Holger Schlarb DESY 22607 Hamburg · 09.11.2004 Holger Schlarb, DESY 8 " ˙ • measurement in...
Transcript of Holger Schlarb DESY 22607 Hamburg · 09.11.2004 Holger Schlarb, DESY 8 " ˙ • measurement in...
09.11.2004 Holger Schlarb, DESY 1
������������������
Holger SchlarbDESY
22607 Hamburg
• Injector run: Feb 04 – Jun 04• Linac commissioning: Sep 04 - now
09.11.2004 Holger Schlarb, DESY 2
����������������������������
Injector run: prove if emittance can be preserved at high energy
Linac run: Not all hardware have been installed/existed
Beam commissioning in parallel to hardware/software commissioning
Early commissioning to identify
⇒ building blocks for controls required for operation
⇒ additional hardware/electronics/diagnostics/controls
⇒ hardware problems
⇒ reliability and stability
Several stages for commissioning:
1. Test of general functionality of component or subsystem
2. Stability and reproducibility of operation
3. High precision measurement and consistent checks with simulations
09.11.2004 Holger Schlarb, DESY 3
�����������������
• Upgrade of injector II
• Booster with 4 SC cavities + 4 to further accelerate
• 3rd harmonic cavity to straighten the longitudinal phase space
• Laser with longitudinal flat-hat profile
• Commissioning up to ACC2
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
ACC2(M1*) ACC3(M3*)
Laser
3rd
harmonic cavity diagnostic section
beam dump
12 MV/m 20 MV/m
§ 3rd harmonic cavity not yet installed
§ Laser with longitudinal Gaussian profile
§ Commissioning up to ACC2
§ operated all 8 cavities at 12 MV/m -> 100 MeV
Final stage: During spring 2004:
09.11.2004 Holger Schlarb, DESY 4
� ���������������������������• RF Gun:
21-Feb-2004 start RF conditioningMarch 04 5 Hz, 900 s, 3 MW
10 Hz, 450 s, 3 MWfirst beam in gun section
April 04 measurements of gun performance» Quantum efficiency of photo cathode» Transmission and beam size» Phase measurements» Energy, energy spread» Dark current
• Injector:April 04 start injector commissioning
» High gradient test of cavity» Emittance measurements» HOM for beam based alignment» CSR measurements
07-Jun-2004 end commissioning
09.11.2004 Holger Schlarb, DESY 5
� ������������������ �������� �• Full transmission through the narrow dipole
chamber only for solenoid current above 280 A
• Focus on last screen before ACC1 (I = 295 A)
• Bucking off, 1 nC, 3 mm diam. laser, 40 dg phase
• Data don’ t fit well at focus:probably a optical resolution problem
• Significant steering required280 A
09.11.2004 Holger Schlarb, DESY 6
��!������������
charge (nC)
1 deg
Several scan in a row:
Reproducibility of RF gun phase adjustment:
Acceptance versusRF phase &Solenoid current
When special cuts are applied
Sole
noid
cur
rent
[A
]Gun phase [deg]
09.11.2004 Holger Schlarb, DESY 7
���������������������������• momentum measurements in dispersion section after RF gun• reflected power is corrected for• p versus Pfwd: data fit well with the simulation;
p versus phase: agreement less good
09.11.2004 Holger Schlarb, DESY 8
" ������������������������ �����• measurement in March 2004 (10 Hz, 400 s, 3.2 MW): max. 230 A
and in June 2004 (5 Hz, 100 s, 3.2 MW): max. 160 A
• No critical dark current levels observed
• But 100-200 A already contribute to beamlineactivation
main solenoid current (A)
dark
cur
rent
(uA
)
dark
cur
rent
(uA
)
2nd FCW
ork
poin
ts
1st and 2nd faraday cup, Pfor=3.2MWDark current entrance of ACC1 (2nd FC)
09.11.2004 Holger Schlarb, DESY 9
# ������������������• electro-polished cavity installed at #5 in ACC1• cavity is equipped with Piezo-tuner• cavity RF test predict G = 36 MV/m (RF power measurements)• RF calibration confirmed with energy meas. of beam in BC2⇒ Successful installation of
high gradient cavity in acc. module.
Cavities limits ACC1:C1 (Z54) 18 MV/m C2 (Z51) 16 MV/m Lower limit for ACC1 C3 (D42) 20 MV/m C4 (D37) 27 MV/m power limited C5 (AC72) 36 MV/m no FE C6 (C47) 23 MV/mC7 (Z53) 20 MV/m large FE large
Lorentz forces C8 (AC69) 18 MV/m large FE
09.11.2004 Holger Schlarb, DESY 10
$���������������������% ��& ����������'���%OTRWS
OTRWS
OTRWS
OTRWSQF QF QFQD QD QD
0.95 m 1.9 m0.46 m 0.49 m
Matching quadrupole = 45°
Camera
3 Lenses
3 Filters
Mirror
OTR station (Frascati)• Four monitor method using OTR monitorsor wire scanners– During commissioning only the OTR monitors in operation
• Beam size measured at four screens in a FODO lattice of six quadrupoles (fixed quad current)
• Emittance and Twiss parameterscalculated from the measured beam sizes and beam size errors using chi-square fitting (90% of beam image)
• Gun parametersas optimized at PITZ (except solenoid)
• Measurements with by-passed bunch compressor
E=100MeV
09.11.2004 Holger Schlarb, DESY 11
� �������������������������������������
4DBC2 6DBC2
10DBC28DBC2
Beam images from 4 OTR screens: phase advance of 45°, 1 nC, magnification =1
09.11.2004 Holger Schlarb, DESY 12
��������������������������������
• Normalized emittance in vertical direction < 2.0 umhor izontal direction < 2.5 um
• Large scattering in measurement results for x
• Systematic studies for horizontal orbit versus emittance still open.
• Emittance growth may caused by – Laser mirror – Kicks in ACC1– Alignment problems GUN/ACC1
• Nevertheless, a very promising though still preliminary result
• Study of systematic in beam size determination and measurement errors not completed yet
09.11.2004 Holger Schlarb, DESY 13
# ( ) *� �����������������������• The signal of a dipole mode in a cavity can be used to
determine the beam position• Due to different polarization x and y can be measured • Handle to investigate misalignment gun/module
example for vertical steering and dipole mode response in C1
09.11.2004 Holger Schlarb, DESY 14
$�������!�������������������������• Energy spread measured from horizontal beam profile in the dispersivesection of the bunch compressor (OTR screen) • Residual energy spread estimated from the rising edge about 30 keV (rms), tail of about 200 keV• Energy stable within 0.12 % measurements with single bunches on-crest acceleration (LLRF FB on but low gain)
If slow drift is removed ~ 0.12%
Cal = 24 keV/pixelE0 =100 MeV
Energy (a.u.)
Inte
nsity
(a.
u.)
Energy spread
09.11.2004 Holger Schlarb, DESY 15
���������������������������%�+�+��� �%
~ 15 m transfer lineZ-cutQuartzwindow
09.11.2004 Holger Schlarb, DESY 16
���������������������������% ���������������������������%
Input polarizer
Beam splitter
Roof mirror
Inputbeam
Parabolic mirror
Detectors removed, types used DTGS, Pyro, Golay
Martin-Puplett Far Infrared Inter ferometer :
09.11.2004 Holger Schlarb, DESY 17
First autocorrelation taken:
Spectra for different compression phase:
Expected Maximum ofcompression
���������������������������% ���������������������������%
09.11.2004 Holger Schlarb, DESY 18
10 bunches, 1 nC, Gun = -40 degred, green: DTGS detectors in TOSYLAB blue: Sum of both DTGS black: Pyro P1-65 (100 MOhm) at 10DBC2
Compression monitor: coherent power ~ 1/σz
⇒ ideal suited to measure relative bunch lengths
Max. compression
On-crestCTR(CDR)
Two maxima for CSR observed!
���������������������������% ���������������������������%
Acceleration phase ACC1 [deg]
Det
ecte
d si
gnal
s [V
]
09.11.2004 Holger Schlarb, DESY 19
�������������������% ���������%
• Commissioning of linac:August dark current measurements C6@ACC5September restart of operation gun
PS commissioned up to exit BC2beam operation ACC1 with 4*12.5 +4*18.5 MV/mBPM commissioning and calibration in BC2coarse cavity phasing of ACC2&ACC3
October transmission through BC3transmission up to collimator sectioncavity phasing of ACC2&ACC3cavity phasing of ACC4&ACC5all PS for magnets in bypass available
November transmission to dump through bypass
09.11.2004 Holger Schlarb, DESY 20
��������������'�,• after coarse phasing of ACC2&ACC3 (21-Oct-2004):
Good transmission with BC3 on/off
09.11.2004 Holger Schlarb, DESY 21
'���������) �������
• Alarms: HV type of beam losses• Not yet connected to linac interlock• Very useful for steering and beam adjustments• Dark current fire BLM interlock (attenuation)
beam
Only gun d.c.
ACC1 + gun d.c.
09.11.2004 Holger Schlarb, DESY 22
������������������������������!• after commissioning of by-pass dipoles: ~ 25% transmission• few days later ~ 75% transmission• empirical optics …
09.11.2004 Holger Schlarb, DESY 23
-���������!��������.
• aperture problem in gun section (dipole chamber) ⇒ limits regime for beam operation
• missing BPM in gun dump line⇒ no control of energy stability in macro pulse
• misalignment in gun area⇒ dark current collimator cannot be used
• BPMs in BC2 & BC3 does not work⇒ no online control on energy after ACC1 and ACC2&3
• only about 360 MV energy at BC3 (400MeV design/required?)⇒ higher space charge effects
. ������������������/����������������