HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

29
A Presentation on Practical Training taken at DURATION: 23/05/2016 to 23/07/2016 SUBMITTED BY : 1. TEJPRAKASH KUMAWAT Final Year B.Tech (Civil) SUBMITTED TO : DEPARTMENT OF CIVIL ENGG. DEPARTMENT OF CIVIL ENGINEERING GOVT ENGINEERING COLLEGE BANSWARA HIGH FLOOD LEVEL BRIDGE ACROSS MAHI RIVER

Transcript of HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Page 1: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

APresentation

onPractical Training

taken at

DURATION: 23/05/2016 to 23/07/2016

SUBMITTED BY : 1. TEJPRAKASH KUMAWAT

Final Year B.Tech (Civil)

SUBMITTED TO :DEPARTMENT OF CIVIL ENGG.

DEPARTMENT OF CIVIL ENGINEERINGGOVT ENGINEERING COLLEGE

BANSWARA

HIGH FLOOD LEVEL BRIDGE ACROSS

MAHI RIVER

Page 2: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Details Of The Project:Site location:- HFL Bridge across Mahi river, Pipalkhut , Pratapgarh

abutment type:- Conterfront Type.

Bearing:- POT/ PTEF Bearing.Girder:- Precast PSC Girder.Handrail:- Steel Hand rail with welded mesh.Reinforcement:– HYSD Bar ( 8 mm To 32 mm).About the project:- Construction of HFL bridge across Mahi river at Chain age 118+363 at pipalkhut on Pratapgarh padi road (National highway NH-113).

Construction Company:- Dilip Buildcon Ltd. , Bhopal

Project In charge:- Mr. P.K. Mishra

Project Engg.:- Mr. Ramesh Babu

Expect Cost:- Rs. 12 cr after dismantling.

Date of Initiate:- 26 –Apr-2014

Date of Completion:- 24-Oct- 2016

Bridge length- 360 m

span- 12 (12×30) m

 

Page 3: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

CONTENT1. EXCAVATION WORK FOR RAFT2. RAFT OF ABUTMENT AND PIER3. PIER4. PIER CAP5. ABUTMENT6. PEDESTAL7. PLACE FOR JACK8. GIRDER LAUNCHING9. SLAB

Page 4: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

EXCAVATION WORK FOR RAFT

• A RAFT FOUNDATION IS A TYPE OF FOUNDATION THAT SPREADS THE LOAD FROM A BUILDING OR STRUCTURE OVER A LARGE AREA.  

• RAFT FOUNDATIONS ARE ALSO USED TO REDUCE THE SETTLEMENT OF STRUCTURES LOCATED ABOVE HIGHLY COMPRESSIBLE DEPOSITS.

• RAFT ARE USUALLY AT SOME DEPTH IN THE GROUND ,A LARGE VOLUME OF EXCAVATION MAY BE REQUIRED.

Page 5: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: excavation work for foundation

Page 6: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

RAFT OF ABUTMENT AND PIER• LEVEL THE GROUND

• PCC OF M15 GRADE CONCRETE

• PLACE THE REINFORCEMENT AS PER DRAWING

• COVER =75MM.

• HEIGHT = 1.1 M

Page 7: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: Reinforcement details of raft

Page 8: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: Reinforcement cage

Page 9: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

PIER• MULTI-SPAN BRIDGES REQUIRE PIERS TO SUPPORT THE ENDS OF SPANS BETWEEN

ABUTMENTS• TRANSFER LOAD OF SLAB,GIRDER,PIERCAP TO RAFT

Fig: pier

Page 10: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: details: of pier

Page 11: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

PIERCAP

THE UPPER OR BEARING PART OF THE PIER, USUALLY MADE OF CONCRETE OR HARD STONE; DESIGNED TO DISTRIBUTE CONCENTRATED LOADS EVENLY OVER THE AREA OF PIER.

THE WIDTH OF PIER CAP DEPENDS UPON THE WIDTH OF CARRIAGEWAY, ITS SIZE DEPENDS UPON THE LIVE LOAD AND DEAD LOAD BRIDGE CAPACITY

GRADE OF CONCRETE M35

QUANTITY OF CONCRETE 35.567 M3

Page 12: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: piercap

Page 13: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

ABUTMENT

ABUTMENT CONSIST OF THREE PARTS

MAIN WALL

COUNTER FRONT WALL

RIDING RETAINING WALL

Page 14: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: abutment

Page 15: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

PEDESTAL

• USED TO TRANSFER LOAD FROM BEARING TO PIERCAP• GRADE OF CONCRETE USED M35

Fig: pedastel

Page 16: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

PLACE FOR JACK

• THE LOCATION OF JACK AND TEMPORARY BEARING FOR LIFTING OF THE SUPERSTRUCTURE TO REPLACE BEARING ETC. THIS IS SHOWN BY SYMBOL

• THE TWO LAYRS OF MESH REINFORCEMENT ONE AT 20 MM FROM TOP AND THE OTHER AT 100 MM FROM TOP OF PEDESTAL AND PIERCAP EACH CONSISTING OF 8 MM BARS AT 75 MM IN BOTH DIRECTIONS SHALL BE PROVIDED DIRECTLY UNDER THE BEARING/JACK AND TEMPORARY BEARING

+

Page 17: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig:detail of piercap

Page 18: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

LAUNCHING OF GIRDERS SITE PREPARATION

BASIC PLANNING

PLACING OF GIRDER ON EXCEL PULLER OF CAPACITY 125 T

TRANSPORT TO THE LOCATION

LIFTING THE GIRDER BY USING THE CRANE CAPACITY OF 250 T

FIXING THE POT/ PTEF BEARING IN GIRDER

PLACING OF GIRDER IN PROPER LOCATION WITH PROPER SAFETY & SUPPOR

Page 19: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE
Page 20: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE
Page 21: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

FIXING THE POT/ PTEF BEARING IN GIRDER

Page 22: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE
Page 23: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

METHODOLOGY OF CAST IN SITU SLAB1. Reinforcement & Concreting of End & Middle

Diaphram2. Fixing of shuttering3. Placing reinforcement as per drawing &

specification4. Pouring of concrete M40 as per approved mixed

design

Page 24: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Reinforcement & Concreting of End & Middle Diaphram

Page 25: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

FIXING OF SHUTTERING

Fig: shuttering

Page 26: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

PLACING REINFORCEMENT AS PER DRAWING & SPECIFICATION

Page 27: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

POURING OF CONCRETE M40 AS PER APPROVED MIXED DESIGN

Fig: pouring of concrete by boom presure

Page 28: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

Fig: boom pressure

Page 29: HIGH FLOOD LEVEL BRIDGE ,TRAINING PPT, dilip buildicon ltd.,NH113 , MAHI BRIDGE

THANK YOU