Holiday Mentors Build Season Discussion
December 18, 2006
![Page 2: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/2.jpg)
Today’s Discussion
• Items that needed improvement from last year
• Potential Ideas• Mentor Determined Subteams• Detailed Schedule
• Schedule & Assignments
![Page 3: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/3.jpg)
Improvement Needs
• Some students didn’t get to work on robot items, even though they wanted to
• Not enough mentors to help mentor robot items
• Spent too much time prototyping/building things not used
• Not enough time for programming• Not enough communication• Others?
![Page 4: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/4.jpg)
Students didn’t get to work on robot items
• Create Pre-Determined Subteams• Mentors Pre-Assigned, get to select
students• At least 1 Experienced student• At least 1 CAD student• At least 1 New Student
![Page 5: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/5.jpg)
Not enough mentors to help mentor robot items
• We have many new mentors this year
• Would like to have at least 2 mentors per subteam
• Mentors can switch off or fill in for eachother
![Page 6: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/6.jpg)
Too much time prototyping & building things not used
• Leadership Team Creating Day to Day Schedule
• Will stick to Build Process better (PDR, CDR, milestones, etc)
• Better up front robot design (determine which sensors)
![Page 7: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/7.jpg)
Not enough time for Programming
• Tighter Schedule• More Milestones• More focus on Sensors
![Page 8: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/8.jpg)
Not Enough Communication• Integration Team Meeting (like subteam
leaders meeting)• Twice a week• 1 person from each subteam• Detailed reports & schedule updates
• Leaders will put tasks & upcoming milestones on board
• MS Project Schedule will be updated daily
• Possible thermometers?
![Page 9: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/9.jpg)
Schedule PossibilitiesParallel Track 2-3
Prototypes of Each System
• Allows Room for Design Failure
• Smaller Groups (more hands on)
• Longer to get to Final Design 1/16
Select Robot “Design” 1/9
• Faster time to production
• Get in Pre-select groups faster
• No spending time on things not used
• Highest Potential for Design Failure
Finish Robot by the end of Week 4? Or Week 5?
![Page 10: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/10.jpg)
Other Concerns?
• Any other concerns from last year?• Any new mentor concerns?
![Page 11: Holiday Mentors Build Season Discussion December 18, 2006.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ede5503460f94beee30/html5/thumbnails/11.jpg)
Your Schedule
• When ARE you available?• When are you NOT available?• What would you like to be involved
in?