Herriman City Municipal Water PowerPoint Presentation March 10, 2011.
Herriman City Municipal Water
description
Transcript of Herriman City Municipal Water
Herriman City Municipal Water
PowerPoint PresentationMarch 10, 2011
System Maintenance Service of Booster
Pumps & Wells
Fire Hydrant Flushing
Valve Exercising
Tank Cleaning
Service Of Booster Pumps & Wells
• Shut Down Power/Lockout-Tagout
• Disassemble Pump
• Clean All Parts
• Replace All Bearings, Packings & Seals
• Repair Or Replace Other Parts As Needed
• Reassemble Pump
• Realign Pump
• Lubricate With Ultra Sound Equipment
• Test & Bring Back On Line
Pump Shaft Alignment Ultra Sound Equipment
Fire Hydrant Flushing &
Valve Exercising
• Annually We Flush & Inspect All Fire Hydrants & Dead Ends With The Assistance Of Unified Fire
• Fully Close & Reopen Each Valve In Our Water System
Tank Cleaning
• Clean, Inspect & Video Every 3-5 Years
Why?•This Provides Us With Visual
Conditions Of The Inside Of Our Tanks
•This Allows Us To Clean The Tanks Without Taking Them Off-Line.
• All Our Water Tanks Were Cleaned In November 2010
Projects
•Well 1 Booster Station
•Chlorine & Fluoride Analyzer
•5600 W Culinary & Secondary Water Lines
•Early Stages of Implementation Of Secondary Water System
•Mountain View Corridor Betterments
Well 1
Booster
Pump
Station
Completed
Chlorine & Fluoride Analyzer
• Installed At Well 1, HP Tanks & The RoseCrest Booster Pump Station
•Provides Trending Of Fluoride & Chlorine Levels
•Connected To The SCADA System Which Allows Off Site Tracking & Control Of Chemical Levels.
•Analyzers Provide Additional Safety To The Water System & Our Residents
Silver Spur Construction Won Bid Project Will Begin March 16, 2011
This Project Has A Completion Time Of 90 Days
Secondary Water System
Secondary Water Rate Study-Bowen Collins
Project Will Go Out To Bid Early Summer
Purple Shaded Area Will Be First Area To Receive Secondary Water
Mountain View Corridor March 2011
There Is A 32” Culinary & 10” Secondary HDPE Pipe
The Betterments Are Approximately 50%
Completed Trench is 32’
? ? ? ? ?Questions