Presentation How we support Agile teams in estimates

Transcript of How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow...

Page 1: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

Presentation

How we support Agile teams in estimates

Page 2: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

The Context for Agile in Computaris projects

Customer and business context

Rapid changes in telecom infrastructure: changes of technologies combined with an increased variety of network elements

Managing growing deployments

Complex systems that require an adaptive change management system

Integrating customer feedback early through demos and presentations, transparently and adapting to changing requirements

Page 3: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

What did we accomplish?

> Successful delivery of complex products

(1500+ MDs and 9+ people teams) through Agile methodologies, specifically where GUI is involved

> Meeting aggressive timelines, while producing

higher-quality software more productively

Page 4: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

How did we accomplish?

Quality assurance prevention techniques,

requirements validation

requirements traceability

code coverage automated tools

code inspection

simulators

continuous integration

automated regression suite

Page 5: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

What did we need?

The necessary steps:

To build from scratch accurate estimates

To plan the schedule

Page 6: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Facts

>It’s not easy to estimate something that is being built for the first time.

>We rarely built the same feature twice, so we had to use comparisons to

potentially similar features or use expert judgement.

>Estimating is an ongoing process, and we estimated closer to reality as we got to

the project end

>The velocity variated up to 25%

>The classical Bottom-up/top-down estimation estimating techniques did not work

> Estimating is a continuous learning effort for the team. Same is documenting them

>Sometimes it was easier to estimate relative size (T-shirts, complexity:

Low/Medium/High) or consider a mix of techniques

Page 7: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Lessons Learned

> Setup effort is smaller if one senior developer builds a project structure and then bring the whole team on board

> Trainings for new technologies had be accounted for 50-100% of Sprint 0 time, and at least 25% for the next 3 Sprints

> Rework should be planned in case we use new technologies

> We learned to plan for maintaining regression tests in each sprint or once in 2-3 Sprints

Page 8: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Lessons Learned

> Each sprint we learned to account for bug fixing and re-testing bug fixes for at

least 10-15% of dev time

> It proved easier to have QA start 1 Sprint behind Dev

> Thanks to our innovation program we never stop work : )

> Spend time in estimating in advance only for items that the PO targets for the

next 1 or 2 Sprints

Page 9: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Tip: Workload Pie Chart Report

Page 10: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

How we refined our estimates

Questions when doing estimates:

>Have we done this before in our team?

>Have we done this before in the company?

>Is there anything free we can reuse?

>In how many ways can we do it?

>What is the best way to do it? Why?

>Can we study this and regroup tomorrow

morning for Sprint Planning?

>At Sprint Planning, ask the Product Owner: any

chance what we’ll be working on in next Sprint?

Page 11: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Tip – check remaining Effort

Page 12: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

How we refined our estimates

Questions upon tasks completion:

> Did you log the actual effort? How accurate?

>What could you have automated?

> How would you do it differently?

> If you knew what you know now, how long would it

take you? What about other colleagues?

> Did we document what we did?

> Did we contribute to internal twiki/forums/community?

Page 13: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

Tips and tricks

Understanding and managing risk attitude when making estimates

Consider level of experience of the persons making the estimates, especially when these are different than the ones executing the tasks

Once there is a new technology that people get in love with it, it is hard to stop them from work

Page 14: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

In the end…we got there!We’ve built a solution which can

> ensure consistent quality and continuity of processes by validating human

manual operations

> save time with operation and maintenance flows

> fill in the gap between network planning and engineering departments

> prevent downtimes due to misconfiguration settings

> make better business decisions

Page 15: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

In the end…we got there!

Page 16: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...

In the end…we got there!

Page 17: How we support Agile teams in estimates - Meetupfiles.meetup.com/1305678/Estimates_Agile_v2.pdfHow we support Agile teams in estimates /... The Context for Agile in Computaris projects

/

...