Herschel / HIFI. Status mirrors FM/FS Status COA QM Status COA FM Financial situation COA FM Status MSA FM/FS. Status mirrors FM/FS. Request for a quote sent out to TNO/LFM2003-08-13 Quotation available at ETH2003-09-01 Purchase order sent out to TNO2003-09-03 - PowerPoint PPT Presentation

Transcript of Herschel / HIFI

  • Herschel / HIFIStatus mirrors FM/FSStatus COA QMStatus COA FMFinancial situation COA FMStatus MSA FM/FS

  • Status mirrors FM/FS Request for a quote sent out to TNO/LFM2003-08-13Quotation available at ETH2003-09-01Purchase order sent out to TNO2003-09-03Circulation of purchase order in Holland2003-09-10Expected delivery of 1st batch (42 mirrors)2003-11-01Expected delivery of 2nd batch (22 mirrors)2003-12-01Expected delivery of 3rd batch (22 mirrors)2004-01-15

    Further requests, quotations, purchase ordersis an ongoing process between SRON, LFM,TPD/TNO and ETH

  • Status COA QMRelease for riveting 2003-05-18Delivery rivet samples to SRON Stork FDO2003-06-30Conclusions from rivet samples by SRON2003-08-13Updated riveting procedures HTS/RUAG2003-08-21Delivery of single parts for riveting2003-09-15Start riveting process at RUAG aerospace2003-09-24Riveting completed ~2003-10-06Delivery review foreseen ~2003-10-07

  • Status COA FMKick off COA FM phase C/D2003-07-10Full set of drawings available at HTS2003-07-22Starting date at HTS Wallisellen2003-08-04Review MAIP2003-08-18Manufacturing release2003-09-16Latest documents delivered to HTS2003-09-26Manufacturing assembly review2003-12-15

    Delivery review COA + Container2004-02-05

  • Financial situation COA FM1st estimation from experience in phase B495,0 KEuroNew estimation during man. in phase B445,0 KEuroQuotation explicitly given by HTS430,5 KEuroAgreed Firm Fix price by ESA350,0 KEuro

    Available budget from PRODEX325,0 KEuro

    Missing amount of money to pay for 25,0 KEuro

  • Status MSA FM/FSNegotiation meeting at HTS2003-07-10Starting date 2003-07-28Review MAIP2003-09-16Manufacturing AR2003-12-15Delivery review2004-02-05

    Permanent delivery of MSA parts to SRON foreseen according to priority list

  • Financial situation MSA FMQuotation given by HTS542,2 KEuroAgreed Firm Fix price by ESA542,2 KEuro

    Available budget from PRODEX666,0 KEuro

    Left over to cover FM COA (25 KEuro), ECR (~30 KEuro) + unforeseen expenses123,8 KEuro