egkjktiq j, Xokfy;j & 474 005 Maharajpur, GWALIOR - 474 005 CAMTECH/E/15-16/Trip Shed Inspection/1.0 March, 2016 Hkkjr ljdkj GOVERNMENT OF INDIA jsy ea=ky; MINISTRY OF RAILWAYS dsoy dk;Z ky;hu mi;ksx gsrq (For Official Use Only) HANDBOOK ON UPKEEP OF ELECTRIC LOCO TRIP SHED END USER : ELECTRIC LOCO TRIP SHED MAINTENANCE STAFF

Transcript of Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric...

Page 1: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

egkjktiqj, Xokfy;j & 474 005

Maharajpur, GWALIOR - 474 005

CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016

Hkkjr ljdkj GOVERNMENT OF INDIA

jsy ea=ky; MINISTRY OF RAILWAYS

dsoy dk;Zky;hu mi;ksx gsrq

(For Official Use Only)

HANDBOOK ON UPKEEP OF ELECTRIC LOCO TRIP SHED

END USER : ELECTRIC LOCO TRIP SHED MAINTENANCE STAFF

Page 2: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

HANDBOOK ON UPKEEP OF ELECTRIC LOCO TRIP SHED

QUALITY POLICY

“To develop safe, modern and

cost effective Railway

Technology complying with

Statutory and Regulatory

requirements, through

excellence in Research, Designs

and Standards and Continual

improvements in Quality

Management System to cater

to growing demand of passenger

and freight traffic on the

railways”.

Page 3: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

FOREWORD

With increasing trends of passenger and freight traffic,

the maximum availability of locomotives on line is desirable.

To ensure reliable and safe operation of electric locomotives, it

is essential to carryout proper schedules maintenance and

safety checks at regular intervals.

Trip inspection is very important as during trip

inspection not only the attention is given to scheduled activities

but also some other defects come to the notice which otherwise

may result in loco failure on line. For carrying out this activity,

the proper upkeep of trip shed is essential.

CAMTECH has prepared this handbook on “Upkeep of

Electric Loco Trip Shed” with the objective to check and

upgrade the infrastructure and facilities required for proper

upkeep of trip sheds. I am sure that this handbook will be

useful to the users.

CAMTECH Gwalior A.R.Tupe

Date: Executive Director

Page 4: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

PREFACE

Reliability and safety aspects of electric locos are of

highest priority which may only be ensured by proper

inspections and timely attention. Trip shed is the first line

maintenance spot where locomotives are inspected,

attended at regular interval/after trip.

For ensuring proper trip inspection and maintenance

at trip sheds, it is essential to have sufficient infrastructure

and facilities in trip sheds and also their proper upkeep.

This handbook on “Upkeep of Electric Loco Trip

Shed” comprises brief on infrastructural facilities , check

list for upkeep of trip shed. Approach to equipment failure

investigation and proforma for communicating repeated

failure of particular type to home shed have also been

added.

It is clarified that this handbook does not supersede

any existing provisions laid down by RDSO or Railway

Board/Zonal Railways. This hand book is for guidance only

and it is not a statutory document.

I am sincerely thankful to all field personnel who

helped us in preparing this handbook. Technological up-

gradation & learning is a continuous process. Please feel

free to write us for any addition/ modification in this

handbook.

CAMTECH, Gwalior Peeyoosh Gupta

Date: 23.03.2016 Director Electrical

Page 5: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CONTENTS

Chapter No. Description Page No.

Foreword iii

Preface iv

Contents v

Correction Slip vii

1. General Description 1

1.0 Introduction 1

1.1 Brief on trip inspection activities 2

2. Upkeep of Trip Shed 4

1. Covered Shed 4

2. PIT 6

3. Infrastructure Facilities 7 4. Storage of Spare Ready Equipment 8

5. Human Safety Aspects 9

6. Earthing Rod 9

7. Isolation of OHE 11

8. Fire Fighting Arrangement 12

9. First Aid 13

10. Safety Precautions 14

11. Earthing of Shed supply/ equipment 17

12. Tools 18

13. Sand 19

14. Loco Safety Items 19

15. Electrical Fittings 21

16. Shed Premises 21

Page 6: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

Chapter No. Description Page No.

17. Up-dation of Staff knowledge 22

18. Track 29

19. Availability of M & P 29

20. Outsourcing of Services 31

21. Other Miscellaneous Items 32

3. Check List 33

Check list for of upkeep of trip shed 33

ANNEXURE-1 35

Approach to Equipment Failure Investigation

ANNEXURE-2

Proforma for Communication Repeated Defect /Deficiency/ Failure of Particular Type to Home Shed 37

Page 7: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

ISSUE OF CORRECTION SLIP

The correction slips to be issued in future for this handbook

will be numbered as follows:

CAMTECH/E/15-16/Trip Shed Inspection/1.0/ C.S. #

XX date---

Where “XX” is the serial number of the concerned

correction slip (starting from 01 onwards).

CORRECTION SLIPS ISSUED

Sr. No. Date of

issue

Page no. and Item

no. modified

Remarks

Page 8: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect
Page 9: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 1

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

CHAPTER 1

GENERAL DESCRIPTION

1.0 INTRODUCTION

Electric locomotives are working horses of

Indian Railways hauling efficiently and economically

both passenger and freight trains. To ensure reliable and

safe operation of electric locomotives, it is essential to

carryout maintenance schedules and safety checks at

regular intervals.

Reliability and safety aspects of electric locos

are of highest priority which may only be ensured by

proper inspections and timely attention. Trip shed is the

first line maintenance spot where locomotives are

inspected, attended at regular interval/after trip.

Trip sheds are meant to carry out trip inspection

of both types of electric locomotives i.e. coaching and

freight locomotives. The trip inspection of conventional

as well three phase locomotives are being carried out at

same trip shed.

In general two electric locomotives could be

accommodated in a trip shed which has pit lines for

under gear safety examination of the engines. Overhead

electrification line (OHE) isolation arrangement is also

provided at the trip shed lines to enable roof

examination of the electric locos.

Page 10: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

2 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

1.2 BRIEF ON TRIP INSPECTION ACTIVITIES

General maintenance, working of electrical and

pneumatic equipment of the loco, filling up of lubricants

in the under gear equipment and minor repairs are

carried out at trip sheds. For major repairs locos are

directed to nearby electric loco sheds to avoid dead loco

or light engine movement to home shed.

Examination of roof equipment such as

pantograph and circuit breakers, checking and

inspection of safety features, circuit, operation,

lubrication level are also carried out before being sent

back for regular operations.

Trip inspection also includes topping up of

distilled water in batteries, sand filling in sanders and

attention to various minor defects which have been

recorded in the logbook by loco pilots. In addition

certain checks are necessary mainly due to severe

environmental conditions (hot, humid and dusty)

existing in the various areas of Indian Railways.

The major activities during trip inspections include:

Detailed checks in regard to any unusual occurrence

reported by the drivers in the loco logbook.

Visual inspection of loco roof, under-gear, HT/ LT

compartment connections/ contactors, and other

equipment

Working of all auxiliary motors and circuits.

Temperature feeling of axle boxes, traction motors

etc.

Page 11: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 3

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

Functioning of control, indication and alarm

circuits.

Condition checking of batteries and topping up of

distilled water.

Working of pantograph, circuit breakers, and other

traction equipment.

Inspection of transformer, resistances, DBR, etc.

Checking of loco safety items such as headlight,

flasher light, fire extinguishers, wooden wedges etc.

Pit examination for any hanging part or unusual in

the under-slung equipment.

Examination of mechanical items such as brake

gears, coupling, wheel sets etc. and replacement of

brake blocks etc. if required.

Testing of traction and braking aspects of

locomotives, pneumatic examination etc.

Working of sanders and filling of dry sieved sand.

Functioning of various gauges, meters, indicators

and alarms etc.

From all of the above, it is very clear that trip

shed is a very important and crucial point of loco

maintenance which should be given proper attention

for its upkeep and infrastructure requirements.

Page 12: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

4 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

CHAPTER 2

UPKEEP OF TRIP SHEDS

The examination pattern in recent years has been

changed considerably resulting into extensive utilization of

locomotives. Hence, any compromise on quality of examination

and repairs will affect the efficiency and reliability of electric

locomotives. This is only possible when proper working

conditions are provided to the staff with suitable infrastructure

and facilities.

1. COVERED SHED

The covered shed should be in good condition

with sufficient air and light to protect from extreme

weather conditions like sun, heavy rains etc.. There shall

be provision of approach road to the trip shed.

There should be no

water leakage from

roof top in rainy

season. The roof

should be repaired as

and when required.

Page 13: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 5

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

The shop floor should be

cleaned on regular basis.

There should be proper

lighting arrangement for

general inspection with

sufficient illumination.

For directed maintenance, staff may use helmet based

LED lights/torch/hand-lamp for precision inspection and

work.

On both ends of shed proper flood light arrangement

should be ensured for safe movement of staff and

locomotive.

Page 14: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

6 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

2. PIT

The depth of pit

from rail level

shall be as per

standard design.

Proper cleaning of

the pits should be

ensured.

There should be

proper water

drainage system

in pits and it

should be cleaned

in pre monsoon

precautions.

There should be

arrangement for drain water (trolley mounted

motor pump etc.) in rainy season from pits.

There should be proper pit light arrangement at

safe voltage 24 volts and it should be maintained

in working condition.

Page 15: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 7

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

3. INFRASTRUCTURE FACILITIES

Separate well furnished room for trip shed in-charge

with attached toilet. Well equipped with computer,

printer, LAN connectivity with division/ net

connection and communication facilities.

Separate room for shift in-charge with suitable

furniture and attached toilet.

Staff Room with table, chairs, lockers etc.

Separate toilet for staff.

Two rooms for storing of lubricants, loco spares,

brake blocks etc.

Page 16: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

8 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Separate space/room for

scrap material storage

Drinking Water facility

with water cooler and filter.

Separate space with proper

heating arrangement for

cardium compound.

Loco body washing

arrangement with proper drain system and OHE

isolation facility.

4. STORAGE OF SPARE READY EQUIPMENT

Proper storage of ready spare equipment in racks etc.

Proper record of ready spare equipment in register

and with daily position display on board in shift

incharge room.

Tagging on spare ready equipment i.e. O/H date,

receive date etc.

Use ready/overhauled spare within time i.e. 09

months in FIFO (First in First Out) order.

Page 17: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 9

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

5. HUMAN SAFETY ASPECTS

Helmet – should be used while working in under gear

/roof.

Industrial shoes- staff should wear industrial shoes.

Hand gloves – for using while cleaning Look Out

Glass, cleaning cattle guard etc. after CRO.

Dress material or stitched dress for winter and

summer season for staff and apron for JE/SSEs.

6. EARTHING ROD

Earthing rod shall be as per specification and should

be in good condition.

Ensure periodic checking of earthing rod and cable

with clamp connection.

Page 18: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

10 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Proper procedure of providing discharge rods i.e. –

first connect one end of cable (clamp) to earthed

structure and another end of cable (clamp) to rail

and then provide earth discharge rod to OHE.

(Note: Structure bond must be connected between rail

to this structure, this should be ensured.

Page 19: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 11

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

7. ISOLATION OF OHE

Castle lock arrangement in isolator shall be working

order.

Provide additional pad lock in isolator for personal

safety and staff will keep key with him till working

on loco roof.

Ensure periodic checking and maintenance of

Isolator by TrD department.

Page 20: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

12 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

8. FIRE FIGHTING ARRANGEMENT

Availability of sand and water at appropriate

locations

Availability of fire extinguishers at easily accessible

location.

Training of staff about fire fighting & fire

prevention measures and keep record

Display of Fire prevention/ Fire Safety Slogans

Page 21: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 13

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

9. FIRST AID

Ensure availability of first aid box and its timely

recoupment.

Training of staff about rendering first aid to the

electrocuted and display of chart for treatment of

Electric Shock.

Display of emergency nos. such as hospital,

ambulance, Fire Brigade, RPF, GRP, controlling

officers etc.

Page 22: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

14 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

10. SAFETY PRECAUTIONS

Display of safety slogans/ precautions at various

locations.

Provision of boards like ‘MEN AT WORK’,

‘SUPPLY OFF’, SUPPLY ON’

Regular counseling of staff and keep record.

Depute staff for safety seminar at least once in a

year being organized at nearby electric loco shed by

safety department and keep record.

Page 23: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 15

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

Page 24: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

16 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 25: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 17

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

11. EARTHING OF SHED SUPPLY/ EQUIPMENT

Ensure proper earthing of equipment such as

welding plant, electric panel etc.

Ensure periodic maintenance of earth pits/ earth

resistance by concerned department.

Page 26: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

18 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

12. TOOLS

Ensure availability of sufficient & proper tools like

megger, temperature sensing device etc..

Ensure calibration of testing equipment, tools and

gauges like pressure gauges, meters etc.

Digital Multimeter Cell Tester

Digital Megger Digital Clamp Meter

Infra red

Temperature Gun

Sockets Wrench Set

Page 27: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 19

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

13. SAND

Ensure availability of dry and sieved sand.

Ensure proper working condition of sand drying

plant (not required in shed if off loaded to trade).

14. LOCO SAFETY ITEMS

Ensure all safety items and safety fittings are intact

while dispatching the locos.

Ensure availability of spare safety items in trip shed.

Ensure securing of locomotives as per the

procedure.

Page 28: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

20 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 29: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 21

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

15. ELECTRICAL FITTINGS

Ensure proper condition of electrical distribution

panels.

Ensure proper condition of shed wiring, it should

not be in defective condition.

Ensure proper condition of switch boards etc.

16. SHED PREMISES

Ensure general upkeep of shed premises.

Ensure proper cleaning of rooms, shop floor, pits.

Keep scrap material in proper place and arrange

for timely disposal.

Page 30: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

22 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

17. UP-DATION OF STAFF KNOWLEDGE

Display Electrical power, control and pneumatic

circuit diagrams in trip shed premises.

Staff shall be deputed for periodic training and

refresher courses at training centres and maintain

record.

Maintenance staff should be trained in a systematic

manner for 3 phase loco technology so that

technology of 3 phase loco is imbibed smoothly for

better and correct maintenance practices.

Staff shall be made familiar about advance/ digital

tools by means of training for efficient working.

Display motivational slogans as and where possible.

Page 31: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 23

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

Page 32: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

24 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 33: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 25

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

Page 34: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

26 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 35: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 27

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

Page 36: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

28 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 37: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 29

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

18. TRACK

Ensure proper condition of track.

Ensure periodic inspection and maintenance by P-

way staff.

19. AVAILABILITY OF M & P

Ensure proper working and maintenance of machine

and plant available in trip shed for smooth working.

Portable welding plants- 02 nos.

Speedometer data extraction unit (speed-cum-

energy) – one of all makes.

Meggar 500 V and 1000 V- 1 no. each

Temperature sensing device (non-contact type

thermometer) – 4 nos.

Additional

Oil drum/barrel

lifter cum tilter

(Various

manufacturers are

available in market,

these are available

in variants like

manually, hydraulic,

battery operated

etc.)

Page 38: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

30 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

Page 39: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 31

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

20. OUTSOURCING OF SERVICES

Many typed activities have been out sourced for

efficient working of trip sheds like:

Shed premises and pit cleaning.

Supply and filling of dry, cleaned and sieved sand

Loco internal cleaning (cabs and corridors), loco

body washing and look out glass cleaning.

Others………as required.

Page 40: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

32 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

21. OTHER MISCELLANEOUS ITEMS

Suitable AT (Auxiliary Transformer) supply, DG

Set/ Inverter may be provided to ensure continuous

electric supply to trip shed.

Notice board shall be provided to display any

notice/important instructions for staff.

Page 41: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 33

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

CHAPTER 3

CHECK LIST

CHECK LIST FOR UPKEEP OF TRIP SHED

1. Whether supply is made dead & earthed before

working on power/ equipment.

2. Availability of fire extinguishers & whether staff are

familiar with fire fighting & fire prevention

measures?

3. Availability of first aid box & whether all the staff is

familiar with rendering first aid to the electrocuted.

4. Whether the staff observing safety precautions

during their work & protecting the work spot and

himself.

5. Ensure whether proper earthing is done to the

equipment through earth pits/ earth resistance.

6. While attending electrical repair works, ensure

proper power block/ OHE isolation. Also the boards

like ‘MEN AT WORK’, ‘SUPPLY OFF’, SUPPLY

ON’ to be ensured at switching panels and

distribution boards.

7. Check whether calibrated recommended standard

tools like pressure gauges, meters & testing

equipment (electrical & mechanical) are being used.

8. General upkeep of shed premises & proper

environment.

Page 42: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

34 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

9. While dispatching the locos from trip shed whether

all safety items and safety fittings are intact and in

function or not?

10. Securing of locomotives as per the procedure or not?

11. Availability of sand and water at welding locations.

12. Proper locking of ‘Isolator’ handles of OHE.

13. Proper condition of earth discharge rods.

14. Condition of distribution panels.

15. Availability of spares and their condition.

16. Use of proper tools by staff.

17. Attention to look out glasses.

18. Availability of dry and sieved sand.

19. Usage of personal safety items viz. helmets and

shoes by staff.

20. Proper lighting of shed and pit line.

21. Knowledge of proper procedure of providing

discharge rods.

22. Staff knowledge to attend different class of

locomotives.

23. Safety and fire hazard posters.

24. Display of electrical and pneumatic circuits.

25. Any other items noticed related to safety.

Page 43: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 35

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

ANNEXURE-1

APPROACH TO EQUIPMENT FAILURE INVESTIGATION

A. On Failure Aspects

1. Occurrence

2. Date of occurrence

3. Past similar occurrences if any

4. Analysis of failure i.e. why did it happen?

5. Whether the rate of failure is worse than other

installations?

B. On Maintenance Aspects

1. Whether schedule maintenance & required testing

have been carried out on the failed equipment as per

norms stipulated?

2. Does the frequency of maintenance require change?

3. Was the work properly supervised?

4. Was any RDSO modification required to be done?

5. Is any modification possible to avoid failure?

C. About Staff

1. Is the quality of work done satisfactorily?

2. Is the skilled staff properly trained to carry out the

work?

3. Is the SMI available with them?

4. Are proper tools available with the staff?

D. About Material

1. Is the material received from approved source?

2. Whether the material is as per approved specification?

3. Can a better material be used?

Page 44: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

36 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

E. About Testing

1. Is the testing equipment available?

2. Could testing procedure be improved to weed out the

failures?

3. Whether testing equipment are calibrated?

F. General Points

Whether following points were checked / performed

properly?

1. Proper contact

2. Clearances

3. Capacity

4. Proper contact pressure

5. Crack detections

6. Cleaning

7. Proper connections/alignment

8. Cross checks/super checks

Page 45: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 37

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

ANNEXURE-2

Proforma for Communication Repeated Defect/Deficiency/ Failure of Particular Type to Home Shed

Name of Reporting Trip Shed: Name of Locos Home Shed: ………………………. Period under Observation: …………….to………………. Type of Failure/Defect/Deficiency Observed: …………….……………………………………………………. …………………………………………………………………... ………………………………………………………………….. Details of locomotives:

S.N. Date Loco Type & No.

Defect/Deficiency Noticed

Action Taken

1.

2.

3.

4.

5.

Signature of Trip Shed In charge:

Name:

Designation:

Contact No.;

Page 46: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

38 CAMTECH/E/15-16/Trip Shed Inspection/1.0

March, 2016 Handbook on Upkeep of Electric Loco Trip Shed

REFERENCES

1. Report No.RDSO/2007/EL/RM/0110, (Rev.0), January 2007 on Review of Trip Inspection of Electric Locomotives.

2. Check List Proforma for Trip Shed Inspection (Prepared by Central Raiway, Bhusawal)

3. Literature collected from Trip Sheds during field visits.

4. Suggestion/ Comments received during seminar held on 23.11.2015 on the subject.

******

Page 47: Hkkjr ljdkj GOVERNMENT OF INDIA MINISTRY OF RAILWAYS · March, 2016 Handbook on Upkeep of Electric Loco Trip Shed Proper procedure of providing discharge rods i.e. – first connect

CAMTECH/E/15-16/Trip Shed Inspection/1.0 39

Handbook on Upkeep of Electric Loco Trip Shed March, 2016

To upgrade maintenance technologies and methodologies and achieve improvement in productivity and performance of all Railway assets and manpower which inter-alia would

cover reliability, availability, utilisation and efficiency.

OUR OBJECTIVE

CAMTECH is continuing its efforts in the documentation and up-

gradation of information on maintenance practices of electrical assets.

Over the years a large number of publications on electrical assets have

been prepared in the form of handbooks, pockets books, pamphlets &

video films etc. These publications have been uploaded on the internet as well as rail net.

For downloading these publications please do following:

1. On internet visit : www.rdso.indianrailways.gov.in

Go to Directorates CAMTECH Publications for download

Electrical Engineering

2. On Railnet visit RDSO website at 10.100.2.19

Go to Directorates CAMTECH Publications for download

Electrical Engineering

For any further information regarding publications please contact:

Director (Elect.) – 0751- 2470740 (O) BSNL, 9752447030 (CUG)

SSE/Electrical - 9755549297 (CUG)

E-mail at [email protected]

Fax to 0751- 2470841

Write at : Director (Electrical)

Indian Railways

Centre for Advanced Maintenance technology,

In front of Hotel Adityaz,

Airport Road, Maharajpur,

Gwalior, Pin code – 474 005