The Program
1 lump sum contract 4 years 5 light rail lines 30 miles of
infrastructure 100 vehicles$2,000,000,000 investment
Lets Talk RISKThe Relationship Risk
• Development agreement
• Design/Build contract• Operations & maintenance contract• Financing plan
• Development agreement• Design/Build contract• Operations & maintenance contract• Financing plan
Facility Provider
Integrated Master Development Structure
Lets Talk RISKThe Relationship Risk
The Evolution RISK - Team Building
Civil Engineer +Facility Provider
D/B Contractor(s)Financiers
+Vehicle Supplier
The Evolution RISK - Team Building
Civil Engineer +Facility Provider
Financiers +
Vehicle Supplier
O & M Contractor
Development Agreement
• CE & facility provider marriage• Scope & definition• Transparent costing• Construction sequencing &
schedule• Utility agreements• Property acquisition• Risk register
RISK Register
• 154 Items 92 Facility provider 62 METRO / owner
• 35 Categories• 30% - 15% Project value• $460M - $250M
RISK Register
• Imputed risksReal (equity) risks
• Cost going in = Cost coming out
• Risk take of last resort
The Ultimate RISK
• METRO will not buy/own the project
• Availability payment Debt service – year five (5)
onward Operating – year one (1)
• Avoid latent defect risks• Long term business model
Long term lease•Buy out in increments•Buy out total
Private or public operation
The Vehicle RISK
• METRO takes what industry makes
• No specs• No custom work• No kidding!
Design / Build
• 3,000’ – 5,000’ segments one & done
• No change order• No claims• No litigation• No liquidated damages• Target cost pricing mechanism
Risk vs. Incentives
Would you RISK IT??