P3 This Is Our Faith P3 RERC 1-25a P3 RERC 1-26a P3 RERC 1-27a P3 RERC 1-27b
Honolulu Authority for Rapid Transportation’s P3 Owner’s...
Transcript of Honolulu Authority for Rapid Transportation’s P3 Owner’s...
Honolulu Authority for Rapid Transportation’s P3 Owner’s Forum
Regional Transportation District
Eagle P3 ProjectDenver, CO
About RTD• Service area: 2,342 square miles
• Population served: 3.03 million
• RTD staff 2,863 + 1,608 private
contractor staff
• Buses, Call-n-Ride and ADA
vehicles: 1,433
• Light rail vehicles: 172
• Commuter rail Vehicles: 66
• 2017 statistics:
− Total ridership: 99 million
− Assets: $6.8 billion
− Revenue: $990 million
− Operating exp.: $581.9million
− Capital outlay: $451 million
2
• University of Colorado A Line
• 22.8 miles of commuter rail between Denver Union Station and DIA
• B Line
• 6 miles of commuter rail between Denver Union Station and Westminster
• G Line
• 11.2 miles of commuter rail between Denver Union Station and Wheat Ridge
Eagle P3 Project
Eagle P3 - History
• In 2003, RTD and CDOT initiated an Environmental Impact Statement (EIS) for the I 70 Corridor
• In 2006, RTD initiated an EIS for the Gold Line Corridor
• In August 2007, approved by FTA to participate in the Penta-P program
• Provided for accelerated review process
• Reduced oversight during project development
• In September 2009, issued final RFP to pre-qualified teams.
• In July 2010, entered into a Concession Agreement with Denver Transit Partners (DTP)
4
Eagle P3 Project Scope
• Overall capital cost $2.2 billion
• 36 miles of new electrified (25kV) commuter rail
• 37 major bridge structures
• 14 new stations plus Denver Union Station hub
• Commuter Rail Maintenance Facility
• 66 cars in married pair configuration (including 12 for N Metro)
• 29 at-grade crossings shared with Class 1 Railroads
Eagle P3 - Terms
• Concession Agreement – DBFOM• Design• Build• Finance • Operate• Maintain• 34 Year Agreement (2011-2044)
• Includes 5 year design/ build • 29 year maintain and operate
• RTD sets and retains fares
• RTD owns assets
• RTD pays traction power and security costs
6
Eagle P3 - Funding & Financing Sources
7
Total Asset Cost - $2.3 billion
• $1.1 billion in federal funds
• $1.03 billion New Starts grant
• $65 million CMAQ funding
• $450 million in private financing
• $396 million in private activity bonds
• $54 million private equity
• $460 million in local funds
• Includes sales tax revenue bonds, sales and use tax revenues, and contributions from local jurisdictions
• $280 million Transportation Infrastructure Finance Innovation Act (TIFIA) loan
Eagle P3 - Repayment
• Construction Phase
• Set amounts tied to earned value
• Maintain and Operate Phase
• Service Payments
• Funds maintenance and operations
• Concessionaire receives 100% of availability payment for meeting 95% of performance standards
• Bonus of up to 0.5% for perfect delivery
• Deduction of up to 25% for inferior delivery
Eagle P3 – Service Payments
Although there are many factors that go into the service payment calculation. There are three factors that influence whether there is a bonus or deduction.
• Rolling Stock Availability
• On Time Performance
• Station Availability
Monthly Payments – Calculation
• TABOR payment (debt & equity)• Indexed Service Availability payment:
10
Start with: Base Service Availability Payment
Adjusted by: Availability Factor ¹
Equals: Availability Adjusted Base Service Payment
Less: Performance Deduction
Plus: Special Events
Equals: Amount Due
(3 x Rolling Stock Availability) + (2 x On-Time Availability) + (1 x Station Availability)²Availability Ratio =
¹Availability Factor corresponds to the Availability Ratio². Once the Availability Ratio is calculated, the Availability Factor
is found in the Availability Factor Tables in the Concession Agreement
6
Eagle P3 - Risk Sharing
RTD
• ROW Acquisition
• Railroad Force Account Work
• Unidentified Environmental Conditions
• Unidentified Utilities
• Ridership
Concessionaire
• Cost Overruns
• FRA Approvals
• 3rd Party Claims
• Failure to meet Performance Standards
• Operation and Maintenance Costs
• Condition of System at end of Concession Period
11
Lessons Learned
• Procurement• Maintain a competitive field
• Provide stipend• Listen to concerns over risk allocation
• Allow for innovations• Performance Specifications• Alternative Technical Concepts
• Ensure confidential communication between bidders and owner
• Follow procurement schedule
• Keep Board of Directors informed
• Public outreach
• Impact of local taxes on pricing
Lesson Learned
• Service• Joint understanding of metrics and calculations
• Data capture and reporting
• P3 Delivery• Jurisdictions do not understand the constraints of a P3
• Lock down scope and involvement early
• Lenders do not like changes
• Even simple design changes are perceived as increasing risk to a Concessionaire
• Complexities of dealing with multiple jurisdictions, railroads, airports, FTA, FRA, regulatory bodies, etc.
Lesson Learned
• P3 Funding and Financing• Make sure you get what is eligible for federal funds in writing
• Make sure owner finance and accounting staff are at the table during negotiations
• Ensure private concessionaire understands documentation needed
• Keep external auditors updated and involved
Eagle P3 – Completion Dates
• University of Colorado A Line
• Opened April 22, 2016
• B Line
• Opened July 25, 2016
• G Line
• Scheduled to be open Fall 2016 – Still TBD
15
Questions?
16