HIGH VOLTAGE TOWER RELOCATION, KENSINGTON 10 APRIL 2018

Transcript of HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session,...

Page 1: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

HIGH VOLTAGE TOWER RELOCATION,

KENSINGTON

10 APRIL 2018

Page 2: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

AGENDA

1. Community issues and concerns

2. Overview of works

3. Communication about these works

4. Open discussion

Page 3: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

METRO TUNNEL PROJECT

Page 4: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

FUTURE RAIL PATRONAGE

• Population growth

• Inner city jobs

• Road congestion

• Parking costs

• Environmental

impacts

Page 5: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

RAIL NETWORK PINCH POINTS

RICHMOND

TRAINS QUEUE

FOR CITY LOOP

CITY LOOP

APPROACHING

CAPACITY

NORTH

MELBOURNE

TRAINS QUEUE

FOR CITY LOOP

PINCH POINTS ARE AFFECTING RAIL NETWORK OPERABILITY

Page 6: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,
Page 7: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

CAPACITY BENEFITS

Page 8: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

OVERVIEW OF HV TOWER WORKS

Page 9: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

BACKGROUND ON RELOCATION WORKS

Page 10: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

EXISTING HV TOWER ALIGNMENT

Page 11: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

STAGE 2- TEMPORARY ALIGNMENT

Page 12: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

STAGE 3- PERMANENT ALIGNMENT

Page 13: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

ALTERNATIVE LOCATIONS EXPLORED

B

Page 14: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

HV TOWER HEIGHTS – TOWER 33

• Temporary tower = 56.2m

• Permanent tower = 52m

• Existing tower = 43.3m

Page 15: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

COMMUNITY ENGAGEMENT

Page 16: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

COMMUNITY FEEDBACK

• Engagement and consultation underway in Kensington since

early 2015, including the Environment Effects Statement

planning process

• Feedback from Kensington residents has informed planning and

design for the western tunnel entrance:

o Significant reduction in private property acquisition

o Removal of rail bridge over Kensington Road

o Updated alignment for High Voltage transmission tower

location

o Significant reduction in impacts from service relocations

Page 17: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION SESSIONS

• September 2015: Community Information Session, Kensington Recreation Centre

• October 2015: Community Information Session, Kensington Recreation Centre

• June 2016: Two EES Information Sessions, Kensington Recreation Centre

• April 2017: Early Works Western Portal Community Information Session, Bill Vanina Pavilion

• September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street)

• October 2017: Two Pop-up Information Sessions, JJ Holland Park

• November 2017: Presentation to the Kensington Association

• December 2017: Pop-up Information Session, Kensington Recreation Centre

Page 18: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

metrotunnel.vic.gov.au - works overview information & latest notifications

Page 19: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

Fact sheets (April 2017)

Page 20: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

Letter and map (August 2017)

Page 21: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

Letter and map (August 2017)

Page 22: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

Works notifications

Page 23: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

INFORMATION CHANNELS

Works notifications

Page 24: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

KEEPING THE COMMUNITY INFORMED

• Dedicated MMRA and contractor engagement staff

• Community representation on Kensington and Arden

Community Reference Group

• One-on-one meetings with residents and businesses

• Regular works notifications

• Information sessions

• 24/7 Metro Tunnel Project Information Line 1800 105 105

Page 25: HIGH VOLTAGE TOWER RELOCATION, KENSINGTON€¦ · • September 2017: Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions,

QUESTIONS