Highway 15 Project – Hutchinson, MN Adjacent Properties and Businesses Meeting Hutchinson Area Chamber of Commerce 1 Thursday, August 24, 2017 | mndot.gov/d8/projects/hwy15downtownhutch

Transcript of Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing,...

Page 1: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Highway 15 Project – Hutchinson, MN

Adjacent Properties and Businesses Meeting

Hutchinson Area Chamber of Commerce1Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 2: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Agenda

Topic

1) Introduce the project scope

2) Project goals and benefits

3) Project timeline

4) Discuss project elements and process

Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch 2

Page 3: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Project Location 

• Full Reconstruction of Highway 15 and underground utilities between 2nd Ave. N and 5th Ave. S 

• Pavement Resurfacing between 5th Ave. S and just south of Denver Ave.

3Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 4: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Summary of Work 

• Complete reconstruction of Main Street/Highway 15 through downtown 

• Pavement resurfacing of Highway 15 between 5th Ave S and just south of Denver Ave 

• Update sidewalk and pedestrian crossings along project area to meet Americans with Disabilities Act (ADA) standards 

• The City of Hutchinson will also be replacing, updating, and modernizing underground utilities

4Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 5: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Benefits 

• Smoother road surface 

• Modernize sanitary sewer, water main and storm sewer 

• Help ensure city and state infrastructure serves their purpose for many years 

• The City of Hutchinson views this project as an opportunity to enhance downtown and improve livability in the central district

5Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 6: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Downtown Typical Sections

6Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 7: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Hwy 15/Main St. Reconstruction Detour

7Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Construction and detours begin in 2020.

Preliminary detour route utilizes Highway 22 to the east, between Highway 7 and Airport Road (County Road 115).

Page 8: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Project Timeline

8Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 9: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Construction Process & Timeline

• Construction begins in Spring 2020

• Project will take an entire construction season, with final work occurring in 2021

• Construction will be from building face to building face

• All street, sidewalk & utilities will be replaced 

• Multiple excavations will be required 

• Work will be phased to limit time of disturbance 

• Close coordination with the Chamber of Commerce and others will be required 

• Consider improvements to alternate accesses

9Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 10: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

ADA Improvements (Americans with Disabilities Act) 

• Extensive survey, design and construction efforts are required 

• Close coordination with building owners will be required

Opportunity for owners to make improvements

Chamber of Commerce helping to facilitate 

10Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 11: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Building Inspections

• Project includes inspection of building basements in order to: 

Identify any potential structural concerns related to the construction 

Identify potential intrusions into the construction area (old coal chutes, window wells, vents, etc.) 

Identify sanitary sewer and water service locations and related issues/improvements 

• SEH and City staff to complete inspections in September 2017

Notifications and requests for access pending 

11Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 12: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Project Elements

• Landscaping items to be reviewed/discussed

• Will use “Imagine Hutchinson” document and wayfinding study as guides during project design

• Will coordinate efforts with local groups 

12Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 13: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Process / Next Steps 

• Public Involvement and Outreach 

• Open houses, public meetings and outreach 

• Project newsletters 

• Stakeholder meetings 

• Informal sessions at Chamber of Commerce 

• Design process 

• Preliminary design, traffic and environmental studies, outreach and other design efforts in 2017 

• Final, detailed design starting in 2018 

• Project letting proposed for November 2019 

13Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 14: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Questions?

14Thursday, August 24, 2017  | mndot.gov/d8/projects/hwy15downtownhutch

Page 15: Highway 15 Project –Hutchinson, MN · • The City of Hutchinson will also be replacing, updating, and modernizing underground utilities ...

Thank you!