How to set up and manage a Project ? Niten Chandra, IAS Joint Secretary Ministry of Rural...
-
Upload
kelsi-bowling -
Category
Documents
-
view
223 -
download
1
Transcript of How to set up and manage a Project ? Niten Chandra, IAS Joint Secretary Ministry of Rural...
How to set up and manage a Project ?
Niten Chandra, IASJoint SecretaryMinistry of Rural DevelopmentGovernment of [email protected]: 9958445904
Five Key Phases of Project Management
1. Set up and Contract2. Plan Project3. Implement4. Monitor & Report Progress5. Complete & Review
Niten Chandra, JS, MoRD, GoI 2
Set up & Contract
1. Setting up Process2. Develop Project Brief3. Write Issue Statement4. Define Mission & Key Objectives5. Specify Outputs & Timings6. Set Scope & Limits7. Clarify Roles8. Develop Personal Contracts9. Develop Project Contract
Niten Chandra, JS, MoRD, GoI 3
Setting up Process
1. Formulate issues, mission, objectives, output and timing2. Identify and engage with Stakeholders, beneficiaries, clients and customers3. Ascertain cross-departmental links4. Assess the feasibility of project5. Determine the principal means of achieving project mission and primary
objectives6. Work out the resources it will need and who will provide them7. Recommend how far its scope and authority should extend8. Formulate the best strategy for executing the project9. Select and appoint team members10. Arrange training to ensure common approach and understanding11. Formulate and sign the contract
Niten Chandra, JS, MoRD, GoI 4
Develop Project Brief
Purpose : •To brief project team on its task•Helps in establishment of a project team•Provides preliminary terms of reference from which a project contract can be derived
Niten Chandra, JS, MoRD, GoI 5
Issue Statement: Chronic inability of CAPART to meet its goals, poor networking, weak focus on rural community, entrenchment of malpractices and erosion of credibility
Sample Project Brief
Project Title: Restructuring of CAPART
Required Outputs: Implementation plan, MPR, Notes for decision Timing
Mission: To enable CAPART meet its goal of rural prosperity through engagement with government and voluntary agenciesPrimary Objective: Change organizational structure within 3 months
Scope & Limits: Only MoRD & CAPART to be involved, no engagement of professionals Budget: Rs 25 lakhs
Authorization procedure: Executive Committee & General Body, MRD
Cost Center: CAPARTProject termination date: 31/May/12.Members : DG(CAPART), JS (CAPART), Dir/US (CAPART) Support Team
Signed Administrative DepartmentDate
Niten Chandra, JS, MoRD, GoI 6
Write issue statement
It is a clear description of what the problem is and
what needs to be improved
Niten Chandra, JS, MoRD, GoI 7
Define Vision, Mission and Objectives
1. Vision provides the overall goal or purpose of the project. It defines how it will look like when we get there. It clarifies where the project is trying to get to.
2. Mission is what should be achieved in order to get to the vision.
3. Objectives are the means by which mission will be achieved.
Niten Chandra, JS, MoRD, GoI 8
Specify Required Outputs and Timing
• Reduces misunderstanding between owner and executant of project
• Provides a basis for assessing progress
• Provides means for establishing extent to which it has fulfilled project requirements
• Output should include:– Plan to achieve mission– Milestones with dates– MIS– Interim progress report– Measures of progress– Audit report, UC,
Evaluation study, documentation (video), etc.
– Timing : online, monthly, quarterly, annual, etc.
Niten Chandra, JS, MoRD, GoI 9
Set scope & limits
• These prescribe the DONTs• Budget constraint• Territorial limits• Performance standard /
target• Product type • Procedures or process
standards• Limit of authority or
delegation
• It prevents team from straying into areas not allowed or waste effort on low priorities.
• Limits have to be carefully judged so that they do not make objectives unrealistic.
Niten Chandra, JS, MoRD, GoI 10
Agree project budget
• Identify cost heads:– Manpower– Materials– Equipment– Premises– Expenses– Subcontractors: lawyers,
auditors, consultants, etc.
– Reorganization costs
• Quantify project benefits over its life
• Clarify authorization level and cost center.
Niten Chandra, JS, MoRD, GoI 11
Clarify roles
Getting the right players involved in clearly defined
roles ensures the necessary experience, skills and personal qualities are
available to the project. Without these the project
is unlikely to succeed.
Niten Chandra, JS, MoRD, GoI 12
Develop personal contracts
• Contracts clarify what is expected and who is doing what.
• It helps all parties in a project to define their roles and reach agreement with each other on how to work together.
Niten Chandra, JS, MoRD, GoI 13
Develop project contract
1. Encourages team to feel a genuine party to the contract2. Generates ownership of the means or the how3. Helps to ensure project brief is appropriate4. It should be signed to demonstrate commitment &
understanding
Mission Key Measures
Milestones Principal Means
Measures Objectives
By 31.3
By 31.7
Niten Chandra, JS, MoRD, GoI 14
Plan What To Do
1. Use a Project Management Plan2. Decide what to do3. Develop implementation plans
a. Work breakdown structureb. Key Activity & Task Plansc. Responsibility Chartsd. Resource Requirement Liste. Cost Breakdown Structure
4. Produce a schedulea. Gantt Chartb. Critical Path Analysisc. Draft Contingency Plans
Niten Chandra, JS, MoRD, GoI 15
Use a Project Management Plan
• This sets out five main phases in the life of a project and their key steps, with scheduled completion dates and assigned responsibilities:– Set up & contract, Plan project, Implement, Monitor & report
progress, Complete & Evaluate
Project Step Start By Complete By Responsibility Status
Niten Chandra, JS, MoRD, GoI 16
Decide what to do
1. Collect datai. Current processesii. Performance standardiii. Measuring waste, errorsiv. Surveying customers/
suppliers, etc.v. Efficiency & productivity
2. Analyse root causes3. Find best solutions
a. Check sheetsb. Data Displayc. Asking whyd. Brainstorminge. Cause & effect analysisf. Paired comparisonsg. Process mappingh. Time cost analysisi. Pareto analysisj. Cost Benefit analysisk. Decision Chartl. Priorities Grid
Niten Chandra, JS, MoRD, GoI 17
Develop Implementation Plans
Niten Chandra, JS, MoRD, GoI 18
Develop Implementation Plans
Niten Chandra, JS, MoRD, GoI 19
Develop Implementation Plans
Niten Chandra, JS, MoRD, GoI 20
Responsibility Chart
Task Name
Estimated Work Days
Duration of Work (No of Weeks)
SRD JS IFD Dir DG DDG
1 2 3 4 5 6
Responsibility Types:1.P: Prime Responsibility2.W: Does Work3.A: Advises4.I: Provides Input5.D: Takes Decision6.C: Must be consulted7.IF: Must be Informed
Niten Chandra, JS, MoRD, GoI 21
Resource Requirement List (Materials, manpower, systems, equipment, specialist help, funds, etc.)
Task Name Resources Required
Availability Problems Options Action Taken
Comments
Niten Chandra, JS, MoRD, GoI 22
Cost Breakdown
Task Name Resource Required
Cost Cost Code Expenditure Authorized
Invoice Received
Payment
• Record the dates for expenditure authorized, invoice received and payment made.
Niten Chandra, JS, MoRD, GoI 23
Produce a Schedule
• Gantt or Bar Chart• Critical Path
Method (CPM)• Programme or
Performance Evaluation & Review Technique (PERT)
Task Name Months
Jan Feb Mar Apr
Set goals
Set Budget
Engage Professionals
Draft Plan
Approve Plan
Release Funds
Procure Equipment
Operationalise
Train usersNiten Chandra, JS, MoRD, GoI 24
Contingency Planning
Potential Problem Solution Options Action Taken
Project: Date:Prepared by:
Niten Chandra, JS, MoRD, GoI 25
Implement
Implementation is about getting things done according to plan and
ensuring that a number of things are in place to support the activities and
manage the resultant changes.
Niten Chandra, JS, MoRD, GoI 26
Checklist for Successful Implementation
1. Community / Client Focus : Is the focus on community / client and the end users’ views and needs being attended to through regular check and feedback.
2. An Effective Communication System: knowing what should be communicated to whom, by whom, when, how, what outcomes are required, etc. Are goals, means, roles, responsibility, procedures, rules, guidelines and instructions clear to people ?
3. Effective Teamwork: what training, support and review mechanisms are in place. Is the Responsibility Chart working ? Do frictions persist ?
4. Working conditions: are the working conditions of team members adequate ? What incentives and awards are given to performers?
5. Information systems: Have measures been agreed ? How will data be captured, who will do it ? How will it link into the communications system? Is the protocol for sharing information with public in place ?
6. Progress Monitoring: Is the planned frequency and format working ? Are deviations analysed and corrective actions taken?
7. Risks and contingency planning: Have risks been identified and contingency planning done? What are the unforeseen problems and their likely impact ? How will they be dealt with ?
8. Legal, etc: Is full compliance to all legal, health, safety, administrative, audit and financial procedures being achieved ?
Niten Chandra, JS, MoRD, GoI 27
Monitor & Report Progress1. Is work being done within the estimates ?2. Will each activity be completed within schedule ?3. Is quality of work within specification?4. Are expected results being achieved ?5. Are there other changes or special problems ?
Corrective Action 1. Clarifying roles & removing confusion 2. Rearranging the workload 3. Resolving disputes4. Putting in more resources or effort5. Moving target completion date(s)6. Lowering targets
Feedback (MIS)
Results Chain
MIS should be :i.Focussed on prioritiesii.Responsive i.e initiates corrective actioniii.Timely – no undue delaysiv.User friendlyv.Flexiblevi.Simple & Clear
Niten Chandra, JS, MoRD, GoI 28
Progress Report
1. Current Project Status: Cost, time & quality2. Future Status: likely deviations3. Critical Tasks status: 4. Risk Assessment: 5. Information relevant to other projects/States :
lessons learnt, best practices
Task Name Planned Result Actual Result Deviations Remedial Action
Date: Submitted By:
Niten Chandra, JS, MoRD, GoI 29
Project Log
Purpose: Monitor project process in a qualitative way to deal with important management issues and to generate useful information for future project improvement
Entry Date Issues Numerical Data
Opinion Action Required
Responsibility
Niten Chandra, JS, MoRD, GoI 30
Niten Chandra, JS, MoRD, GoI 31
1. Financial2. Administrative3. MIS4. Monitoring &
Evaluation5. Performance Audit6. Incentives7. Training8. Coordination9. Discipline10. Stress Management
Training & Learning Stages
1. We come to know about something which is new and different
2. We understand the possible applications of the new idea or information
3. We accept the idea as useful, a desirable option and are willing to make the changes
4. We are able to apply the new learning.
Niten Chandra, JS, MoRD, GoI 32
Management Competencies
Clusters of Personal Competence Dimensions of personal competence
1. Planning to optimize the achievement of results
1.1 Showing concern for excellence1.2 Setting & prioritizing objectives1.3 Monitoring & responding to actual against planned activities
2. Managing others to optimize results 2.1 Showing sensitivity to the needs of others2.2 Relating to others2.3 Obtaining the commitment of others2.4 Presenting oneself positively to others
3. Managing oneself to optimize results 3.1 Showing self-confidence and personal drive3.2 Managing personal emotions and stress3.3 Managing personal learning & development
4. Using intellect to optimize results 4.1 Collecting & organizing information4.2 Identifying and applying concepts4.3 Making decisions
Niten Chandra, JS, MoRD, GoI 33
Job Description with Performance Plan & Behavioural Criteria
Key Result Areas Measures & Reports
Standards & Targets Timing
Direct regional operations to ensure that all planned targets are met within agreed budgets and time scales
Monthly Management Reports on :•Expenses•Sales•Staffing•Budget Variance Reports
For year ending Mar 2012•Not more than $ X million in expenses•Target is $ Y million•< 5 % increase in costs•Not more than +- 5%
Reports due one week after month end.
Behavioural criteria Decisiveness, Planning & Organizing, Problem Analysis, Work Standards, Inter-personal sensitivity, Management control, Initiative, Persuasiveness, Leadership, Judgment
Niten Chandra, JS, MoRD, GoI 34
Planning for Performance
Major Areas of Responsibility Results or standards expected to be achieved. Agreed actions and priorities.
Due Dates of action initiation and completion.
Niten Chandra, JS, MoRD, GoI 35
Reviewing Performance
Niten Chandra, JS, MoRD, GoI 36
Aligning Members within an Organization
Achievement of Department’s mission & objectives depends on how individuals within an organization
are aligned with the mission & objectives. There are essential attributes that may be fostered in
individuals to ensure proper alignment of individuals within a Department by building appropriate
performance culture.
Niten Chandra, JS, MoRD, GoI 37
Checking for Attributes
Sl. No. Attributes Score (0-1)
1 Competence: has or seeks knowledge and skills relevant for job, continually learning
2 Effort: tries to complete tasks, does not delay
3 Productivity: stamina, endurance with high volume of work done
4 Creativity: lateral thinking, produces useful & innovative ideas or approaches to problem solving
5 Quality: does work with accuracy, calm & thoroughness , does not offend, not moody has self-control
6 Communication: listens and explains ideas or concepts clearly, pleasantly, persuasively
7 Dependability: is firm & follows up on completion of assignments despite odds, gives no excuses
8 Initiative: has enthusiasm, seeks new assignments or opportunities for contribution, crosses boundaries and reaches out
9 Decision-making: sets priorities and gives options, provides focus & clarity
10 Leadership: fosters team-work, helps team solve problems, tactfully resolves disputes, inspires, is kind, not fault-finding, mentors, coaches and develops others
Total Score Niten Chandra, JS, MoRD, GoI 38
Building Performance Culture in an Organization
1. Set short-term, challenging, motivating and realistic goals2. Provide support for performance3. Invite people to workshops and seminars to present success tales and share
experience with others at agreed intervals4. Appreciate & reward performers5. Investigate problems with non-performers6. Get together performers and non-performers to share the key success
drivers, provide solutions & make the tasks doable for the non-performers.7. Provide additional support, training to non-performers and lower their
targets to make them achievable 8. Let non-performers attain the respect for showing performance, taste the
joy of performance, and have the anxiety to avoid non-performance
Niten Chandra, JS, MoRD, GoI 39
How can Leader solve problems of team members
Niten Chandra, JS, MoRD, GoI 40
Outline Plan for Performance Discussion1. Warm up2. Job Responsibilities
1. What do you see as your major responsibilities at present2. What are the priorities ? Why ?3. What would you change about your project?4. How could your time and talents be used better?
3. Performance goals1. Overall, how do you we feel about the targets we set?2. Have any of them proved to be inappropriate? Why?
4. Job accomplishments1. How do you feel the job is doing?2. What has interested you most in your project in the past?3. What have been the major accomplishments?4. Where do you think you are being most effective in your project?
5. Areas for Improvement1. What disappoints or frustrates you most about your project at the present time?2. Where do you feel least effective?3. What can we do to increase your effectiveness4. What help or support can we give you?
6. Assessment7. Plans for Improvement
1. This should be discussed and agreed and not imposed
8. Conclusion1. Summarize the discussion2. Agree on future action3. Describe what will happen with the results of the review4. Thank everyone for their time and contribution
Niten Chandra, JS, MoRD, GoI 41
Post-Completion Evaluation : Capitalising on Learning
1. Lessons Learnt2. Things which could have been done better3. Leadership and motivation4. Enthusiasm and passion of the team members5. Clarity & focus on goals6. Coordination among interdependent units/departments7. Quality of communication- internal & external, flow of information8. Efficiency, effectiveness, flexibility, freedom, trust9. Quality of support received10. Authority, responsibility & delegation11. Resourcing issues12. Robustness and value of contract13. Problems of personal time management
Niten Chandra, JS, MoRD, GoI 42
Thank You
Niten Chandra, JS, MoRD, GoI 43