US Williston Basin Oil Production, BOPD
2
22JJ Kringstad - North Dakota Pipeline Authority 2
Estimated Williston Basin Oil Transportation
3
33JJ Kringstad - North Dakota Pipeline Authority 3
4
Estimated ND Rail Export Volumes
4JJ Kringstad - North Dakota Pipeline Authority 4
Rail Destinations Market Share (Oct 2018)
55
Data for Rail Destination Market Share Provided by the US Energy Information Administration
JJ Kringstad - North Dakota Pipeline Authority 5
Cushing $51.06
Brent $59.99WTI + $8.93
Crude Oil Prices – January 9, 2019
6JJ Kringstad - North Dakota Pipeline Authority
Pricing Data: Bloomberg &
CME (LLS-Argus)Houston WTIWTI + $5.28
JJ Kringstad - North Dakota Pipeline Authority 6
North Dakota Oil Pricing
77JJ Kringstad - North Dakota Pipeline Authority 7
Midwest (PADD 2) Refinery Crude Oil Consumption
99JJ Kringstad - North Dakota Pipeline Authority 9
EIA Data
North Dakota Oil Pricing
1010JJ Kringstad - North Dakota Pipeline Authority 10
11
Bakken Drilling Economics
JJ Kringstad - North Dakota Pipeline Authority 11
www.northdakotapipelines.com
12
Bakken Breakeven Price Range (20% IRR)
Bakken Breakeven Prices
$6 - $8 Million
Completed Wells Cost
Background Map: Esri, HERE, DeLorme, MapmyIndia, © OpenStreetMap contributors, and the GIS user community
JJ Kringstad - North Dakota Pipeline Authority 12
13
Bakken-Three Forks Drilling Inventory Study
JJ Kringstad - North Dakota Pipeline Authority 13
www.northdakotapipelines.com
Cumulative Remaining Wells – Peak Month Minimum BOPD
1414JJ Kringstad - North Dakota Pipeline Authority 14
30-Day Initial Production (BOPD)
Years Remaining* / Minimum Wellhead Oil Price*Assumes 1,200 Completions Per Year and $7MM Well Costs (20% After Tax IRR)
1515JJ Kringstad - North Dakota Pipeline Authority 15
16
Statewide Oil Performance
JJ Kringstad - North Dakota Pipeline Authority 16Average BKN/TF Well Performance Statewide
~13% Improvement
Over 2017
North Dakota Oil Production Forecast Assumes Current Technology – Enhanced Oil Recovery Not Included
1717JJ Kringstad - North Dakota Pipeline Authority 17
1818JJ Kringstad - North Dakota Pipeline Authority 18
North Dakota Oil Production Forecast Assumes Current Technology – Enhanced Oil Recovery Not Included
1919JJ Kringstad - North Dakota Pipeline Authority 19
Williston Basin Oil Production & Export Capacity, BOPDAssumes Current Technology – Enhanced Oil Recovery Not Included
Production forecast is for visual demonstration purposes only and should
not be considered accurate for any near or long term planning.
2020JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 20
NDPA North Dakota Gas Production ForecastAssumes Current Technology – Enhanced Oil Recovery Not Included
2121JJ Kringstad - North Dakota Pipeline Authority 21
2222JJ Kringstad - North Dakota Pipeline Authority 22
NDPA North Dakota Production Forecast SummaryAssumes Current Technology – Enhanced Oil Recovery Not Included
Simple Terms
Blue – Lack of pipelines
Orange – Challenges on existing
infrastructure
GREEN – % of gas captured and sold
Blue – % flared from zero sales wells
Orange – % flared from wells with at
least one mcf sold.
Oct. 2018 Data – Non-Confidential WellsStatewide
Solving the Flaring Challenge
JJ Kringstad - North Dakota Pipeline Authority 23
Bakken and Three Forks Gas Performance
JJ Kringstad - North Dakota Pipeline Authority 24
Dunn McKenzie Mountrail Williams
25JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 25
Solving the Flaring ChallengeAssumes Current Technology – Enhanced Oil Recovery Not Included
26JJ Kringstad - North Dakota Pipeline Authority
Solving the Flaring ChallengeAssumes Current Technology – Enhanced Oil Recovery Not Included
JJ Kringstad - North Dakota Pipeline Authority 26
27JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 27
Upcoming or
Recent Plant
Expansion
WBI Transmission
Andeavor
Major Gas Pipeline and Processing Infrastructure
JJ Kringstad - North Dakota Pipeline Authority 28
Northern Border Pipeline
*Data Source: Northern Border IPS
• 42” Pipeline
• Carries Canadian (Port of Morgan) and Domestic Gas
• Receives Gas From ND Plants, WBI Transmission Interconnections, and WY Pipelines (Bison & Grasslands)
• Midcontinent Deliveries
JJ Kringstad - North Dakota Pipeline Authority
Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND
gas production could increase 1.11-1.41 BCFD (from Oct-18) before Northern Border is 100% Bakken
production. BTU management becomes increasingly important for Bakken residue gas.
29
Now What?
3030JJ Kringstad - North Dakota Pipeline Authority 30
Regional NGL Infrastructure
Kinder
JJ Kringstad - North Dakota Pipeline Authority 31
North Dakota Captured* NGL’s
3232JJ Kringstad - North Dakota Pipeline Authority 32*Non-flared NGL’s & Assumes 10 GPM
NGL Pipeline Takeaway Options
33
3333JJ Kringstad - North Dakota Pipeline Authority 33
ONEOK Elk Creek NGL Pipeline
Project Highlights
• 900 Miles - 20” Pipeline
• $1.4 Billion
• 240,000 BPD Capacity
• Expandable to 400,000
BPD
• End of 2019 Proposed
Completion
• Y-Grade Transportation
JJ Kringstad - North Dakota Pipeline Authority 34
North Dakota Pipeline Construction
35
Sources: NDIC & PHMSA
35JJ Kringstad - North Dakota Pipeline Authority 35
North Dakota Pipeline Construction
36
Sources: NDIC & PHMSA
36JJ Kringstad - North Dakota Pipeline Authority 36
Justin J. Kringstad, DirectorNorth Dakota Pipeline Authority
600 E. Boulevard Ave. Dept. 405Bismarck, ND 58505-0840
Phone: (701)220-6227Fax: (701)328-2820
E-mail: [email protected]
Websites: www.pipeline.nd.gov
www.northdakotapipelines.com
Contact Information
JJ Kringstad - North Dakota Pipeline Authority 37