Hornsea Offshore Wind Farm Project One ... Hornsea Offshore Wind Farm Project One ... HVAC High...
date post
30-Dec-2019Category
Documents
view
3download
0
Embed Size (px)
Transcript of Hornsea Offshore Wind Farm Project One ... Hornsea Offshore Wind Farm Project One ... HVAC High...
Hornsea Offshore Wind Farm
Project One
Environmental Statement
Volume 6 – Onshore
July 2013
ii
SMart Wind Limited
Hornsea Offshore Wind Farm
Project One – Environmental Statement
Volume 6
Annex 6.9.1 – Electromagnetic Fields Study
SMart Wind Limited
11th Floor
140 London Wall
London
EC2Y 5DN
Tel 0207 7765500
Email [email protected]
Copyright © 2013
All pre-existing rights reserved.
Liability
This report has been prepared by SKM and RPS, with all reasonable skill, care and diligence within the terms of their contracts with SMart Wind Ltd or their subcontractor to RPS placed under RPS’ contract with SMart Wind Ltd as the case may be.
Document release and authorisation record
PINS Document Reference 7.6.9.1
Report Number UK04-050700-REP-0071
Date July 2013
Client Name SMart Wind Limited
Client contact(s)
Chris Jenner
Penny Pickett
Rachael Mills
Rosemary Tingle
Liam Leah
Sheelagh Guilmartin
Ditte Bilde
iii
Table of Contents
1 Introduction ........................................................................................................... 1
1.1 Scope of Report .................................................................................................... 1
1.2 Sources of EMF .................................................................................................... 1
1.3 Cable Configuration .............................................................................................. 2
2 Calculations and Results ....................................................................................... 3
2.1 Approach ............................................................................................................... 3
2.2 Cases Studied ....................................................................................................... 3
Table of Figures
Figure 1.1 Magnetic field produced by current in conductor. ...................................................1
Figure 2.1 3 x 335 MW circuit arrangement. ...........................................................................3
Figure 2.2 4 x 300 MW circuit arrangement. ...........................................................................4
Figure 2.3 2 x 600 MW HVDC circuits arrangement. ..............................................................5
Figure 2.4 3 x 335 MW + 5 x 360 MW HVAC circuits arrangement. .......................................6
Figure 2.5 2 x 600 MW + 3 x 600 MW circuit arrangement. ....................................................7
Table of Graphs
Graph 2.1 Magnetic field density due to 3 x 335 MW circuits. ................................................4
Graph 2.2 Magnetic field density due to 4 x 300 MW circuits. ................................................5
Graph 2.3 Magnetic field density due to 2 x 600 MW circuits. ................................................6
Graph 2.4 Magnetic field density due to 3 x 335 MW circuits + 5 x 360 MW circuits. .............7
Graph 2.5 Magnetic field densities due to 2 x 600 MW + 3 x 600 MW circuits. .......................8
Table of Tables
Table 2.1 Magnetic field densities due to 3 x 335 MW HVAC circuits. ...................................4
Table 2.2 Magnetic field densities due to 4 x 300 MW HVAC circuits. ...................................4
Table 2.3 Magnetic field densities due to 2 x 600 MW HVDC circuits. ...................................5
Table 2.4 Magnetic field densities due to 3 x 335 MW + 5 x 360 MW HVAC circuits. ............6
Table 2.5 Magnetic field densities due to 2 x 600 MW + 3 x 600 MW circuits. .......................7
iv
Glossary
Term Definition
Project One
With a maximum capacity of 1.2 Gigawatts (GW) or 1,200 MW, Project One is the first offshore wind farm project within the Hornsea Round 3 Zone and includes all necessary offshore and onshore infrastructure required to connect to the existing National Grid substation located at North Killingholme, North Lincolnshire. Project One is the first of a number of wind farm projects planned for the Hornsea Zone to meet a target Zone capacity of 4 GW by the year 2020. Project One will be the subject of a single application to PINS for a DCO under the Planning Act 2008.
Project Two
With a maximum capacity of 1.8 Gigawatts (GW) or 1,800 MW, Project Two is the second offshore wind farm project within the Hornsea Round 3 Zone and includes all necessary offshore and onshore infrastructure required to connect to the existing National Grid substation located at North Killingholme, North Lincolnshire. Project Two is the second of a number of wind farm projects planned for the Hornsea Zone to meet a target Zone capacity of 4 GW by the year 2020. Project Two will be the subject of a single application to PINS for a DCO under the Planning Act 2008.
Round 3
Round 3 was announced by The Crown Estate in 2008 with nine development zones. The successful bidders were announced in January 2010 with a potential generating capacity of 32 GW. The Crown Estate announced the first round of UK offshore wind farm development in December 2000 and the second round of larger sites in July 2003.
Cable circuit and phase
A cable or cables that make up an entire electrical circuit. Usually used in reference to export cables. Where the cables are AC, a circuit could consist of a single three-core cable or three single-core cables. Each core carries one phase of electrical power. Where the cables are DC, the circuit could consist of a single two-core cable or two single-core cables. Typically, offshore AC cables are three-core and onshore cables are single-core. Typically, both offshore and onshore DC cables are single-core.
Acronyms
Acronym Full term
A Amperes
DCO Development Consent Order
EMF Electromagnetic Field
GW Gigawatt
H Henrys
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
MW Megawatt
OFTO Offshore Transmission Operator
PINS The Planning Inspectorate
RMS Root Mean Squared
T or µT Tesla (more commonly µT – microtesla – due to magnitude)
1
1.1.1 SMart Wind has been awarded a licence by The Crown Estate to develop
approximately 4,000 MW of wind capacity off the coast of East Yorkshire known as
Zone 4 under the Round 3 Offshore Wind Licensing Arrangements.
1.1.2 As part of the initial design process, SMart Wind has requested that SKM studies the
electromagnetic field (EMF) densities produced by each of the cable connection
arrangements that are being considered for the first two stages of the development
zone (1.2 GW + 1.8 GW), Project One and Project Two respectively. The cable sheath
material will fully shield the electric field at ground level. Therefore only the magnetic
field has been assessed. This note covers the following arrangements:
The HVDC onshore connection between the onshore transition pit at the landfall
and the OFTO converter station; and
The HVAC onshore connection between the onshore transition pit at the landfall
and the OFTO substation.
1.1.3 Calculations of the maximum expected magnetic field strength in the vicinity of the
cable trench have been made which include the combined effect of the cables
operating in parallel. The connections will be made in two stages. Results have been
provided for both Project One (1.2 GW) and when Project One and Project Two (3
GW) are connected.
1.2.1 When a current passes through a conductor a magnetic field is produced around the
conductor. The direction of the field depends on the direction of current flow in the
conductor as shown below in Figure 2.1.
Current
Conductor
Direction of EMF
produced
Figure 1.1 Magnetic field produced by current in conductor.
1.2.2 With an AC current source the density and direction of the field will vary with the
current. With a DC source the field will have a constant magnitude (providing the
current stays constant) and will be in a constant direction.
1.2.3 The density of the magnetic field is proportional to the current flowing through the
conductor and the distance between the conductor and point of measurement. The
magnitude of the field density is calculated using the Biot-Savart law, from which the
following equation can be derived:
Equation 1 Magnetic flux density.
1.2.4 Where:
B = Magnetic flux density (T)
μ0 = Permeability of free space = 4 x x 10 -7 (H m-1)
I = Current through conductor (A)
r = Distance from centre of conductor (m)
1.2.5 An additional source of EMF is the natural static magnetic field produced by Earth
which has a (relatively) constant strength and direction at any specific location. For DC
cables this will interact with the magnetic field produced by the