and Reasons (Terms and Conditions of Tariff

Regulations2009):

“As regards norms for the state sector projects, the Commission expects the State Commissions to

specify suitable norms after due regard to the actual situation and distance involved in the

transportation of coal in respect of stations being regulated by them.”

Gujarat Electricity Regulatory Commission (GERC) in Multi-Year Tariff Order and Truing up Order

for FY 2009-10, Annual Performance Review for FY 2010-11, Aggregate Revenue Requirement for

Page 34: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

32

FY 2011-12 to FY 2015-16 and Determination of Tariff for FY 2011-12 for Torrent Power Limited

(TPL) under Case No. 1092 of 2011 dated 6th

September, 2011 stated that

“The Commission has allowed a transit Loss of 1.4%, as against the normative loss of 0.8%,

considering the long distance involved and consequential losses. The Commission feels there is

scope for considerable reduction in transit loss through vigorous and sustained efforts.”

Also,

“The Appellate Tribunal for Electricity (APTEL), in its order dated 23rd March, 2010, opined that

some consideration deserves to be given for increased transit loss. However, the APTEL left it to

the State Commission, to decide increased percentage of allowable coal transit losses for TPL-G

stations. Consequently, GERC decided to approve transit loss of coal at 1.9% for the years FY 2009-

10 and 2010-11 in their review order dated 05.09.2011 in the Petition No. 966 of 2009.”

On the matter of distance and related transit loss, the state such as the power stations of BSEB

which receives coal from CIL (and subsidiaries) and ECL; the highest distance for the coal transit from

the mines of CIL and ECL located in the state of Jharkhand, west Bengal to the Barauni Thermal plant

of BSEB is around 300 km. However, the coal transit loss as approved by the Hon’ble BERC is 3.8%

keeping in mind the fact the uncontrollable nature of coal transit loss. Further, this allowance by

BERC is in line with the actual situation and is more than the transit loss norm specified by the BERC

in its tariff regulation.

On the same line if we look at the distances of the HPGCL plant from the coalfield from where HPGCL

is sourcing the coal, a higher transit loss cannot be avoided. The details of the coal suppliers and the

distance of coal block from of the HSPGCL plant is as given below:

Table 17: Source-wise distance of coal block from HPGCL plants

Sl.

Name of

the Power

Plant

Name of

the Coal

company

Head

quarter Location of the mines

Name of the

State

Average

distanceof HPGCL

plant from coal-

block (Km)

1. PTPS CCL Ranchi Bokaro, Karanpura,

Ramgarh and Giridih Jharkhand 1350

2. PTPS BCCL Dhanabad Jharia,Raniganj Jharkhand West

Bengal 1440

3. PTPS WCL Nagpur

(Maharashtra - Nagpur ,

Chandrapur, Yeotmal),

MP ( Betul,

Chhindawara)

Maharashtra,

Madhya

Pradesh

1125

Page 35: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

33

Sl.

Name of

the Power

Plant

Name of

the Coal

company

Head

quarter Location of the mines

Name of the

State

Average

distanceof HPGCL

plant from coal-

block (Km)

4. PTPS,

RGTPS NCL Singruli Singruli

Madhya

Pradesh 1110

5. RGTPS MCL Sambalpur IB valley and Talcher Orissa 1535

It is also to be noted that, the dispatch and transportation of coal calls for inter-agency coordination

between Railways and Coal Companies. HPGCL does not have much control in this area. Railways do

not own the responsibilities for loss of coal in transit. The coal is transported in open wagons from

coalmines from a distance of more than 1000 km and there are high chances of pilferage of coal en-

route.

However, it is a fact that in-spite of having higher transit loss, HPGCL has no control over the inter-

agency involvement namely Indian railways and coal companies and HPGCL cannot claim any

compensation from coal company/ railway which add to the financial burden of the HPGCL. It is also

to be noted that neither railway nor other companies such as Insurance companies are ready to take

the responsibility of coal transit loss even after HPGCL is ready to pay premium to them. None of

these agencies are ready to accept to bring down the coal transit loss at the HERC specified norms.

HPGCL prays to the Hon’ble commission to suggest any third party agency which may take up the

responsibility of controlling transit loss at HERC’s specified norms; HPGCL will bear the charges for

appointment and services of such agency for handling coal transit losses.

Table 18: Year wise transit loss (%) of HPGCL plants

Year FY 01 FY 02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11 FY 12 (Upto

Sep’11)

PTPS 6.32 6.07 6.16 3.79 3.69 4.53 3.02 4.59 1.76 3.71 7.57 5.26

RGTPP - - - - - - - - - - - 6.96

DCRTPP - - - - - - - - - 3.19 7.17 9.09

Thus, keeping in view the fact that loss of coal in transit is beyond the control of HPGCL, HPGCL prays

the Hon’ble Commission to consider the impact of abovementioned issues in the coal transit and

kindly approve the coal transit losses for FY 2012-13 as proposed in the petition.

2.3.4. Coal agent

Coal agents/firms are appointed for the purposes of supervision of loading and weighment at the

loading points of coal rakes consigned to power stations in order to minimize short receipt of coal at

destination and also to render liaison services with Coal Companies, Railways and other agencies for

Page 36: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

34

linkage materialization, quality assurance in connection with dispatch of coal. Because of the stiff

transit loss reduction target set by the Hon’ble Commission, even the agencies are not ready work

on behalf of HPGCL at the stipulated coal transit loss at a level of 0.8%. In this regard, HPGCL prays to

the Hon’ble commission to suggest any third party agency which may take up the responsibility of

controlling transit loss at HERC’s specified norms; HPGCL will bear the charges for appointment and

services of such agency for handling coal transit losses.

2.4. R&M of HPGCL power plant: PTPS Panipat

In order to improve the performance of all the 4X110 MW Units of PTPS-1, which are quite old and

of obsolete technology, the Renovation & Modernisation of these Units has been started with the

following objectives:

· To extend the life of the Units.

· To restore original rated capacity of the Units.

· To improve Plant availability/load factor.

· To enhance operational efficiency and safety

· To remove ash pollution and to meet up environmental standards.

In order to overcome problems/constraints adversely affecting the generation of Units-1 and 2 of

110 MW each commissioned in November 1979 and March 1980 under Stage-I, Renovation and

Modernisation (R & M) Schemes under Phase I and Phase II were approved by the Planning

Commission in March 1987 and November 1990 respectively. In pursuance to the policy of

Government of India to optimise power generation, a comprehensive R & M Scheme was adopted

by the erstwhile Board for rehabilitation of the existing four Units of 110 MW each at PTPS.

Competitive bids were invited (August 1995) and the contracts were awarded (23 May 1997) to ABB

Kraftwerke Berlin GmbH (now ABB Alstom Power), being the successful lowest bidder. ABB Alstom

Power (contractor) had guaranteed to enhance the capacity of the four Units (Unit-1 to 4) from 110

MW to 118 MW each with the objective to achieve a PLF of 85 per cent and improve the heat rate of

the Units from 3339 kCal/kWh to 2051 kCal/kWh.

Table 19: Shut-down details of PTPS Unit- 1&2

Power Station Period of Shut-down

PTPS Unit-1 Sep 2007 to Oct 2008

PTPS Unit-2 Jan 1999 to Mar 2003

Page 37: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

35

The R&M scheme undertaken by the erstwhile Board at huge cost to improve the performance of

these Units did not produce the desired results. The refurbishment work taken up (May 1997) for

Unit-1 to 4 through a foreign contractor could not be completed as planned due to dispute with the

foreign contractor who had terminated the contract itself. The dispute could not be sorted out in

spite of intervention of the Government of India and CEA. As a result, substantial investment was

locked up in certain works put on hold besides huge loss of potential generation and payment of

commitment charges/guarantee fee on loans.

As per plan, the entire refurbishment work of all the four Units was to be completed by 21

November 2000. As per the schedule of refurbishment work, Unit-2 (first target Unit) was placed

under shutdown and handed over to the contractor M/s ABB Germany (now Alstom Power) on 21

January 1999 for refurbishment of the Unit which was to be completed by 20 May 1999.Meanwhile,

the contractor terminated (17 April 2000) the contract and abandoned the work unilaterally.

Figure 4:Impact of R&M on the PLF of PTPS Unit-2

Subsequently, the pending works of Unit-2 had to be completed from BHEL and HPGCL awarded the

contract for R&M of Unit-2 of PTPS having capacity of 110 MW to M/s BHEL vide L.O.I. dated

27/03/2002. It is also to be noted that M/s BHEL did not agree for any guaranteed parameter on

completion of pending R&M work of Unit-2. The main reason was that M/s BHEL was not having the

drawing of the work completed by M/s ABB (now Alstom Power). As per the contract Unit-2 was to

be commissioned within 8 months from the issue date of L.O.I. BHEL started the work on BTG in July

2002 and BHEL EDN, Bangalore and BHEL Bhopal started the work of C&I and electrical resp. in

October 2002 only.

Table 20: Impact of R&M on performance of PTPS Unit 2(110 MW)

Year PLF(%) Auxiliary

Consumption (%)

Generation

(MUs)

Station Heat

Rate (Kcal/kwh)

Oil Consumption

(ml/kwh)

19 17 18 20 17 26 29 30 32

1

72 59

71 77

67 74 71

35

82

0

20

40

60

80

100

PLF Trend for PTPS Unit-2

32

1

R&M

Phase

Page 38: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

36

Year PLF(%) Auxiliary

Consumption (%)

Generation

(MUs)

Station Heat

Rate (Kcal/kwh)

Oil Consumption

(ml/kwh)

1995-96 26.47 14.87 255.80

38.35

1996-97 28.70 14.67 276.59

44.57

1997-98 30.04 12.56 289.45

38.12

1998-99 31.96 12.86 307.96 3916 32.10

1999-00 - - - - -

2000-01 - - - - -

2001-02 - - - - -

2002-03 0.87 0.00 8.42 4973 172.06

2003-04 72.38 11.05 699.38 3511 6.33

2004-05 59.34 12.13 571.82 3555 5.22

2005-06 70.65 11.75 680.81 3509 5.07

2006-07 77.37 11.59 745.50 3345 3.41

2007-08 67.39 12.13 651.13 3474 3.43

2008-09 73.61 11.48 709.27 3416 2.38

2009-10 71.26 11.75 686.70 3290 2.10

2010-11 35.05 13.59 337.79 3208 4.42

2011-12

(upto Sep’11) 82.07 11.21 396.49 3217 2.93

Note-1: The unit was under shutdown for R&M from Jan 1999 to March 2003

Note-2: ABB Alstom Power had guaranteed to enhance the capacity of the four Units (Units 1 to 4) from 110

MW to 118 MW each with the objective to achieve a PLF of 85 per cent and improve the heat rate of the Units

from 3339 K.Cal./kWh to 2051 K.Cal./kWh.

After carrying out the R&M work of the Unit-2, the testing and commissioning activities of 110 MW

Unit- 2 were started by BHEL in the first week of December 2002. The boiler lighted up on

05.02.2003 with HSD and the Unit was synchronized on 09.02.2003 at 12.19 hrs. However the same

was de-synchronized on the same day at 12.40 hrs to make available all other systems including

milling system for the sustainable operations of Unit. The coal firing was achieved on 21/22.03.2003

and Unit was synchronized with Grid. The maximum load of 100 MW was achieved on 26.03.2003 at

17:00 hrs and Unit-2 had recorded the generation of 8.415 MU in two days. Till 31 March 2003 four

(4) coal mills had been commissioned and taken into the service but the 5th

mill E was not

commissioned by BHEL. However Unit was boxed up on 28.03.2003 to check and plug the excessive

hydrogen leakage from generator. As a whole, the R&M had not resulted into achievement of

desired results for PTPS Unit-2 as shown in the Graph-3 above; also post R&M the Unit-2 of PTPS

could never achieve the guaranteed level of PLF of 85%. In terms of annual SHR of PTPS Unit-2which

was 3916 Kcal/kWh for FY 1998-99 before refurbishment and it was 3511 Kcal/kWh during FY 2003-

04 against the contracted provision of around 2051 Kcal/kWh.

Page 39: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

37

Table 21: Impact of R&M on performance of PTPS Unit-1 (100 MW to 117.8 MW)

Year PLF(%) Auxiliary

Consumption (%)

Generation

(MUs)

Station Heat Rate

(Kcal/kwh)

Oil Consumption

(ml/kwh)

1997-98 27.17 12.56 261.78 3984 34.72

1998-99 21.90 12.86 211.03 3984 39.73

1999-00 44.47 12.90 429.65 3693 13.36

2000-01 46.17 12.69 444.87 3682 11.97

2001-02 30.77 12.39 296.55 3847 11.68

2002-03 58.09 11.66 559.78 3741 6.26

2003-04 63.09 11.05 609.64 3497 4.50

2004-05 52.59 12.13 506.77 3554 5.13

2005-06 59.40 11.75 572.40 3508 4.97

2006-07 62.63 11.59 603.53 3342 3.11

2007-08 25.29 12.13 244.38 3480 4.14

2008-09 28.94 11.30 278.86 3480 9.42

2009-10 79.08 10.37 815.16 3047 1.95

2010-11 48.90 10.71 504.60 3112 4.08

2011-12

(upto Sep’11) 79.18 11.38 409.66 2886 2.04

* Unit has been uprated from 110 MW to 117.8 MW w.e.f. 07.04.2009.

Note: The unit was under shutdown for R&M from Sept. 2007 to Oct 2008

Note-2: ABB Alstom Power had guaranteed to enhance the capacity of the four Units (Units 1 to 4) from 110

MW to 118 MW each with the objective to achieve a PLF of 85 per cent and improve the heat rate of the Units

from 3339 K.Cal./kWh to 2051 K.Cal./kWh.

After that, R&M work of PTPS Unit-1 was also awarded to M/s BHEL in October 2006 which was

completed in October 2008.Under the R&M of Unit-1 of PTPS Panipat, refurbishment of Unit-1was

carried out through M/s BHEL during FY 2007-08 & 2008-09. In this case also, the performance of the

Unit after refurbishment has not been up to the mark and the desired improvements in performance

have not been achieved. The annual SHR of PTPS Unit-1 was 3342 Kcal/kWh for FY 2006-07 before

refurbishment and it was 2886 Kcal/kWh during FY 2011-12 (up to Sep’11) against the contracted

provision of around 2346 Kcal/kWh. Although the Unit-1 was commissioned in 04.11.2008 after

refurbishment, the PG Tests are yet to be completed. Similar to Unit-2, the performance of PTPS

Unit -1 posts R&M was also not sustainable as shown in the graph below:

Page 40: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

38

Figure 5: Impact of R&M on the PLF of PTPS Unit-1

HPGCL till date have not got any Capital Expenditure approved for R&M of PTPS Unit 1-4, except for

Unit No. 1, for which they have already proposed better norms than other Units. Additionally, HPGCL

submits that R&M of PTPS Unit - 3 & 4 has been finalized with the World Bank funding and shall be

carried out in FY 2013-14. An analysis of the performance during FY 2011-12 (up to September 2011)

reveals that PLF of PTPS Units 1-4 is 68.65% as against 57.89% during FY 2008-09 and last seven

years best achieved of 72.45% (FY2003-04). PTPS Unit-1 attained a marginal improvement in PLF in

FY 2009-10 i.e. 79% consequent to the comprehensive R&M & up gradation to 117.8 MW got carried

out by BHEL.

Moreover, HPGCL has already submitted their business plan to the Hon’ble HERC on 8th

April 2009

vide Memo No. HPGC/ FIN/ Reg-317/535. Subsequently, after a series of queries and their responses

to the Hon’ble HERC, on 15th

Oct 2010, HPGCL has responded to the Hon’ble regarding all the

clarification w.r.t.the Business plan. However, the Hob’ble HERC has not yet approved the Business

plan, which is also impacting the performance of HPGCL plants.

Case of R&M of Guru Nanak Dev Thermal Plant, Bhatinda (GNDTP), PSPCL

PSPCL has carried out the R&M of GNDTP, Bhatinda during FY 06 and FY07. The details of the GNDTP

are as follows:

Table 22: Unit-wise GNDTP plant capacity and date of commissioning

Name Unit Capacity (MW) Date of Commissioning Date of Commissioning after R&M

GNDTP

U-1 110 22.9.74 April 2007

U-2 110 19.9.75 January 2006

U-3 110 29.3.78 -

U-4 110 31.1.79 -

27 22

44 46

31

58 63 53

59 63

25 29

79

49

79

0

20

40

60

80

100

PLF Trend for PTPS Unit-1

25 29

R&M

Phase

Page 41: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

39

As seen from the above table it is clear that all Units of the GNDTP had completed more than their

designed life of 25 years. The PSPCL had undertaken the R&M of the all Units in a phased manner

with the following objectives as stated:

· To restore original rated capacity of the Units. (Uprating of capacity from 110MW to 120

MW for Units-3 & 4)

· To improve plant availability/load factor.

· To extend the life of the Units by 15 to 20 years.

· To enhance operational efficiency and safety

· To remove ash pollution and to meet up environmental standards of Pollution Control Board

· Energy Conservation.

Results of R&M work of Unit-1 and 2 at GNDTP Bhatinda:

Table 23: Operational parameters of GNDTP pre and post R&M

Parameter FY01 FY02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11

PLF (%) 72.5 71.7 64.8 66.0 68.9 57.8 56.8 77.8 73.8 70.7 46.0

SHR (kCal/kWh) 2929 2870 2865 2801 2899 2923 2841 3047 3151 3035 2963

Specific Oil

Consumption(ml/kwh) 1.47 1.68 1.35 1.66 1.46 1.43 1.52 1.39 2.30 2.49 3.74

Specific Coal

Consumption

(Kg/kwh)

0.73 0.72 0.71 0.71 0.74 0.74 0.72 0.73 0.74 0.74 1.34

As evident from the table, post R&M of Unit-1 and 2 of GNDTP’s there is no encouraging

improvement in the parameters such as PLF, SHR and specific fuel consumption of GNDTP, Bhatinda.

2.5. Loss of Generation due to Backing Down

During the past four years HPGCL is facing loss of generation due to backing down of Units on the

request of distribution licensee which has significant impact on the performance of its generating

stations. The table below presents the details of loss of generation in HPGCL plants.

Table 24: Loss of Generation due to Backing Down

Station Actual (in MUs)

2007-08 2008-09 2009-10 2010-11 2011-12**

PTPS Unit (1-4) 5.800 26.944 1.277 123.962 95.095

PTPS (Unit-5) 0.711 7.197 16.376 102.661 45.222

PTPS (Unit-6) 0.565 14.334 23.074 59.679 39.902

PTPS (Unit-7) 0.882 8.836 1.017 6.647 3.268

PTPS (Unit-8) 0.690 24.351 1.177 110.035 45.181

PTPS (Unit 1-8) 8.648 81.662 42.921 402.984 228.668

DCRTPP Unit-1 - 1.114 1.246 66.112 35.991

DCRTPP Unit-2 - 3.292 0.872 90.395 33.510

RGTPP Unit-1 - - - 98.195

RGTPP Unit-2 - - - 25.872

Page 42: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

40

Station Actual (in MUs)

Total HPGCL* 12.107 87.876 45.039 559.491 422.235

* includes loss of generation for FTPS; **Figures for 2011-12 are for 6 months ending September 2011

As can be seen in the table above, the HPGCL has already lost a total of 422.23 MUs in the six (6)

months of the current financial Year (FY2011-12). It is also to be noted that as per the decision made

in the meeting of “Steering Committee for Power Planning” under the Chairmanship of Financial

Commissioner and Principal Secretary (Power), Govt. of Haryana on 20th

September 2011, it was

decided that HPGCL would recover the fixed charge in the event of backing down in FY 2011-12,

including deemed generation credit for regulatory perspective. Accordingly, the Petitioner prays to

the Hon’ble Commission to kindly consider the impact of backing down/ deemed generation while

allowing the technical parameter of the plants or the earlier arrangement of recovery of the fixed

charge in the event of backing down as decided by Govt. of Haryana for FY 2011-12 may be allowed

to be continued for FY 2012-13 i.e. PLF to be worked out including generation loss on account of

backing down etc.

2.6. Force Majeure

A ‘Force Majeure’ means any event or circumstance or combination of events and circumstances

including those that wholly or partly prevents or unavoidably delays an Affected Party in the

performance of its obligations and could not have been avoided if the Affected Party had taken

reasonable care or complied with Prudent Utility Practices. The following shall be treated as Force

Majeure: acts of God, war, riots, embargoes, industry-wide strikes, the reduction in quantity of coal

supply to generating station, communal agitation, forced outages of power plant or any other causes

circumstances, or contingencies, whether of a similar or dissimilar nature to the foregoing, beyond

the control of the HPGCL, which cannot be reasonably forecast or prevented, thereby, hindering the

performance of the HPGCL plant.

There are few such cases in HPGCL wherein the plant has to go for long forced shut-down either for

carrying out major repairs works or because of the shortage of coal; which are beyond the control of

HPGCL and hence can be treated as force majeure condition.

Few such conditions are as discussed below:

Forced outage of 300 MW Unit-2 of DCRTPP Yamuna Nagar Plant: The 300 MW Unit-2 of DCRTPP

Yamunanagar was commissioned on June 24, 2008 and has been running on commercial operation

since then. The Unit achieved a PLF of 70% during FY 2008-09, 77% during FY 2009-10 and 62%

Page 43: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

41

during FY 2010-11. As per contract, the provisional Taking over (PTO) of Unit-2 was done by HPGCL

on August 31, 2009, whereas the Final Taking Over (FTO) has not been achieved.

On September 25, 2011 while the machine was being re-taken after tripping of station transformer

on earth fault, the barring gear motor tripped on overload and the Turbine rotor came to stand still.

Efforts were made but the turbine could not be put on barring gear. After consultation with RInfra,

SEC China and various other experienced personnel, attempts were made to increase the speed of

the machine beyond 600 RPM but in all attempts, the machine got tripped at around the speed of

1300 RPM on high vibration at bearing No. 1. It was suspected by RInfra and SEC Engineers that the

cause of the problem might be either hogging or sagging of rotor or heat shock/ crack in blade/

blade mountings, due to ingress of water/ cold steam and the machine was put under shutdown for

in depth investigation. In the past too, Unit-2 of DCRTPP Yamunanagar was tripped because of the

following reasons:

· Unit-2 was running on partial load during Merch’10 to Oct’10 due to collapse of EPS hopper;

· EPS and other emergency works in Unit-2;

· Tripped due to turbine vibration high at bearing No.-7 (Fault in C&I control cable);

The reasons of such a frequent tripping and shut-down of DCRTPP, Yamunanagar could be many

which may require further investigation. However, on the commercial front HPGCL would incur huge

loss due to such uncontrollable events. Such events results into lower availability of the plant. Taking

such a unique case of DCRTPP Yamuna Nagar, HPGCL prays to the commission to consider the force

majeure condition which are beyond the control of HPGCL such as current scenario of long shut

downs of Unit-2 of DCRTPP, Yamunanagar and allow the full recovery of fixed cost for rectification of

the chronic problems in the plant. Further HPGCL prays to the Hon’ble HERC to accordingly review

and revise the plant load factor of DCRTPP, Yamuna Nagar for the FT 2011-12.

Loss of Generation due to coal shortage: Apart from this HPGCL is also facing acute shortage of coal

for RGTTP, Hisar plant where there is no FSA and HPGCL is losing revenue on account of lower

generation because of coal shortage. At RGTPP, Hisar the percentage of coal receipt was 57.41%

during FY 2010-11 and 78.70% during FY 2011-12 till Sep’11. Over and above RGTPP, Hisar is

receiving significant quantum of coal from MCL area which is of poor quality and has about 40-42

per cent ash content. HPGCL prays to the Hon’ble Commission to consider the current status of fuel

supply and allow the full recovery of fixed cost.

Page 44: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

42

On the similar case of Indraprastha Power Generation Co. Ltd. Versus Delhi Electricity Regulatory

Commission the Appellate Tribunal for Electricity vide Appeal No. 81 of 2007 has given the following

judgment on 10th

January, 2008:

“Taking the case of RPH station the Commission has considered the vintage and current status of

plant operation including long shut downs of Unit nos. 1 and 2 and has relaxed the target availability

for the recovery of fixed charges of RPH to 60% combined for FY 2005-06 and 2006-07 as against

70%. It is to be noted that practically one Unit of the station was not available for operation because

of major repairs for more than 8 months out of 24 months in FY 2005-06 and 2006-07. Viewing it

year-wise, the station was having one Unit with chronic problem and the second Unit was available

for only 4 months after the repairs in FY 2005-06. Whereas in FY 2006-07 one Unit was available after

repairs for the entire year and the second Unit was only available for nearly 7 months after repairs.

Expected availability of RPH in FY 2005-06 is widely different from that achievable in FY 2006-07 and

combining them and fixing relaxed normative target availability of 60% will not represent true

picture. It will be reasonable to fix target availability separately for each year. We, therefore,

direct the Commission to fix target availability of RPH for recovery of fixed cost separately for each

year while taking into account the factors for relaxation. No incentive, however, is allowed if the

PLF does not exceed target PLF of 70%.”

Page 45: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

43

3. Submission

3.1. Brief of Submissions

The Haryana Power Generation Corporation Limited (HPGCL or Petitioner) is submitting this Tariff

Petition for FY 2012-13. This current petition is based on the technical and financial parameters

approved as per Central Electricity Regulatory Commission (Terms and Conditions of Tariff)

Regulations, 2009 and the principles adopted by Hon’ble HERC in Tariff Orders for previous years

and Haryana Electricity Regulatory Commission (Terms and Conditions of Generation Tariff)

Regulations 2008.

The Petitioner is filing the petition without prejudice to its right to initiate appropriate legal

proceedings and seek legal remedies thereto, on the application submitted before the Hon’ble

Appellate Tribunal for Electricity (APTEL) seeking review of technical and financial parameters

approved by the Hon’ble Commission in Tariff Orders.

In the aforesaid petitions, the Petitioner has raised the following issues:

a. Review and relaxation of technical norms i.e. Station Heat Rate, PLF, Auxiliary Consumption,

Specific oil consumption due to reasons beyond the control of the Petitioner;

b. Review & relaxation in norms related to coal transit losses for the generating stations of the

Petitioner;

c. Quality and quantity of coal constraints and its impact on the technical performance of the

generating stations;

d. Approval of O&M expenses and Return on equity as proposed by the Petitioner;

e. Issues related with Two-part Tariff and recovery of fixed cost in the event of backing down of

generating stations;

In this Petition, the Petitioner has considered the submissions based on the Central Electricity

Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009. However, the Petitioner

has reiterated the submissions made in the previous petitions and the realistic/ achievable norms at

appropriate instances for ease of reference. In certain cases, where the Petitioner is of the view that

the said norms and principles are not achievable, the Petitioner has submitted based on the actual

performance of the generating stations for the past three years. The Petitioner requests the Hon’ble

Commission to consider the same while determination of the tariff for the respective stations.

Page 46: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

44

HPGCL has filed the requisite information in this application along with the Audited Annual Accounts

for FY 2010-11 and Cost Accounting record along with Cost Audit report for FY 2009-10.

The Petitioner submits that the present petition has been filed for relief and relating to Tariff

determination for the FY 2012-13 as detailed in the petition. Further, it is submitted that the tariff be

made applicable with effect from April 1, 2012.

Proposed Generation tariff for FY 2012-13

A summary of the projected generation tariff for HPGCL during the year FY 2012-13 is provided

below:

Table 25: Summary of projected generation tariff for HPGCL for FY2012-13 (In Rs. Crore)

Total Proposed Generation Tariff (FY2012-13)

Fuel Cost 5,514.56

Total Variable Cost 5,514.56

Proposed Depreciation 469.69

Interest & Finance Charges 634.97

Interest on Working Capital 362.17

Return on Equity 425.52

O&M Cost 670.73

Total Fixed Cost 2563.08

Net Units Generated (MUs) 21,022.3

Variable cost per Unit (Rs/kWh) 2.62

Fixed cost per Unit (Rs/kWh) 1.22

Total Tariff per Unit (Rs/kWh) 3.84

The summary of total cost for each generating station of HPGCL for FY2012-13 is summarized in

tables below:

Table 26: Plant wise breakup of total cost; PTPS for FY 2012-13 (In Rs. Crore)

Station PTPS

(Unit1-4)

PTPS

(Unit-5)

PTPS

(Unit-6)

PTPS

(Unit-7)

PTPS

(Unit-8)

PTPS

(Unit 1-8)

Fuel Cost 744.07 432.40 435.23 454.11 453.93 2,519.69

Proposed Depreciation 28.91 12.20 50.89 44.34 44.35 180.69

Interest & Finance Charges 14.74 2.82 13.07 27.67 27.67 85.96

Interest on Working Capital 50.74 254.78 273.55 293.78 293.69 1,623.16

Return on Equity 15.64 9.12 29.04 40.23 40.23 134.26

O&M Cost 172.50 45.17 45.17 53.78 53.78 370.40

Total Cost of Generation 1,025.65 527.19 600.75 690.74 608.08 3,452.41

MUs Generated 2,075.75 1,407.45 1,414.33 1,693.97 1,693.97 8,285.46

Cost per Unit (Rs./kWh) 4.95 3.75 4.25 3.83 3.83 4.17

Page 47: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

45

Table 27: Plant wise breakup of total cost; DCRTPP and RGTPP for FY 2012-13 (In Rs. Crore)

Station DCRTPP

Unit-1

DCRTPP

Unit-2

DCRTPP

Unit 1 –2

RGTPP

Unit -1

RGTPP

Unit-2

RGTPP

Unit 1-2

Fuel Cost 486.88 486.88 973.77 1,010.53 1,010.53 2,021.06

Proposed Depreciation 51.10 51.10 102.21 88.68 88.68 177.36

Interest & Finance Charges 86.83 86.83 173.66 186.04 186.04 372.09

Interest on Working Capital 50.74 25.48 27.36 30.39 28.36 162.32

Return on Equity 330.60 330.60 661.20 659.23 659.23 1,318.46

O&M Cost 56.73 56.73 113.46 82.92 82.92 165.84

Total Cost of Generation 1,026.60 527.19 600.75 690.74 608.08 3,453.35

MUs Generated 2,032.76 2,032.76 4,065.52 4,199.54 4,199.54 8,399.09

Cost per Unit (Rs./kWh) 3.75 3.75 3.75 3.64 3.64 3.64

Table 28: Plant wise breakup of total cost: Hydro Plants of HPGCL for FY 2012-13 (In Rs. Crore)

Station WYC &Karkoi Total HPGCL

Fuel Cost - 5,514.52

Proposed Depreciation 9.43 469.69

Interest & Finance Charges 3.26 634.97

Interest on Working Capital 1.48 361.77

Return on Equity 5.48 425.52

O&M Cost 21.04 670.73

Total Cost of Generation 40.69 8,077.60

MUs Generated 272.26 21,022.32

Cost per Unit (Rs./kWh) 1.51 3.84

The Petitioner humbly prays to the Commission to approve the proposed Generation tariff as

proposed and permit the Petitioner to recover the actual cost of generation as also envisaged in the

National Tariff Policy Section 5.3 (f) which states that

“The norms should be efficient, relatable to past performance, capable of achievement and

progressively reflecting increased efficiencies and may also take into consideration the latest

technological advancements, fuel, vintage of equipment, nature of operations, level of service to be

provided to consumers etc.....”

Page 48: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

46

3.2. Prayer

In view of the above, the petitioner respectfully prays that Hon’ble Commission may kindly:-

a) Admit this Petition;

b) Condone delay in submission of the petition;

c) consider deemed generation for computation of technical parameters of HPGCL generating

station;

d) Permit HPGCL the right to sell the power to third party outside state in event of payment

default by the distribution licensee of Haryana and also to recover the fixed charge of the

power sold outside the state instead of Haryana discoms;

e) Approve the two part tariff for FY 2012-13 to the extent claimed by HPGCL in accordance

with the submissions and rationale given in the Petition;

f) Allow coal import beyond 10% as mandated by Govt. of India and also to procure coal

through e-auction process as well as from private sources to meet the coal shortage in

HPGCL.

g) Permit recovery of fixed charges for the Units which are under forced shut-down because of

force majeure conditions and in case of backing down of the plant;

h) Pass such orders as Hon’ble HERC may deem fit and proper and necessary in the facts and

circumstances of the case, to grant relief in the operational norms related to Plant Load

factor, Station Heat Rate, Auxiliary Consumption, Specific oil consumption for PTPS Unit-1 to

4as they are more than 25 years old;

i) Approve the coal transit losses and moisture loss for FY 2012-13 as proposed in the petition

in line with APTEL order dated 07.04.2011 on Appeal No. 26 of 2008, CERC (Terms and

Conditions of Tariff) Regulations, 2009 - Statement of Objects and Reasons & Tariff order

passed by Hon’ble BERC;

j) Approve all pending petitions filed by HPGCL in the past such as business plan etc;

k) Approve the other consideration expressed by the petitioner in the current petition;

l) Condone any inadvertent omissions / errors / short comings and permit the applicant to add

/ change /modify / alter this filing and make further submissions as may be required at later

stages;

Page 49: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

47

4. Projections of the Technical Parameters

In this section, HPGCL has provided the actual performance of the stations for the past years

including first six months of the FY 2011-12 (Current year) and projections for the FY 2012-13 (the

ensuing year). The station wise details and rationale for projections for FY 2012-13 is provided in the

following sub-sections.

4.1. Plant Load Factor

The table given below outlines the actual PLF achieved by HPGCL’s generating stations in the past

years.

Table 29: Actual Plant Load Factor achieved by HPGCL from FY 2004-05 onwards

Station

Actual (in %)

2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

2011-12

(Upto

Sep’11)

PTPS Unit-1 52.59 59.40 62.63 25.29 28.94 70.08 48.90 79.18

PTPS Unit-2 59.34 70.65 77.37 67.39 73.61 71.26 35.05 82.07

PTPS Unit-3 69.95 21.42 49.06 77.57 68.46 50.02 69.11 57.54

PTPS Unit-4 64.86 79.61 77.3 67.4 60.56 72.39 60.75 55.05

PTPS Unit-5 79.76 79.73 91.55 96.23 94.27 79.06 83.91 79.62

PTPSUnit-6 80.51 91.77 91.4 93.18 91.64 97.49 88.86 86.60

PTPS Unit-7 77.17 42.08 90.32 98.91 85.35 98.4 92.63 92.54

PTPS Unit-8 - 85.32 91.24 86.48 94.41 96.93 90.08 90.62

PTPS (Unit 1-8) 71.14 68.53 83.17 82.55 80.48 85.19 77.39 81.47

DCRTPP Unit-1 - - - 68.66 85.73 85.08 94.53

DCRTPP Unit-2 - - - 69.53 76.97 62.6 61.83

DCRTPP(Unit 1-2) - - - 69.05 81.35 73.85 78.18

RGTPP Unit-1 - - - - - - 52.06

RGTPP Unit-2 - - - - - - 43.55

RGTPP (Unit 1-2) - - - - - - 47.80

WYC & Karkoi 67.00 78.78 78.94 75.01 82.93 76.28 ___

HPGCL 67.00 78.78 78.94 75.01 82.93 76.28 68.09

As can be seen, the overall PLF performance of HPGCL has improved from 67% in FY 2005-06 to

nearly 83% in FY 2009-10. However, during FY 2010-11 the PLF has declined due to poor

performance of PTPS Unit 1-4 and DCRTPP Unit-2. The PLF during the first 6 months ending

September of FY 2011-12 for HPGCL as a whole has also declined considerably, due to the lower PLF

of RGTPP Unit 1-2 on account of stabilization issues and inadequacy of coal.

Page 50: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

48

4.1.1. Unit-wise details PLF for PTPS Unit 1-4:

Table 30: Actual Plant Load Factor for PTPS Unit I-IV

Power Station

Actual (in %)

FY -05 FY -06 FY -07 FY - 08 FY -09 FY -10 FY -11

FY-12

(upto

Sep’11)

FY-13

(proposed

)

PTPS Unit-1 52.59 59.40 62.63 25.29 28.94 70.08 48.90 79.18 52.59

PTPS Unit-2 59.34 70.65 77.37 67.39 73.61 71.26 35.05 82.07 59.34

PTPS Unit-3 69.95 21.42 49.06 77.57 68.46 50.02 69.11 57.54 69.95

PTPS Unit-4 64.86 79.61 77.3 67.4 60.56 72.39 60.75 55.05 64.86

PTPS Unit (1-4) 61.69 57.77 66.59 59.41 57.89 68.38 53.37 68.65 59.88

The PTPS Unit-1 to 4 has achieved a consistently low PLF during the last 6 years due to the vintage of

the Plant. During FY2008-09, R&M works were completed for Unit-1, owing to which the overall

performance witnessed a significant improvement in the following year and the plant achieved a PLF

of 68%. The PLF declined in year 2010-11 due to the forced outages of Unit-1 from 01.03.2010 to

23.08.2010 due to damage of all the bearings of Turbine & Generators & Unit-4 from 20.04.2010 to

27.05.2010 due to high vibrations in Generator bearing. Also the annual overhauling of Unit-2 which

commenced on 25.10.10 for 45 days has been extended due to unforeseen fault in ABB modified

turbine.

The poor performance of Unit-1 to 4 can be attributed to the lack of R&M activity, as the R&M of

only Unit I has been completed so far and the Petitioner has not claimed R&M capital expenditure

for any other Units in any Tariff Petition. The R&M for Unit 1-4 was awarded to M/S ABB Germany,

now Alstom Power, in the year 1997. The firm had left the work in year 2000 for which the matter is

still under arbitration. Subsequently, the work was awarded to BHEL in year 2002, which was merely

rehabilitation work and BHEL did not agree for any guarantee towards the improved technical

performance of the Plant. In the above background, the Petitioner has completed the R&M of only

Unit-1 during the year 2008-09, whereas, the R&M of Unit-2 still remains pending. The R&M for

Unit-3 and Unit-4 are planned in the year 2013-14, through financial assistance from the World Bank

for which the Business Plan shall be submitted subsequently.

Therefore, the Petitioner has proposed a PLF of 59.88% for Unit-1 to 4 based on the average of

actual PLF achieved during the preceding three complete years of operations. The Petitioner prays

the Hon’ble Commission to consider the above-mentioned difficulties in the achieving the norms.

The petitioner would also like to present a similar case where the Jharkhand Electricity regulatory

Commission (JERC) has passed an order with relaxation of norms due to the aging effect for the

Page 51: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

49

vintage Patratu Thermal Power Station (PTPS) for FY 10-11. Relevant excerpt from the tariff order

passed by Jharkhand ERC for PTPS are as follow:

4.1.2. PTPS Unit-5 to 8

Table 31: Actual Plant Load Factor for PTPS Unit-5 to 8

Power Station

Actual PLF (%)

FY - 05 FY - 06 FY - 07 FY - 08 FY - 09 FY - 10 FY - 11

FY-12

(upto

Sep’11)

2012-13

(Propos

ed)

PTPS Unit-5 79.76 79.73 91.55 96.23 94.27 79.06 83.91 79.62 85.00

PTPS Unit-6 80.51 91.77 91.4 93.18 91.64 97.49 88.86 86.60 85.00

PTPS Unit-7 77.17 42.08 90.32 98.91 85.35 98.4 92.63 92.54 85.00

PTPS Unit-8 - 85.32 91.24 86.48 94.41 96.93 90.08 90.62 85.00

PTPS Unit (5-8) 91.84 73.70 91.09 93.61 91.29 93.38 89.09 87.71 85.00

The Unit-5 to 8 have performed satisfactorily in the past years, except for FY 2010-11. Therefore, the

Petitioner envisages the normative PLF of 85% as achievable and prays to the Hon’ble Commission

for allowance.

4.1.3. DCRTPP Unit-1&2

Table 32: Actual Plant Load factor for DCRTPP Unit-1&2

Power Station

Actual PLF (%)

2008-09 2009-10 2010-11

2011-

12(upto

Sep’11)

2012-13

(Projected)

DCRTPP Unit-1 68.66 85.73 85.08 94.53 85.00

DCRTPP Unit-2 69.53 76.97 62.6 61.83 85.00

DCRTPP (Unit-1&2) 69.05 81.35 73.85 78.18 85.00

The 300 MW Unit-2 of DCRTPP Yamuna Nagar was commissioned on June 24, 2008 and has been

running on commercial operation since then. The Unit achieved a PLF of 70% during 2008-09, 77%

during 2009-10 and 62% during 2010-11. As per contract, the provisional Taking over (PTO) of Unit-2

was done by HPGCL on August 31, 2009, and Final Taking Over (FTO) has not been achieved.

“In view of the analysis and directions given in Hon’ble APTEL’s Order dated 8.5.2008 and also

considering that many Units of PTPS are more than 35-40 years old and it may not be feasible for

the licensee to achieve the operational targets, the Commission has now decided to relax the

norms of the operational parameters vis-à-vis the target set in the previous Tariff Orders. The

Commission sets the timelines for the improvement of operational parameters as per the revised

norms for attaining PLF of 45% and SHR of 2950 Kcal/Kwh by the end of FY 2013-14.”

Page 52: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

50

On September 25 2011, while the machine was being re-taken after tripping of station transformer

on earth fault, the barring gear motor tripped on overload and the Turbine rotor came to stand still.

Efforts were made but the turbine could not be put on barring gear. After consultation with Reliance

Infra, SEC China and various other experienced personnel, attempts were made to increase the

speed of the machine beyond 600 RPM but in all attempts, the machine got tripped at around the

speed of 1300 RPM on high vibration at bearing No. 1. It was suspected by Reliance Infra and SEC

Engineers that the cause of the problem might be either hogging or sagging of rotor or heat shock/

crack in blade/ blade mountings, due to ingress of water/ cold steam and the machine was put under

shutdown for in depth investigation. It is expected that the Unit-2 will be put under operations in the

FY 2012-13. The Petitioner envisages the normative PLF of 85% as achievable and prays to the

Hon’ble Commission for allowing the same subject to adjustment at the end of year based on the

actuals.

4.1.4. RGTPP Unit-1&2

Table 33: Actual Plant Load factor for RGTPP Unit-1&2

Power Station Actual (in %)

2011-12(Upto Sep’11) 2012-13 (Projected)

RGTPP Unit-1 52.06 85.00

RGTPP Unit-2 43.55 85.00

RGTPP (Unit-1&2) 47.80 85.00

The proposed PLF for RGTPP, Hisar is as shown above. Although the actual PLF till Sep’11 is 47.8%,

the petitioner has proposed a PLF of 85% assuming that the operation would be stabilized and the

constraints of coal quality and quantity will be removed. However the projection as above for

FY2012-13 is subject to adjustment at the end of the year based on the actuals. The factors that are

affecting the PLF of RGTPP, Hisar which are beyond the control of HPGCL are:

· Increase in the ash content of coal leading to inability of the coal mills to run on full load,

increase in the turbidity of cooling water leading to frequent maintenance outages of condenser

tubes for cleaning, inadequate and intermittent coal supply affecting the loading of the Units

etc;

· Inadequacy of coal for the RGTPP Unit-1&2;

Considering the above submission, the Petitioner has projected the PLF for PTPS Unit-1 to4 based on

the actual achievable PLF, a normative PLF of 85% for the remaining Units of HPGCL.

Page 53: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

51

The table below summarizes the achievable PLF as envisaged by the Petitioner subject to adjustment

at the end of year based on the actuals.

Table 34: Proposed PLF of all plants of HPGCL

Station Proposed PLF (in %)

2012-13

PTPS Unit-1 to 4) 59.88%

PTPS (Unit-5) 85.00%

PTPS (Unit-6) 85.00%

PTPS (Unit-7) 85.00%

PTPS (Unit-8) 85.00%

PTPS (Unit-1 to 8)

DCRTPP Unit-1 85.00%

DCRTPP Unit-2 85.00%

Total DCRTPP Unit-1&.2

RGTPP Unit-1 85.00%

RGTPP Unit-2 85.00%

Total RGTPP Unit 1-2 85.00%

WYC & Karkoi

Total HPGCL 81.45%

4.2. Plant Availability Factor (PAF)

In case the intrastate ABT is introduced in the state of Haryana, the values of Plant Load factor (PLF)

would be replaced by Plant Availability Factor (PAF) as shown in the table subject to adjustment at

the end of each year based on the actuals. Plant availability factor shown for the HPGCL Power

Plants have been proposed keeping in view the impediments related to coal supply faced by HPGCL

for its different power plants. The lower value of Plant Availability Factor for PTPS Unit-1 to 4 is

because of the fact that these Units are very old and has been frequently closed down on account of

R&M activity. Similarly for RGTPP and DCRTPP the availability has been proposed based on

availability of coal.

Table 35: Plant Availability Factor for FY 2012-13

Station Proposed PAF (in %)

2012-13

PTPS Unit (1 to 4) 59.88%

PTPS (Unit-5) 85.00%

PTPS (Unit-6) 85.00%

PTPS (Unit-7) 85.00%

PTPS (Unit-8) 85.00%

PTPS (Unit-1 to 8)

DCRTPP Unit-1 85.00%

DCRTPP Unit-2 85.00%

Page 54: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

52

Station Proposed PAF (in %)

Total DCRTPP Unit-1&2

RGTPP Unit-1 85.00%

RGP Unit-2 85.00%

Total RGTPP Unit 1 – 2 85.00%

Total HPGCL 81.45%

The availability proposed by HPGCL is on the best effort basis, subject to supply of required quantity

of coal and other technical constraint such as aging of plants. In this regard the plant availability

factor of the plants should be allowed to revisit at the end of the year based on the actuals.

4.3. Station Heat Rate

The actual Station Heat Rate attained by the generating stations of HPGCL during past years has

been indicated in the table below.

Table 36: Actual Station Heat rate (in kcal/kwh) achieved from FY 2004-05

Station

Actual (in %)

2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

2011-12

(Upto

Sep’11)

PTPS Unit-1 to 4) 3567 3665 3341 3470 3425 3225 3349 3230

PTPS (Unit-5 to 8) 2858 2703 2620 2571 2574 2561 2679 2740

DCRTPP(Unit-1&2) - - - - 2450 2387 2479 2406

RGTPP (Unit-1&2) - - - - - - - 2846

HPGCL 3287 3074 2894 2916 2762 2684 2728 2772

Station Heat Rate for generating stations varies from Unit to Unit depending upon their age, size,

technology, no. of starts/stops, quality of coal etc. The older the Unit becomes, its efficiency goes

down, and it becomes prone to run at higher heat rate. This is primarily on account of the

deterioration of efficiency of a Unit on account of ageing and more number of starts and stops.

In addition, the quality of coal being fed continuously is a prime factor contributing to the

determination of heat rate of a Unit.

In this respect, it is requested that HERC may be requested to consider the provisions given in the

Section 5.3 (f) and 5.3 (i) 2 of the National Tariff Policy dated 6th January, 2006.

Section 5.3 (f) of National Tariff Policy reads as follows:

· The norms should be efficient, relatable to past performance, capable of achievement and

progressively reflecting increased efficiencies and may also take into consideration the latest

Page 55: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

53

technological advancements, fuel, vintage of equipment, nature of operations, level of

service to be provided to consumers etc.....

· The Central Commission would, in consultation with the Central Electricity Authority, notify

operating norms from time to time for generation and transmission. The SERC would adopt

these norms. In cases where operations have been much below the norms for many

previous years, the SERCs may fix relaxed norms suitably and draw a transition path over the

time for achieving the norms notified by the Central Commission.

Section 5.3 (h) 2 of the National Tariff Policy states:

· In cases where operations have been much below the norms for many previous years the

initial starting point in determining the revenue requirement and the improvement

trajectories should be recognized at “relaxed” levels and not the “desired” levels. Suitable

benchmarking studies may be conducted to establish the “desired” performance standards.

Separate studies may be required for each utility to assess the capital expenditure necessary

to meet the minimum service standards

For the old Units like PTPS Unit-1 to 4, the R & M is being planned but the same will take some time

as HPGCL is evaluating the alternatives for funding the schemes. Also, under the provisions of the

Electricity Act, 2003, HPGCL has a mandate to operate on commercial principles only. Therefore, the

need of commercial independence of HPGCL should be factored while approving the SHR. HPGCL has

not claimed any R&M for the old Units except Unit-1 of PTPS, Panipat. For Unit-3&4 the

refurbishment is proposed in FY 2013-14. After the implementation of the proposed R&M HPGCL

expects improvement in the SHR of the Units.

As suggested in the aforementioned paragraphs, HPGCL is going very cautiously in the

implementation of the schemes by ensuring optimization of investments vis-à-vis the commensurate

benefits from schemes. Therefore, in the absence of any R&M scheme being planned for 2012-13.,

HPGCL has adopted the old methodology of suggesting the SHR by considering a deterioration factor

of 1.5% on the test results. Considering the above said reasons the petitioner has arrived at the

following station heat rate for the all Units of the PTPS as follows:

Table 37: Station Heat Rate (SHR) (Kcal/kwh)

Particulars

Station Heat Rate (SHR) (Kcal/Kwh)

2009-10

FY -11 (1.5%

increase for

deterioration)

FY -12 (1.5%

increase for

deterioration)

2012-13 (1.5%

increase for

deterioration)

Last Three

Years

Average

Page 56: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

54

Particulars

Station Heat Rate (SHR) (Kcal/Kwh)

As per Energy Audit

Report dated Dec.2010

Unit-1, PTPS, Panipat

- 2,937.24 2,981.30 3,026.02 3213

As per Energy Audit

Report dated April 2010

Unit-2, PTPS, Panipat

3,308.53 3,358.16 3,408.53 3,459.66 3305

As per Energy Audit

Report dated April 2010

Unit-3, PTPS, Panipat

3,274.01 3,323.12 3,372.97 3,423.56 3366

As per Energy Audit

Report dated April 2010

Unit-4, PTPS, Panipat

3,287.15 3,336.46 3,386.50 3,437.30 3439

Unit-1 to 4

3,336.63 3333.0

As per Energy Audit

Report dated April 2010

Unit-5, PTPS, Panipat

2,806.97 2,849.07 2,891.81 2,935.19 2740

As per Energy Audit

Report dated April 2010

Unit-6, PTPS, Panipat

2,825.53 2,867.91 2,910.93 2,954.60 2703

Unit-7, PTPS, Panipat - - - - 2585.86

Unit-8, PTPS, Panipat - - - - 2584.83

Though the Station heat rate arrived for PTPS are higher than the approved in Tariff Order for the FY

2011-12, the petitioner requests the Hon’ble Commission to relax the norms for these PTPS plants

owing to the difficulty abovementioned.

The petitioner would also like to present a similar case where the Tamil Nadu Electricity regulatory

Commission (TNERC) and Uttar Pradesh Electricity Regulatory Commission (UPERC) has passed an

order with relaxation of norms for the station heat rate.

As per Haryana Electricity Regulatory Commission (Terms and Conditions for Determination of

Generation Tariff) Regulations, 2008;

“The Commission may vary the normative heat rate from those indicated in these regulations on a

case-to-case basis based on the levels of O&M and Life Extension (LE) that the station has been

subjected to in the recent past or adopt the norms as specified by the CERC from time to time.”

Excerpt of TNERC order giving due consideration to SHR relaxation for poor coal quality

Applicant’s (TNEB) appeal:

· As per tariff regulations, SHR norms for TTPS & NCTPS were required to be 2453 kcal/kWh

and 2393 kCal/kWh respectively.

Page 57: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

55

· TNEB sought relaxation of station heat rate norms for TTPS and NCTPS in their letter dated

23-7-2010.

· TNEB prayed for relaxation of heat rate norm to 2560 kcal / kWh for Units I, II & III and 2600

kcal / kWh for Units IV & V for TTPS and 2500 kcal / kWh for NCTPS

TNERC order: (Relevant excerpt)

· The details furnished by TNEB for these power stations have been examined and it is

observed that they have exceeded the normative heat rate in many power stations.

· The Central Electricity Authority commissioned a consultant by name Evonic Energy Services

India Pvt Ltd in June 2008 to evaluate the performance of TTPS and in August 2008 to

evaluate the performance of NCTPS. The consultant recorded the heat rate as 2575.31 kcal /

kWh for NCTPS and 2826 kcal / kWh for TTPS.

· The TNEB has prayed for relaxation of heat rate norm to 2560 kcal / kWh for Units I, II & III

and 2600 kcal / kWh for Units IV & V for TTPS and 2500 kcal / kWh for NCTPS.

· Considering that the Commission has prescribed a norm of 2500 kcal / kWh for new plants,

the Commission approves relaxation of norms for TTPS and NCTPS upto 2500 kcal / kWh in

terms of Clause 90 of the Tariff Regulations 2005 for the year 2010-11

· The Commission allows the following station heat rate in relaxation of the Regulation 90 of

TNERC Tariff Regulations.

o TTPS: 2500kCal/kwh

o NCTPS: 2466 kCal/kWh

In another case SHR for plants in Uttar Pradesh have been given relaxation in norms by UPERC in

tariff order 2008-09.

Excerpt from UPERC order allowing higher SHR to meet increased fuel expenses

· “In order dt.13.10.08, the Commission also observed that it was not averse to consider

difficulty, if any, being experienced by the petitioner in achieving the operational norms at

the time of determination of tariff has been able to achieve for this station during the period

in question.”

· The Commission is aware of increased quantity of fuel input due to higher Station Heat Rate

with respect to the bench mark values mentioned in the Regulation. Therefore the

Commission in order to compensate UPRVUNL for its losses, due to hard cost on enhanced

quantity of fuel, thinks it is appropriate to allow the Station Heat Rate for Obra-A, Obra-B,

Page 58: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

56

Harduaganj and Panki as proposed by the Petitioner for FY 2008-09 instead of the values

mentioned in the Regulations, 2004 and its amendment on the grounds of non-payment by

the Respondents but without sharing so that the Petitioner does not suffer losses on fuel

purchase.

· In view of the above decision, Station Heat Rate as approved by the UPERC is as below:

Table 38: Station Heat Rate approved by the UPERC at relaxed norms

Name of the thermal

Power Plant

SHR (kcal/kWh) as per

Regulation

SHR (kcal/kWh) as per the

Petition

SHR (kcal/kWh) as Approved

by the Commission

Obra A 2850 3000 3000

Obra B 2700 2900 2900

Panki 2950 3100 3100

Harduaganj 3300 3450 3450

Another important case to be referred in this context is the case of MSPGCL wherein the operating

norms were relaxed in favour of the generating company after truing up process. MERC vide its MYT

tariff order dated 25th April 2007 approved the following SHR for MSPGCL plants. The relevant

extract reads as under:

Table 39: Approved Station Heat Rate by MERC

Name of the

Plant

Approved

FY05-06 FY 06-07 FY 07-08 FY 08-09 FY 09-10

Koradi 2996 2907 2786 2792 2797

Khaparkheda 2725 2644 2556 2561 2566

Chandrapur 2502 2480 2545 2551 2556

Nasik 2663 2584 2648 2653 2642

Bhusawal 2735 2561 2649 2654 2652

Parli 2649 2573 2652 2657 2660

Paras 3200 3105 3105 - -

MSGPCL filed an appeal before the Appellate Tribunal against the above said highlighting various

issues including operating norms and in particular SHR norms for its stations. The Hon’ble Appellate

directed MERC to carry out an independent study to reasonable assess the achievable heat rate of

the plants owned by MSPGCL and to suggest measures to improve the heat rates over a period of

time. ATE directed MERC to determine the heat rate based on the outcome of the study and align its

Regulations by prescribing achievable norms and not merely ideal norms. Relevant extract of the

truing up order is as below:

“As regards norms for performance parameters, viz., transit loss of coal, station heat rate, auxiliary

consumption, and specific oil consumption of MSPGCL’s generating stations, Appellate Tribunal for

Page 59: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

57

Electricity (ATE) directed the Commission to undertake an independent study, either through MSPGCL

or on its own, and reset the operating parameters and align its Regulations by prescribing achievable

norms and not merely ideal norms after taking into consideration the results of such independent

study.”

MERC has now allowed the actual SHR achieved by MSPGCL stations for FY 05-06, 06-07 & 07-08 and

has also relaxed the SHR norms for 08-09 and 09-10 based on the results of the study carried out by

the independent agency.

Relevant extracts of the truing up order are as under:

“The Commission noted that MSPGCL has claimed truing up of fuel expenses for FY 2005-06, FY 2006-

07 and FY 2007-08 based on actual fuel expenses incurred by MSPGCL, and if CPRI suggested heat

rates for FY 2005-06, FY 2006-07 and FY 2007-08 are considered, it will result in allowing fuel

expenses in excess of actual fuel expenses, being passed through to the consumers. Hence, for truing

up of fuel expenses for FY 05-06, 06-07 and 07-08, the Commission has considered the actual fuel

expenses as per audited accounts and hence, the actual performance parameters achieved by

MSPGCL.”. Thus the final approved SHR for FY 05-06, 06-07 and 07-08 for MSPGCL stations are as

below:

Table 40: Approved Station Heat Rate by the MERC in case of MSPGCL

Heat Rate (kCal/kWh)

FY05-06 FY 06-07 FY 07-08

Approved

earlier by

MERC

Approved after

truing up

Approved

earlier by

MERC

Approved

after truing

up

Approved

earlier by

MERC

Approved

after truing

up

Koradi 2996 2977 2907 2997 2786 3249

Khaparkheda 2725 2597 2644 2612 2556 2755

Chandrapur 2502 2611 2480 2600 2545 2599

Nasik 2663 2651 2584 2672 2648 2659

Bhusawal 2735 2656 2561 2666 2649 2914

Parli 2649 2661 2573 2765 2652 2779

Paras 3200 3196 3105 3262 3105 3291

Similar case may be put up to the Hon’ble Commission highlighting the judgment of Appellate

Tribunal of Electricity (ATE) in appeal no. 81 of 2007 in Indraprastha Power Generation Co. Ltd.

(IPGCL) Vs Delhi Electricity Regulatory Commission (DERC).

An excerpt from the judgment for approval of SHR for IPGCL Units reads as follows.

Page 60: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

58

“The petitioner (IPGCL) submitted before the Commission that in order to comply with the directions

of Delhi Pollution Control Committee the generating station was proposed to be closed down and

therefore no R&M expenses could be taken for improvement or even maintain the same station heat

rate. We are informed during the arguments that the final decision to close down was taken after the

end of 2006-07. The final closing will be in 2010. In view of this situation, it will not only be fair for

the Commission to bear with the station heat rate which the appellant has been able to achieve for

this station during the period in question.”

Excerpt of JERC order for PTPS for the FY 2010-11 giving due consideration to ageing effect

“In view of the analysis and directions given in Hon’ble APTEL’s Order dated 8.5.2008 and also

considering that many Units of PTPS are more than 35-40 years old and it may not be feasible for the

licensee to achieve the operational targets, the Commission has now decided to relax the norms of

the operational parameters vis-à-vis the target set in the previous Tariff Orders. The Commission sets

the timelines for the improvement of operational parameters as per the revised norms for attaining

PLF of 45% and SHR of 2950 Kcal/Kwh by the end of FY 2013-14.”

Table 41: Relaxed norms approved by the JERC in case of vintage thermal power plant (PTPS)

Approved Operating

Norm FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13 FY 2013-14

PLF in % 34 36 38 40 42 45

SHR (kCal/kWh) 3450 3350 3250 3150 3050 2950

The Petitioner prays the Hon’ble Commission to consider the above-mentioned genuine difficulties

in achieving the norms and the regulatory approach adopted by SERCs while approving the station

heat rate.

The design turbine heat rate & boiler efficiency of RGTPS Unit-1&2 are 1954 Kcal/kWh & 87.2%

respectively. The design station heat rate of these Units works out to 2240.83 Kcal/kWh and the

normative station heat rate as per CERC regulation, dated 19-01-09 would be 2240.83 x 1.065 = 2386

Kcal/kWh. Therefore station heat rates for RGTPS Unit-1&2 are fixed as 2386 Kcal/kWh.

The Petitioner has proposed a following Station Heat Rate for the FY 2012-13 as given in the table

below:

Table 42: Proposed Station Heat rate for the FY 2012-13

Sl. No Name of Plant / Unit Proposed Station Heat Rate in Kcal/ Kwh for FY 2012-13

1. PTPS Unit-1 to 4 3,336.63

2. PTPS Unit-5 2,935.19

Page 61: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

59

Sl. No Name of Plant / Unit Proposed Station Heat Rate in Kcal/ Kwh for FY 2012-13

3. PTPS Unit-6 2,954.60

4. PTPS Unit-7 2,585.86

5. PTPS Unit-8 2,584.83

PTPS Total 2,899.41

6. DCRTPP Unit-1 2,500.00

7. DCRTPP Unit-2 2,500.00

DCRTPP Total 2,500.00

8. RGTPP Unit-1 2,386.47

9. RGTPP Unit-2 2,386.47

RGTPP Total 2,386.47

The proposed Station Heat Rate (SHR) for FY 2012-13 for the HPGCL power plants as shown in the

table above is subject to adjustment at the end of each year based on the actual Station Heat Rate

(SHR) for the plants.

4.4. Auxiliary Consumption

Auxiliary Consumption for a generating station depends on quality of coal it receives at the feeding

point, the nos. of frequent start-ups and shut downs it encompasses and the ageing of the

equipment of the station. In addition the no. of drives being used in actual operation on account of

the decline in the above mentioned factors would increase leading to an increase in auxiliary

consumption.

An example of Maharashtra state wherein MERC in its order for MSPGCL for APR of FY 09-10 and

tariff for FY 10-11 has also approved the auxiliary consumption of FY 09-10 based on actual auxiliary

consumption for FY 08-09 on account of vintage of stations and poor quality of coal. Relevant

particulars of the case are as under:

“MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11 (Case No. 102 of 2009)

· MSPGCL submitted that the Auxiliary Consumption for the first six months of FY 2009-10 for

Paras was 15.00%, and projected Auxiliary Consumption of 13.38% for second half of the

year, which is considerably higher than the approved auxiliary consumption of 9.70% in FY

2009-10, on account of the vintage of the stations and poor quality of coal. MSPGCL further

submitted that the capacity of Unit-2 has been derated w.e.f. April 2007 and therefore, the

auxiliary consumption for the Unit has increased. The other factors that are responsible for

such increase is the partial loading due to inferior quantity of coal and supply of wet coal in

the rainy season. MSPGCL has projected the auxiliary consumption of 14.10% for FY 2009-10

and 13.38% for FY 2010-11. It is also observed that there has been a considerable increase in

the auxiliary consumption as compared to previous year's 12.18%.

Page 62: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

60

· The Commission in its Order dated March 5, 2010 in Case No. 16 of 2008 observed that the

Auxiliary Consumption norm suggested by the independent agency (CPRI) for FY 2008-09 for

some of the stations was substantially higher than the actual auxiliary consumption and

hence, the Commission approved the Auxiliary Consumption norm for FY 2009-10 based on

actual auxiliary consumption for FY 2008-09. The Commission at this stage has not revised

the auxiliary consumption norm for FY 2009-10. For FY 2010-11, the Commission has

considered the norms suggested by CPRI.”

Table 43: Comparison of the proposed and approved auxiliary consumption in case of MSPGCL and MERC case

Name of the

thermal Station MYT Order

FY 2009-10 FY 2010-11

MSPGCL CPRI Approved by

Commission MSPGCL CPRI

Approved by

Commission

Paras 9.70% 14.10% 12.18% 12.18% 13.38% 12.45% 12.45%

A similar example of relaxation in auxiliary consumption norms can be seen in UPERC order 08-09 for

UPRVUNL. Relevant excerpt of the order is reproduced below.

“Excerpt from UPERC Order for UPRVUNL for FY 2008-09 for allowing relaxation in auxiliary

consumption norms

In order dt.13.10.08, the Commission also observed that it was not averse to consider difficulty, if

any, being experienced by the petitioner in achieving the operational norms at the time of

determination of tariff. The Commission is aware of consumption of increased quantity of input due

to high energy loss in auxiliaries in comparison to that on bench mark values, but petitioner’s failure

to carry out timely maintenance, which has actually led to higher auxiliary consumptions in the

plants, can also not be ignored. The petitioner attributes the failure of maintenance to non-

availability of adequate funds due to defaults in payment by the Respondents. In such situation, the

Commission is of the view that impact of inefficiency in Obra-A, Obra- B, Harduaganj, Panki and

Parichha should be shared by the Petitioner and the Respondents. Half of the increased auxilliary

consumption above the benchmarks shall be borne by the Respondents for their failure in timely

payment and the rest half shall be afforded by the petitioner for not being diligent in realising its

revenue.

In view of the above decision, Auxiliary Consumption as approved by the Commission is given

below:

Table 44: Proposed and approved auxiliary consumption UPRVUNL and UPERC case

Name of the Station Aux. consumption % ( in

Regulation)

Aux. consumption % ( in

Petition)

Aux. consumption %

(Approved)

Obra A 10 12 11

Page 63: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

61

Obra B 9 12 10.5

Panki 10 12 11

Harduaganj 11 12 11.5

Parichha 11 12 11.5

Following table gives the trends in the auxiliary consumption for HPGCL plants from FY 2004-05

onwards.

Table 45: Trends in the Auxiliary Consumption

Name of the Plant FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11

FY 12

(upto

Oct’11)

PTPS-1 (Unit-1 to 4) 12.13 11.75 11.59 12.13 11.48 11.4 12 12.35

PTPS-2 (Unit-5 to 8) 9.80 9.06 8.74 8.81 8.80 9.13 9.66 10.00

PTPS, Panipat 10.76 9.79 9.48 9.58 9.42 9.73 10.19 10.65

DCRTPP, Yamunanagar 9.33 9.29 9.73 9.49

RGTPP, Hisar

7.05

Faridabad Thermal Power Plant 12.94 13.1 14.96 14.82 16.32 16.07

HPGCL Thermal Total 11.04 10.08 9.8 9.93 9.66 9.77 10.06 9.44

WYC and Kakroi (Hydel)

In the ensuing Tariff petition the petitioner has proposed Unit wise auxiliary consumption as given in

the following table. For the PTPS Unit-1 to 6 the petitioner has proposed the auxiliary consumption

based on three years average of the actual auxiliary consumption. For Unit- 7 & 8 of PTPS and

DCRTPS Unit-1 & 2 the petitioner has proposed auxiliary consumption in line with the HERC norms

dated 18th

Dec’08. For the RGTPS the petitioner has proposed the auxiliary consumption on

normative basis.

Table 46: Proposed Auxiliary consumption for the FY 2012-13

Name of the Plant FY 2012-13 (Projected)

PTPS-1 (Unit-1 to 4) 11.63

PTPS-2 (Unit-5) 9.99

PTPS-2 (Unit-6) 9.55

PTPS-2 (Unit-7) 9.00

PTPS-2 (Units-8) 9.00

PTPS (Panipat Thermal Power Station, Panipat) 9.93

DCRTPP, Yamunanagar Unit-1 9.00

DCRTPP, Yamunanagar Unit-2 9.00

DCRTPP, Yamunanagar 9.00

RGTPP, Hisar Unit-1 6.00

RGTPP, Hisar Unit-2 6.00

RGTPP, Hisar 6.00

HPGCL Thermal Total 8.19

Page 64: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

62

Name of the Plant FY 2012-13 (Projected)

WYC and Kakroi (Hydel) 1.00

As per Haryana Electricity Regulatory Commission (Terms and Conditions for Determination of

Generation Tariff) Regulations, 2008;

“During stabilization period, normative auxiliary consumption shall be reckoned at 0.5 per cent

over and above the norms. The Commission may relax the above norms on a case-to-case basis

based on unique plant lay out and inherent technology of the stations of older vintage.”

The Petitioner prays the Hon’ble Commission to consider the auxiliary Consumption for the vintage

PTPS Plants as proposed and also to consider the regulatory approach adopted by different SERCs

while approving the auxiliary Consumption in similar cases.

4.5. Fuel Price and Calorific Value

The calorific value considered for the computation of coal requirement is given in the following

table:

Table 47: Proposed Gross Calorific Value in Kcal./ Kg for coal and oil

Particulars PTPS, Panipat DCR TPP, Yamuna Nagar RGTPP, Khedar, Hisar

Gross Calorific Value of Coal (Kcal /Kg) 3,697 4,017 3,641

Gross Calorific Value of Oil (Kcal /Kg) 10,112 10,198 10,313

The calorific value is calculated by taking weighted average of the calorific value of coal and oil used

for the first five months of the FY 2011-12. The Fuel cost, both coal and oil for each station has been

calculated based on the actual average cost of the coal purchased during the first five month of the

FY 2011-12. The cost of coal also includes the transit loss. The details of the fuel cost taken are

mentioned in the following table below:

Table 48: Cost of fuel considered for calculating the variable cost

Type of the Fuel PTPS Panipat DCRTPP, Yamunagar RGTPP Hisar HPGCL

Rate of coal/ MT 3447.96 3458.77 3403.15 3433.30

Rate of Oil/ KL 37243.58 35818.93 40976.08 38325.14

4.6. Specific Oil Consumption

For the Unit-1 to 4 of PTPS, the petitioner proposes specific oil consumption as 2 ml/ kWh and rest

of the Units of PTPS and other thermal plants petitioner proposes specific oil consumption of 1

ml/kwh.

Page 65: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

63

4.7. Coal Transit Loss

The petitioner has considered following coal transit loss:

Table 49: Proposed coal transit Loss

Particular PTPS, Panipat DCR TPP, Yamuna Nagar RGTPP, Khedar, Hisar

Coal transit Loss 4.35 3.34 3.34

The transit loss has been discussed in details in the chapter No 2 on performance of the HPGCL. Here

the average transit loss for the last three years has been considered while calculating the final coal

requirement. The petitioner prays Hon’ble Commission to approve the coal transit loss as proposed

in the petition subject to adjustment at the end of each year based on the actual transit loss for each

power plants of HPGCL.

4.8. Moisture Loss:

HPGCL for its RGTPP, Khedar, Hisar power plant IPGCL is getting washed coal to the extent of 5.5

MTPA in FY 2011-12 pursuant to the contract with four (4) washery operators. During benefaction of

coal through washing technique, coal absorbs water resulting in higher weight at the time of loading.

The extra moisture evaporates during transit and storage. Therefore, usage of Washed coal leads to

higher moisture content and results into higher losses during transit. The loss of approx. 3% is due to

extra moisture in washed coal used in the Stations. Since, the coal transit loss in terms of moisture

loss is beyond the control of HPGCL, the Hon’ble HERC is requested to allow moisture loss @ 3% for

its RGTPP Coal based stations for FY 2012-13.

Hon’ble Appellate Tribunal of Electricity in the appeal filed by IPGCL in regard to MYT Tariff Order for

FY 2007-08 to FY 2010-11 has given the following ruling in its Order dated 07.4.2011 in respect of O

& M expenses:

22. “According to the Appellant, the State Commission has allowed a normative coal

transit loss of 0.8% by holding that the same is nationally accepted loss level as prescribed

in the Tariff Regulations of the Central Commission. It is noticed that the State Commission

has rejected the claim of the Appellant merely on the ground that NTPC had not

challenged the coat transit loss for the Dadri and Badarpur Stations which requires the

same washing of coal. As pointed out by the Learned Counsel for the Appellant, the ground

that NTPC had been allowed only 0.8% coal transit loss and the same had not been

challenged by the NTPC cannot be the valid ground to deny the claim of the Appellant. The

Page 66: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

64

important aspect that the State Commission has failed to consider is that the transit loss

cannot be the same both for unwashed and washed coal. The weight of the coal at the

time of loading is significantly increased due to higher moisture content which evaporates

during transit and storage. We notice that the State Commission has not given a reasoned

order regarding transit loss. Instead of examining the transit loss in case of the Appellant’s

power station the State Commission has noticed that the use of washed coal is likely to

improve the functioning of the plant. This matter, therefore, needs reexamination.

Therefore, the State Commission is required to determine the actual coal transit loss in

respect of the Appellant’s Power Station without comparing the coal transit loss with the

NTPC. This point is answered accordingly”.

Since, the higher coal transit loss is beyond the control of IPGCL, the Hon’ble Commission is

requested to true- up transit & moisture loss @ 3.8% for its Coal based stations for FY 2007-08 to

FY 2010-11 and approves the same percentage for FY 2011-12 for Rajghat Power House.

Page 67: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

65

5. Estimated expenses for FY 2012-13

In this section the Petitioner has provided details of the fixed components of the tariff based on

Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 and

estimates based on the actual data of HPGCL. The detailed submission is provided in the following

sections:

5.1. Return on Equity

HPGCL submits that it has considered the equity base as per the books of accounts and has

considered a return of INR 425.52 crore for the FY 2012-13. So far as the funding of additional

capitalization is concerned, HPGCL has envisaged a 100% debt funding for the same. The return on

equity has been calculated at the opening balance of equity capital towards existing plants of HPGCL

based on the CERC norms of 15.5% pre-tax. The Petitioner prays to the Commission that for the

RGTPP generating station, an additional return of 0.5% pre-tax to be allowed for completion of the

Project within time limit (44 months for Unit-1 and 50 months for Unit-2), based on the CERC norms.

The overall calculation for return on equity for the existing stations of HPGCL is provided below:

Table 50: Return on Equity on existing stations (In Rs. Crore)

Particulars FY 2012-13

Opening Balance of Equity (A) 2165.1

Return on Equity 425.52

The Unit wise return on equity calculation is computed in the prescribed format for individual

existing stations.

5.2. Income-tax

The Petitioner has considered the income tax for FY 2012-13 on the eligible return on equity for each

station and computed the income tax at the MAT rate of 20.01% (18.50% base rate +5% surcharge

+3% cess). The estimated tax portion included in the Return on Equity comes out to be INR 85.13

Crores.

5.3. Interest on Loan Capital and Finance Charges

The Petitioner has considered the actual interest rate as applicable to existing loans for computation

of interest charges. Whereas the finance charges constitute of Guarantee fees and other Bank

charges, etc. The basis of projections of the interest and finance charges is based on the actual

Page 68: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

66

charges incurred during the FY 2010-11, as per annual accounts. However, after an interval of reset

period i.e. three (3) years the interest and finance charges would be adjusted as per actuals.

The plant wise details of all the existing and new loans are provided in the relevant forms as

submitted to the Hon’ble Commission. The interest expenses and other finance charges for various

plants, as proposed by the Petitioner, are summarized in the table below:

Table 51: Interest and Finance Charges for 2011-12 (In Rs. Crore)

Station Proposed Interest and Finance Charges

FY 2012-13

PTPS Unit-1 to 4) 14.74

PTPS (Unit-5) 2.82

PTPS (Unit-6) 13.07

PTPS (Unit-7) 27.67

PTPS (Unit-8) 27.67

PTPS (Unit – 1 to 8) 85.96

DCRTPP Unit-1 86.83

DCRTPP Unit-2 86.83

DCRTPP Unit-1&2 173.66

RGTPP Unit-1 186.04

RGTPP Unit-2 186.04

RGTPP Unit-1&2 372.09

WYC & Karkoi 3.26

Total HPGCL 634.97

5.4. Depreciation

HPGCL has calculated station wise depreciation, on the opening Gross Fixed Asset (GFA) at the rates

specified in the Central Electricity Regulatory Commission (Terms and Conditions of Tariff)

Regulations, 2009. For the purpose of this petition, HPGCL has considered the opening Gross Fixed

Assets for FY 2012-13 based on the addition/deletion/transfers as estimated in the accounts for FY

2012-13. The table below presents the proposed Unit-wise depreciation for FY2012-13.

Table 52: Proposed Unit wise Depreciation (In Rs. Crore)

Station Proposed Depreciation

FY 2012-13

PTPS Unit-1 to 4) 28.91

PTPS (Unit-5) 12.20

PTPS (Unit-6) 50.89

PTPS (Unit-7) 44.34

PTPS (Unit-8) 44.35

PTPS (Unit-1 to 8) 180.69

Page 69: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

67

Station Proposed Depreciation

DCRTPP Unit-1 51.10

DCRTPP Unit-2 51.10

DCRTPP Unit-1&2 102.21

RGTPP Unit-1 88.68

RGTPP Unit-2 88.68

RGTPP Unit-1&2 177.36

WYC & Karkoi 9.43

Total HPGCL 469.69

The details of such expenses have been shown in the specific formats attached as annexed to this

petition.

5.5. Interest on Working Capital (IoWC)

HPGCL has projected the working capital requirement in a normative manner as per the Central

Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009. The interest

on working capital has been computed at the SBI PLR as on the date of submission of the tariff

petition at @14.75%. The station wise IoWC for all the stations is provided in the table below:

Table 53: Normative Interest on Working Capital for FY 11-12 (In Rs. Crore)

Station Proposed Interest on Working Capital

FY 2012-13

PTPS Unit-1 to 4 50.74

PTPS (Unit-5) 25.48

PTPS (Unit-6) 27.36

PTPS (Unit-7) 30.39

PTPS (Unit-8) 28.36

PTPS (Unit-1 to 8) 162.32

DCRTPP Unit-1 34.24

DCRTPP Unit-2 31.88

DCRTPP Unit1&2 66.12

RGTPP Unit-1 68.34

RGTPP Unit-2 63.50

RGTPP Unit-1&2 131.85

WYC & Karkoi 1.48

Total HPGCL 361.77

5.6. Operation and Maintenance Expenses

The O&M expenses comprise of Repair & Maintenance (R&M) charges, Employees cost and

Administrative expenses. The estimates for O&M cost for PTPS Unit-1 to 4 is based on the average of

Page 70: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

68

actual level of such expenses for three preceding years escalated by 5.72% based on CERC norms to

account for inflation, pursuant to Hon’ble Commission’s observations in Tariff Order dated 16th

April

2010 which says that

“The guiding factor for working out O&M expenses should have been the actual level of such

expenses incurred during the preceding three years for the existing stations escalated by an

appropriate factor to account for inflation.”

Accordingly, the O&M cost computations for PTPS-1 (Unit-1 to 4) are based on the details of actual

O&M expenses in the preceding three years FY2008-09, FY2009-10 and FY 2010-11 as per the annual

accounts.

In line with Hon’ble Commission’s order for previous years, the O&M expense in case of PTPS Unit-5

to 8, DCRTPP Unit-2& RGTPP Unit-1&2 are based on the CERC Regulations, as applicable for the FY

2012-13. The O&M expenses proposed for WYC & Karkoi are based on the O&M expense approved

by Hon’ble Commission during the previous Tariff Order dated 18th

April 2011, escalated by 5.72% in

line with CERC Tariff Regulations 2009-14 to account for the impact of inflation. The table below

summarizes the O&M expenses submitted by the Petitioner. The petitioner prays to the Hon’ble

Commission to allow O&M as per the submissions.

Table 54: Proposed O&M Expenses for FY2012-13 (In Rs. Crore)

Station Proposed O&M Expenses (Rs. Crore)

FY 2012-13

PTPS Unit-1 to 4 172.5

PTPS (Unit-5) 45.17

PTPS (Unit-6) 45.17

PTPS (Unit-7) 53.78

PTPS (Unit-8) 53.78

PTPS (Unit-1 to 8) 370.4

DCRTPP Unit-1 56.73

DCRTPP Unit-2 56.73

DCRTPP Unit-1&2 113.46

RGTPP Unit-1 82.92

RGTPP Unit-2 82.92

RGTPP Unit-1&2 165.84

WYC & Karkoi 21.03

Total HPGCL 670.73

Page 71: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

69

The Appellate Tribunal For Electricity vide Appeal No. 81 of 2007 in the matter of Indraprastha

Power Generation Co. Ltd. Versus Delhi Electricity Regulatory Commission has given the following

judgment on 10th

January, 2008 related to the pas through of O&M expenses:

“O&M Expenses: As mentioned in Paragraph 4(a) above, the Commission has strictly adhered to the

normative increase as suggested by the CEA. The petitioner requested the Commission to ask the CEA

to re-consider the report. The Commission, however, went by the CEA report which according to the

Commission had been prepared after taking all relevant parameters of operation into consideration.

The Commission, however, was uncertain as to how long the IP station can be operated based upon

various conditions imposed by statutory authority / courts etc. The Commission therefore did not

relax the norms. However, the Commission did not consider if it was proper to give any further time

to the appellant to improve its performance for the purpose of reducing cost.

11) Reverting to the report of the CEA, we find that the authority itself never meant that the norms

prescribed by it be strictly taken for compliance. In recommendation No.VI, the authority itself says

that the assessment is recommendatory in nature and within the framework of constraints /

limitations of the data furnished. The Commission feels satisfied with applying the CEA norms and

also feels compelled to do so for otherwise the interest of consumers will suffer. The Commission is

duty bound to allow all reasonable O&M expenses as pass through. The Commission is allowed to

only impose a prudence check. If the O&M expense had escalated within the norms prescribed by

CEA, the task of the Commission would have been quite easy. However, in the present case, the O&M

expenses have gone higher than the CEA norms. The Commission, therefore, was required to examine

the expenditure incurred by the appellant for various purposes and to detect if the appellant had

incurred any avoidable expense. The appellants are only successors in interest of the erstwhile DVB

and it has inherited some old power plants. It, along with power plant, has also received a large

number of employees which in the present legal regime cannot be shed immediately. The appellant

has attempted to reduce the number of employees by offering VRS. The plant being old the

maintenance expense can also be higher than what is estimated at the given point of time. The fact

that the appellant has been making efforts to improve its performance is clear from the figures of

actual heat rate for 2005-06 and 2006-07 which show that there is a fall in the station heat rate in

2006 compared to in the year 2005. It cannot be said that the appellant had altogether been

irresponsible in its expenditure. Therefore, it will be appropriate for the Commission to examine

individual items of expenditure and disallow only those which it finds as avoidable or imprudently

high. We had an occasion to examine the concept of prudence check in the case of NDPL Vs. DERC

Energy Law Reports (APTEL) 2007 193. The Commission had allowed an A&G expenses for

distribution companies of Delhi only to the escalation of 4% over the previous year’s expenses. The

Commission had made deduction on account of legal expenses and other general expenses. We held

that the Commission would have to allow such expenses which are justifiable and can disallow

such expenditures which were not justified. The Commission cannot simply apply the normative

rates of escalation and feel that its function of regulation is thereby over. While the Commission is

duty bound to regulate the generation, transmission and distribution keeping in view the interest

of consumers, it is also bound to see that the generator, transmitter and distributor gets a fair

return, over and above the expenses. We, therefore, have no option but to hold that the

Commission has to do some more exercise in arriving at the correct figure of O&M expenses which

can be taken as pass through in tariff. It has to examine individual items of expenditure and reject

those which were clearly avoidable or imprudent or impermissible and allow the rest as pass

through.”

Page 72: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

70

6. Other Considerations

6.1. Two Part tariff

· HPGCL proposes to determine tariff for sale of power of HPGCL for FY 2012-13 on Two Part

Tariff basis.

· Incentive for higher generation shall be at the rate of capacity charges per Unit in line with

present CERC Regulations. Similarly capacity charges for lower generation shall be recovered

on pro-rata basis.

· PLF for recovery of capacity charges shall be worked out by including deemed generation on

account of backing down instructions/ scheduling of lower generation than declared

availability

· HPGCL shall have the right to sell power not scheduled by Discoms to third party(ies) out of

State and for that power sold outside state, HPGCL shall be entitled to recover fixed/

capacity charges from the Haryana Distribution Licensee.

6.2. Recovery of Capacity (Fixed) Charges

· Capacity charges including incentive shall be recovered on pro-rata basis.

6.3. Third party sell in case of payment default by distribution licensee

HPGCL is under huge cash crunch scenario because of the poor payment history of the distribution

company of Haryana. Both the distribution companies in the state have an outstanding of around Rs

3242.28 Crore (Consisting of Rs. 2023.48 Crore from UHBVN, Panchkula and Rs. 1218.80 Crore from

DHBVN, Hisar) as on 27th

Nov’11. The result is that HPGCL, which supplies power to the two discoms,

is in a tight spot and nearly defaulted on its loan repayments. Apart from that, the non-payment of

bills in time by the distribution Licensee is causing HPGCL to pay heavily on short term funds for

working capital loan requirement and therefore there is an urgent need to enforce payment

discipline amongst the distribution Licensee. HPGCL humbly prays before Hon'ble Commission that

HPGCL should have the right to sell the power to third party outside state in the event of payment

default beyond 60 days for any of its bill by the distribution licensee of Haryana and in that case to

recover the fixed charge of the power sold outside the state from distribution Licensee of Haryana.

6.4. Terms of payment and adjustment of receipts towards outstanding dues

The terms of payment and adjustment of receipts towards outstanding dues of HPGCL shall be as per

HERC order 793-796/ HERC dated 03.07.2008. However, as Fuel Price Adjustment (FPA) is not

included in the working capital, no rebate on the same shall be allowed. Further, on the same

ground it is prayed that the payment of FPA shall be made by the Haryana discoms within seven (7)

days of the presentation of the bill failing which surcharge for delayed payment at HERC already

approved rate shall be applicable from the date of presentation of the bill.

Page 73: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

71

6.5. Application Fees and Publication Expenses

The application filing fee and the expenses incurred on publication of notices in the application for

approval of tariff be allowed to be recovered directly from the beneficiaries i.e. UHBVNL & DHBVNL

as per CERC Norms.

Page 74: HPGCL Tariff Petition for the FY 2012-13 - Haryana …hpgcl.gov.in/userfiles/file/Finance/Tarrif Applications...HPGCL Tariff Petition for the FY 2012-13 November 30, 2011 Haryana Power

Petition for Approval of Tariff for the year FY 2012-13

72

7. Annexures

7.1. Audited Annual Accounts for FY 2010-11

7.2. Cost Accounting record along with Cost Audit report for FY 2009-10

7.3. Minutes of meeting of “Steering Committee for Power Planning” under the

Chairmanship of Financial Commissioner and Principal Secretary (Power), Govt. of

Haryana dated 20th

September 2011

7.4. Appellate Order on Appeal No. 81 of 2007 dated 10th

January, 2008

7.5. Appellate Order on Appeal No. 26 of 2008 dated 7th

April, 2011

7.6. CERC (Terms and Conditions of Tariff) Regulations, 2009, Statement of Objects &

Reasons

7.7. Cost benefit of Imported Coal

7.8. Unit wise depreciation