hello Neophitos AntoniadesEskom journey to perform S/4HANA migration in 35 Weeks
Eskom Holdings
Agenda Items
About Eskom – Video
SAP at Eskom
S4/HANA Journey
Background
Program Scope
Project Objectives & Duration
Project Cycles & Conversion steps
High-level Project Plan
Cutover weekend
Project Risks
Gaps
Improvements and next Steps
About Eskom: Video
Agenda Items
About Eskom – Video
SAP at Eskom
S4/HANA Journey
Background
Program Scope
Project Objectives & Duration
Project Cycles & Conversion steps
High-level Project Plan
Cutover weekend
Project Risks
Gaps
Improvements and next Steps
SAP at ESKOM
Modules in SAP ERP
Other SAP Solutions
SAP Landscape
Eskom | Current IT state and challenges
Complex SAP solution landscape with 29 production and 63 non-production environments.
More than 100 databases and 200 application servers.
High demand on Group IT to automate processes.
IT cost pressure │ Demand for analytics │Digital utility imperatives
ECC
SRM
BW CRM
APO
HR
23 other
Agenda Items
About Eskom – Video
SAP at Eskom
S4/HANA Journey
Background
Program Scope
Project Objectives & Duration
Project Cycles & Conversion steps
High-level Project Plan
Cutover weekend
Project Risks
Gaps
Improvements and next Steps
Why S/4HANA?
1. Innovation – SAP HANA Technology In line with our Digital Strategy.
2. Operational Sustainability – SAP HANA only supported platform in the
SAP Roadmap.
3. Financial Sustainability – Beneficial for Eskom to migrate at current
prices.
4. Improved reporting – Real-time, incl. flexible reporting based on line
items.
5. Speed & Agility – Faster Access to data.
6. Modern user experience with FIORI.
7. Technical Benefits – Performance improvement | less storage cost |
simplified SAP landscape.
SAP HANA Project Scope
The two SAP HANA options:
1. S/4 HANA
Migration and Conversion to S4HANA and certain functionality changes.
2. Suite on Hana (SoH)
Technical migration to HANA and NO new functionality during the project
implementation and remain on ECC6 EHP7.
Scope Baseline | Conversion to S/4HANA
1. SAP ERP - Enterprise Resource Program (PFS).
2. Technical migration done on the other SAP systems to SoH and remained on ECC6 (HR, Insurance, GRC, SolMan, etc.).
3. SAP SRM* - Supplier Relationship Management (PSR).
4. SAP MDG - Master Data Governance.
5. SAP BPC - Business Planning & Consolidation.
6. S/4HANA Cash Management (new implementation).
7. S/4HANA New Asset Accounting.
8. Commercial Sourcing and Collaboration (ARIBA)**.
9. Limited SAP FIORI Applications applications (pre-requisite).
SAP SRM* - An investigation is required to migrate data from SRM to S/4 SRM using SLO. If data migration is not possible, a display only solution
will be required.
Ariba ** – Not implemented because of marketplace restrictions.
Project Objectives: S/4HANA
Eskom planned the migration of their central ERP system to S/4HANA.
Source: ECC6 (EHP7), Oracle - 7TB (uncompressed), Memory 80 GB.
Target: S/4HANA 1610 (FSP2), HANA - 5 TB, Memory 4 TB.
Modules: FI, FI-AA, FI-CO, MM, PM, PS, PP, SD, Travel Management.
S/4HANA Migration Project duration
Pre-project:
SAP Value Assurance Planning Services (ISR, VIS, MPW, MPS, PED, TAI & BDS).
CVI Strategy / conversion approach.
Project Start: 10 April 2017:
Go-Live: 12 December 2017 - [8 month duration] S/4HANA 1610.
Project End: 12 January 2018 - [4 weeks post Go-Live support] .
Eskom’s late scope changes:
In Aug ‘17: Eskom moved up the planned Go-Live date from Feb 2018 to Dec 12th, 2017.
Reason: too close to year end closing activities in Feb 2018.
SAP S/4HANA Conversion CyclesCycle 1 Cycle 2 Cycle 3 Cycle 4 Cycle 5 Cycle 6
Test Upgrade and
Migration /
Conversion Steps
Create an Upgrade
/ Migration
Cookbook
Functional testing
Basic system
validation
Define the
technical Downtime
Soft freeze - Delta
Code Adjustment
Testing
Environment
Sanity Checks
Unit tests
Transport Queue
testing
System
adjustments
Enhance Cookbook
Testing
Environment:
Full Functional
test
Full Role test
Full integration
test
UAT test
Volume test script
preparation
New HANA
Production H/W
Final functional
adjustments
Soft Freeze period
starts
Define/Verify
business downtime
Testing
Environment:
Load test
Infrastructure / HA
Prod Test
Conversion
Hard Freeze period
starts
Cutover Rehearsal
Verify business
downtime
Production
*Conversion (Refer
next slide)
Interim Hardware Interim Hardware Interim Hardware Prod. Hardware Prod. Hardware Prod. Hardware
Sandpit Development Quality Assurance Mock Rehearsal Dress RehearsalProduction
Go-Live
Conversion Steps
High-level Project Plan
S/4 ScheduleQu
ality
Sys
tem
Dres
s Re
h.Mo
ck C
utov
erSa
ndbo
xGo
-Li
veDe
v Sys
tem
2017 2018
Activity May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Prepare conversion
Convert to S/4HANA with DMO
Post activities – Technical
Cookbook creation
Post App Work & Functional testing
Cash Management Configuration
Data clean-up
Prepare conversion
Convert to S/4HANA with DMO
Post activities
Custom code adjustments
Unit testing
Data clean-up
Prepare conversion
Convert to S/4HANA with DMO
Post activities - Technical
Integration/Regression Testing
User Acceptance Testing
Data clean-up
Convert to S/4HANA with DMO
Post activities – Technical
Performance & Infrastructure Test
Convert to S/4HANA with DMO
Cutover plan and cookbook
Convert to S/4HANA with DMO
Delayed
√
Go-Live
Stabilisation
Training
Complete
11 Dec
√√
√
√
√
Organisational Change Management
√
Not on critical path
√
√
√
√
√
√
√√
√
√ indicates complete
Mid Oct 2017 snapshot.
√
√
Cutover Weekend
Cut over Weekend Time Lines
Lock out users
13:00 End users
17:30 Month end users
BCP Loads / BW extractors
One hour
Technical Migration
SUM run for 30 Hours
Transports
4 Hours Pre
1 Hour Post
Financial Migration
31 hours
Business Validation
6,5 hours
Go-Live
13:00
Friday
17:30
Friday
18:30
Friday
00:30
Sunday
11:30
Monday
17:30
Monday
Month end processes
Reference Client
Recon Report
Financial Reporting
Rollback6 Hrs
23:30
Go / No-Go decision
GAPS between ECC6 and S/4HANA (1610)
Eskom Gaps
Pre Readiness report:
MRP can only run on MRP Areas and not S_LOC.
CVI (BP) – All vendors/customers must be created as a BP prior S/4 going live.
CVI (BO) – All employee vendors/customers must be created as a BP prior S/4 going live.
RWD needed to be uninstall as it was not compatible with S/4HANA.
RIB needed to be uninstall as it was not compatible with S/4HANA.
QIM needed to be uninstall as it was not compatible with S/4HANA.
Eskom Gaps | Finance
Conversion checks revealed inconsistencies found between some tables e.g. COSS vs COSP (S/4HANA has more
validation checks).
SAP optimisation notes (slow response times on IDC, Asset Recalc & Report drill down reports).
New Asset Accounting, impact how the system creates a document for each accounting principle in the general
ledger.
Classic Cash Management -> New Cash Management (Fiori expectations).
Some secondary cost elements not created as GL accounts (SAP Note 2389136).
SAP standard tables not displaying address data of user ID’s on workflow items after the S4 implementation (OSS:
logged).
Eskom Gaps | Material Management
Conversion checks revealed inconsistencies found between some tables e.g. MARA & MCHBH.
Material number field length on S/4 is 40 characters, Eskom decided to stick to the current 18 Characters, that
causes some Idoc’s to fail on PM.
Stock requirements list (MD04) run on Plant /MRP areas (previously Sloc) that need to be individually selected to
reflects replenishment requirements. No bulk list exists for MRP area (Sloc) customised program created.
New fields on MIRO “NF”, ME21N, ME53N & ME23N transaction screens.
Eskom Gaps | Supplier Master Data
MDM CREMAS OSS incidents logged:
Central deletion and posting block not updating Business Partner (BP) via CREMAS.
Vendor service level field not visible on BP.
Errors with postings CREMAS Idoc’s to update BP.
Errors on CREMAS Idoc’s when creating vendors as external on BP.
Some CREMAS Idoc’s reflect “GREEN” icon, but BP was not reflecting on the update.
Vat and tax number fields were switched around on the BP after the CVI conversion.
Eskom Gaps | Plant Maintenance
English translation
OSS note implemented to resolve translation issue on text fields.
Field length
Material number field was extended to 40 characters and caused most of the IDOC’s to fail (Floc, Equipment,
work order interfaces) - New data element (DE) was created “MATNR18”.
Material number field length also impacted on the “Construction type” that include the MAT NO. Use same DE.
Classification field was extended to 70 characters and a new DE was created to cater for existing 30
characters “ATWRT30”.
OSS logged as you cant edit Existing IDOC segment to correct material numbers.
IP30 - Maintenance Schedule Date Monitoring ran 200% - 20 000% slower.
Project(s) | Key RisksNo. Risk Mitigation
1Projects moved forward by 9 months: Original go-live
August 2018 moved to December 2017
Executive Support, Business involvement, Motivated Team and strategic
partnership with the OEM (e.g. MaxAttention)
2 SAP HEC Strategy changeLeverage on other strategic partnership to source on premise HANA certified
hardware within a short period
3 Limited local skills for S/4 HANAEnsure SAP HANA training and certifications of internal teams ahead of time.
Training vouchers incl. SAP EA
4 Retention of highly skilled SAP resources within Eskom A retention strategy need to be put in place.
5Reimplementation of certain modules (e.g. cash
management & engineering extensions)Ensure appointed third party consultants have the necessary skill set
6 Complex Eskom solution Ensure proper testing are done and all defects are resolved before going life.
7 End user appetite for change Appoint skilled change management team
Post S/4HANA:Improvements / Next steps
Post SAP Systems on HANA
Databases (30)
Tenants (97)Total
Database Size (34Tb)
SAP Systems (101)
SAP Versions
( NW 7.4 / 7.5 / ECC6 / S4HANA /
BW4HANA )
Response Times Improvements
Optimised Custom Code Reports Response Times Improvements
Technical performance optimization of the Top 45 frequently used Z-reports
BPMoN automatic alerts
Implement Embedded Analytics | Fiori applications
Leverage embedded analytics within Finance, Purchasing and Plant Maintenance functionality.
Manage critical targets by using FIORI KPI design.
Eliminate extract of S/4HANA data to BW.
Lower solution support costs.
Decision-
making cycle
opportunities
Activate Fiori Applications
Improve
productivity
and usability
FROM TO HOW
Manual interventions of
approvals / management
reviews due to lack of
mobile device support
Increased customer
satisfaction with multi-form
factor approval and
notification support
Wave 1 deployment of 18
FIORI apps across Finance,
CRM, GRC, HR and IT SM.
18 of 49 FIORI
apps identified for
employment
FI EA CRM GOV HR ITSM MM PM Travel Total
Wave 1 6 3 1 1 2 3 2 18
Wave 2+ 13 6 1 17 - 2 24 3 66
Potential 359
Wave 1 deploys 18 FIORI apps in March 2019
Some FIORI deployments
Where to next