Hebron Asset Development Presentation Contentssbruneau/research/energy/hebron.pdf · Presentation...
Transcript of Hebron Asset Development Presentation Contentssbruneau/research/energy/hebron.pdf · Presentation...
North Atlantic Pipeline Partners, L.P. in cooperation with
Aker Maritime ASA and Peter Kiewit and Sons
Aug 2000 Presentation of:
Hebron Asset Development Conceptsfor
Chevron Canada Resources
Presentation Contents1 Introduction
Team Strengths, Objectives, Hebron Asset Challenges,Criteria for Concept Development
2 Development Concepts
3 GBS Design Details
4 Construction Schedules and Costs
5 Gas Hub Concept
6 Key Issues and GBS Advantages
7 Way Forward
Hebron Asset Development
Team Strengths
Hebron Asset Development
Experience in financing, constructing, owning andoperating offshore pipelines and platforms
World leaders in GBS engineering, construction andinstallation
World class in platform topsides engineering,construction and installation
Broad experience in lump sum EPCI deliveries
Local knowledge and Bull Arm construction and Unionexperience
ObjectivesToday:
To present a development concept which addresses the uniqueenvironmental and reservoir challenges of Hebron/Ben Nevis whilemaximizing commercial value and meeting the socio-economicexpectations of the region.
Short Term:
To provide a lump sum EPCI solution to construct GBS platforms forthe Hebron/Ben Nevis development.
Long Term:
To provide an opportunity for NAPP to establish a host facility for itsGrand Banks gas gathering and pipeline strategy.
Hebron Asset Development
NAPP’s Understanding of the HebronAsset Challenges• Significant portion of resource is heavy oil
• Flow assurance/well intervention
• High well counts
• Artificial lift requirement
• Icebergs, sea ice, wind, waves
• Achieving competitive capital costs
• Maximizing operating efficiencies
Hebron Asset Development
Criteria for Development Concepts
• At least two drill centres required to access reservoirs
• Fixed platform drilling required to minimize drilling cost and provide operational flexibility
• Accelerated drilling required to achieve acceptable production ramp up
• Provide oil storage capabilities
• Provide flexibility for future field and basin developments
Hebron Asset Development
- Development Concepts -
Hebron Asset Development Hebron Asset DevelopmentProduction, Storage and Drilling Arrangement Concepts
Concept 1: Production, storage anddrilling GBS at Hebron, similar at BenNevis with fewer slots and more risersfor gas hub function
Concept 2: Large Production, storageand drilling GBS at Hebron, small well-head and riser GBS gas hub at BenNevis
Concept 3: Small wellhead GBS atHebron, small wellhead and riser GBSgas hub at Ben Nevis, storage andproduction on FPSO
Ben NevisHebron
Ben NevisHebron
Hebron Ben Nevis
Hebron Asset DevelopmentProduction, Storage and Drilling Arrangement Concepts
Concept Location StructureProduction
FacilityDrilling
rigs QuartersStorage mmbo
Topside* weight t
Hebron GBS yes 2 yes 1.1 25000Ben Nevis GBS yes 1 or 2 yes 1.1 25000
Hebron GBS yes 2 yes 1.1 35000Ben Nevis GBS no 1 or 2 yes no 12000
Hebron GBS no 2 yes no 12000Ben Nevis GBS no 1 or 2 yes no 12000
Field centre FPSO yes - yes 0.8 - 0.9 n/a3
2
1
*Topside weight capability at towout
Concept 1 - Two GBSs with Oil Storage
Terra Nova
Springdale
Hebron In Field Lines
STL Tanker Offloading
Hebron GBSOil Platform50 slots, 2 rigs, 1.1 mmbo
Ben NevisGBS Hub30 slots, 1 or 2 rigs,
20+risers, 1.1 mmbo
View of the GBSPDQRS Hub
Hebron Asset Development
Oil lines tostorage
cells.
Oil pumpcasings
Water pumpcasings
Platformwells
Flowlinesto/from
satellites
Access toutility shaft
Conductorguides
Concept 1: Ben Nevis
PDQRS Hub 25kt
Vertical section ofconcrete structure
Hebron Asset Development
Concept 1:Ben Nevis
PDQRS Hub25kt
Horizontalsection ofconcretestructure
Hebron Asset Development
Concept 1:Ben Nevis
95m PDQRS 25kt,Shaft outfittingSection throughshaft
J-Tubes (typ) 23 off
Platform wells (typ)30off
Hebron Asset Development
Concept 1:Ben Nevis
Key figures concrete GBS 95m PDQRS HubHebron Asset Development
Tops ide weight at tow-to f ie ld and ins ta l la t ion 25 ,000 tonnesOil storage volume (avai lable net) 1.1 mi l l BBLSWater depth 95mWave load cr i ter ia , Wave height 100 year Associated wave per iod Horizontal force Over turn ing moment
30m16-19 seconds
1,035 MN28,500 MNm
Iceberg loading 10,000 year impact force on ice-wal l Over turn ing moment 10,000 year impact force on shaft
1,200 MN80,000 MNm
135 MNSoi l parameters : Assumed dense to medium dense sand poss ib lyover laying layer of over-consol idated clay.Concrete Grade (cube strength) Volume of structural concrete Volume of non-structural concrete (est imate only)
70MPa110,630 m
3
4 ,000m3
Reinforc ing steel Grade 500 (500 MPa yield strength) 29 ,100 tonnesPost- tens ion ing cab les Grade 270 (1670 MPa) 4,200 tonnesUnder-base grout ing (~0.5m thickness) 3 ,700m
3
Sol id bal last f i l led inshore ( iron ore, saturated densi ty 3.3t/m3) 38 ,200m
3
Base area ( diameter 102 m)Area of caisson (equiv. diameter 92 m)Height of caisson above sea-bedTotal height of concrete structure above seabed
8 ,171 m2
6 ,648 m2
68.0 m120. 0m
On-bot tom weight Maximum (no o i l in the s torage) Minimum ( o i l s torage ful l )
3,300 MN3,000 MN
Draft at tow-out from dry-dockDraft at tow to fieldDisplacement when tow to f ieldMetacentr ic height(GM) when tow to f ie ld
15m90-100 m
480,000 tonnes~2 m
Concept 1:Ben Nevis
95m PDQS 25kt,Shaft outfittingSection throughshaft
Platform wells (typ)50off
Hebron Asset Development
Concept 1:Hebron
Key figuresconcreteGBS 95m
PDQS Hub
Hebron Asset DevelopmentTopside weight at tow-to field and installation 25,000 tonnesOil storage volume (available net) 1.1 mil l BBLSWater depth 95mWave load criteria, Wave height 100 year Associated wave period Horizontal force Overturning moment
30m16-19 seconds
1 ,035 MN28,500 MNm
Iceberg loading 10,000 year impact force on ice-wall Overturning moment 10,000 year impact force on shaft
1 ,200 MN80,000 MNm
135 MNSoil parameters: Assumed dense to medium dense sand possiblyoverlaying layer of over-consolidated clay.Concrete Grade (cube strength) Volume of structural concrete Volume of non-structural concrete (estimate only)
70MPa110,630 m
3
4,000m3
Reinforcing steel Grade 500 (500 MPa yield strength) 29,100 tonnesPost-tensioning cables Grade 270 (1670 MPa) 4,200 tonnesUnder-base grouting (~0.5m thickness) 3,700m
3
Solid ballast fil led inshore (iron ore, saturated density 3.3t/m3) 38,200m
3
Base area ( diameter 102 m)Area of caisson (equiv. diameter 92 m)Height of caisson above sea-bedTotal height of concrete structure above seabed
8,171 m2
6,648 m2
68.0 m120. 0m
On-bottom weight Maximum (no oi l in the storage) Minimum ( oil storage full )
3 ,300 MN3,000 MN
Draft at tow-out from dry-dockDraft at tow to fieldDisplacement when tow to fieldMetacentric height(GM) when tow to field
15m90-100 m
480,000 tonnes~2 m
Concept 1:Hebron
Terra
Nov
a
Spr
ingd
ale
Hebron
In Field Lines
STL Tanker Offloading
Hebron GBSOil Platform50 slots, 2 rigs, 1.1 mmbo
Ben Nevis GBSWellhead Hub
30 slots, 1 rig, 34 risers, 23 J-tubes
Concept 2 - One Drilling, Production and Storage GBS andOne Smaller Drilling GBS
View ofconcrete
GBS
DQR Hub12Kt
Hebron Asset Development
Concept 2:Ben Nevis
DQR Hub12kt
Verticalsection ofconcretestructure
Hebron Asset Development
Concept 2:Ben Nevis
DQR Hub 12ktHorizontalsection ofconcretestructure
Hebron Asset Development
Concept 2:Ben Nevis
95m DQR 12kt,Shaft outfittingSection throughshaft
J-Tubes (typ) 23 off
Platform wells (typ)30off
Hebron Asset Development
Concept 2:Ben Nevis
Key figuresconcrete GBS95m DQR Hub
scenario 2
Hebron Asset DevelopmentTopside weight at tow-to field and installation 12,000 tonnesOil storage volume (available net) N/AWater depth 95mWave load criteria, Wave height 100 year Associated wave period Horizontal force Overturning moment
30m16-19 seconds
735 MN21,000 MNm
Iceberg loading 10,000 year impact force on ice-wall 10,000 year overturning moment 10,000 year impact force on shaft
1,160 MN63,000 MNm
135 MNSoil parameters: Assumed dense to medium dense sand possiblyoverlaying layer of over-consolidated clay.Concrete Grade (cube strength) Volume of structural concrete Volume of non-structural concrete (estimate only)
70MPa72,070 m3
4,000m3
Reinforcing steel Grade 500 (500 MPa yield strength) 19,000 tonnesPost-tensioning cables Grade 270 (1670 MPa) 2,660 tonnesUnder-base grouting (~0.5m thickness) 3,050m3
Solid ballast filled inshore (iron ore, saturated density 3.3t/m3) 26,060m3
Base area ( diameter 93 m)Area of caisson (equivalent diameter 78m)Height of caisson above sea-bedTotal height of concrete structure above seabed
6,793 m2
4,778 m2
58.0 m120. 0m
On-bottom weight 2,080 MNDraft at tow-out from dry-dockDraft at tow to fieldDisplacement when tow to fieldMetacentric height(GM) when tow to field
15m90-100 m
320,000 tonnes~2.5 m
Concept 2:Ben Nevis
95m PDQS 35kt,Shaft outfittingSection throughshaft
Platform wells (typ)50off
Hebron Asset Development
Concept 2:Hebron
Key FiguresConcrete GBS95m PDQSPlatform
Hebron Asset DevelopmentTopside weight at tow-to field and installation 35,000Oil storage volume (available net) 1,15 mill. BBLSWater depth 95mWave load criteria, Wave height 100 year Associated wave period Horizontal force Overturning moment
30m16-19 seconds
1,320 MN35,000 MNm
Iceberg loading 10,000 year impact force on ice-wall 10,000 year Overturning moment 10,000 year impact force on shaft
1,250 MN84,000 MNm
135 MNSoil parameters: Assumed dense to medium dense sand possiblyoverlaying layer of over-consolidated clay.Concrete Grade (cube strength) Volume of structural concrete Volume of non-structural concrete (estimate only)
70MPa127,430 m3
5,000m3
Reinforcing steel Grade 500 (500 MPa yield strength) 34,000 tonnesPost-tensioning cables Grade 270 (1670 MPa) 5,000 tonnesUnder-base grouting (~0.5m thickness) 4,600m3
Solid ballast filled inshore (iron ore, saturated density 3.3t/m3) 67,000m3
Base area ( diameter 114m )Area of caisson (equivalent diameter 106.17m)Height of caisson above sea-bedTotal height of concrete structure above seabed
10,207 m2
8,853 m2
68.0 m120. 0m
On-bottom weight 4,300 MNDraft at tow-out from dry-dockDraft at tow to fieldDisplacement when tow to fieldMetacentric height(GM) when tow to field
15m90-100 m
635,000 tonnes~2-2.5 m
Concept 2:Hebron
Hebron In Field LinesHebron GBSWellhead Platform50 slots, 2 rigs
Ben Nevis GBSWellhead Hub30 slots, 1 rig, 34 risers, 23 J-Tubes
Concept 3 - Two Wellhead GBSs with FPSO
Hebron Asset FPSO
Offloading Tanker
View ofconcrete
GBS
DQ Hub12Kt
Hebron Asset Development
Concept 3:Hebron
95m DQ 12kt,Shaft outfittingSection throughshaft
Platform wells (typ)50off
Hebron Asset Development
Concept 3:Hebron
Key figures concreteGBS 95m DQ
Hebron Asset DevelopmentTopside weight at tow-to field and installation 12,000 tonnesOil storage volume (available net) N/AWater depth 95mWave load criteria, Wave height 100 year Associated wave period Horizontal force Overturning moment
30m16-19 seconds
735 MN21,000 MNm
Iceberg loading 10,000 year impact force on ice-wall 10,000 year overturning moment 10,000 year impact force on shaft
1,160 MN63,000 MNm
135 MNSoil parameters: Assumed dense to medium dense sand possiblyoverlaying layer of over-consolidated clay.Concrete Grade (cube strength) Volume of structural concrete Volume of non-structural concrete (estimate only)
70MPa70,070 m3
1,000m3
Reinforcing steel Grade 500 (500 MPa yield strength) 18,400 tonnesPost-tensioning cables Grade 270 (1670 MPa) 2,660 tonnesUnder-base grouting (~0.5m thickness) 3,050m3
Solid ballast filled inshore (iron ore, saturated density 3.3t/m3) 26,060m3
Base area ( diameter 93 m)Area of caisson (equivalent diameter 78m)Height of caisson above sea-bedTotal height of concrete structure above seabed
6,793 m2
4,778 m2
58.0 m120. 0m
On-bottom weight 2,080 MNDraft at tow-out from dry-dockDraft at tow to fieldDisplacement when tow to fieldMetacentric height(GM) when tow to field
15m90-100 m
320,000 tonnes~2.5 m
Concept 3:Hebron
View ofconcrete GBS
DQR Hub12Kt
Hebron Asset Development
Concept 3:Ben Nevis
95m DQR 12kt,Shaft outfittingSection throughshaft
J-Tubes (typ) 23 off
Platform wells (typ)30off
Hebron Asset Development
Concept 3:Ben Nevis - GBS Design Details -
Hebron Asset Development
Hebron/Ben Nevis GBSCompleted Design Activities• Iceberg load assessment• Environmental load analysis• Weight and stability analysis• Geotechnical stability evaluation• Finite element analysis (iceberg loads only)• Structural design checks to verify the dimensions
and assess reinforcement intensities
Hebron Asset Development
Global Loads on Hebron and Ben Nevis Structures with Annual Probability of 10-4.
PARAMETER HEBRON BEN NEVIS Base Load 1258 MN 1141 MN Shaft Load 135 MN 135 MN Roof Load 130 MN 100 MN Overturning Moment on base 84 GN?m 77 GN?m Torsional Moment on base 7 GN?m 4 GN?m
Parameters used in Hebron and Ben Nevis runs.
PARAMETER WHITEROSE VALUE
HEBRON VALUE BEN NEVIS VALUE
IBPerDegree 0.97 0.60 0.60 DraftMax 131 105 105 WaterDepth 121 95 95 uEffWidth 70.6 63.7 63.7 BaseDiameter 106 106 70 BaseDepth 20 24 24 Definitions: IBPerDegree: Iceberg aerial density (per degree). DraftMax: Draft cut -off for impacting icebergs (m). WaterDepth: Water depth (m). uEffWidth: Mean effective width of icebergs (m). BaseDiameter: Diameter of GBS base (m). BaseDepth: Depth below water to the top of the base (m).
IcebergLoads:Hebron GBS& Ben NevisGBS
Site conditions and ice loads basis• Ice load 10,000 year condition: Ben Nevis PDQRS (dia~92m) H=1200 MN M=80,000MNm Ben Nevis DQR (dia~78m) H=1160 MN M=63,000MNm Hebron PDQsS (dia 106m) H=1250MN M=84,000MNm• Environmental condition: 100 year wave, Hmax=30m, T=16-19 sec• Soil condition Assumed dense to medium dense sand
Hebron Asset Development
H
M
Hmax
Event Return period Obtained material coefficient
Required material coefficient
Ultimate Limit State Accidental Limit State
100 year 10 000 year
1.34 1.08
1.25 1.0
StructuralAnalysessummary
Diffraction wave load analysis (WADAM)
FEM analysis (SESAM)
Foundation stability (CAP)
Hebron Asset Development
- Construction Schedulesand Costs -
Hebron Asset Development Hebron Asset DevelopmentCombined Schedule Concept 1
ID Task Name Dur.1 Contract Award 0,67 days
2
3 CONCRETE GBS - 25.000 tons Topside 859,68 days
4 Engineering Prior to start Construction 180 edays
5 Procurement and Work Preparation 600 days
6 Detail Engineering 650 edays
7 Engineering Follow On 140 days
8 Site and Dry Dock Mobilization 83,33 days
9 DRY DOCK CONSTRUCTION PHASE 243,33 days
101 FLOOD DOCK, TOW TO DEEP WATER SITE 53,09 days
110 DEEP WATER SITE CONSTRUCTION PHASE 368,92 days
197 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
207 OFFSHORE PHASE 39,99 days
214 INSTALLATION COMPLETED 0 days
215 dummy 1 day
216 CONCRETE GBS - 25.000 tons Topside - GASHUB 904,05 days
217 Engineering Prior to start Construction 181 edays
218 Procurement and Work Preparation 600 days
219 Detail Engineering 642 days
220 Engineering Follow On 101 days
221 Site and Dry Dock Mobilization 83,33 days
222 DRY DOCK CONSTRUCTION PHASE 308,56 days
381 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
390 DEEP WATER SITE CONSTRUCTION PHASE 368,64 days
478 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
488 OFFSHORE PHASE 39,99 days
495 INSTALLATION COMPLETED 0 days
01.01
01.10
19.01
Qtr 1 Qtr 2Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Y e a r 1 Y e a r 2 Y e a r 3 Y e a r 4 Y e a r 5 Y eID Task Name Dur.
1 Contract Award 0,67 days
2
3 CONCRETE GBS - 25.000 tons Topside 859,68 days
4 Engineering Prior to start Construction 180 edays
5 Procurement and Work Preparation 600 days
6 Detail Engineering 650 edays
7 Engineering Follow On 140 days
8 Site and Dry Dock Mobilization 83,33 days
9 DRY DOCK CONSTRUCTION PHASE 243,33 days
101 FLOOD DOCK, TOW TO DEEP WATER SITE 53,09 days
110 DEEP WATER SITE CONSTRUCTION PHASE 368,92 days
197 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
207 OFFSHORE PHASE 39,99 days
214 INSTALLATION COMPLETED 0 days
215 dummy 1 day
216 CONCRETE GBS - 25.000 tons Topside - GASHUB 904,05 days
217 Engineering Prior to start Construction 181 edays
218 Procurement and Work Preparation 600 days
219 Detail Engineering 642 days
220 Engineering Follow On 101 days
221 Site and Dry Dock Mobilization 83,33 days
222 DRY DOCK CONSTRUCTION PHASE 308,56 days
381 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
390 DEEP WATER SITE CONSTRUCTION PHASE 368,64 days
478 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
488 OFFSHORE PHASE 39,99 days
495 INSTALLATION COMPLETED 0 days
01.01
01.10
19.01
Qtr 1 Qtr 2Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Y e a r 1 Y e a r 2 Y e a r 3 Y e a r 4 Y e a r 5 Y e
Combined Schedule Concept 2ID Task Name Dur.2
3 CONCRETE GBS - 35.000 tons Topside 892,86 days
4 Engineering Prior to start Construction 180 edays
5 Procurement and Work Preparation 600 days
6 Detail Engineering 650 edays
7 Engineering Follow On 178 days
8 Site and Dry Dock Mobilization 83,33 days
9 DRY DOCK CONSTRUCTION PHASE 251 days
113 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
122 DEEP WATER SITE CONSTRUCTION PHASE 396,54 days
217 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
227 OFFSHORE PHASE 40,99 days
234 INSTALLATION COMPLETED 0 days
235 dummy 1 day
236 CONCRETE WELLHEAD GBS - 12.000 tons Topside - GASHUB 807,49 days
237 Engineering Prior to start Construction 181 edays
238 Procurement and Work Preparation 600 days
239 Detail Engineering 550 edays
240 Engineering Follow On 180 days
241 Site and Dry Dock Mobilization 83,33 days
242 DRY DOCK CONSTRUCTION PHASE 292,65 days
401 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
410 DEEP WATER SITE CONSTRUCTION PHASE 270,95 days
480 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
490 OFFSHORE PHASE 40,99 days
497 INSTALLATION COMPLETED 0 days
08.11
29.11
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Y e a r 1 Y e a r 2 Y e a r 3 Y e a r 4 Y e a r 5ID Task Name Dur.
2
3 CONCRETE GBS - 35.000 tons Topside 892,86 days
4 Engineering Prior to start Construction 180 edays
5 Procurement and Work Preparation 600 days
6 Detail Engineering 650 edays
7 Engineering Follow On 178 days
8 Site and Dry Dock Mobilization 83,33 days
9 DRY DOCK CONSTRUCTION PHASE 251 days
113 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
122 DEEP WATER SITE CONSTRUCTION PHASE 396,54 days
217 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
227 OFFSHORE PHASE 40,99 days
234 INSTALLATION COMPLETED 0 days
235 dummy 1 day
236 CONCRETE WELLHEAD GBS - 12.000 tons Topside - GASHUB 807,49 days
237 Engineering Prior to start Construction 181 edays
238 Procurement and Work Preparation 600 days
239 Detail Engineering 550 edays
240 Engineering Follow On 180 days
241 Site and Dry Dock Mobilization 83,33 days
242 DRY DOCK CONSTRUCTION PHASE 292,65 days
401 FLOOD DOCK, TOW TO DEEP WATER SITE 52,98 days
410 DEEP WATER SITE CONSTRUCTION PHASE 270,95 days
480 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
490 OFFSHORE PHASE 40,99 days
497 INSTALLATION COMPLETED 0 days
08.11
29.11
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Y e a r 1 Y e a r 2 Y e a r 3 Y e a r 4 Y e a r 5
Hebron Asset DevelopmentCombined Schedule Concept 3
Hebron Asset DevelopmentID Task Name Dur.
1 Contract Award 0.67 days
2 CONCRETE WELLHEAD GBS - 12.000 tons Topside - DQ 806.86 days
3 Engineering Prior to start Construction 181 edays
4 Procurement and Work Preparation 600 days
5 Detail Engineering 550 edays
6 Engineering Follow On 180 days
7 Site and Dry Dock Mobilization 83.33 days
8 DRY DOCK CONSTRUCTION PHASE 293.57 days
165 FLOOD DOCK, TOW TO DEEP WATER SITE 52.98 days
174 DEEP WATER SITE CONSTRUCTION PHASE 252.37 days
241 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
251 OFFSHORE PHASE 39.99 days
258 INSTALLATION COMPLETED 0 days
259
260 CONCRETE WELLHEAD GBS - 12.000 tons Topside - DQR 806.72 days
261 Engineering Prior to start Construction 181 edays
262 Procurement and Work Preparation 600 days
263 Detail Engineering 550 edays
264 Engineering Follow On 180 days
265 Site and Dry Dock Mobilization 83.33 days
266 DRY DOCK CONSTRUCTION PHASE 292.88 days
425 FLOOD DOCK, TOW TO DEEP WATER SITE 53.98 days
434 DEEP WATER SITE CONSTRUCTION PHASE 269.32 days
504 TEST RUN\DECK MATING\INSHORE HOOK UP 115 days
514 OFFSHORE PHASE 39.99 days
521 INSTALLATION COMPLETED 0 days
1/1
7/29
8/31
Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1Y e a r 1 Y e a r 2 Y e a r 3 Y e a r 4
Summary of Requirements and Results
Parameters PDQRS 95m 25kt
DQR 95m 12kt
PDQS 95m 25kt
PDQS 95m 35kt
DQ 95 m 12kt
Requirements: Water depth 95m 95m 95m 95m 95m Topside load at tow to field 25,000 t 12,000 t 25,000 t 35,000 t 12,000 t Oil storage (net) (million bbl) 1.1 0 1.1 1.15 2.0 Number of well slots 30 30 50 50 50 Number of risers & J-tubes 57 56 4 5 4 Main Quantities and Results: Concrete volume (net) (m³) 110,000 72,000 110,000 127,500 72,000 Inshore solid ballast (m³) 38,200 26,000 38,200 67,000 26,000 GBS Outfitting (MTO) (t) 3,700 3,300 2,340 2,420 2,168 Estimated cost (mill US $) 326 237 311 352 223 Construction duration (months) 26 22 24 26 22
Hebron Asset Development
Concept 1 Concept 2,3 Concept 1 Concept 2 Concept 3
Ben Nevis Ben Nevis Hebron Hebron Hebron
Potential for cost reduction with ‘close series’ construction
• Management - man-hours 10 %
• Engineering man-hours 5 %
• Labour man-hours 15 %
• Mechanical Outfitting man-hours 5 %
• Facilities cost 10 %
• Marine Operations cost 5 %
Project cost reduction potentialProject cost reduction potential 7 - 12 %7 - 12 %
Hebron Asset Development
- Gas Hub Concept -
Hebron Asset Development
Gas HubConcept
RegionalPlan
Hebron Asset Development
Grand Banks Pipeline DevelopmentBen Nevis Gas Hub Concept
48o 00’
EL 1025
46o 30’
48o 30’Trave
Fortune
SouthMara
North BenNevis
Ben Nevis
West Bonne Bay
HiberniaGBS
Terra NovaFPSO
30 inch 635 kmexport pipeline
to Bull Arm
12 inch 28 km
8 inch 11 km
12 inc
h 45 k
m
HebronGBS
White Rose
Ben NevisGBS
N
Tanker Offloading
Hebron In f ieldHebron In f ield
E. Rankin
Terra NovaSpringdale
Hibernia1
Mara/S.Mara/Nautilus
Export RiserExport Riser
Export Riser
Fortune
TrepasseyAmethyst
White Rose
TraveNorth Dana
“Future” JTubes
Hibernia2
N.Ben Nevis
Hebron In f ield
S.Tempest
N
Export Riser
Cape Race
“Future” J Tubes
Ben Nevis Hub:Riser and J-Tube Sizes
RisersHydrocarbons Water injection
Diameter Diameterinches inches
North Dana 20 12Trave 12 10South Tempest 12 10Trepassey 10 8Amethyst 10 8Cape Race 10 8North Ben Nevis 10 8Fortune 10 8Springdale 10 8E. Rankin 10 8Mara/S.Mara/Nautilus 10 8Hebron in-field 2 @ 14 14Oil Loading 20
OtherHibernia 2 @ 12Terra Nova 8White Rose 12
Gas Export 2 @ 30
Oil Export 2 @ 24
Total number of risers = 22 12
J - TubesKnown 11 @ 11"Future 10 @ 18"
2 @ 24"
Conductors Total 30 @ 30"
- GBS Key Issues -
and
- GBS Advantages -
Hebron Asset Development Hebron Asset Development
Key Issues
~ Capital Cost
~ Construction Time
~ Ramp up to Full Production
~ Abandonment
~ Capital Cost1. Cost efficient GBS design
2. Utilization of existing Bull Arm facilitiesand equipment
3. Contract available for GBS on lump sumEPCI basis
Hebron Asset Development
Key Issues
~ Capital Cost
~ Construction Time
~ Ramp up to Full Production
~ Abandonment
Construction Time Efficiency accomplished through:
1. Simplified construction driven design
2. Maximum use of well established slipforming techniques
3. Moderate rebar density
4. Full Union/Trades cooperation through incentives
Hebron Asset Development
Key Issues
~ Capital Cost
~ Construction Time
~ Ramp up to Full Production
~ Abandonment
~ Ramp up to full Production1. Provides for two drill centres
2. First platform, 2 drill rigs; second platform, one ortwo drill rigs
3. Potential for advance drilling at one or both centres prior to production facility arrival
Hebron Asset Development
Key Issues
~ Capital Cost
~ Construction Time
~ Ramp up to Full Production
~ Abandonment
~ Cost of Abandonment1. GBS design provides for decommissioning
2. No offshore ballast simplifies abandonment
3. North Sea GBS abandonment costs and procedures developed
Hebron Asset Development
Key Issues
~ Capital Cost
~ Construction Time
~ Ramp up to Full Production
~ Abandonment
GBS Advantages~ Dry wellheads
~ No complex turret system
~ Ice resistance
~ Reduced well construction cost
~ Longer extended reach and more complex wells possible
~ Enhanced well intervention capabilities with lower OPEX
~ Facilitation of artificial lift
~ Higher processing facility uptime
~ Capability of topsides capacity expansion
~ Reduced flow assurance risks
~ Can accommodate large number of Risers/J-tubes and export pipelines
Hebron Asset Development
- Way Forward -
Hebron Asset Development
Way Forward~ Refine depletion plan economics
~ Site geotechnical work - select preferred option
~ Develop commercial proposal
1/ Construction• Lump sum construction contract
• Joint venture construction/shared risk
2/ Ownership of Facilities• Lease purchase arrangement?
• Joint or separate ownership?
• Separate arrangements for each platform?
Hebron Asset Development
End of Presentation
August, 2000
Hebron Asset
HebronAsset
RegionalPerspective
Hebron Asset Development
Hibernia
Jeanne D’Arc
Avalon
Ben Nevis
Hebron Field West Ben Nevis Field
Ben Nevis Field
Hebron AssetDescription
Jeanne d’Arc Lithostratigraphy
Heavier Oil
Lighter Oil
GBS
GBS
Hebron:
Ben Nevis Horizon - 27 wells
Hibernia Horizon - 7 wells
Jeanne d’Arc Horizon - 12 wells
Total = 46 wells
Includes Injectors
West Ben Nevis
Ben Nevis/Avalon Horizons - 7 wells
Ben Nevis
Ben Nevis Horizon = 21Hebron andBen Nevis GBSLocationPossibilities
Ben Nevis Hub
Intra Field Lines
Iceberg Scour Risks
White Rose
Terra Nova
Hibernia
Hebron Ben Nevis
Annual Iceberg Contact Frequency Vs
Pipeline Exposure
0
0.1
0.2
0.3
0.4
0.5
0.6
0 0.2 0.4 0.6 0.8 1Top of Pipe Above Seabed (m)
Ann
ual I
cebe
rg C
onta
ct
Freq
uenc
y
Hebron
Terra NovaHibernia
White Rose
Ben Nevis Gas Hub - Jeanne D'Arc Intra Field Lines
Hebron Terra Nova Hibernia White RoseLabel Number 200 202 203 201Length 11.1 km 15.3 km 35.6 km 36.8 kmSimulation period 5000 yrs 5000 yrs 5000 yrs 5000 yrs
Ben Nevis to