HELMSLEY COUNTRY ESTATE RESIDENTIAL DEVELOPMENT … · 2019. 1. 9. · Section C3.1 Sanitation...
Transcript of HELMSLEY COUNTRY ESTATE RESIDENTIAL DEVELOPMENT … · 2019. 1. 9. · Section C3.1 Sanitation...
-
f:\bigen-data\admin\0938\ped report cover vol 1.docx
THE HELMSLEY DEVELOPMENT COMPANY
PRELIMINARY ENGINEERING DESIGN REPORT FOR
HELMSLEY COUNTRY ESTATE RESIDENTIAL DEVELOPMENT
VOLUME 1
MAY 2018
Compiled for:
The Helmsley Development Company
Saxe Farm,
Umhlali, 4390
P O Box 263
Umhlali, 4390
Tel: (032) 942 2066
Attention: Mr S Hulett
Compiled by:
BIGEN AFRICA Services (Pty) Ltd
Block B, Bellevue Campus
5 Bellevue Road, Kloof, 3610
PO Box 1469
KLOOF, 3640
Tel: +27(0)31 717 2571
Fax: +27(0)31 717 2572
e-mail: [email protected]
Enquiries: Mr B. Oosthuizen
mailto:[email protected]
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - i -
THE DEVELOPMENT COMPANY
HELMSLEY COUNTRY ESTATE – RESIDENTIAL DEVELOPMENT
INTERNAL ENGINEERING SERVICES:
PRELIMINARY DESIGN REPORT
CONTENTS LIST
PRELIMINARY ENGINEERING DESIGN REPORT
Executive summary
Contents list
Part A General Matters
Section A1 Project brief and project team
Section A2 Terms of Reference
Section A3 Assessment Information Basis
Section A4 Project Details
Section A5 Other Reports and Assessment Information
Part B Natural Environment
Section B1 Geographical Location and Topography
Section B2 Geological and geotechnical aspects
Section B2.1 Site Geology
Section B2.2 Landform
Section B2.3 Slope Stability
Section B2.4 Founding
Section B2.5 Groundwater Conditions
Section B2.6 Excavatability/Trenchability
Section B2.7 Sub-soil Drainage
Section B2.8 Stormwater Management
Section B2.9 Pavement Sub-grade characteristics
Section B2.10 Conclusions
Section B3 Environmental and cultural/historical issues
Section B3.1 Environmental
Section B3.2 Cultural/Historical
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - ii -
Part C Layout and planning
Section C1 Development Profile and Planning Issues
Section C1.1 Development Boundary
Section C1.2 Planning Approval
Section C1.3 Spatial Impact
Section C1.4 Topography
Section C1.5 Existing Land Uses
Section C1.6 Provincial Roads
Section C1.7 Geological Stability
Section C1.8 Land Use Requirements
Section C2 Bulk and link services
Section C2.1 Institutional Arrangements
Section C2.2 Bulk Water
Section C2.3 Bulk Sanitation
Section C2.4 Bulk Roads
Section C2.5 Stormwater Drainage
Section C2.6 Bulk Electricity
Section C2.7 Telecommunications
Section C2.9 Waste Removal
Section C3 Internal engineering services
Section C3.1 Sanitation scheme
Section C3.2 Water supply scheme
Section C3.3 Road Infrastructure
Section C3.4 Stormwater Infrastructure
Section C3.5 Electricity & Street Lighting
Section C3.6 Telecommunications
Section C3.7 Solid Waste Removal/Collection
Section C3.8 Maintenance
Part D Conclusions and Recommendations
Section D1 Phasing of Implementation
Section D2 Conclusion
Section D3 Bulk Water Supply
Section D4 Bulk Sewage Treatment Facility
Section D5 Bulk Electrical Supply
Section D6 Bulk Telecommunications Supply
Section D7 Internal Services
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - iii -
Part E Programme and Financing
Section E1 Programme
Section E2 Capital Costs
Part F Appendices
Annexure F1 Locality Maps
Annexure F1.1 Regional Context
Annexure F1.2 Local Context
Annexure F1.3 Project Context
Annexure F2 Development Diagrams
Annexure F3 Geotechnical Site Plan
Annexure F3-1 Geotechnical Zonation Plan
Annexure F3-2 Hydrological Wetland
Annexure F4 Slope Analysis
Annexure F5 Land Use Plan
Annexure F6 Electrical Supply
Annexure F7 Water Reticulation Analysis
Annexure F8 Cost Schedules
Annexure F9 Project Programme
Annexure F10 Project Cash Flow
Part G Report Drawings (Please refer to Volume 2)
Part G1 Roads
0938.00.ZA.03A001 Road Servitude Layout
0938.00.ZA.03A002 Access Road Watercourse Crossing
0938.00.ZA.03D001 Typical Services Servitude Details
0938.00.ZA.03D002 Typical Pavement Design Details
0938.00.ZA.03D004 Position of Support Brackets & Installation details of Road
Signs
0938.00.ZA.03D005 Road Marking Details
0938.00.ZA.03D006 Road Signage Schedule
0938.00.ZA.03S001 Road Layout Keyplan
0938.00.ZA.03U001 Road Layout Detail & Setting out Data – Sheet 1 of 3
0938.00.ZA.03U002 Road Layout Detail & Setting out Data – Sheet 2 of 3
0938.00.ZA.03U003 Road Layout Detail & Setting out Data – Sheet 3 of 3
0938.00.ZA.03S002 Road Markings and Road Sign Layout Keyplan
0938.00.ZA.03U004 Road Markings & Road Sign Layout – Sheet 1 of 3
0938.00.ZA.03U005 Road Markings & Road Sign Layout – Sheet 1 of 3
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - iv -
0938.00.ZA.03U006 Road Markings & Road Sign Layout – Sheet 1 of 3
0938.00.ZA.03L001 Road Long Section Road 1 CH 0.000 – CH 560.000
0938.00.ZA.03L002 Road Long Section Road 1 CH 54.000 – CH 1100.000
0938.00.ZA.03L003 Road Long Section Road 1 CH 1080.000 – CH 1236.107
Road 2 CH 0.000 – CH 197.475
0938.00.ZA.03L004 Road Long Section Road 3 CH 0.000 – CH 560.000
0938.00.ZA.03L005 Road Long Section Road 3 CH 540.000 – CH 722.931
Road 4 CH 0.000 – CH 183.654
Part G2 Stormwater
0938.00.AA.04A001 1:100 Year Floodline
0938.00.AA.04A002 Orthophoto indicating perennial/non-perennial streams/
rivers
0938.00.AA.04A003 Topographic map indicating perennial/non-perennial
streams/rivers
0938.00.AA.04A006 Stormwater Master Plan
0938.00.ZA.04D001 Typical Kerb Inlet Details
0938.00.ZA.04D002 Manhole & Surface Stormwater Collection manhole Details
0938.00.ZA.04D003 Typical Kerbing Details
0938.00.ZA.04D004 Pipe Bedding Details: Rigid Pipes Class A, B, C and D
0938.00.ZA.04D005 Underdrain Details for Stormwater Trenches
0938.00.ZA.04D006 Wingwall Brickwork Details
0938.00.ZA.04D007 Low level river crossing, cover slab with guide block
Part G3 Water Supply
0938.00.ZA.05S001 Water Reticulation Layout Keyplan
0938.00.ZA.05U001 Water Reticulation Layout – Sheet 1 of 3
0938.00.ZA.05U002 Water Reticulation Layout – Sheet 2 of 3
0938.00.ZA.05U003 Water Reticulation Layout – Sheet 3 of 3
0938.00.ZA.05D001 Pipe Bedding Details: Rigid Pipes Class A, B, C and D
0938.00.ZA.05D002 Typical Excavation & Backfill Details for Water Pressure
Pipes
0938.00.ZA.05D003 Typical Excavation and Backfill Details for Rigid Water
Pressure Pipes (Trough Road Pavement)
0938.00.ZA.05D004 Typical Underdrain Details for Water Trenches
0938.00.ZA.05D005 Detail of Backfilling prior to the testing of Pipes
0938.00.ZA.05D006 Concrete Encasement of Pressure Pipes (uPVC)
0938.00.ZA.05D007 Thrust Block Details and Graph
0938.00.ZA.05D008 Water Pipeline Markers (Option 1)
0938.00.ZA.05D009 Water Pipeline Markers Type 1 and Type 2
0938.00.ZA.05D010 Typical Pillar Fire Hydrant
0938.00.ZA.05D011 Typical Double Headed Pump Booster Connection
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - v -
0938.00.ZA.05D012 Typical Chamber for Hydrant Suction Valve
0938.00.ZA.05D013 Typical Valve Chamber for pipes 50Ø>D 2150 (Concrete Cover)
0938.00.ZA.06D010 Manhole when D > 2150 (Concrete Cover)
0938.00.ZA.06D011 Section: Drop Manhole – When IL 1– IL 2 < 840mm
0938.00.ZA.06D012 Section: Drop Manhole – When IL 1– IL 2 > 840mm
0938.00.ZA.06D013 General Precast Base Details
0938.00.ZA.06D015 Typical Cast-Iron Sewer Rodding Eye
0938.00.ZA.06D016 House Connection (uPVC) D < 1200
0938.00.ZA.06D017 House Connection (uPVC) 1200 < D < 2000
0938.00.ZA.06D018 House Connection (uPVC) D > 2000: Plan
0938.00.ZA.06D019 House Connection (uPVC) D > 2000: Section
0938.00.ZA.06D020 Anchor Blocks for Steep Slope Sewers
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Contents List
F:\Bigen-Data\Admin\0938\PED Report Contents.docx - vi -
0938.00.ZA.06D021 Sewer Connection Marker Block Details
0938.00.ZA.06D022 Concrete Encasement of uPVC Sewer Pipes &
Reinforced Concrete Encasement of uPVC Sewer Pipes
Part G5 Electrical
0938.00.ZA.07A001 Electrical Bulk Suppl
0938.00.ZA.07A002 Internal Electrical Supply
Part G6 Fencing
0938.00.ZA.17U001 Proposed Fencing Layout
Part H Bulk Water and Sanitation (Please refer to Volume 2)
Annexure H1 Regional Bulk Water Supply
Annexure H2 Geotechnical Reports 1 & 2
Annexure H3 Water and Sanitation Flow Diagram and Layouts
Annexure H4 Pumphouse and Pumpstation Pipe Configuration
Annexure H5 Water Treatment Works Layout
Annexure H6 Water Treatment Works Process
Annexure H7 Low Lift Pumpstation and Chemical Storage
Annexure H8 WWTW Site and Bulk Gravity Sewer Layout Plan
Annexure H9 WWTW Flow Diagram
Annexure H10 Final Effluent End Structure Wingwall
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Executive Summary
F:\Bigen-Data\Admin\0938\PED Report Executive Summary.docx 1
THE HELMSLEY DEVELOPMENT COMPANY
HELMSLEY COUNTRY ESTATE – RESIDENTIAL
INTERNAL ENGINEERING SERVICES:
PRELIMINARY DESIGN REPORT
Executive Summary
Background and Locality of Project
The Client of The Helmsley Development Company, also acting as the Developer of the proposed
project, has appointed Bigen Africa Services (Pty) Ltd to undertake the design and construction
monitoring of the bulk and internal engineering services for the Helmsley Country Estate development.
The proposed 21,0801ha residential housing estate will deliver some 125 housing opportunities, of
which 32 will be full title individual special residential type I stands and 93 sectional title units on 5
medium density residential type II and III stands.
The property is situated on Portion 177 (of 161) of the Farm Compensation No. 868, Registration
Division PU, located along the north coast of KwaZulu-Natal, in the vicinity of Compensation. The site
is located directly adjacent to road D176 which traverses through the north eastern section of the site
and then runs in a north westerly direction at a distance that varies between 50m to 200m from the
north eastern boundary of the original farm. The Helmsley farm is located approximately 6,2km north
west of Ballito and the N2 north highway which forms the main development corridor between Durban
and Richards Bay running approximately 2km west of Ballito.
Geotechnical Investigation
From the basis of the hydromorphic wetland mapping and a preliminary geotechnical assessment, the
following are the key developmental considerations and findings:
● Stable and satisfactory for development which is considered feasible subject to the adoption of
suitable development controls to engineer’s details;
● Development along any slopes steeper than 1 vertical: 3 horizontal (> 18°) and any 1:100 year
floodline is not recommended;
● Hydromorphic wetland areas have been mapped along the south-eastern valley of the site. A
provisionally 20 metre wide environmental setback indicated around the “temporary” wetland area
should be verified by the Department of Agriculture and Environmental Affairs in consultation with
Ezemvelo KZN Wildlife;
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Executive Summary
F:\Bigen-Data\Admin\0938\PED Report Executive Summary.docx 2
● Soakpits should not be employed for the disposal of either stormwater or sewage;
● A mini sewage package plant or communal conservancy tanks should be planned;
● Guidelines are given on appropriate founding solutions which will require further investigation and
engineers design;
● Effective stormwater management will minimise maintenance of the slopes.
It is considered that the design of the civil engineering infrastructure and foundations should be based
on a detailed geotechnical subsurface site investigation.
Archeological Assessment
A preliminary archaeological assessment was undertaken by eThembeni Cultural Heritage in
September 2005 to report on the proposed development site. Two heritage resources of significance
were identified. The first of which (Site A, being a Late Iron Age hilltop settlement) would require further
assessment to determine its significane. The second (Site B) being an ancestral grave, would require
protection from disturbance of any sort or a permit from Amafa. It is however, to be noted that the
eThembeni Report to Amafa aKwaZulu Natali indicates that further survey is required once the cane is
harvested.
Conclusions and Recommendations
Based on the various investigations that were conducted on the proposed development site, we
conclude the following :
- The construction of civil and electrical infrastructure to service the proposed layout planning is
feasible. However, the costs are significantly higher than the average. This is largely attributed to
the relatively small size of the development and the required bulk and link services complement;
- Access to the higher order road infrastructure network is possible;
- There are no adverse geotechnical conditions that would prohibit the proposed development;
- There are no municipal bulk and link water and sanitation services currently available in the area;
- The provision of bulk electrical infrastructure depends on close co-operation with the KwaDukuza
Local Municipality and other developers, or development initiatives, in the area;
- Nevertheless, notwithstanding the abovenoted challenges, the proposed development can in the
interim, almost be entirely self sufficient within the various bulk water services options recommended
and investigated for implementation.
In terms of which, it is hereby recommended that the following servicing options be adopted for the
development of the proposed Helmsley Country Estate.
The operation and maintenance of the internal roads network, bulk sewage treatment, internal
sewerage reticulation, bulk water supply and internal water reticulation within the proposed residential
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Executive Summary
F:\Bigen-Data\Admin\0938\PED Report Executive Summary.docx 3
housing estate will be the responsibility of the Home Owners Association/Body Corporate, unless
otherwise agreed to with the relevant services authority in terms of the Service Level Agreements (SLA)
that have been entered into between the respective parties.
The electrical reticulation is the only municipal service and will be operated and maintained by the
KwaDukuza Local Municipality.
Summary of Estimate of Costs
Total Project Costs
* Internal Infrastructure
* Bulk Infrastructure
* Professional Fees
R
R
R
27 674 494,29
45 786 857,42
5 866 960.80
* Total Infrastructure R 79 328 312.51
Costs per Unit
* Housing Estate (125 units)
R
634 626.50
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part A: General Matters
F:\Bigen-Data\Admin\0938\PED Report Part A.docx A - 1
THE HELMSLEY DEVELOPMENT COMPANY
HELMSLEY COUNTRY ESTATE – RESIDENTIAL DEVELOPMENT
INTERNAL ENGINEERING SERVICES:
PRELIMINARY DESIGN REPORT
Part A General Matters
Section A1 Project Brief and Project Team
The Client, The Helmsley Development Company, also acting as the developer, has
appointed Bigen Africa Services (Pty) Ltd to undertake the design and construction
monitoring of the bulk and internal engineering services for the Helmsley Country
Estate development. This portion of the now proclaimed residential property has been
subdivided from the surrounding John Albert Trust farmland and has been earmarked
as a stand alone Country Estate development that is surrounded by a Macadamia Nut
Production Farm.
The proposed residential housing estate will deliver some 125 housing opportunities,
of which 32 will be full title individual special residential type I stands and 93 sectional
title units on 5 medium density residential type II and III stands.
The property is situated on the north coast of KwaZulu-Natal, in the vicinity of
Compensation. The site is located directly adjacent to road D176 which traverses
through the north eastern section of the site and then runs in a north westerly direction
at a distance that varies between 50m to 200m from the north eastern boundary of
the original farm. The Helmsley farm is located approximately 6,2km north west of
Ballito and the N2 north highway which forms the main development corridor between
Durban and Richards Bay running approximately 2km west of Ballito.
Bigen was originally requested to investigate and report on any formal planning that
was underway for the maintenance and upgrading of the existing bulk and link
infrastructure and/or the provision of any new bulk or link services that may influence
the proposed development area, either by other developers or by one of the municipal
authorities having jurisdictional authority over this area, namely the ilembe District
Municipality and/or the KwaDukuza Local Municipality.
From the various investigations and studies that have been conducted in the area, it
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part A: General Matters
F:\Bigen-Data\Admin\0938\PED Report Part A.docx A - 2
has been concluded that there are no existing or planned new bulk infrastructure
available in the area in the short to medium term.
Further, all the internal and link civil and electrical infrastructure shall have to be
provided by the Developer as part of the proposed development application, at the
prescribed levels of service recorded in this report, as well as the Service Level
Agreements (SLA’s) entered into by the Developer with the respective Services
Authorities having powers and sanction over the development area.
Property Information:
From the subdivisional diagrams for the Helmsley Country Estate - Portion 177 (of
161) of the farm Compensation no. 868, Registration Division FU, Province of
KwaZulu-Natal, comprises of approximately 21,0801ha of the original 189,0027ha
John Albert Trust farm.
Section A2 Terms of Reference
Bigen Africa Services (Pty) Ltd have been appointed to design and monitor all the
consulting engineering services in respect of delivering the civil and electrical
infrastructure for the proposed development. The infrastructure includes water
supply, electricity supply, sewage disposal, streets and stormwater drainage facilities.
The following stand alone and/or separate reports and services agreements have
been compiled by Bigen Africa Services (Pty) Ltd and/or their specialist Services
Providers, and should be read in conjunction with this PED report :
▪ Traffic Impact Assessment – dated August 2007 and revised in October 2008
▪ Determination of 1 : 100 year floodlines (tributaries of the Wewe River) – dated
August 2007 and revised in October 2008
▪ Geophysical Investigation and Borehole Siting Report – dated 30 August 2007,
Ref. No. 2007/155 (Geomeasure Group)
▪ Final Geohydrological Report on the Drilling Pump Testing Water Quality
Analysis and Preliminary Reserve Determination for the proposed Helmsley
Housing Development, dated 3 March 2008, Ref. No. 2007/155 (Geomeasure
Group)
▪ KwaDukuza Local Municipality Services Agreement (Roads, Stormwater and
Electricity Services) and Addendum HG1 dated 15 August 2008 and
13 February 2018 respectively.
▪ iLembe District Municipality Services Agreement (Water and Sanitation Services)
dated 10 April 2017.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part A: General Matters
F:\Bigen-Data\Admin\0938\PED Report Part A.docx A - 3
Section A3 Assessment Information Basis
Various discussions were held with the following services authorities over an
extended period of time in order to obtain information regarding the availability and
status quo of the existing bulk and link infrastructure, as well as any formal planning
underway in respect of the various services in the vicinity of the proposed
development area:
▪ Water : Ilembe District Municipality and Sembcorp Siza Water
▪ Sanitation : Ilembe District Municipality and Sembcorp Siza Water
▪ Roads (Provincial) : Department of Transport – KZN
▪ Roads (Local) : KwaDukuza Municipality
▪ Electricity : KwaDukuza Municipality and Eskom
▪ Stormwater Control : KwaDukuza Municipality
▪ Telecommunications: Telkom, Vodacom, MTN, Cell C & Virgin Mobile
▪ Solid Waste : KwaDukuza Municipality
The assessment of, as well as the comments received from the various services
authorities in respect of each service is contained in sections Part C of this report.
Section A4 Project Details
Project Funder : The Helmsley Development Company
Project applicant : The Helmsley Development Company
District Municipality : Ilembe District Municipality DC 29
Local Municipality : KwaDukuza Municipality KZN292
Project Manager : Lead Associates (Pty) Ltd (LA)
Civil Engineer : Bigen Africa Services (Pty) Ltd (BAS)
Electrical Engineer : Ibuya Consulting Engineers (Pty) Ltd (BAS)
Geotechnical Engineer : Groundwork Geotechnical Solutions cc (GGS)
Ground Water Consultant : Geomeasure Group (GG)
Town Planner : Helena Jacobs PSF (HJ) – original layout
Stott, Milton & Conway (SMC) – PUD layouts
Environmentalist : Sustainable Development Projects cc (SDP)
Land Surveyor : Stott, Milton & Conway Professional Land
Surveyors
The project name is : Helmsley Country Estate Residential Housing
Development
Number of Residential Units : 125 units
Project location within municipal
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part A: General Matters
F:\Bigen-Data\Admin\0938\PED Report Part A.docx A - 4
Ward : 4
Project area : 21,0801ha of the original 189,0027ha John Albert
Trust farm area
Section A5 Other Reports and Assessment Information
▪ Environmental Scoping Report – dated January 2006, Ref. No. EIA6241 (SDP)
▪ Preliminary Ecological Appraisal on the Establishment of a Macadamia Plantation
and Residential Development at Helmsley Farm – dated December 2005 (SDP)
▪ A Hydromorphic Delineation of Wetland areas and a Preliminary Assessment of
anticipated Geotechnical Conditions – dated October 2005, Ref. No. GS 59/05
(GGS)
▪ Preliminary Engineering Report – dated 6 December 2005 (SMW KwaDukuza
Consultants cc)
▪ Heritage Impact Assessment – dated 12 September 2005 (eThembezi Cultural
Heritage).
▪ Layout Plan – Ref. No. Helmsley 01 – 06 un-dated (HJ) October 2007.
▪ PUD’s Layout Plan – Ref. No. D17/R. Conway Dwg No. Full-LP3.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 1
THE HELMSLEY DEVELOPMENT COMPANY
HELMSLEY COUNTRY ESTATE – RESIDENTIAL DEVELOPMENT
INTERNAL ENGINEERING SERVICES:
PRELIMINARY DESIGN REPORT
Part B Natural Environment
Various specialist service providers, as noted in Section A4 have been appointed as
part of the professional team for the project in order to conduct the required studies
and surveys in respect of the natural environment for the proposed project area, which
includes the following:
Civil and Electrical Consultants;
Geotechnical Consultants;
Environmental Consultants;
Town and Regional Planners; and
Topographical and Land Surveyors.
Section B1 Geographical Location and Topography
The project area is located approximately 45km north-east of the Durban City Centre
(CBD) within ward 4 of the KwaDukuza Local Municipality. This, in turn, falls within
the ilembe District Municipality’s area of jurisdiction that stretches along the eastern
sea board on the north coast of KwaZulu-Natal and is bordered by the eThekwini
Metro to the south, Ndwedwe and Maphumulo Municipalities to the west, and the
Mandeni Municipality towards the north. The most prominent development centres in
close proximity to the site include the towns of Ballito approximately 10km towards
the south east, uMhlali and Stanger approximately 6km and 20km towards the north
east and Tongaat approximately 12km towards the south west of Helmsley
respectively. Please refer to the locality maps included in Annexure F1.
Further, the geographical location of the respective land parcels that make up the
proposed development area (project footprint) has been co-ordinated as a sngle point
of reference at the properties approximate centroid (refer to Table 1 below).
Furthermore, the properties consolidation, subdivisional diagrams and SG plans have
been obtained from the appointed land surveyor for this project and included in
Annexure F2.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 2
Table 1: Geographical Location of PTN 161 of the farm Compensation No. 868
Land Parcel Name Municipal
Ward
Land Parcel
No.
Latitude Longitude
PTN 161 of the farm
Compensation No. 868
4 161 29°28’48” S 31°09’36” E
The project is located between approximate latitude 29°28’12” and 29°29’24” south and
longitude 31°09’00” and 31°10’12” east
The site generally slopes from the north-west towards the south-east. Drainage from
the elevated hillock on which the development has been located is governed by three
(3) non-perennial streams within the valley lines that drain towards the south eastern
corner of the farm where they converge into a single stream/tributary that eventually
joins up and flows into the Wewe river approximately 3km south of the project area.
A characteristic of the township layout is the elevated views over the Compensation
flats, and the feeling of ample wide open space that has been created by locating the
majority of the residential erven along the ridgeline of the farms isolated hillock.
Section B2 Geological and Geotechnical Aspects
A geological assessment was undertaken by Groundwork Geotechnical Solutions in
October 2005 which has been briefly summarised below. For a more detailed
overview in this regard, kindly refer to the specific report titled “A Hydromorphic
Delineation of Wetland areas and a Preliminary Assessment of anticipated
Geotechnical Conditions – dated October 2005, Ref. No. GS 59/05 (GGS)”.
Section B2.1 Site Geology
Due to the variable geology of the project area, the site has been divided into three
geotechnical zones. The typical nature of each of the geotechnical zones are
summarised below. The Geotechnical Site Plan, Ref. No. GS/84/05, Fig. No. G
attached as Annexure F3, illustrates the inferred extent of these geotechnical zones.
5.2.1 Alluvium
“Which is formed as organic soils along the bottom of the valley terrain”.
Alluvial sandy and silty clays are present typically along the outer edges and
central portions of the valley bottoms.
Seasonal and permanent standing water conditions are anticipated, resulting
in an organic-rich compressible soil.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 3
5.2.2 Berea Formation (Q6)
“Presented as limited unconsolidated Aeolian (windblown) sandy to clayey
deposits along the elevated northern and north-western slopes”.
Former dune/Aeolian (windblown) deposits of the Berea Formation were
mapped and recorded along the uppermost northern and north-western
slopes.
From experience with similar soils on other sites, the above soils are known
to be favourably permeable, highly erodible and prone to collapse settlement
under loading when wet. The soils can also become unstable within steep
excavations eg. platform embankments.
5.2.3 Vryheid Formation (Pv)
“Comprising sandstone and siltstone bedrock and derived colluvial and
residual clays / clayey soils”.
Sedimentary siltstone and sandstone bedrocks belonging to the Vryheid
Formation where encountered over the majority of the site.
Section B2.2 Landform
A slope analysis of the entire farm (property) was undertaken by ourselves and the
majority of the proposed development area was found to be within the 0 – 20%
gradient range with small isolated areas reaching a maximum gradient of 25% along
the lower edges of the elevated development footprint perimeter (refer to
Annexure F4, for a copy of the slope analysis undertaken of the development area
onto which the layout plan has been superimposed).
Variation in elevation ranges between approximately 84m AMSL in the south eastern
sector of the site to approximately 184m AMSL along the northern boundary of the
farm.
Section B2.3 Slope Stability
As part of the geotechnical brief, the shallow slope stability has been assessed to
gauge the suitability of the site for development in terms of the prevailing slope
stability conditions.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 4
On the basis of their observations, no evidence of a landslip in the recent past was
observed and the existing satisfactorily drained shallow slope conditions appear to be
inherently stable.
Provided good stormwater controls are maintained, and injudicious earthworks are
not attempted, gross slope instability at shallow levels is not expected.
Furthermore, satisfactorily stable development is considered feasible, provided
suitable development controls and guidelines recommended in this report are
implemented to the approval of the engineering and geotechnical professionals.
In broad terms, the planning and development controls on site would pertain to
carrying out the following :
- Slope analysis: In terms of shallow slope stability, development densities and
costs, it is considered that any slopes steeper than 18° (1 vertical: 3 horizontal)
display a significantly lower potential for development and should be excluded
from the estate scheme. It is advisable that a slope analysis is conducted to
determine the extent of any such steep slopes on site;
- Judicious earthwork design: Field measurements indicate that the bedrock
laminations of the Vryheid Formation are orientated typically to the southeast.
This characteristic should be taken into account if earthworks are carried out on
slopes with a south-easterly aspect. It is unlikely that the relatively mild to
moderately undulating nature of the majority of the slopes will incur costly
earthworks. Notwithstanding this, limits on heights and batters of building and
road platform embankments should be implemented as good practice. Use
should also be made of suitable retaining measures to engineer’s detail in any
critical/steep areas during any platform/road cut/fill earthworks and sound
compaction measures should be implemented;
- Stormwater management and erosion controls: to manage slope maintenance
and prevent any slope damage associated with erosion/slumping of the prevailing
erodible sandy to silty soils due to uncontrolled surface runoff;
- Suitable foundation solutions: to structural engineer’s details and in
accordance with geotechnical design recommendations, to address the variation
in the subsoil-founding materials and settlement design tolerances of new building
structures;
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 5
- Possible subsoil drainage: in the designated non-wetland seepage (“S”) area
as confirmed on site during construction.
Section B2.4 Founding
A detailed subsurface geotechnical site investigation to facilitate infrastructural and
house foundation design processes has not been included in the Preliminary
Geotechnical Conditions Report dated October 2005. Guidelines are however, given
on appropriate founding solutions which will require further investigation and
engineers design.
Section B2.5 Groundwater Conditions
The majority of the site area appears to be satisfactorily drained.
Although, along the central valley bottom terrain where relatively low impermeable
clayey and organic rich soils are anticipated, poor drainage characteristics and the
risk of near surface saturation problems due to the low permeability of the clayey
subsoils are typical. Weakly to poor drained slope conditions are therefore anticipated
in the general area of the valley bottom terrain. Where seepage is anticipated the
approximate footprint is designated with an “S” on the attached preliminary
geotechnical site zonation plan Figure G (enclosed as Annexure F3.1 of this report).
It is recommended that subsoil drainage measures be provided where all services or
roads cross these areas. The design of the subsoil drainage measures should be
concluded on-site during construction and in consultation with a geotechnical
professional.
Section B2.6 Excavatability / Trenchability
DCP (Dynamic Cone Pentrometer) tests have been conducted in four places across
the site. The two north-western tests refused at depths of 1,6m and 1,0m whereas
the two south-eastern tests refused at depths of 0,9m each.
Section B2.7 Subsoil Drainage
The preliminary geotechnical report further suggests that the planning and
development controls on site would pertain to carrying out:
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 6
- Possible subsoil drainage: in the designated non-wetland seepage (“S”) area
as confirmed on site during construction and as shown on the geotechnical site
zonation plan in the preliminary geotechnical report attached in Annexure F3 of
this report.
Section B2.8 Stormwater Management
It is important to dispose of stormwater effectively as uncontrolled runoff can cause
damage to the site through erosion. In severe instances, this may destabilise
embankments arising from a proposed development.
The objectives of the stormwater management system should be as follows:
- To adequately dispose of runoff from developed areas without causing soil
saturation or erosion/sloughing. The importance of this is greater on slopes
showing grades exceeding 20%;
- If required, to provide overland flow routes from access roads/driveways through
developments to cater for major storms and thereby minimising any risk of
damage to property;
- Stormwater systems should be designed to function adequately with low
maintenance in the long term and should cater for silting;
- After construction, the final ground levels around the perimeter of units should be
evenly sloped away from building structures, to ensure effective runoff of surface
water and prevent concentrations of stormwater on surface next to any structures.
Section B2.9 Pavement Subgrade Characteristics
Although laboratory analysis of road subgrade materials did not form part of the brief
of the preliminary geotechnical investigations, the road subgrade materials have been
visually appraised below on the basis of experience from testing carried out on similar
subgrade.
Moderate road subgrade materials are anticipated to occur if sandy deposits of the
Berea Formation are encountered at or immediately below road formation level.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 7
Unsuitable road subgrade characteristics are inferred for areas underlain by the
colluvial and residual clays/clayey soils of the Vryheid Formation, where the
requirement for a select layer is anticipated.
Allowance for subsoil drainage should be made in the seepage area “S”.
Section B2.10 Conclusions
From the basis of the hydromorphic wetland mapping and a preliminary geotechnical
assessment, the following are the developmental considerations and key findings:
● Stable and satisfactory for development, which considered feasible subject to the
adoption of suitable development controls to engineer’s details;
● Development along any slopes steeper than 1 vertical: 3 horizontal (> 18°) and any
1:100 year floodline is not recommended;
● Hydromorphic wetland areas have been mapped along the south-eastern valley of
the site. A provisionally 20 metre wide environmental setback indicated around
the “temporary” wetland area should be verified by the Department of Agriculture
and Environmental Affairs in consultation with Ezemvelo KZN Wildlife;
● Soakpits should not be employed for the disposal of either stormwater or sewage;
● A mini sewage package plant or communal conservancy tanks should be planned;
● Guidelines are given on appropriate founding solutions which will require further
investigation and engineers design;
● Effective stormwater management will minimise maintenance of the slopes.
It is considered that the design of the civil engineering infrastructure and foundations
should be based on a detailed geotechnical subsurface site investigation.
Section B3 Environmental and Cultural/Historical Issues
Section B3.1 Environmental
An Environmental Scoping Report was prepared by Sustainable Development
Projects CC in January 2006.
Some of the conclusions and recommendations of this report are summarised as
follows:
It is apparent tht the development, in its present proposed format, will have positive
local repercussions from a biological perspective in terms of the removal and
replacement of surgarcane both with macadamia plantation and the establishment of
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 8
open space/conservation ares, as well as the establishment of a residential housing
component.
The site has been severely impacted upon by agricultural activities over an extended
period of time resulting in loss of biological diversity.
The proposed development could play a significant role in establishing a precedent
for the proposed open space system and conservation corridors in the Compensation
sub-region.
Social impacts will be positive during the construction phase in respect of job creation
and lcoalised investment in the short term, with improved service provision in the form
of roads and infrastructural service provision.
Long term services provision in the form of water and sewerage provision are not
adequately catered for in the region. Insufficient information is available to predict
with any degree of accuracy the nature of the impacts associated with the proposed
long term provision of water and there is a need for some further hydrological
consideration in this respect.
Local economic development opportunities would be improved in the short to medium
term with improved job creation and infrastructural development. The diversification
of crop lands will have improved local and regional economic impacts with job creation
for the medium to long term also being identified.
Section B3.2 Cultural / Historical
A preliminary archaeological assessment was undertaken by eThembeni Cultural
Heritage in September 2005 to report on the proposed development site. Two
heritage resources of significance were identified. The first of which (Site A, being a
Late Iron Age hilltop settlement) would require further assessment to determine its
significane. The second (Site B) being an ancestral grave, would require protection
from disturbance of any sort or a permit from Amafa. It must however, be noted that
the eThembeni Report to Amafa aKwaZulu Natali indicates that further survey is
required once the cane has been harvested.
In their correspondence dated 5 October 2005, Amafa indicated that of the two
heritage resources identified by eThembeni, “Site A” should be assessed to identify
its significance, and “Site B”, being an ancestral grave, should not be altered,
destructed or removed without a permit. Further survey of the areas under cane is to
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part B: Natural Environment
F:\Bigen-Data\Admin\0938\PED Report Part B.docx B - 9
be conducted once the cane has been harvested, any artifacts found are to be
sampled subject to permits being issued.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 1
THE HELMSLEY DEVELOPMENT COMPANY
HELMSLEY COUNTRY ESTATE – RESIDENTIAL DEVELOPMENT
INTERNAL ENGINEERING SERVICES:
PRELIMINARY DESIGN REPORT
Part C Layout and Planning
Section C1 DEVELOPMENT PROFILE AND PLANNING ISSUES
Section C1.1 Development Boundary
The proposed development area is located very close to the N2 (Level 1) multi-
sectoral activity corridor and the Ballito (level 3) development node, which has
experienced an extremely high growth rate during recent years, and the demand for
affordable, gap, luxury and leisure residential property remains high. However, the
recent series of interest rate hikes has appeared to ease the market activity slightly.
The proposed 20,0801ha Helmsley Residential Country Estate development is
planned for approximately 93 (sectional title) medium density and 32 (stand alone)
special residential housing units respectively for the luxury and leisure/retirement
industry that will form part of a larger proposed 170ha macadamia nut plantation/farm
estate that is already in the process of being established over a 5 – 10 year production
time frame/period.
Section C1.2 Planning Approval
At the beginning of 2007 - the Helmsley Development Company decided to develop
a portion of the land, following on from the successful outcome and support received
from the Ordinance’s Needs and Desirability Planning Application submitted to the
various planning approval authorities during the beginning of 2006 and the latter part
of 2005. The Developer has subsequently obtained planning approval over No. ….
From the Development Facilitation Tribunal (DFA) in order to establish a township for
the proposed development. After obtaining the abovementioned planning consent in
………………….. 20…, the Developer decided to make use of the newly promulgated
(SPLUMA) in order to apply for the SDP approval(s) on the 5 medium density PUD
residential stands (site no. 1, .., .., ..., and .. on the approved SG Plan No. 991/2011).
Bigen Africa Services (Pty) Ltd have been appointed by the Developer to investigate,
analyse and report on the availability, as well as design and monitor the construction
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 2
of the required bulk, link & internal civil and electrical services for the proposed
development in terms of the approved layout plan. This is a statutory requirement in
terms of the DFA and SPLUMA Acts and other developmental legislation.
Section C1.3 Spatial Impact
The KwaDukuza Local Municipality is the local authority that is responsible for the
PDA and SPLUMA planning approvals of all township establishment applications in
respect of new residential housing estate development projects within their area of
jurisdiction.
From our investigations, it has been concluded that the majority of households within
Ward 4 (59.98%) in relation to the rest of KwaDukuza Local Municipality (50.76%) are
residing in brick houses built on separate stands.
The proposed Helmsley Housing development will entail 32 high cost residential
houses on free hold stands, as well as 5 sectional title stands with approximately 93
residential units of similar class with and equal or slightly lower affordability range. It
is anticipated that the proposed development will be of such a standard that it will
improve the value of the surrounding properties and provide a unique country life style
type of living opportunity.
Section C1.4 Topography
The site generally slopes from the north-west towards the south-east. Drainage from
the elevated hillock on which the development has been located is governed by three
(3) non-perennial streams within the valley lines that drain towards the south eastern
corner of the farm where they converge into a single stream/tributary that eventually
joins up and flows into the Wewe river approximately 3km south of the project area.
A characteristic of the township layout is the elevated views over the Compensation
flats, and the feeling of ample wide open space that has been created by locating the
majority of the residential erven along the ridgeline of the farms isolated hillock.
Section C1.5 Existing Land Uses
Cognisance of neighbouring land-uses, zoning, social and infrastructure requirements
were taken into account during the various layout planning processes for the Helmsley
Residential Development.
Section C1.6 Provincial Roads
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 3
There are no provincial roads that have been proclaimed through the project area,
however, existing access to the site is already established and obtained from District
Road D176.
Section C1.7 Geological Stability
Geological stability of the site directs land development options as well as housing
typologies and densities. Refer to ‘A Hydromorphic Delineation of Wetland areas and
a Preliminary Assessment of anticipated Geotechnical Conditions’ – dated October
2005, Ref. No. GS 59/05 (GGS).
Section C1.8 Land Use Requirements
The Helmsley Country Estate Development (with a total area of 21,0801ha) will be
developed to have land uses such as:
Those recorded on the land use plan for the approved development site is included
in Annexure F5.
Section C2 BULK AND LINK SERVICES
Section C2.1 Institutional Arrangements
Prior to the finalisation of Powers and Function on 3 January 2003 by way of a
Proclamation in the Government Gazette No. 24228 (Government Notice No. 52),
with effective date being 1 July 2003, wherein the Water Services Authorities were
promulgated in terms of the Water Act, the Department of Water Affairs and Forestry
(DWAF), now the Department of Water and Sanitation (DWS), were the Water
Services Sector leader and Principle Funder of all public water infrastructure with
selective CMIP (now MIG) funding assistance on a project by project basis, whereas
the iLembe District Municipality, in association with DWAF, took up the role as the
Implementing Agent.
With the advent of the new legislation already alluded to above, the iLembe District
Municipality (iLembe DM) have, as from 1 July 2003, taken over this role and are the
Water Services Authority (inclusive of the Water Service Provider (WSP) functions)
for the development area which falls outside of the Sembcorp/Siza Water concession
supply area.
Further, as from 1 March 2004, all previously DWAF owned assets (water services
infrastructure assets as well as staff) were transferred to iLembe DM in terms of the
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 4
Joint Policy Position Agreement on the transfer of water services, dated January
2003.
As per the services agreement entered into between the developer and iLembe DM,
the WSP provider function for this development will be the Developer’s responsibility,
and bulk water supply and sewage treatment operations will be fulfilled by the
developer, until such time as a Home-Owners Association (HOA) has been
established and WSP function transferred to the HOA. More detail on the WSP
function for the Bulk Water and Sanitation is discussed under section C2.3.6 of this
PED report.
Section C2.2 Bulk Water
Section C2.1.1 Existing Bulk Water Infrastructure
The iLembe DM does not have any existing bulk water supply pipelines or other
related water treatment infrastructure available in close proximity to the development
area at this stage. iLembe DM is however planning a bulk water off-take (Off-take
No. 13) from the newly constructed 900Ø mm bulk gravity water main from Mandini
to Mvoti, that was completed in 2015 as part of the Lower Thukela Bulk Water Supply
Scheme implemented by Umgeni Water.
A high level conceptual layout of the bulk supply lines located in close proximity to the
Helmsley Development is reflected on a layout drawing obtained from Black Balance
and is included in Annexure H1. The said plan reflects a proposed 700Ø mm bulk
water supply pipeline on the North Eastern boundary of the development site, from
which a future connection along the Northern boundary of the development site could
be obtained in the long term. The iLembe DM has confirmed that they have not set
aside any funding for this bulk water supply infrastructure and its implementation is
not foreseen in the near term future.
Section 11(3) of the Water Services Act states that in ensuring access to water
services; a Water Services Authority must take into account, amongst other factors:
Alternate ways of providing access to water services:- Unfortunately, no bulk water
supply service, other than ground water is currently available within the
surrounding project area;
The need for regional efficiency:- A regional water supply scheme from the iLembe
District is not available;
The availability of resources from neighbouring water services authorities:- No
other Bulk services other than ground water is currently available from the
surrounding area.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 5
We have assumed that both Sembcorp/Siza Water and Ilembe have adopted the
iLembe District Municipality’s general requirements relating to water supply as a
common standard throughout their respective supply areas of jurisdiction. These
general requirements can be summarized as follows:
Water services in general shall be described according to “Guidelines for Human
Settlement Planning and Design”. Consideration should be given to:
o Flow characteristics
o Catchment specific water quality objectives
o Final Effluent, Storage for reuse or irrigation
Therefore, with the absence of a bulk municipal water supply scheme in the area, as
noted above, the proposed development will have to make use of sustainable
groundwater resources that will have to be established from 2 x DWS registered and
licensed boreholes located somewhere within the said property and developed in
terms of the following specialist reports;
Geophysical Investigation and Borehole Siting Report, as compiled by Messrs.
Geomeasure Group (refer to Annexure H2 for a copy of same).
Final Geohydrological Report on the Drilling, Pump Testing Water Quality Analysis
and Preliminary Reserve Determination for the proposed Helmsley Housing
Development, as compiled by Messrs. Geomeasure Group (also refer to
Annexure H2 for a copy of same).
Section C2.2.2 Proposed Bulk Water Supply System
With reference to the Water and Sanitation Flow Diagram and Infrastructure Layout
Drawing included in Annexure H3, the bulk water supply infrastructure can be
described as follow:
2 x small borehole pump stations (BH1 & BH2), pumping water through a dedicated
uPVC rising main to a package WTW and Reservoir located at highest point on the
site (184Amsl above mean sea level)
260kℓ/day WTW (refer to demand calculation below) & pump transfer to ground
level reservoir (at top water level (TWL) 190Amsl)
Booster pump or high level reservoir (Water Tower) that will feed to high level
supply zone > 180Amsl
Bulk water distribution pipelines to the high and low level supply zones
respectively, discussed under the internal services below.
Section C2.2.3 Water Demands
The expected water demand for the development of a proposed new residential
housing estate as indicated on the final/approved layout plan is estimated as follows:
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 6
Table 1: Expected AADD Water Demands (and Associated Sewage Runoff)
Land Use Water Demand Sewage Runoff
Phasing/ Zoning No. of
Stands/
Residential
Units
Unit Flow
(ℓ/day)
Total
Ave.
Flow
(kℓ/d)
SPD
(kℓ/d)
IPD
(kℓ/d)
% Run-
off
Unit
Run-
off
ADWF AWWF
(kℓ/d)
Peak
Run-off
(kℓ/d)
Special Residential 32 1500 48 72 384 80% 1200 38 46 96
Sectional Title 93 1200 112 167 893 80% 960 89 107 223
Conservation Reserve 5 15kℓ/ha 14 20 108 n/a
Total 173 260 1385 1731 128 153 319
Household water demand:
Special Residential – 1500ℓ/day (annual average daily water demand)
Sectional title – 1200ℓ/day (annual average daily water demand)
Conservation Reserve – 15kℓ/ha (annual average daily water demand)
Annual average daily:
demand (AADD) – 173kℓ/day
Summer Peak – 1 385kℓ/d (Factor 1,5)*
Instantaneous peak flow – 692kℓ/d (PF = 4.0)
Daily Peak – 4.8ℓ/s (Factor 2,4)*
Bulk Reservoir Storage – 48 hours*
Fire Flow – 1900ℓ/min/2hours 228kℓ * (SABS 10090:2003)
– 575kℓ storage tank (reservoir)
Elevated Storage – 115kℓ storage tank *(2 hours inst peak)
Treatment plant Capacity – 260kℓ/day
* As prescribed by the Guidelines for Human Settlement Planning and Design.
Section C2.2.4 General Description of Groundwater Source and Treatment Requirements
In terms of item C2.1.1 above, the proposed development will initially make use of
boreholes - a groundwater supply that shall be established by pumping water to the
highest point of the development along the north-eastern boundary of same from two
(2) newly sited boreholes that have already been drilled, pump tested and chemically
analysed (refer to layout drawing in Annexure H3). From the provisional chemical
analysis conducted on the water samples taken, the water will need some basic
treatment, disinfection and filtration before it is used for potable domestic water supply
purposes.
There are many different ways that can be employed for treating the borehole water,
(generally referred to as the treatment process). Based on the initial test results that
were obtained as referred to above – where the water has slightly elevated
manganese levels and package plants are often used in order to address same where
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 7
these specific types of problems exist. In this specific instance, we have opted to use
a conventional standard type of package plant in order to treat the water. Based on
the treatment guide from DWS for domestic water supply, the Construction of a new
water treatment package plant could be considered and is generally modular in
nature. The main advantages of a package plant is that it can be erected in a relatively
short period of time and is a compact self-contained unit capable of producing water
from a variety of raw water supply sources. The Capital costs are generally much
lower than that of a conventional permanent type of treatment plant.
a) Quantum and Quality
The groundwater development program resulted in the siting, drilling and testing
of 2 No. exploration boreholes both of which were successful.
The results of the pump tests undertaken on the new boreholes indicate that the
two boreholes have a combined sustainable yield of 444m³/day, which is well in
excess of the estimated water demand of 196.68 m³/day including 10% loses
for the proposed development.
Under the DWS General Authorisation groundwater use for the property
(Portion 161 of the Farm Compensation No. 868) is limited to 77.67m³/day.
Therefore, the use of ground water above this GA threshold amount for the
proposed Helmsley Residential Housing Development will require specific
registration and licensing with DWS.
The results of the Preliminary Desktop Groundwater Reserve Determination
that was undertaken utilising the GRDM software and available data indicates
that 8.75 Mm³/annum of groundwater is still available for allocation in the
Quaternary Catchment U30D.
While the results of a more detailed site specific preliminary Reserve
determination that was undertaken for Portion 161 of the Farm Compensation
No. 868 and surrounding properties indicated that even for this reduced area, a
total of 0.35 m³/annum of groundwater or 951m³/day is available to be allocated
to ground water users.
The water quality results from the 2 x new boreholes show that the water is
suitable for long term potable water supply after only being subjected to very
only basic water treatment, i.e. disinfection/chlorination followed by filtration in
order to treat the slightly elevated total coliform and turbidity levels.
b) Recommendations:
In light of the favourable results of both of the preliminary reserve
determinations, it is recommended that an application for the registration of the
2 x new boreholes and licensing of the proposed groundwater use is submitted
to DWS for approval.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 8
Once a groundwater license has been obtained from DWS, it is recommended
that both of the boreholes be equipped as per the recommendations contained
in the Geomeasure management sheets.
The area around the boreholes should be graded so as to allow surface
stormwater runoff to drain away freely in order to prevent ponding which could
lead to contamination of the boreholes.
o The boreholes should be covered / protected by borehole-pump houses in
order to prevent tampering with the pumps and possible contamination of the
boreholes, the pump houses should also allow for essential electrical
equipment in order to monitor and control the pumps.
Water treatment as per the recommendation contained in this report should be
implemented in order to ensure that the water is suitable for long term potable
water supply.
Water samples should be collected from the post treatment water supply to the
development on a quarterly basis and submitted to a SANAS accredited
laboratory for Abr. SANS 241:2006 analysis in order to ensure the water is fit
for human consumption.
Static and dynamic water levels should be recorded on a regular basis in order
to ensure that de-watering of the aquifer is not occurring as the water utilisation
increases and that the boreholes are not interfering with each other.
c) Caution:
Any septic tanks, soak-always or water treatment works that may be
constructed as part of the proposed development should be sited away from the
existing boreholes in order to prevent contamination of the developments
primary water supply.
The results of the previous pump tests only represent a “snap shot in time”
and therefore the long term sustainable yield of the boreholes can only be
accurately determined if an accurate record of the static and dynamic water
levels and pumping volumes are kept and analysed on a regular basis by a
hydrogeologist.
The preliminary reserve determinations included in this report are only included
as a guideline and the findings will have to be verified by the DWS RDB office.
Section C2.2.5 Bulk Water Supply System Components
Refer to overall system description in Section C2.1.2
Section C2.2.5.1 Bulk Water Source – Boreholes
Borehole no. BH1 (KZN 070181)
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 9
- Pump Installation (mbgl) : 60m
- Dynamic Water level (m) : 12m
- Rec. Pumping Cycle (Hrs/day) : 8
- Rec. Pumping rate on pump cycle : 18m3/hr 5,00ℓ/s 144m3/day
- Analytical Water Quality Analysis
▪ General Determinants
Mostly Class I
Exemptions: Turbidity – Class III *
▪ Macro Determinants
Mostly Class I
Exemptions: Iron – Class II ▪
▪ Micro Determinants
Manganese – Class II ▪
▪ Microbiological Determinants
Mostly Class I
Total Coliforms: Class III
Borehole no. BH2 (KZN 070182)
- Pump Installation (mbgl) : 50m
- Dynamic Water level (m) : 20m
- Rec. Pumping Cycle (Hrs/day) : 12
- Rec. Pumping rate on pump cycle : 25m3/hr; 6,94ℓ/s; 300m3/day
- Analytical Water Quality Analysis
▪ General Determinants
Mostly Class I
Exemptions: Turbidity – Class III *
▪ Macro Determinants
Mostly Class I
Exemptions: Iron – Class II ▪
▪ Micro Determinants
Manganese – Class II ▪
▪ Microbiological Determinants
Mostly Class I
Total Coliforms: Class III
* The turbidity of the water quality will probably improve over time seeing as though
these are newly drilled/developed boreholes.
▪ Class II: maximum allowable for limited duration use (7 years)
Class III: exceeds maximum allowable limits
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 10
The two x boreholes shall be equipped with suitable positive displacement or
submersible pumps and the controls for same will be housed in an enclosed masonry
pump house.
The equipment for the boreholes shall be designed in order to meet the
geohydrologist’s management recommendations:
BH 1 – KZN 070181 can provide a safe yield of 5.0ℓ/s with max 8 hour pump cycle.
BH 2 – KZN 070182 can provide a safe yield of 6.94ℓ/s with max 12 hour pump
cycle.
Table 2: Borehole Pump Design Detail
Pipe Section: Pump 1 Pump 2
Q (ℓ/s) = 5.000 6.940
D (m) = 0.075 0.090
L (m) = 1132.0 420.0
S (m/m) = 0.02 0.01
v (m/s) = 1.13 1.09
FSL level - Entering WTW 184 184
Suct Side Min water level 20 83
h stat 164 101
hf tot 21.94 6.08
Δ h - Total Head (m) 185.94 107.08
Power kW 14.29 11.42
Borehole Equipment includes:
Borehole Pump House installation
o Both boreholes to be housed inside a separate brick pumphouse (Refer to
Annexure H4 for Pump house and pump station pipe configuration.
Casing and Rising Mains
o Casings are 140mm Ø uPVC Sleeves (The diameter and condition of the
casings would have to be reviewed as the small diameter limits the suitable
pump options)
o The pipework below ground level to be 110mm Ø Galvanised Mild Steel (GMS)
pipes in order to be able to handle a max pressure of up 18.5 Bar.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 11
o Each pump to be equipped with non-return valve in order to prevent short
circulating back into the ground, from one borehole to the other.
Section C2.2.5.2 Rising Main Pipelines
The rising main shall be constructed using uPVC piping:
Rising main section 1 = 915m, 75mm Ø Class 10 uPVC pipes
Rising main section 2 = 203m, 90mm Ø Class 12 uPVC pipes
Rising main section 3 = 217m, 90mm Ø Class 12 uPVC pipes
Section C2.2.5.3 Potable Water Treatment – Water Treatment Works (Refer to Annexure H5 for
Layout Plan)
Raw Water Quality
Only a single raw water quality analysis was carried out on the two boreholes
(KZN070181 and KZN070182) during 2007, which only provides a snapshot of the
raw water quality in 2007. It is, however, advised as part of the detail design phase
to carry out a more detailed water quality sampling exercise in order to provide a
clear overall picture of the current raw water quality for these boreholes.
The average values for various parameters tested during 2007 have been listed in
Table 4 below.
Table 3: Raw water quality data
Water characteristic Unit Average raw water value
SANS 241-2015 Drinking water limits
Water pH pH 7.5 ≥5 - ≤9.7 Operational
Total alkalinity mg/l as CaCO3 175 n/a
Water turbidity NTU 5.9 ≤5 Aesthetic ≤1 Operational
Conductivity mS/m 58.8 ≤170 Aesthetic
Colour mg/l as Pt 1.5 ≤15 Aesthetic
Total dissolved solids mg/l 411.6 ≤1200 Aesthetic
Iron μg/l as Fe 360 ≤300 Aesthetic ≤2000 Chronic Health
Manganese μg/l as Mn 185 ≤100 Aesthetic ≤400 Chronic Health
E.coli Count per 100ml 0.0 Not Detected
Total coliform bacteria
Count per 100ml >2419 ≤10 Operational
Faecal coliforms Count per 100ml 0 Not Detected
Calcium mg/l as Ca 37.1 N/A
Magnesium mg/l as Ca 23.1 N/A
Sodium as Na mg/l as Na 75.7 ≤200 Aesthetic
Chloride mg/l as Cl 76.7 ≤300 Aesthetic
Sulphate mg/l as SO4 14.71 ≤500 Acute Health ≤250 Aesthetic
Total Organic Carbon mg/l as C 0.147 ≤10
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 12
Water characteristic Unit Average raw water value
SANS 241-2015 Drinking water limits
Fluoride mg/l as F 0.36 ≤1.5 Chronic Health
Nitrate nitrogen mg/l as N 2419 cfu/100ml
respectively, which indicates potential groundwater contamination through the
ingress of sewage or effluent. In the event that similar results are found during the
detail design stage the source of the contamination should be investigated rather
than treating the end result of the contamination, ultimately leading to higher
treatment costs.
The raw water turbidity of both boreholes are below 10 NTU.
The level of iron (Fe = 0.46mg/ℓ) and manganese (Mn0.19 mg/ℓ) are above the
prescribed limits required by the SANS 241:2015.
Treatment Objectives
The target water quality standards shall be in accordance with SANS 241:2015.
The water quality objectives, potential unit treatment process and process
function, as well as the treatment targets are illustrated in Table 4 below.
Table 4: Summary of treatment process
Water Quality Objective
Unit Treatment Process
Process Function Target
Removal of suspended material (reduce turbidity)
1) Sedimentation
2) Rapid sand filtration
1) Removal of settling suspended matter
2) Removal of fine suspended matter
1.0 NTU
Oxidation of iron and manganese
1) Pre-chlorination 1) Oxidation of iron and manganese
0,1 mg/l Mn
0,3 mg/l Fe
Ensure distribution system residual disinfectant
1) Post-Chlorination 1) Establish a chlorine residual
DOC removal 1) Sedimentation
2) Rapid gravity sand filtration
Reduce DOC by coagulating dissolved organics remove with phase separating steps
DOC < 1
Proposed Unit Treatment Processes
It is foreseen that a conventional water treatment process will be required. The
main treatment process/aspects are briefly discussed below:
A pre-oxidation step will be required in order to oxidize the iron and
manganese to the acceptable target levels.
With the raw water turbidity of less than 10 NTU it is foreseen that direct
filtration will be sufficient for phase separation.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 13
Conventional stabilization and disinfection strategies are expected to be
sufficient to ensure a good quality of treated water.
It is expected that the raw water will be of such a quality that stabilization will
not be required for most of the time. However, provision will be made for the
addition of soda Ash to increase the pH to acceptable levels during coagulation.
During the preliminary engineering design phase of the Helmsley WTW, provision
has been made to dose a polymeric, as well as a metal coagulant.
The proposed process train is schematically reflected in Annexure H6 and will
comprise of the following:
pre-oxidation (using chlorine);
pH correction (using lime);
coagulation;
flocculation;
clarification (sedimentation);
Pressure filtration; and
Disinfection.
Raw Water Supply
Raw water shall be transferred from the boreholes to the WTW up to a maximum
flow rate of 12ℓ/s over a 12 hour period. This will require the inclusion of a flow
balancing tank in order to provide a constant throughput of 3ℓ/s (260m³/day) over
a 24 hour period.
Pre-oxidation
Pre-oxidation processes are required for the oxidation of heavy metals such as iron
and manganese. Chlorine is a strong oxidant and is often used for the oxidation of
inorganic compounds such as iron and manganese. In such cases a phase
separation process is required downstream of the pre-chlorination step in order to
remove the metal precipitate.
Provision shall be made to pre-chlorinate the raw water in extreme cases when
severe problems are experienced with the iron and manganese complexes. Pre-
oxidation shall be provided by means of a chlorine dosing process into the raw
water feed pipeline (i.e. one dosing point) between the collection tank and raw
water feeder pumps.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 14
pH Adjustment
Numerous chemicals are currently available to increase the pH and alkalinity of
water (i.e. calcium hydroxide, sodium carbonate and sodium hydroxide) to pre-treat
the raw water for coagulation dosing (i.e. increase the alkalinity).
Soda Ash shall be dosed immediately downstream of the flow balancing tank.
Sufficient mixing energy will be provided for the soda ash through an inline static
mixer. This will stabilize the pH prior to coagulation.
Coagulation
Allowance shall be made to dose a coagulant into each 5.5m3/hour streams
respectively downstream of the raw water feed pumps. Hydraulic flash-mixing will
be created by means of an inline static mixer in order to produce a head loss of at
least 1.0m downstream the dosing point.
Sufficient flash-mixing inducing a G-value > 2000 sec-1 is of prime importance in
order to optimize the efficiency of coagulants. The polymer dosing system is sized
to dose a maximum of 10mg/ℓ and the ferric-chloride dosing system shall be sized
to dose a maximum of 20mg/ℓ.
a) Poly-electrolyte
Two single phase dosing pumps shall be provided (one as stand-by) in order to
feed diluted poly-electrolyte from the day tanks to the dosing point downstream
of the balancing tank.
The dosing pumps shall each be required to deliver between 0 and 1ℓ /hour at
a pumping head of 10m by means of flow paced electronic variable speed
controls. Dosing pumps shall also be stroke adjustable between 10 and 100%
of the maximum stroke
One bulk storage tank of 100ℓ shall be adequate to provide more than 30 days’
storage for 260m3/d at the average coagulant dosage concentration.
One calibrated 20ℓ day tank shall be provided from which the coagulant dosage
can be controlled on a shift basis. The coagulant gravitates from the bulk tanks
into the day tanks where after it shall be pumped to the dosing point.
Each day tank shall be equipped with a mechanical mixer with stainless steel
shaft and impeller, and shall be capable of maintaining a homogeneous mixture
of chemicals and water. These mixer motors shall be manually controlled from
the local motor control centre in the chemical building.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 15
b) Ferric-Chloride
Two single phase dosing pumps shall be provided (one as stand-by) in order to
feed diluted poly-electrolyte from the day tanks to the dosing point downstream
of the balancing tank.
The dosing pumps shall each be required to deliver between 0 and 2ℓ /hour at
a pumping head of 10m by means of flow paced electronic variable speed
controls. Dosing pumps shall also be stroke adjustable between 10 and 100%
of the maximum stroke.
One bulk storage tank of 250ℓ shall be adequate to provide more than 30 days
storage for 260m3/d at the average coagulant dosage concentration.
One calibrated 50ℓ day tank shall be provided from which the coagulant dosage
can be controlled on a shift basis. The coagulant gravitates from the bulk tanks
into the day tanks where after it shall be pumped to the dosing point.
Each day tank shall be equipped with a mechanical mixer with stainless steel
shaft and impeller, and shall be capable of maintaining a homogeneous mixture
of chemicals and water. These mixer motors shall be manually controlled from
the local motor control centre in the chemical building.
Flocculation/clarification
Flocculation follows coagulation to promote optimum conditions for floc formation.
The success of the flocculation process is primarily depended on three factors
namely: effectively mixing the coagulant into the water; the time available for floc
formation; and turbulence intensity promoting floc growth.
The flocculated water shall be transferred to the pressure filters through a 160mm
diameter uPVC pipe with a velocity at maximum throughput of 0.3m/s in order to
allow floc formation.
a) Filtration System
Pressure filters shall be used for the filtration from the groundwater or high
quality surface water that does not require clarification. In certain groundwater
systems they can also be used for the removal of iron and manganese in
addition to turbidity.
The coagulated water shall be transferred to three filters filled with silica quartz
media operating under pressure.
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 16
b) Filter Feeder Pumps
The feed water shall be extracted from the flow balancing tank and fed into the
pressure filters at a flow rate of between 10 and 15m3/hour at a maximum duty
head of 20m through two filter feeder pumps fitted with VSD’s (1 duty + 1 stand-
by installation).
The hydraulics for the proposed filter feed system are listed below:
Minimum velocity in 75mm diameter uPVC suction and delivery line:
0.720m/s
Maximum velocity in 75mm diameter uPVC suction and delivery line:
0.924m/s
c) Pressure Filters
The pressure filters shall be fed at a loading rate of 15m3/hour through the
feeder pumps. The filtration rate ranges between 5m/hour and 10m/hour, 6
m/hour is required for the filters. Should one filter be out of operation or being
backwashed, the filtration rate shall automatically increase to 9.5m/hour, which
is deemed the upper limit for safe operation.
The backwash water from the filters shall be wasted to the waste chamber that
will be constructed outside the container as shown in Figure 8. The solids in
the wasted backwash water shall settle out while the excess water will be
allowed to drain into the stormwater system through a proposed outlet pipe or
allowed to simply evaporate. This shall require the removal of sediment from
the chamber from time to time.
The backwash system shall consist of two backwash pumps (1 duty + 1 stand-
by installation) and 2 compressors (1 duty + 1 stand-by installation). The
backwash pumps must have a maximum duty of 25m3/hour at a head of 25m.
The hydraulics for the proposed filter feed system are listed below:
Maximum velocity in 75mm diameter uPVC suction and delivery line:
0.924m/s
Disinfection
Provision shall be made to feed chlorine gas for pre-chlorination into the raw water
delivery system, as well as for disinfection into the final treated water in the
clearwater tank. A full stand-by unit should be provided for either the pre- or the
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 17
post-chlorination. The pre and post chlorination units shall be automated
proportionally in order to accommodate the raw water flow rate.
Table 5: CT Values for Inactivation of Giardia Cysts
Disinfectant Inactivation (mg ∙ min/L)
0.5-log 1-log 1.5-log 2-log 2.5-log 3-log
Chlorine 1 17 35 52 69 87 104
Chloramine 2 310 615 930 1 230 1 540 1 850
Chlorine Dioxide 3 4 7.7 12 15 19 23
Ozone 3 0.23 0.48 0.72 0.95 1.2 1.43
CT values were obtained from AWWA, 1991 1. Values are based on a free chlorine residual less than or equal to 0.4mg/L, temperature of 10°C, and a
pH of 7
2. Values are based on a temperature of 10°C and a pH in the rant of 6 to 9
3. Values are based on a temperature of 10°C and a pH of 6 to 9
(Alternative Disinfectants and Oxidants Guidance Manual, EPA, April 1999)
Table 5 above indicates a CT value of 104mg.min/ℓ is required for a 3-log
inactivation of Giardia Cysts. Assuming a residual chlorine value of 2mg/ℓ, the
estimated contact time required is 52 min.
Table 6: CT Values for Inactivation of Bacteria and Viruses
Disinfectant
Inactivation (mg ∙ min/L)
Bacteria Viruses
2-log 4-log 2-log 4-log
Chlorine 0.1 – 0.2 10 - 12 2.5 – 3.5 6 - 7
Chlorine Dioxide
8 - 10 50 - 70 2 - 4 12 - 20
Ozone 3 - 4 N/A 0.3 – 0.5 0.6 – 1.0
Clearwater Storage
A Clearwater storage tank with a full supply capacity of 15m³ shall provide the
following:
balancing tank for clear water pumps;
chlorine contact tank with 83 minutes contact time for 260 m3/day; and
Adequate volume with a constant head to the filter washwater pumps.
The contact time in the clear water tank at a flow rate of 260m3/hour is sufficient.
Low Lift Pumps
-
Helmsley Country Estate - Residential Development Internal Engineering Services: Preliminary Design Report Part C: Layout and Planning
F:\Bigen-Data\Admin\0938\PED Report Part C.docx C - 18
Two low lift pumps (1 duty + 1 stand-by installation) shall be required to transfer
the potable water to the groundwater reservoir. These pumps shall be fitted with
variable speed drives (VSD’s) in order to operate during variable flow conditions.
The low lift pumps fitted with variable speed drives (VSD’s) shall have a capacity
of at least 5.5 to 11.0m3/hour at a duty head of at least 10m.
The hydraulics for the proposed raw water feeder system are listed below:
Minimum velocity in 63mm diameter uPVC suction and delivery line: 1.6m/s
Maximum velocity in 63mm diameter uPVC suction and delivery line: 1.120m/s.
The low lift pump house shall also serve as a chemical storage facility for basic
chemicals and operation items in order to conduct daily quality monitoring
(Refer to Annexure H7).
Electrical, Control and Instrumentation
MCC Panels for the boreholes, shall be mounted inside the pump house, and
will include timers, low and high level transmitters with flow switches, to
automatically stop and start the pump(s).
A HMI/SCADA system shall provide flow and pump details to the operating room