HH-36DB - Electrical Power Resiliency, Utility and Building Improvements at the HHB
![Page 2: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/2.jpg)
HH-36DB Scope of Work
▪ Upgrade Dyckman Substation capacity from 225KVA to 750 KVA.
▪ In kind replacement of Kappock Substation, and installation of new HVAC unit for the electrical room.
▪ Install new fire suppression and alarm systems for Dyckman and KappockSubstations.
▪Complete unfinished work from HH-88B
Second Floor Air Handler Unit Replacement
Substation Replacement Maintenance Garage Build Out
▪ Install new Air Handler Unit into the modified Mechanical Room’s
available limited space.
▪Resurface 1,500 LF of existing park path
Park Path
![Page 3: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/3.jpg)
HH-36 DB schedule – Contract duration 36 months
Design Build Contract Award – December 2021
Design Build Contract Completion – December 2024
![Page 4: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/4.jpg)
HH-36 DB Lane Closure hours
HHB North Bound Parkway – 7am to 3pm
HHB South Bound Parkway – 10am to 3pm
![Page 5: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/5.jpg)
Existing Dyck. St. Substation within the North Abutment:
![Page 6: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/6.jpg)
New Dyck. St. Location:
* New substation enclosure to be constructed on the new parcel TBTA acquired from NYC DPR. Construction shall not impact the existing structure
![Page 7: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/7.jpg)
Dyckman Street Electrical Upgrade SOW: Build a new Substation Enclosure (minimum 25’-10”W X 15’ L)and Upgrade Substation Capacity. Work include but not limited to coordination with Con Edison, identification of underground utilities, installation of underground feeders, manholes and duct banks, new heating ventilation and air conditioning system new fire alarm and detection system and demolition of the existing substation.
![Page 8: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/8.jpg)
Location of the existing Con Ed Manhole at Dyckman Street
![Page 9: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/9.jpg)
Photos of existing substation within the abutment
![Page 10: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/10.jpg)
Kappock Electrical Upgrade SOW: Replace existing Substation transformer and
all associated equipment, equipment pad, resurface concrete floor,
mechanical and heating system and Fire detection and alarm system.
![Page 11: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/11.jpg)
Access to Kappock Substation
![Page 12: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/12.jpg)
Existing Kappock Substation photos
![Page 13: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/13.jpg)
Maintenance Garage HHB SOW- The maintenance Garage shell
was completed under HH-88B project. The Garage and basement
Interior shall be completed to comply with the latest NYS Building
and NYS Energy Codes
![Page 14: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/14.jpg)
Existing Garage Photos – First Floor - SOW includes but not limited to:
Slab on Grade, insulation, interior walls and doors, wall and floor finishing,
lighting, electrical, mechanical, electric heating system, plumbing systems, fire
suppression & alarm systems, security systems, interior drainage
![Page 15: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/15.jpg)
Existing Garage Photos – Basement – SOW includes but not limited to:
Slab on Grade, insulation, interior walls and doors,
wall and floor finishing, lighting, electrical,
mechanical, electric heating system, plumbing
systems, fire suppression & alarm systems, security systems, interior drainage, paving and fence.
![Page 16: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/16.jpg)
Maintenance Garage First Floor Plan
![Page 17: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/17.jpg)
Maintenance Garage Floor Plan
![Page 18: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/18.jpg)
Maintenance Garage First Floor Lighting Plan
![Page 19: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/19.jpg)
Work to be done in the parking Lot: SOW includes but not limited to: Clean &
reline Sewage Holding Tanks, Installation of new sanitary manholes, Installation of
new 550 Gallon Oil Water Separator
![Page 20: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/20.jpg)
Work to be done in the parking Lot – Existing Photo of the Parking Lot
![Page 21: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/21.jpg)
Second Floor Air Handler Unit SOW - Design, procure and install all equipment to
replace the existing air handler unit. Restoration of the mechanical room to an
outdoor space to meet energy conservation and building code.
![Page 22: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/22.jpg)
Second Floor Air Handler Unit – SOW includes but not limited to: removal of the existing unit, restoration of the building envelope, removal of the temporary wall, insulation of the existing wall, replacement of 2nd floor interior doors and installation of the new unit.
Second Floor Outdoor Space
![Page 23: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/23.jpg)
Second Floor Air Handler Unit
Second Floor interior corridor
Existing Unit on the second
floor
![Page 24: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/24.jpg)
1,500 LF of Park path Resurfacing per NYCDPR details: SOW includes but not
limited to coordination with NYCDPR for forestry and construction permits, path
closure schedule, restrictions and detour signs & schedule restrictions. The
equipment access to the Path location is limited. A DPR approved arborist shall
be present for the duration of this work.
![Page 25: HH-36DB Electrical Power Resiliency, Utility and Building ...](https://reader030.fdocuments.in/reader030/viewer/2022012605/619a3aae9824d1603911ec51/html5/thumbnails/25.jpg)
Park
Path Photos