Completion Report Project Number: 28212 Loan Number: 1922 August 2014 People’s Republic of China: Hebei Zhanghewan Pumped Storage Project This document is being disclosed to the public in accordance with ADB’s Public Communications 2011.

Transcript of Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project...

Page 1: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Completion Report

Project Number: 28212 Loan Number: 1922 August 2014

People’s Republic of China: Hebei Zhanghewan

Pumped Storage Project This document is being disclosed to the public in accordance with ADB’s Public Communications 2011.

Page 2: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

CURRENCY EQUIVALENTS

Currency Unit – yuan (CNY)

At Appraisal At Project Completion 18 October 2002 01 December 2013

CNY1.00 = $0.1208 $0.1645 $1.00 = CNY8.2767 CNY6.0773

ABBREVIATIONS

ADB – Asian Development Bank EIA

EIRR EMP FIRR HEPC HPG HSPG LARP O&M PCR PRC PSH SEIA SGCC WACC ZPSC ZPSHPP

– – – – – – – – – – – – – – – –

environmental impact assessment economic internal rate of return environmental management plan financial internal rate of return Hebei Electric Power Corporation Hebei Provincial Government Hebei South Power Grid land acquisition and resettlement plan operation and maintenance project completion review People’s Republic of China pumped storage hydropower summary environmental impact assessment State Grid Corporation of China weighted average cost of capital Zhanghewan Pumped Storage Company Zhanghewan Pumped Storage Hydro Power Plant

Page 3: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

WEIGHTS AND MEASURES

ha km kV m m3 MW t TWh V

– – – – – – – – –

hectare kilometer kilovolt (1,000 volts) meter cubic meter megawatt (1 million watts) ton terawatt-hour volt

NOTE

In this report, “$” refers to US dollars and “ton” refers to metric ton.

For an explanation of rating descriptions used in ADB evaluation reports, see: ADB. 2006. Guidelines for Preparing Performance Evaluation Reports for Public Sector Operations. Manila.

Page 4: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Vice-President S. Groff, Operations 2 Director General A. Konishi, East Asia Department (EARD) Director A. Bhargava, Energy Division, EARD Team leader P. Perera, Principal Energy Specialist, EARD

Team members N.W. Kim, Environment Specialist, EARD

W.Y. Lee, Energy Specialist, EARD D. Molina, Operations Assistant, EARD T. Oi, Senior Energy Specialist, EARD

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 5: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

CONTENTS

Page

BASIC DATA ii

I. PROJECT DESCRIPTION 1

II. EVALUATION OF DESIGN AND IMPLEMENTATION

A. Relevance of Design and Formulation 1

B. Project Outputs 3

C. Project Cost 5

D. Disbursements 6

E. Project Schedule 6

F. Implementation Arrangements 6

G. Conditions and Covenants 7

H. Consultant Recruitment and Procurement 8

I. Performance of Consultants, Contractors, and Suppliers 8

J. Performance of the Borrower and the Executing Agency 8

K. Performance of the Asian Development Bank 9

III. EVALUATION OF PERFORMANCE

A. Relevance 9

B. Effectiveness in Achieving Outcome 10

C. Efficiency in Achieving Outcome and Outputs 10

D. Preliminary Assessment of Sustainability 11

E. Impact 12

IV. OVERALL ASSESSMENT AND RECOMMENDATIONS

A. Overall Assessment 13

B. Lessons 13

C. Recommendations 15

APPENDIXES

1. Project Framework 16 2. Project Cost and Financing Plan 19 3. Cost Breakdown, by Project Component 20 4. Projected and Actual Disbursement 21 5. Project Implementation Schedule 22 6. Chronology of Main Events 23 7. Status of Compliance with Loan Covenants 25 8. ADB-Financed Contract Packages 31 9. Economic Reevaluation 32 10. Financial Reevaluation 37 11. Environmental Impact Assessment 42 12. Implementation of Land Acquisition and Resettlement Plan and Other Social Benefits 61 13. Quantitative Assessment of Overall Project Performance 71

Page 6: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

BASIC DATA

A. Loan Identification 1. Country 2. Loan Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Project Completion Report Number

People’s Republic of China 1922–PRC Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9 million net of cancellation) PCR:PRC 1469

B. Loan Data

1. Appraisal – Date Started – Date Completed 2. Loan Negotiations – Date Started – Date Completed 3. Date of Board Approval 4. Date of Loan Agreement

5. Date of Loan Effectiveness – In Loan Agreement – Actual – Number of Extensions 6. Closing Date – In Loan Agreement – Actual – Number of Extensions 7. Terms of Loan – Interest Rate – Maturity (number of years) – Grace Period (number of years) – Front-end Fee 8. Terms of Relending – Interest Rate – Maturity (number of years) – Grace Period (number of years) – Second-Step Borrower

25 February 2002 12 March 2002 22 August 2002 22 August 2002 18 October 2002 28 August 2003 28 November 2004 16 January 2004 0 31 December 2009 11 July 2013 2 LIBOR-based 25 7 1.0% LIBOR-based 25 7 Zhanghewan Pumped Storage Company

9. Disbursements a. Dates Initial Disbursement

15 June 2004

Final Disbursement

23 August 2012

Time Interval

99 months

Effective Date

16 January 2004

Original Closing Date

31 December 2009

Time Interval

60 months

Page 7: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

iii

b. Amount ($ million)

Category

Original

Allocation (1)

Amount

Canceled (2)

Last Revised

Allocation (3 = 1-2)

Amount

Disbursed (4)

Undisbursed

Balancea

(5 = 3-4)

A. ADB Loan 01 – Civil Works 18,960,000 (9,540,000) 28,500,000 28,303,708 196,292 02 – Equipment 94,230,000 4,238,000 89,992,000 89,826,410 165,590 03 – Materials 4,710,000 4,710,000 0 0 0 04 – Institutional Strengthening

and Training 1,250,000 455,000 795,000 794,034 966

05 – Consulting Services 2,500,000 1,597,000 903,000 902,852 148 06 – Front End Fee 1,440,000 0 1,440,000 1,440,000 0 07 – Interest and Commitment

Charge 14,680,000 0 14,680,000 14,680,000 0

08 – Unallocated 6,230,000 6,230,000 0 0 0

Total 144,000,000 7,690,000 136,310,000 135,947,004 362,996 a An undisbursed amount of $362,996 was cancelled when the loan was financially closed on 11 July 2013.

( ) = negative.

10. Local Costs (Asian Development Bank-Financed) - Amount ($ million) 0 - Percentage of Local Costs 0% - Percentage of Total Cost 0%

C. Project Data

1. Project Cost ($ million) Cost Appraisal Estimate Actual

Foreign Exchange Cost 165.3 136.0 Local Currency Cost 609.6 765.9 Total 774.9 901.9

Page 8: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

iv

2. Financing Plan ($ million)

Cost Appraisal Estimate

Actual

A. Loan

Asian Development Bank 144.0 135.9

China Development Bank 275.8 251.7

Agriculture Bank of China 117.3

Shareholder’s Loan 108.6

Subtotal (A) 537.1 496.2

B. Equity

Hebei Electric Power Corporation 135.7 191.2a

Hebei Construction & Investment Company 72.8 73.7

Xinyuan Company 83.5

Local Government 29.3 57.3

Subtotal (B) 237.8 405.7

Total 774.9 901.9 a

includes $184.0 million spent on rural electrification and $7.4 million equity investment in Zhanghewan Pumped Storage Hydro Power Plant.

3. Cost Breakdown by Project Component ($ million)

Component Appraisal Estimate Actual

A. Base Costs

1. Pumped Storage Power Planta

438.7 625.6

2. Rural Electrification 135.5 184.6 3. Closure of Coal-fired Power Plants 1.4 0.8 4. Afforestation 1.6 2.2 5. Institutional Strengthening 12.9 17.7 6. Irrigation 10.6 14.5 Subtotal (A) 600.7 845.4 B. Capacity Building 1. Consulting Service 0.9 Subtotal (B) 0.9 C. Contingencies 1. Physical Contingencies 58.4 2. Price Contingencies Systems 58.7 Subtotal (C) 117.1 D. Financial Charges during Development 57.1 55.6

Total 774.9 901.9 a Includes land acquisition and resettlement cost estimated at CNY150.6 million at appraisal but actual land

acquisition and resettlement cost was CNY289.8 million.

Page 9: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

v

4. Project Schedule

Item Appraisal Estimate Actual

Date of Contract with Consultants

Sep 2002

Feb 2004

Completion of Engineering Designs Aug 2002 Aug 2002 Civil Works Contract Date of Award Jun 2005 June 2003 Completion of Work Dec 2007 Jul 2008 Equipment and Supplies First Procurement Dec 2003 Feb 2004 Last Procurement Mar 2007 Sep 2005 Completion of Equipment Installation Mar 2008 June 2009 Start of Operations Completion of Tests and Commissioning Jun 2009 Feb 2009

5. Project Performance Report Ratings

Implementation Period

Ratings

Development Objectives Implementation Progress

From 18 Oct 2002 to 31 Dec 2002 Satisfactory Satisfactory From 01 Jan 2003 to 31 Dec 2003 Satisfactory Unsatisfactory From 01 Jan 2004 to 31 Dec 2004 Satisfactory Highly Satisfactory From 01 Jan 2005 to 31 Dec 2005 Satisfactory Highly Satisfactory From 01 Jan 2006 to 31 Dec 2006 Satisfactory Highly Satisfactory From 01 Jan 2007 to 31 Dec 2007 Satisfactory Satisfactory From 01 Jan 2008 to 31 Dec 2008 From 01 Jan 2009 to 31 Dec 2009 From 01 Jan 2010 to 31 Dec 2010 From 01 Jan 2011 to 31 Dec 2011 From 01 Jan 2012 to 31 Dec 2012

Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Satisfactory Satisfactory Highly Satisfactory Highly Satisfactory Highly Satisfactory

From 01 Jan 2013 to 11 Jul 2013 Satisfactory Highly Satisfactory

D. Data on Asian Development Bank Missions

Name of Mission

Date No. of Persons

No. of Person-Days

Specialization of Members

Loan Fact finding a

Loan Inception Loan Review 1 Loan Review 2 Loan Review 3 Loan Review 4 Loan Review 5 Loan Review 6 Loan Review 6 Loan Review 7 Loan Review 8 Loan Review 9 Project completion review

25 Feb–12 Mar 2002 21–23 Dec 2003 13–17 Dec 2004 09–17 May 2005 12–17 Apr 2007 26–27 Nov 2007 22–27 Sep 2007 19–20 Oct 2009 27–28 Jul 2010 14 Jul 2011 09–10 Apr 2012 20–23 Mar 2013 26 Feb–04 Mar 2014

4 2 2 1 1 3 1 3 2 2 2 2 4

64 6 10 9 6 6 6 8 4 1 4 6 5

a, c, k, k a, a a, m

a j

d, j, m a

j, k, n j, h j, n

a, m h, n

a,b,h,j a = engineer, b = financial analyst, c = counsel, d = economist, e = procurement consultant or specialist, f = control officer, g = programs officer, h = environment specialist, i = co-financing officer, j = social development specialist, k = energy specialist, l = young professional, m = project analyst, n = consultant. a Waiver of loan appraisal approved during the management review meeting on 28 May 2002.

Page 10: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

I. PROJECT DESCRIPTION 1. Zhanghewan Pumped Storage Hydro Power Plant (ZPSHPP) is located in Hebei Province of the People’s Republic of China (PRC), about 400 kilometers southwest of Beijing. It is connected to Hebei South Power Grid (HSPG) serving the southern part of the Hebei Province.1 At the time of project appraisal, HSPG had insufficient peaking capacity due to an unbalanced generation mix and inadequate transmission interconnections with neighboring provinces.2 These system constraints resulted in poor quality of electricity supply and prolonged load shedding in rural areas in the Hebei Province. 2. Hebei Electric Power Corporation (HEPC) operated old coal-fired power plants with low thermal efficiency and high coal consumption peaking plants. 3 Most of these plants were over 30 years old, had a unit size of less than 50 megawatts (MW), and lacked the peak load regulation capability.4 The project design included the closure of old heavily polluting coal-fired power plants that had been used as peaking plants. Due to inadequate conventional hydropower capacity and the absence of adequate natural gas infrastructure in Hebei Province in the 1990s, the ZPSHPP was conceived to provide peaking capacity to HSPG and to improve the reliability and stability of power supply. 3. Although Hebei Province was rapidly industrializing, with large investments in heavy industries (such as the iron and steel and cement industries) majority of the population lived in rural areas and relied on agriculture at the time of appraisal. HSPG’s service area covered over 23 nationally designated poor counties, including Jingxing County where the ZPSHPP is located. Given the high emphasis on poverty alleviation at the time of approval, the project design included components to improve the reliability and quality of electricity supply to poor rural counties and expansion of the irrigation network to rural farming villages in Jingxing County. The project design also included an afforestation component to improve soil conservation and environmental sustainability of Jingxing County. The project was approved when the government was contemplating a power sector reform program, and it included a separate capacity building component for institutional strengthening of HEPC to support the establishment of a competitive power market in Hebei Province.

II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation 4. At appraisal, the project design was consistent with the government’s energy sector development priorities, which focused on meeting the growing electricity demand in an environmentally sustainable manner by improving the thermal efficiency of the power sector and

1 The service area of Hebei South Power Grid (HSPG) included six out of the 13 prefectures of Hebei Province and

a population of 40 million. HSPG had an installed capacity of 7.25 gigawatts (GW), peak load of 6.33 GW, and annual electricity sales of 43.2 terawatt-hours, at the time of the approval of feasibility study in 1998. Annual electricity sales of HSPG have reached 142 terawatt-hours by 2012 (i.e., growth rate of 8.8% per annum).

2 The peak power shortage in HSPG was estimated to be 1.6 GW in comparison to peak demand of approximately

8.5 GW in 2001. Furthermore, more than 95% of generation capacity in HSPG was provided by inflexible coal-fired power plants. HSPG had limited transmission interconnection capacity with neighboring provinces such as Shanxi and Shandong as well as Hebei North Power grid.

3 Coal consumption was as high as 550 grams/kilowatt-hour compared to 325 grams/kilowatt-hour possible in

modern ultra super critical coal power plants. 4 Coal-fired power plants response to changes in demand is slower compared to gas-fired power plant or pumped-

storage plant.

Page 11: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

2

reducing coal consumption. In addition, the government’s short-term priorities were to improve the reliability of electricity supply and eliminate the peak generation capacity shortage and resultant load shedding.5 The project was designed to meet these objectives by (i) increasing the generation capacity during peak time, (ii) closing old and inefficient coal-fired power plants used for meeting peak demand, and (iii) increasing the utilization of more efficient supercritical coal-fired power plants during off-peak period. Moreover, the project was designed to improve the socioeconomic well-being of the local population in Jingxing County by enhancing the flood protection capacity and irrigation coverage of the existing Zhanghewan reservoir. 5. A capacity building component to enhance the capacity and readiness of HEPC to establish a competitive power market in Hebei Province was included in the project. Although this component was relevant at the time of approval, the central government decided to restrict the unbundling only between generation and grid (including distribution) assets. As a result five generating companies and two grid companies were established. ZPSHPP was transferred to the State Grid Corporation of China (SGCC), which established Xinyuan Company to own and operate pumped storage hydropower (PSH) plant in SGCC’s operating area, including the ZPSHPP.6 As the original scope of the consultancy services was no longer relevant, the budget allocation for institutional reforms was utilized for capacity building of Xinyuan Company and for preparing a strategy for developing PSH plants. 6. The project was aligned with the Asian Development Bank (ADB) country partnership strategy for the PRC, which supported environmentally sustainable and inclusive economic growth. The ZPSHPP financed under the project is consistent with the objective of promoting economic growth in an environmentally sustainable manner by eliminating the peak generation capacity shortage and improving the overall thermal efficiency of HSPG. This has contributed to the reduction of greenhouse gas emissions in the power sector and improvement of the urban environment. 7. Rural electrification and irrigation expansion components were also included in the project to promote social inclusiveness and poverty alleviation. It included loan covenants to eliminate the tariff disparity between urban and rural areas (rural tariffs were higher than urban tariffs) and to provide tariff discounts to poor households. However, the socioeconomic survey conducted at project completion indicated that the irrigation expansion component may not be relevant in the changed socioeconomic conditions in Hebei Province. Significant outward migration of farm laborers to cities and non-farm jobs, caused by increased employment opportunities and relatively poor farm yields in Jingxing County, resulted in reduced water demand for irrigation. 8. The project design included distinct components (i.e., rural electrification and afforestation) to address environmental sustainability, social inclusiveness, and poverty alleviation aspects and to draw and force attention of the relevant government agencies to ensure their timely completion that would enhance development impact of ZPSHPP project. The rural electrification and afforestation activities have been completed as intended, and the government is continuing the afforestation in Jingxing County as part of the national afforestation program.

5 Load shedding is the deliberate shutdown of electric power in parts of the power distribution system, when demand

exceeds the available generation capacity. 6 State Grid Corporation of China is one of the two grid companies after restructuring.

Page 12: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

3

B. Project Outputs 9. The project included six components: (i) pumped storage power plant with associated ZPSHPP and a transmission line connecting the plant to HSPG; (ii) rural electrification in 23 counties in HSPG, consisting of substations and medium-voltage distribution system7 (iii) establishment of a competitive power market and institutional reforms of HEPC; (iv) closure of 20 power generating units of 50 MW or less in five coal-fired power plants totaling 505 MW; (v) expanded irrigation capacity of the Zhanghewan lower reservoir from 1,467 hectares (ha) to 8,167 ha; and (vi) afforestation of 16,330 ha of trees in Jingxing County. Appendix 1 shows the project framework and the actual performance.

1. Zhanghewan Pump Storage Hydro Power Plant 10. The 1,000 MW ZPSHPP consisted of (i) increasing the dam height of the existing Zhanghewan reservoir from 54 meters (m) to 77 m and the live storage capacity from 22 million cubic meters (m3) to 52.5 million m3; (ii) constructing an upper reservoir of 7.85 million m3 at an elevation of 800 m; (iii) excavating two underground caverns to house the turbines or pumps, generators or motors, and the power transformers; (iv) constructing two headrace tunnels of 612 m to connect the upper reservoir to the power station; (v) constructing four tailrace tunnels of 175 m to connect the power station with the lower reservoir; (vi) installing 4 x 250 MW pump and turbine units and the associated motors or generators, transformers, switchyard, and control system; (vii) constructing 63 kilometers single circuit 500 kilovolt (kV) transmission line to connect the ZPSHPP to HSPG; and (viii) providing relocation and livelihood restoration for people affected by project construction. 11. The ZPSHPP was constructed as designed and commissioned in 2009 without any significant delays. Since its commissioning, it has been operating without any major technical issues. It has offered the following services to HSPG: (i) peaking generation capacity; (ii) demand for base load coal-fired power plants during off peak hours (e.g., at night) to enable their operation at rated load and efficiency; and (iii) ancillary services to maintain grid stability. 8 12. The ZPSHPP construction affected 2,878 persons in eight villages mainly as a result of expansion of the surface area of the lower reservoir. In five out of the eight villages, the affected people (664 persons) were resettled within the same village and in the three remaining villages (Beihaoting, Shimen and Nanhaoting Villages); the affected people (2,214 persons) were relocated in newly constructed villages. Residents of Beihaoting Village (343 persons) moved to the newly established Beihaoting Village in December 2007 prior to commissioning of the ZPSHPP. However, the relocation of Shimen Village (229 affected persons) and Nanhaoting Village (1,642 affected persons) was significantly delayed due to the disagreement between the affected people and county government on the location of the resettlement site. The relocation of Shimen Village was completed in December 2010.

7 Refers to 10 kilovolt (kV), 35 kV, and 110 kV.

8 Ancillary services refer to spinning reserve (i.e., generation capacity that can be called up at short notice), load

following capability (i.e., changing the generator output to match changes in demand), frequency regulation (i.e., maintaining the system frequency by instantaneously varying the output), and black start capability (ability to restart the power plant in the event of system collapse).

Page 13: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

4

13. The delay in selecting the resettlement site for Nanhaoting Village resulted in a cost increase of CNY 139 million,9 which was borne by the Zhanghewan Pumped Storage Company, Ltd. (ZPSC). The resettlement of Nanhaoting Village was substantially completed in December 2013 and by the time of the project completion mission in March 2014, 420 out of 438 affected households have been relocated. Jingxing County government expects the remaining 18 households to move to the new village by September 2014 after they have reached agreement on their entitlement to compensation and livelihood support mechanisms. Due to this delay in resettlement, the water level of the lower reservoir could not be raised to the design level of 480 m. Although this has not affected ZPSHPP operations, the irrigation and flood protection benefits of the project could not be fully realized. It is expected that the water level will be raised to 480 m as soon as the outstanding 18 households move to the new village.

2. Rural Electrification

14. Although ADB financing was not allocated to rural electrification, the project included consulting services to improve the poverty targeting and socioeconomic monitoring of the rural electrification network expansion and rehabilitation, financed by the government. Implementation of the rural electrification component was completed in 2005. ADB also has engaged in policy dialogue with the provincial government to remove the tariff disparity between rural and urban areas and to provide tariff discounts to rural poor. Hebei Province has achieved 100% electrification in 2005 and the electricity consumption in rural areas of HSPG increased from 3.3 terawatt-hours (TWh) in 2000 to 5.4 TWh in 2005 and 15.4 TWh in 2013. The residential tariffs in rural areas have been reduced and made equal to urban residential tariffs in 2005. 15. There has been a significant improvement in quality of electricity supply and the consumer satisfaction increased from 47% in 2005 to 72% in 2010 based on the socioeconomic survey financed by ADB in 2010. The other socioeconomic benefits attributed to improved electricity supply in rural areas included increase in (i) industrial activity in the rural areas, (ii) rural residents employed in non-farm activities, and (iii) the use of electricity for irrigation. It can be concluded that rural electrification has contributed to improved quality of life and non-farm income generating opportunities to rural communities.

3. Institutional Reforms and Introduction of Competitive Power Market 16. The project included a capacity building component to prepare HEPC to implement the institutional reforms and establish a competitive power market. Given the reduced scope of the reforms implemented by the government, the scope of capacity building activities were suitably revised as detailed in para 5.

4. Closure of Old, Inefficient, and Polluting Coal-fired Power Plants

17. As the ZPSHPP was to increase the peak generation capacity of HSPG, decommissioning of 505 MW of generation capacity provided by five small coal-fired power plants was included as a project component. Total generation capacity of 671 MW was decommissioned in the designated five power plants during 2006–2010. The government has

9 The original cost estimate for land acquisition and resettlement was CNY150 million and at project completion the

actual cost incurred was CNY289 million.

Page 14: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

5

further strengthened the requirement for decommissioning old coal-fired power plants under the 11th and 12th Five-Year Plans. An aggregate 3,700 MW of old coal-fired generation capacity has been decommissioned in Hebei Province since 2002.

5. Irrigation Improvement

18. This project component was designed to utilize the increased water storage capacity (para 10) of the lower reservoir and to expand the irrigation coverage from 1,467 ha to 8,167 ha, by constructing two additional irrigation canals and expanding the existing Xiyue Canal. This component was to be fully financed by the local government. ZPSC has also entered into legally binding agreements with Jingxing County Water Resource Committee regarding the utilization and sharing of water stored in the lower reservoir. 19. There has been a reduction in the demand for irrigation due to significant decrease in agricultural activities in Jingxing County as a result of outward labor migration for non-farm employment. In addition, the delays in completing the resettlement of Nanhaoting Village reduced the water storage capacity of the lower reservoir. Given the constraints on water release for irrigation and the reduced demand for irrigation, Jingxing County decided to delay implementation of this component. Although with the completion of relocation of Nanhaoting Village in 2014, the storage capacity of the lower reservoir would reach the designed level, due to lack of demand for irrigation and reduced level of agricultural activities in the project area, there are no immediate plans to commence implementation of this component.

6. Afforestation Program

20. This was included as a separate component of the project to ensure timely implementation of the ongoing afforestation program in Jingxing County. It was expected to contribute to the long-term sustainability of the ZPSHPP by reducing soil erosion and improving the lower reservoir watershed protection. It was confirmed that Jingxing County has afforested more than 16,000 ha from 2004–2010 and is continuing the program. C. Project Cost 21. At appraisal, the total project cost for the ZPSHPP and other project components, including contingencies and interest and other loan charges during construction, was estimated at $774.9 million equivalent—$165.3 million in foreign exchange cost (21.3% of the total) and $609.6 million in local currency cost (78.7% of the total).The base cost (excluding contingencies and interest during construction) was estimated to be $600.7 million, including $438.7 million for construction of the ZPSHPP and associated transmission line. There was no cost increase in local currency terms (the actual cost was CNY5,481.0 million compared with the appraisal estimate of CNY6,413.6 million) or in foreign currency cost (actual cost was $135.95 million compared to the appraisal estimate of $165.30 million). The local currency cost though when expressed in US dollar terms, shows a significant increase due to the appreciation of the Chinese Yuan against the US dollar.10 22. The financing plan for the ZPSHPP at appraisal consisted of (i) an ADB loan of $144.0 million (18.6%); (ii) domestic loans of $275.8 million (35.6%) from China Development

10

The US dollar–yuan exchange rate was $1 = CNY6.0773 at the time of project completion and $1 = CNY8.2767 at appraisal.

Page 15: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

6

Bank and $117.3 million (15.1%) from the Agricultural Bank of China; (iii) equity contributions of $135.7 million (17.5%) from Hebei Electricity Company and $72.8 million (9.4%) from Hebei Construction and Investment Company; and (iv) local government financing of $29.3 million (3.8%). However, the financing plan underwent significant changes during project implementation as a result of changes to the power sector reforms (para 28). SGCC, through Xinyuan Company, contributed $83.5 million to the project equity and $108.6 million as a shareholder’s loan at commercial terms. The other major changes were: (i) the $117.3 million loan from the Agricultural Bank of China was not utilized, (ii) HEPC financing was increased to $191.2 million and mainly allocated to the rural electrification component, and (iii) local government financing was increased to $57.3 million. The financing plan is in Appendix 2 and the detailed cost breakdown is in Appendix 3. D. Disbursements 23. The first disbursement under the loan was on 15 June 2004 amounting to $1.64 million for equipment. Due to the large amount of contracts, commitment and direct payment procedures were used to pay for project expenditures. These procedures resulted in efficient disbursements. Total disbursement as of the loan closing date amounted to $135.95 million, or 94.4% of the loan amount of $144.00 million. The loan amount was reduced to $135.95 million after a partial cancellation of $7.69 million in July 2012, and final cancellation of the undisbursed amount of $0.36 million at financial closing. Appendix 4 shows the disbursement projections at appraisal and the actual disbursements. E. Project Schedule 24. The loan and project agreements were signed on 28 August 2003, 10 months after loan approval, and took effect on 16 January 2004, about 5 months after loan signing. Although the project was physically completed in February 2009, the loan closing date was extended twice because of outstanding warranty and retention payments and pending resettlement issues. The loan finally closed on 31 July 2013. Appendix 5 shows the projected and actual implementation schedules for each completed component and Appendix 6 lists a chronology of main events. 25. An initial delay in loan effectiveness did not affect implementation of the ZPSHPP. Construction activities commenced in December 2003 using counterpart funding, and all four generation units of the ZPSHPP were commissioned by February 2009 as scheduled. The electromechanical equipment financed under the ADB loan was delivered to the site as scheduled. However, relocation of the affected villages was significantly delayed and it has not yet been completed. Although this did not affect commercial operations of the ZPSHPP, it delayed the realization of irrigation and flood control benefits expected from the project. Other project components—such as rural electrification, afforestation, and closure of coal-fired power plants—were implemented ahead of the original schedule. F. Implementation Arrangements 26. The executing agency for the project, HEPC, was responsible for overall project coordination and was directly responsible for (i) the rural electrification program, (ii) closure of old power plants, and (iii) the construction and operation and maintenance (O&M) of the 500 kV transmission constructed under the project. ZPSC, the implementing agency, was formally established in August 2002 as a subsidiary of HEPC with direct responsibility for the design, construction, and operation of the ZPSHPP.

Page 16: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

7

27. Although these institutional changes did not affect implementation of the ZPSHPP, as ZPSC retained the responsibility for implementation and operation of the ZPSHPP, the role of HEPC as the executing agency in coordinating different project components was changed as HEPC did not have supervisory control over ZPSC. Nonetheless, construction of the 500 kV transmission line and implementation of the rural electrification component remained the responsibility of HEPC. The coal-fired power plants to be closed were transferred to newly created power generation companies. The closure of old coal-fired power plants was coordinated by Hebei Provincial Government (HPG), and implementation of the afforestation program and resettlement of affected households were undertaken by Jingxing County government in close coordination with ZPSC. G. Conditions and Covenants 28. The loan covenants were generally complied with, particularly the covenants related to financial management and reporting (Appendix 7). Audited project accounts and audited financial statements, quarterly project monitoring reports, and annual environment monitoring reports were submitted regularly. The ZPSHPP was constructed in compliance with applicable environmental regulations, and adverse environmental impacts during project construction and operation were effectively minimized by implementing the mitigation measures in the environmental management plan (EMP). 29. The loan covenants related to the resettlement of affected people required HEPC and ZPSC to ensure the resettlement, compensation, and livelihood restoration of affected people. These covenants were complied with despite significant delays due to the delay in relocating the affected people (para 13). The primary responsibility for resettling the affected people was with the Jingxing County government and the role of ZPSC was limited to making the required financing available. In particular, obtaining the agreement of affected people to move to relocation sites; determining the compensation payments; constructing resettlement villages, taking into account the preferences of affected people; and providing livelihood support was the responsibility of Jingxing County. 30. The negotiations between affected villages and Jingxing County on the proposed resettlement sites, resulted in increased cost of CNY289 million compared to the original estimate of CNY150 million. As a result, there was a delay on the part of ZPSC in allocating additional funds to Jingxing County for the relocation of the affected people. However, after more than 18 months delay, ZPSC agreed to the revised resettlement cost estimate and the new resettlement village was completed in December 2013. The socioeconomic survey of resettled villages confirmed that the affected people have been adequately compensated; their livelihoods restored and living conditions have shown significant improvement. 31. The project agreement required HEPC to implement the power sector reform program based on the agreed recommendation of the consultants recruited under the project for institutional strengthening and power sector restructuring. Furthermore, HEPC was required to implement the tariff reform action plan to be finalized by December 2005 to eliminate the disparity between rural and urban residential tariffs and to provide tariff discounts to the rural poor. In 2005, the responsibility for end user tariff setting was transferred to the Provincial Price Bureau of Hebei Development and Reform Commission and the tariff reform action plan was not prepared. However, the tariff disparity between rural and urban residential consumers was eliminated and rural tariffs were reduced in 2005.

Page 17: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

8

32. The project agreement also required ZPSC and HEPC to enter into a power purchase and sales agreement to govern the commercial arrangement for electricity sales by ZPSC to HEPC and the supply of electricity by HEPC for water pumping. However, this was no longer required as the ZPSHPP is considered part of the transmission network; and the National Development and Reform Commission stipulated that PSH plants should be paid an annuity payment to compensate their capital and operational costs, and the cost of electricity for water pumping should be absorbed by the grid company. In addition, the project agreement contained financial covenants on HEPC to ensure its financial viability as the majority shareholder of ZPSC. As HEPC ceased to be the majority shareholder of ZPSC since 2005, these covenants are no longer relevant. H. Consultant Recruitment and Procurement 33. ADB loan proceeds were used for the procurement of civil works (one international competitive bidding contract package for bituminous lining of upper reservoir), three international competitive bidding contract packages for equipment (electromechanical equipment for the power plant, 500 kV transformers, and 500 kV switch gear) and two consulting contracts (supervision of civil works and electromechanical equipment installation at the ZPSHPP, and institutional strengthening and power sector reform in Hebei Province). Procurement and consultant recruitment were undertaken in accordance with ADB’s Procurement Guidelines and Guidelines on the Use of Consultants, and the contract packages financed by ADB are listed in Appendix 8. 11 The procurement of goods and civil works funded by domestic financing, followed applicable national procurement procedures. 34. The procurement of goods and civil works was carried out in a timely manner, and no major issues or delays occurred in contract awards. The implementation consultants recruited using ADB loan proceeds reviewed the technical specifications for procurement contracts, and ZPSC retained a procurement agent to manage the procurement process. I. Performance of Consultants, Contractors, and Suppliers 35. The performance of contractors and suppliers in undertaking civil works and supplying equipment has been satisfactory for both ADB-financed contract packages as well as for contract packages funded by domestic financing sources. No major delays or instances of unsatisfactory performance by contractors and suppliers occurred. The consultants recruited for project implementation supervision also performed satisfactorily. A change in scope was processed for the consultant services for institutional reforms and power sector reforms, as the original scope of the consulting assignment was not relevant in the context of the government’s decision to limit the reform process to the unbundling of power generation. The consultancy assignment was restructured to provide capacity building to Xinyuan Company in planning, designing, and operating PSH plants. J. Performance of the Borrower and the Executing Agency 36. HPG acting on behalf of the borrower, was responsible for coordinating the implementation of different project components, as the role of the executing agency (HEPC) was limited to implementing the rural electrification component and the transmission line connecting ZPSHPP to HSPG. ZPSC had the direct responsibility for implementing the

11

ADB. 2002. Procurement Guidelines and Guidelines on the Use of Consultants. Manila

Page 18: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

9

ZPSHPP. Different agencies of HPG were responsible for implementing the other components of the project which did not receive ADB loan proceeds. 37. While ZPSC constructed the ZPSHPP within the original schedule, the local government incurred significant delays in finalizing the resettlement sites for the affected people. While the local government’s efforts to reach a mutually acceptable resettlement site are commendable and consistent with ADB’s safeguards policy, the delay in finalizing these resettlement issues resulted in the irrigation and flood control benefits of the project not being fully realized.12 The provincial government also ensured that the implementation of rural electrification, closure of inefficient coal-fired power plants, and afforestation were completed ahead of schedule. Hence, the performance of the borrower and the executing agency is rated satisfactory. The Xinyuan Company, Hebei Construction and Investment Company and other shareholders have provided equity contributions and Xinyuan also mobilized a shareholder’s loan in a timely manner. In addition, co-financing from local banks was also mobilized without any delay. K. Performance of Asian Development Bank 38. ADB’s performance in monitoring the project is satisfactory. Regular project review missions were conducted, and procurement contracts and disbursements were approved without significant delays. ADB also monitored the project components that were not allocated under ADB loan funds. However, some of the indicators included in the Design and Monitoring Framework (DMF) to monitor the poverty alleviation impacts of the project were poorly defined and difficult to monitor. These indicators have not been appropriately adjusted during the project implementation. In particular, ADB closely monitored the resettlement of affected households and encouraged the relevant parties to reach a mutually acceptable solution. ADB also closely monitored the livelihood improvement of affected households after resettlement. ADB revised the scope of the consulting services for institutional reforms when the original scope became irrelevant as a result of the change in government policy for power sector reforms.

III. EVALUATION OF PERFORMANCE A. Relevance 39. The project design was consistent with the government’s energy sector development priorities at the time of project approval, which focused on meeting the growing electricity demand in an environmentally sustainable manner by improving the thermal efficiency of the power sector and reducing the rate of growth in coal consumption. The techno-economic rationale for the ZPSHPP financed under the project remains valid and relevant at project completion, as it is making a significant contribution to maintain peaking power demand–supply balance as the only large hydropower plant in HSPG. As the original scope of the consulting services for institutional reforms was no longer relevant, the budget allocation was utilized for capacity building of Xinyuan Company and for preparing a strategy for developing PSH plants in the PRC’s restructured power system. The project is also consistent with ADB’s country partnership strategy for the PRC, which supported environmentally sustainable and inclusive economic growth. Hence, the project is rated highly relevant.

12

ADB. 2009. Safeguard Policy Statement. Manila.

Page 19: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

10

B. Effectiveness in Achieving Outcome 40. The project has achieved its main outcome of improving the reliability and stability of HSPG by enhancing the peak load generation capacity and improving the flexibility of electricity generation capacity. This has improved the overall thermal efficiency of the power systems by eliminating the use of inefficient, old, coal-fired power plants as peaking plants, and by reducing greenhouse gas emissions compared with the counterfactual of continued use of small coal fired power plants to meet the peak demand. It has also enabled the closure of over 3,700 MW of old, inefficient, small coal-fired power plants in HSPG during 2006–2010, including the 505 MW of old thermal power plants identified for closure at appraisal. However, the flood control and irrigation expansion benefits resulting from the expansion of water storage in the lower reservoir have not been fully realized because of the delay in finalizing the relocation of one of the affected villages. 41. The rural electrification component of the project was implemented as intended, and the socioeconomic survey of the beneficiaries confirmed the improved quality of electricity supply, increased use of electricity for income-generating activities, and increased employment opportunities in nonfarm sectors. Although the power sector reforms were not implemented as intended at the time of approval, power generation has been separated from transmission, and distribution and tariff reforms have been undertaken to eliminate the urban–rural tariff disparity and to ensure the financial viability of the power sector. As a result, the rural tariff has been reduced in real terms. As most of the key outcomes of the project have been achieved, it is rated effective. C. Efficiency in Achieving Outcome and Outputs 42. Although the project consisted of several components, the efficiency of investment at project completion has been quantitatively assessed for the ZPSHPP, the main component of the project funded by ADB. The efficiency of other components has been assessed based on qualitative analysis of the benefits achieved and the actual costs incurred. No significant cost increases were incurred in implementing any of the project components in local currency terms.13 All project components, except the irrigation component, were implemented ahead of schedule and within budget in local currency terms. The economic and financial evaluation of the ZPSHPP is summarized below and described in detail in Appendixes 8 and 9. The delay in completing the resettlement did not affect the economic benefits of the ZPSHPP, as power plant operations were not affected. However, flood control and irrigation benefits were not realized. As the recalculated economic internal rate of return (EIRR) and financial internal rate of return (FIRR) for the ZPSHPP indicate it to be economically and financially efficient, the project as a whole is rated efficient.

1. Economic Evaluation 43. The economic evaluation of the ZPSHPP was undertaken in accordance with the ADB Guidelines on Economic Analysis. The recalculated EIRR is high but regarded as conservative, as it takes into account only the main benefits of different components and includes all project-related costs. The economic net present value of the project without environment benefits is CNY992.2 million. The actual EIRR of the project without environment benefits is 16.1%, which is lower than the projected EIRR (19.1%) at appraisal but is still greater than the 12% economic

13

A cost increase in US dollar terms was due to appreciation of the local currency. (para 21)

Page 20: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

11

cost of capital (discount rate). This variance is due to (i) exclusion of other parts of the overall project (rural electrification, irrigation, and afforestation, etc.); and (ii) the different methodology used to quantify the economic benefit of the pumped storage plant, particularly the ancillary services.

2. Financial Evaluation 44. The FIRR for the project was determined using actual investment costs, and a combination of historical and projected data for revenues and costs. The recalculated FIRR for the project was 5.9%, compared with 7.3% at appraisal and higher than the weighted average cost of capital of 2.6%. The difference in the recalculated FIRR compared with the appraisal estimate resulted from lower actual annual revenue (CNY415.1 million per year on average) than the appraised revenue of CNY1,048.6 million per year.14 Although the actual revenue is much lower (60%) than the appraisal, the decrease in the FIRR was negligible because of (i) 5% lower actual investment costs; and (ii) lower actual O&M costs since the electricity for water pumping was provided free of charge by the local grid company. The lower actual revenue is partially offset by both lower capital and O&M costs. In addition, the fixed lease revenue has significantly reduced revenue uncertainty since the guaranteed annual fee would be paid regardless of actual usage. The financial analysis is in Appendix 10. D. Preliminary Assessment of Sustainability 45. The ZPSHPP financed under the project is most likely to be sustainable. It is operated by a highly professional and dedicated team of engineers. ZPSC, which owns and operates the ZPSHPP, is a subsidiary of Xinyuan Company belonging to SGCC. ZPSC is financially rewarded through an annuity payment by SGCC for providing peak generation capacity regardless of actual dispatches. The revenues are more than adequate to recover project costs, including O&M costs, and provide adequate cash flows for debt service and a reasonable return on investment. In addition, the ZPSHPP is likely to be sustainable from an environment point of view as the lower reservoir is not subject to excessive sediment loading, and ZPSC is taking measures to protect the watershed and the lower reservoir banks. 46. The other project components are also likely to be sustainable, given the institutional and financial capacity of the relevant agencies. The rural electrification component has been implemented by HEPC, the provincial unit of SGCC, and it is highly likely that HEPC will have adequate financial resources and technical capacity to maintain the electricity distribution network in rural areas. The government at both national and provincial level is committed to improve the living conditions and public services to rural areas, and remove disparities between rural and urban areas. The government is continuing the closure of old, inefficient, coal-fired power plants, with more stringent conditions and enforcement capacity to reduce air pollution and improve energy efficiency. Similarly, the afforestation program has been mainstreamed in the 12th Five-Year Plan, with targets set for lower level government units. However, no

14

At appraisal, it was assumed that the ZPSHPP would purchase electricity from the grid during off-peak time and sell the generated electricity to the grid during peak time. The difference in electricity tariff in peak and off-peak time was expected to provide adequate margin to meet the cash flow requirements of ZPSHPP. However, the central government has stipulated the pumped storage plants should be treated as part of the transmission network and be paid an annuity payment to cover their operating and capital cost by the Grid Company irrespective of the actual utilization of the plant. The Grid Company was required to provide electricity for water pumping free of charge.

Page 21: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

12

immediate plans are in place to initiate a power sector reform program with the objective of establishing a competitive power market. E. Impact

1. Economic Impact

47. The ZPSHPP significantly improved the reliability and stability of HSPG, and facilitated the elimination of load shedding that was prevalent prior to 2006. In addition, it enabled the improvement of thermal efficiency of HSPG by facilitating the closure of old, inefficient, coal-fired power plants. The rural electrification component of the project improved the quality and reliability of power supply in rural areas. The improved power supply in Hebei Province in general and in rural areas in particular contributed to rapid economic growth, increased industrialization, nonfarm employment opportunities, and reduction in rural poverty. Hence, the project had a significant positive economic impact.

2. Environmental Impact 48. The ZPSHPP has been categorized A for environmental safeguards. Compliance with the EMP has been monitored by the independent environment monitoring consultants recruited by the implementing agency, and corrective actions were undertaken during the construction phase of the project. The project was built on an existing reservoir built in the 1970s and only resulted in incremental modifications to the already altered natural environment. The river had already been converted to a seasonal river, and there was no continuous water flow downstream of the existing dam prior to the project. Although the project increased the storage capacity of the lower reservoir and the frequency of fluctuation in water level, as a result of ZPSHPP operations, it had minimal incremental impacts on the aquatic life in the reservoir. However, environmental mitigation measures on rehabilitating the fish habitat and fish population and controlling upstream industrial water pollution sources were seemed overly ambitious in terms of EMP development and unrealistic for ZPSC to implement. 49. The positive environmental impacts of the project were the increased dissolved oxygen level of the lower reservoir, increased flood protection capability, and increased water release capability during drought conditions. In addition, the project contributed to afforestation activities in Jingxing County. The project as a whole also contributed to reducing air pollution in Hebei Province by facilitating the closure of old, inefficient, coal-fired power plants. The project achieved has significant positive environmental benefits at both provincial and local levels, and adverse environmental impacts during construction were effectively mitigated.

3. Social Impacts 50. The social impacts of the ZPSHPP are mainly related to the relocation of 2,878 persons from eight villages.15 In five of the eight villages, the affected people (total of 664 persons) moved within the same village; in the remaining three villages, the affected people were relocated to new villages constructed under the project that are located near a town. Relocation of two of the villages was significantly delayed by the requirement for obtaining the agreement of affected people to the new resettlement site. The relocation of Nanhaoting Village was not undertaken until December 2013. Socioeconomic surveys undertaken after relocation confirmed

15

This does not include the 81 persons affected by the transmission line.

Page 22: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

13

a significant improvement in quality of life, nonfarm employment opportunities, and access to health and education facilities in the new villages in comparison to the old villages. The affected people have been adequately compensated for lost assets. 51. The improvement in rural electricity supply improved quality of life, income-generation opportunities, and nonfarm employment opportunities for rural residents in 23 counties. The closure of old, coal-fired power plants contributed to an improvement in urban air quality and benefitted urban residents. Electricity tariff reforms supported under the project benefitted rural consumers, as the tariff disparities between urban and rural areas were eliminated and rural tariffs were reduced in real terms. This resulted in increased electricity consumption for productive and leisure activities by rural residents.

4. Institutional Development and Capacity Building 52. The project design had a strong emphasis on institutional development and power sector reforms toward the establishment of a competitive power market in Hebei Province. However, the government decided to limit the scope of power sector reforms to unbundling of generation from transmission and distribution. Therefore, the project had a limited impact on developing a more market-oriented institutional structure for the power sector in Hebei Province. On the other hand, the project supported the establishment of a dedicated entity (Xinyuan Company) under SGCC ownership to construct and operate PSH plants in the PRC. Hence, the project contributed to capacity building and institutional development of PSH plant construction and operation in the PRC, which is contributing to the overall improvement of power system stability and reliability.

IV. OVERALL ASSESSMENT AND RECOMMENDATIONS A. Overall Assessment 53. The project is rated successful based on review of its relevance, efficacy, efficiency, sustainability, and impacts. The main investment component of the project financed under ADB financing (the ZPSHPP) is highly relevant to the needs of Hebei Province both at appraisal and completion. The ZPSHPP was implemented within the original schedule, and it has been highly effective in meeting peak electricity demand and improving the grid stability of HSPG. However, completion of the resettlement of some of the affected villages has been delayed due to the disagreement between local government and affected people on the resettlement site for one of the affected villages. The other project components have also been effective in achieving the intended outcomes. The ZPSHPP was implemented within the overall cost estimates (in local currency terms) and is efficient from both financial and economic points of view. Given the high institutional capacity, and strong and steady cash flows, the ZPSHPP is likely to be sustainable from an institutional and financial point of view. The environmental sustainability of the ZPSHPP is ensured through effective implementation of environment mitigation measures. The rural electrification, afforestation, and closure of coal-fired power plants have strong government support and have been mainstreamed into the government’s five-year plans. Hence, these components are also likely to be sustainable. The project as a whole has positive economic, environmental, and social impacts that are likely to be sustained. B. Lessons Learned

54. A strong technical and economic rationale for the project ensures its success even if the institutional arrangements for its implementation change. Significant changes to the power

Page 23: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

14

sector in Hebei Province and to the implementation arrangements of the ZPSHPP did not affect implementation of the ZPSHPP, as it had strong technical and economic relevance to the needs of the Hebei power system. 55. The overall financial strength and institutional capability of the sector are important to ensure the successful implementation of large infrastructure projects such as the ZPSHPP, which require a significant amount of counterpart financing. The ADB loan contributed 21% of the cost of the ZPSHPP and 15% of the total project cost; the remaining financing was mobilized from domestic banks, shareholder financing, and local government financing. 56. Establishing a dedicated entity for the design, construction, and operation the ZHSHPP contributed to the smooth implementation of the project and its subsequent operation. The core staff of ZPSC has been involved in the project from its inception, so ZPSC has a strong sense of ownership and institutional memory. 57. Competent implementation supervision consultants are important to ensure the quality of the technical design and the performance of contractors for complex infrastructure projects. ZPSC highly appreciated the contribution from implementation consultants for the smooth implementation construction of the project within the original schedule. 58. Affected households should be provided with full information regarding their entitlements, livelihood options, and access to other services; and to secure their agreement for proposed resettlement sites as early as possible. The project owner should proactively engage in the consultation process, without delegating the responsibility for managing the resettlement to local government agencies. Consultations with the affected people were not effectively conducted by the local government, which caused significant delays because of lack of consensus on the resettlement sites. This could have been avoided if ZPSC had played a more active role in managing the resettlement program. 59. Obtaining the agreement of affected people to the proposed resettlement sites and entitlements is also significant. Selecting relocation sites near an economic center provides better access to employment opportunities, and public services (such as schools and hospitals) help in obtaining the agreement of the affected people. Providing better housing conditions with basic infrastructure (such as piped water, electricity, internet, and telecommunications) modernized the lifestyle of the affected people, compared with old villages in mountainous areas. In addition, a combined monitoring method—with direct inspection through the missions and regular monitoring—is highly effective for sensitive resettlement cases. 60. The project design and monitoring framework included components that are not directly related to the project. The implementation arrangements for these components were different from ADB-financed ZPSHPP, and ZPSC did not have any role in implementing these components. This prevented effective monitoring of the implementation of these components by ADB review missions, and confirming their efficacy in achieving the outcomes. Furthermore, the indicators to measure the poverty alleviation impacts were poorly defined as a result these could not be monitored during review missions. ADB should have required HEPC to establish a coordinating mechanism to supervise the implementation of different project components and insisted on more information about these components to be included in annual progress reports and safeguard monitoring reports and inappropriate indicators should have been appropriately revised

Page 24: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

15

61. The relevance and rationale for including an institutional strengthening component to promote power sector reforms is questionable given the uncertainty over the government’s strategy for power sector reforms. It is necessary to ascertain the government’s vision and strategy for far-reaching sector reforms before committing resources to implement these reforms in lending projects. C. Recommendations

1. Project Related 62. Future monitoring. As the resettlement of affected households had not been completed at the time of the project completion review mission, it has been agreed that ZPSC monitor and confirm the relocation of the remaining 18 households in Nanhaoting Village, the livelihood restoration of the relocated households, and the construction of road access to old Nanhaoting Village. ADB will continue to monitor the resettlement of Nanhaoting Village until all the outstanding issues are resolved. 63. Watershed Protection: More coordinated and targeted afforestation activities are also needed to ensure watershed protection and the long-term sustainability of the project. In this regard, an effective arrangement for upper watershed protection, in consultation with Shanxi Province, needs to be prepared and implemented.

2. General 64. PSH plants can play an important role in the grid integration of intermittent renewable energy sources, provided that appropriate regulatory regimes are in place to the cost of PSH plants with the end users and renewable energy producers, it is recommended to further explore the role of PSH plants in improving the grid flexibility to facilitate renewable energy in other developing member countries.

Page 25: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

16 Appendix 1

PROJECT FRAMEWORK Design Summary Performance Indicators/Targets Actual Performance

Goal To promote pro-poor, sustainable economic growth in Hebei Province and the project area

Economic growth in Hebei Province: GDP increases by 6.0% between 2010 and 2014 and by 5.6% between 2015 and 2019. Urban unemployment rate decreases from the current 3.2% to 2.5% in 2014 and 2.4% in 2019. Per capita income growth rate increases from the current 4.0% to 5.7% between 2005 and 2009 to 5.6% between 2010 and 2014. Average per capita income of the poor counties increases from the current level of CNY819 to CNY1,586 in 2009 and CNY2,554 in 2014.

Economic growth in Hebei Province averaged 11.70% from 2006 to 2010 and 10.45% from 2011 to 2012 (11.30% in 2011, 9.60% in 2012)

Urban unemployment rate in Hebei Province is 3.69% in 2012.

Per capita income growth increased by 12.3% for urban households and 11.3% for rural residents during 2006–2010 and 12.4% from 2011 to 2012 (13.0% in 2011, and 11.8% in 2012). Per capita income of poor counties reached CNY8,000 in 2012.

Purpose Improve efficiency and reliability of supply of electric power in the project area

Support pro-poor rural development

Reduce load shedding from current 430 hours per year to less than 24 hours per year in 2009 Electricity consumption in Hebei increases by 5.0% between 2005 and 2009, 4.5% between 2010 and 2014, and 4.0% between 2015 and 2019. Line loss reduction from the current 20% to 12% in 2006 and 10% in 2010 Per capita electricity consumption increases from current 1,132 kWh to 1,641 kWh in 2009 and 1,980 kWh in 2014 Reduce rural electricity tariffs from the current CNY0.62/kWh to CNY0.51 kWh by 2005 27,300 new jobs provided to the poor in the project area between 2003 and 2009. Number of electric appliances for poor households increases from the current 1 to 3 in 2005 and 5 in 2009.

No load shedding in Hebei Province was recorded since 2009. Electricity consumption increased on an average by 7.06% per annum during 2006–2012. Line losses reduced to less than 5% in 2010 and 1.5% in 2012. Per capita electricity consumption has reached 4,223 kWh in 2012. The disparity in urban and rural tariffs had been removed and the average tariff paid by rural households was CNY0.52/kWh in 2012. The increase in the per capita income in poor counties and the reduction in unemployment rates suggest that significant number of new jobs were created. There has been increase in household electric appliances but the original indicator is poorly defined to

Page 26: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 1 17

Design Summary Performance Indicators/Targets Actual Performance

Improve the efficiency of coal consumption

Institutional reforms and introduction of competitive power market

Average electricity consumption of the poor household increases from the current 58 kWh to 137 kWh in 2009 and 219 kWh in 2014. Increase irrigation areas by 6,700 ha and increase annual domestic water supply by 2.4 million m

3 by 2009

Improve coal consumption efficiency from the current 360 gce/kWh to 331 gce/kWh in 2014 and 325 gce/kWh in 2019

HEPC’s separation of generation by 2004 Introduction of competitive power market by 2009. Recommend options for the private sector participants in ZPSC. Implementation of the proposed mode privatization of ZPSC.

enable quantitative verification. The average household electricity consumption including in the poor households has increased to more than 200 kWh in 2012 due to higher income levels. Expansion of irrigation area has not occurred due to reduction in agricultural activities in the project area. More villages have been provided with drinking water. Average coal consumption for electricity consumption in Hebei Province in 2012 was 325 gce/kWh. Generation was separated from transmission and distribution in 2005. A competitive power market has not been established in Hebei province. Private sector participation options have not been recommended and the privatization of ZPSC was not carried out.

Outputs Pumped storage generating capacity and dedicated transmission line linking power plant to the grid Rehabilitation of rural electrification network Institutional reforms and introduction of competitive power market

4 x 250 MW pumped storage plant consisting of upper reservoir, height increase of existing lower reservoir, underground waterways and power station by 2009. Erection of one 63 km 500 kV transmission line by 2008. Financial performance, 10% return on net assets of ZPSC starting in 2010 Welfare of those resettled re-established at least to the level prevailing before acquisition. Environmental mitigation measure implemented Restructuring of rural distribution network in 23 counties by 2005 Restructuring of HEPC

4 x 250 MW ZPSHPP was commissioned in 2009. 63 km 500 kv transmission line was commissioned in 2009. ZPSC is complying with the financial covenants. Improved livelihood opportunities for the resettled households have been created. Environmental mitigation measures have been implemented. Rural electrification network rehabilitation has been implemented in the 23 counties. HEPC had been restructured by separating generation from transmission and distribution.

Page 27: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

18 Appendix 1

Design Summary Performance Indicators/Targets Actual Performance

Closure of old, coal-fired power plants Irrigation improvement Afforestation

Introduction of competitive power market in Hebei by 2009 Establish sound management system of ZPSC by 2009. Recommend options on future private sector participation in ZPSC Closure of generating units at five coal-fired power plants totaling

505 MW by 2008.

Increase irrigation areas by 6,700 ha and increase annual domestic water supply by 2.4 million m

3 by 2009

Plant 16,330 ha trees in Jingxing County by 2008 Afforestation of Jingxing County will be improved from 46% to 58%

A competitive power market has not been established in Hebei Province. A sound management system for ZPSC has been established but no plans are in place for private sector participation in ZPSC. 671 MW of capacity in the five identified power plants have been closed. Expansion of irrigation coverage has not been implemented. 16,330 ha of trees have been planted in Jingxing County Forest coverage of Jingxing County has increased due to afforestation activities undertaken.

Activities Inputs: Civil works

Equipment

Land acquisition

Resettlement

Environmental mitigation

Consultants

Closure of old power generation units

Irrigation improvement

Afforestation

Project cost: $774.9 million Funding sources:

(i) ADB loan $144 million (ii) Equity $237.8 million (iii) Domestic Banks

$393.1 million

Project cost: $901.9 million Funding sources:

(i) ADB: $135.9 million (ii) China Development Bank:

$251.6 million (iii) State Grid loan: $108.6

million (iv) Equity: $348.7 million (v) Local government:

$57.3 million

ADB = Asian Development Bank, gce = gram of coal equivalent, GDP = gross domestic product, ha = hectare, HEPC = Hebei Electric Power Corporation, km = kilometer, kV = kilovolt, kWh = kilowatt-hour, m

3 = cubic meter,

MW = megawatt, ZPSC = Zhanghewan Pumped Storage Company, ZPSHPP = Zhanghewan Pumped Storage Hydro Power Plant. Source: Asian Development Bank.

Page 28: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 2 19

PROJECT COST AND FINANCING PLAN

Table A2.1: Project Cost ($ million)

Cost Appraisal Estimate Actual

Foreign Exchange Cost 165.3 136.0 Local Currency Cost 609.6 765.9 Total 774.9 901.9 Source: Asian Development Bank.

Table A2.2: Financing Plan ($ million)

Cost

Appraisal Estimate

%

Actual %

A. Loan

Asian Development Bank 144.0 18.6 135.9 15.1

China Development Bank 275.8 35.6 251.7 27.9

Agriculture Bank of China 117.3 15.1 – 0.0

State Grid Loan 0.0 108.6 12.0

Subtotal (A) 537.1 69.3 496.2 55.0

B. Equity

Hebei Electric Power Corporation 135.7 17.5 191.2 21.2

Hebei Construction & Investment Company 72.8 9.4 73.7 8.2

State Grid Corporation of China 0.0 83.5 9.2

Local Government 29.3 3.8 57.3 6.4

Subtotal (B) 237.8 30.7 405.7 45.0

Total 774.9 100.0 901.9 100.0

Source: Asian Development Bank.

Page 29: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

20 Appendix 3

COST BREAKDOWN, BY PROJECT COMPONENT ($ million)

Appraised Actual

Component Foreign Local Total Foreign Local Total

Exchange Currency Cost Exchange Currency Cost

A. Base Costs

1. Pumped Storage Power Plant 121.1 317.6 438.7 119.6 506.1 625.6 2. Rural Electrification – 135.5 135.5 – 184.6 184.6 3. Closure of Coal-fired Power Plants 0.5 0.9 1.4 0.8 – 0.8 4. Afforestation – 1.6 1.6 – 2.2 2.2 5. Institutional Strengthening

1 – 12.9 12.9 – 17.7 17.7

6. Irrigation2 – 10.6 10.6 – 14.5 14.5

Subtotal (A) 121.6 479.1 600.7 120.4 725.1 845.4 B. Capacity Building 1. Consulting Services – – – 0.9 – 0.9 Subtotal (B) – – – 0.9 – 0.9 C. Contingencies 1. Physical Contingencies 9.1 49.3 58.4 – – – 2. Price Contingencies Systems 18.5 40.2 58.7 – – – Subtotal (C) 27.6 89.5 117.1 – – – D. Financial Charges during Development 16.1 41.0 57.1 14.7 40.9 55.6 Total 165.3 609.6 774.9 136.0 766.0 901.9

Note: Figures may not sum precisely because of rounding. Source: Asian Development Bank and project implementing agencies.

1 The expenses incurred for institutional strengthening are the expenses related to establishment of Xinyuan Company and unbundling of generation and transmission of Hebei Electric Power Company.

2 The expenses incurred for irrigation includes all the expenses incurred by Jingxing County for improving the

irrigation network. Separate accounts for expenses incurred on expanding the irrigation network due to enhanced water storage in lower reservoir is not available.

Page 30: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 4 21

PROJECTED AND ACTUAL DISBURSEMENT

Table A4: Actual Contract Awards and Disbursements ($ million)

Year Contract Award Disbursement

Q1 Q2 Q3 Q4 Total Q1 Q2 Q3 Q4 Total

2004 82.1 0.9 0.0 0.0 83.0 1.4 7.5 0.0 0.9 9.8

2005 0.0 28.3 7.7 0.0 36.0 0.0 1.9 0.0 2.7 4.5

2006 0.8 0.0 0.0 0.0 0.8 0.3 6.7 6.7 19.2 33.0

2007 0.0 0.0 0.0 0.0 0.0 10.1 21.5 15.2 13.4 60.3

2008 0.0 0.0 0.0 0.0 0.0 1.4 4.6 0.2 5.4 11.7

2009 0.0 0.0 0.0 0.0 0.0 2.6 1.7 0.5 3.0 7.6

2010 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 5.1 5.7

2011 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.5 0.8 2.2

2012 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.2 0.0 1.2

Total 82.9 29.2 7.7 0.000 119.8 16.4 44.9 24.3 50.4 135.9

Q = quarter. Source: Asian Development Bank.

Note: Disbursement exceeded Contract Awards because interest during construction was included. Source: Asian Development Bank.

Page 31: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

22

A

pp

en

dix

5

PROJECT IMPLEMENTATION SCHEDULE

Q = quarter. Note: Irrigation and institutional reform components have not been implemented. Source: Asian Development Bank.

Page 32: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 6 23

CHRONOLOGY OF MAIN EVENTS

December 1995 February 1999 and September 2001 February–March 2002 May 2002 August 2002

Project preparatory technical assistance approval Supplementary project preparatory technical assistance approval Loan fact-finding Management review meeting Incorporation of Zhanghewan Pumped Storage Company (ZPSC)

October 2002 Asian Development Bank (ADB) loan approval

June 2003 Award of contract for excavating the upper reservoir

Start of upper reservoir works

July 2003 Signing of loan agreement with China Development Bank

August 2003 ADB loan agreement signing

September 2003 Award of contract for excavating power house

Award of contract for installing headrace and tailrace tunnels

Start of civil works and power house

Start of headrace and tailrace tunnels

October 2003 Award of contract for dam raising

Award of contract for the dam raising

January 2004 Loan effectiveness

February 2004 Award of contract for implementation supervision

April 2004 Award of contract for supply of turbine and generator units and SCADA system

April 2005 Award of contract for limning of upper reservoir

September 2005 Award of contract for switchgear and substation

December 2005 Transfer of majority ownership of ZPSHPP from HEPC to Xinyuan Company

Page 33: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

24 Appendix 6

February 2006 Award of contract for transmission line

October 2006 Delivery of switchgear and substation

December 2007 Completion of transmission line

Completion of intake gates, headrace, and tailrace tunnels

Relocation of Beihaoting Village

July 2008 Completion of the dam construction

Commissioning of Unit 1

August 2008 Commissioning of Unit 2

December 2008 Commissioning of Unit 3

February 2009 Commissioning of Unit 4

June 2009 Completion of delivery of electromechanical equipment

(turbine and generator units )

September 2009 Raising of lower reservoir to 473 meters for the first time

April 2010 Completion of upper reservoir

September 2010 Completion of the civil works of power house

October 2010 Relocation of Shimen Village

December 2013 March 2014

Partial relocation of Nanhaoting Village Project completion review mission

Page 34: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 7 25

STATUS OF COMPLIANCE WITH LOAN COVENANTS Covenant Reference

in Loan Agreement

Status of Compliance

Sector 1. HEPC shall implement, in accordance with the

power sector reform program of the Borrower, the agreed upon recommendations for institutional strengthening and power sector restructuring.

Para. 6, schedule 6, LA; and para. 9, schedule, PA

No longer applicable. The consultants for institutional strengthening and power sector reforms were not recruited as the government decided in 2004 to limit the scope of power sector reforms to separation of generation from transmission and distribution. No recommendations were agreed for power sector reform and structuring.

2. HEPC shall complete the closure of 20 coal fired

power generating units with a total capacity of about 505 MW in HSPG, by 31 December 2008, in accordance with all applicable environment standards.

Para. 3, schedule 6, LA; para. 3, PA.

Complied with. All the identified coal-fired power plants and additional plants have been closed.

3. HEPC shall complete construction and testing of the

500 kV transmission line connecting the project to HSPG before the testing of the first unit.

Para. 4, schedule, PA.

Complied with. The transmission lines were commissioned in December 2007.

4. HEPC shall implement the TRAP, to ensure

alignments of tariff categories. The objective is for the tariffs of rural consumers in Hebei Province to be reduced and brought in line with the tariffs for urban consumers by 31 December 2005. Further, by 31 December 2012, the target is for HEPC’s applicable tariff structure to reflect the corresponding economic costs of supply of electric power for each category as specified in the TRAP.

Para. 5, schedule 6, LA; para. 5, schedule, PA

Complied with. The TRAP was finalized in December 2012 However, the tariff disparity between rural and urban consumers was eliminated in 2005. The end user tariffs are regulated by the government and provide adequate revenues to SGCC to cover the cost of supply.

5. HEPC shall take all necessary actions so that by 31 December 2003, the applicable tariffs for each rural consumer end-user category will have been reduced to reflect efficiency gains from rural electrification and the long term marginal cost tariffs as detailed in the TRAP.

Para. 6, schedule, PA.

Not required. End user tariff captures the cost of supply, including any efficiency gains from the rural electrification program.

Page 35: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

26 Appendix 7

Covenant Reference in Loan

Agreement

Status of Compliance

6. HEPC and ZPSC shall observe the provisions of the Power Purchase and Sales Agreement (PPSA). In particular, HEPC shall perform the obligations of selling power to ZPSC for pumping water to the upper reservoir and buying power from ZPSC for energy generated by the project power plant. HEPC shall also settle the account with the project power plant at the tariff rate as agreed by HEPC and ZPSC in the PPSA and approved by the SDPC of the Borrower.

Para. 7, schedule 6, LA; para. 7, schedule, PA

No longer applicable. The power purchase arrangements between ZPSC and HEPC follow the NDRC regulations applicable to PSH plants. PSH plants are considered a transmission network asset and transmission company. HEPC is required to pay an annuity payment irrespective of utilization of the PSH plant and provide electricity for water pumping free of charge. Hence, a PPSA was not signed between HEPC and ZPSC.

7. ZPSC shall observe the provisions of the ADMLR, in particular, shall be responsible in maintaining and operating the Lower Reservoir and guaranteeing the supply of adequate amount of water for use by ZPSC and for drinking and irrigation by downstream users under normal and dry climatic conditions. In the extremely dry year, ZPSC shall follow the principle in the decision dated 22 April 2002 made by Hebei Provincial Development Commission in Document Jijihan [2002] No. 11, which states that during the extremely dry years the priority of using water in the Lower Reservoir should be given to drinking and irrigation purposes.

Para. 8, schedule 6, LA; para. 8, schedule, PA

Complied with. The lower reservoir has been managed by the Reservoir Management Committee in coordination with ZPSC. Generally, priority is given to maintaining an adequate water level for operation of the ZPSHPP and water has been released for irrigation during the farming season. An extreme dry year has not occurred since commissioning of the plant.

Environmental 8. HEPC and ZPSC shall ensure that the design,

construction and operation of all project facilities comply with applicable environmental laws and regulations of the Borrower and environmental policies and regulations of ADB. HEPC and ZPSC shall ensure that any adverse environmental impacts arising from the construction and operation of the project facilities be minimized by implementing the mitigation measures, environmental monitoring program and other recommendations presented in the EIA and SEIA. During project implementation and the first two

Para. 10, schedule, PA

Complied with. Annual environmental monitoring reports have been submitted. However, some of the parameters were monitored on an annual basis against the EMP requirement for quarterly monitoring, and aquatic life restoration in the lower reservoir was not

Page 36: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 7 27

Covenant Reference in Loan

Agreement

Status of Compliance

years of operations, HEPC shall submit to ADB annual reports which includes mitigation measures undertaken and results of the environmental monitoring program. HEPC shall ensure that any adverse environmental impacts arising from the construction and operation of project facilities are minimized by implementing the mitigation measures as identified in the Environmental Monitoring and Management Plan.

monitored at all.

9. HEPC and ZPSC shall ensure that management programs as specified in the EIA including the reservoirs and land use, afforestation, water quality, sediment and watershed management under the project shall be implemented to improve the general condition of the Gantao River basin. Such activities shall include the planting of 16,330 ha of trees.

Para. 11, schedule, PA; para. 4, schedule 6.

Partially complied with. Although the afforestation has been undertaken on the downstream of the dam as well as on the banks of the reservoir to meet the target, ZPSC has not undertaken upper watershed management and sediment control measures as it falls in Shanxi Province.

Social 10. HEPC and ZPSC shall ensure that all land and

rights-of-way required for the project be made available in a timely manner and that the LARP agreed upon with ADB is carried out promptly and efficiently in line with ADB’s Policy on Involuntary Resettlement.

Para. 9, schedule 6, LA.

Partially complied with after about 3 or more years of delay in reaching agreement on relocation sites with the affected people.

11. HEPC and ZPSC shall ensure, with assistance of the Borrower, that all affected people, including host people who provide land to the affected persons, are provided adequate information and are regularly consulted in advance of signing household compensation agreements and other decisions that affect their livelihoods and living conditions as a result of the project. The ZPSC and local resettlement offices shall keep records of consultations and provide copies to ADB upon request.

Para. 13, schedule, PA.

Partially complied with as inadequate information and consultation with the affected people may have contributed to the delays in reaching agreement on the resettlement site.

12. HEPC and ZPSC shall also ensure, with assistance of the Borrower, that all persons affected by the acquisition of land required for the project are compensated in a timely manner and resettled in accordance with the LARP, so that they will be at least as well off as they would have been in the absence of the project.

Para. 10, schedule 6, LA; and para. 14, schedule, PA.

Complied with. The socio economic surveys undertaken on living conditions and livelihood restoration of affected people indicated that their living conditions and livelihoods have been improved.

Page 37: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

28 Appendix 7

Covenant Reference in Loan

Agreement

Status of Compliance

13. ZPSC shall ensure, with assistance of the Borrower, timely provision of all counterpart funds to meet any obligations in excess of the LARP budget estimate in order to satisfy resettlement objectives of the LARP. HEPC and ZPSC shall ensure that counterpart funds for compensation and entitlements under the LARP are fully provided directly to the affected persons and the relevant village organizations prior to displacement from housing and prior to loss of land, livelihood, income or other assets.

Para. 15, schedule, PA

Complied with, except for some delay in mobilizing additional counterpart funds for the Nanhaoting Village relocation site as a result of the increase in land price of the relocation site.

14. HEPC and ZPSC shall ensure, with assistance of the Borrower, that (i) adequate staff and resources are committed to supervision and internal monitoring of the implementation of the LARP and quarterly reports on resettlement progress will be forwarded to ADB; (ii) an independent domestic monitoring agency is contracted, in accordance with procedures acceptable to ADB, to carry out systematic monitoring twice each year during LARP implementation, conduct two annual evaluations after completion, and forward reports to ADB; and (iii) an annual audit of resettlement disbursements and expenditures is conducted by an auditor acceptable to ADB, and a summary report forwarded to ADB.

Para. 16, schedule, PA

Complied with. Full compensation was paid prior to dispossession of land and assets. Affected persons are better off. Independent monitoring was undertaken from 2004 to 2007. Since then, monitoring has been done using staff consultants because of long delays in resettlement activities.

15. HEPC and ZPSC shall follow the principles of ADB’s Policy on Gender and Development during implementation of the project, including taking all necessary actions to encourage women living in the project area to participate in planning and implementing project activities. HEPC shall monitor project effects on women during project implementation, in consultation with the Hebei Provincial Women’s Federation.

Para. 11, schedule 6, LA; para. 19, schedule, PA

Partially complied with. Scope was limited for women to take part in implementing project activities as project activities were implemented by outside contractors.

16. HEPC and ZPSC shall coordinate with the resettlement offices to (i) ensure that women at county, township and village levels take part in the implementation of the resettlement plan; and (ii) address the preferences of affected women’s households during finalization and implementation of the resettlement plan.

Para. 12, schedule 6, LA; and para. 20, schedule, PA

Complied with. Affected people including women have been consulted during the implementation of resettlement activities.

17. HEPC and ZPSC shall, together with the appropriate authorities of the Borrower and Hebei PG, cause contractors employed under the project to disseminate information on the risks of socially transmitted diseases to those employed during project implementation.

Para. 17, schedule, PA

Complied with, The contractors complied with this requirement.

Page 38: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 7 29

Covenant Reference in Loan

Agreement

Status of Compliance

18. ZPSC shall update the LARP as necessary to reflect any significant changes in project scope or other causes, and such changes will be reported to ADB as part of project reporting.

Para. 13, schedule 6, LA; para. 22, schedule, PA

Complied with.

Financial 19. ZPSC shall (i) maintain separate accounts for the

project; (ii) have such accounts audited annually; and (iii) furnish to ADB audit reports not less than 6 months of the closure of the financial year.

Section 2.09, PA

Complied with.

20. HEPC shall inject, together with HCIC, the equity capital of ZPSC subscribed by HEPC in a phased manner and in accordance with the requirement of the Borrower’s Company Law and legal requirements of company registration and incorporation, Investment Agreement between HEPC and HCIC to set up ZPSC and the need for project power plant construction, with the full amount of equity capital being injected not later than 31 December 2008.

Para. 13, schedule 6, LA; para. 23, schedule, PA

Complied with. ZPSC has been adequately capitalized. However, the shareholding structure of ZPSC was changed from what was expected at loan approval and HEPC was replaced by Xinyuan Company as the majority shareholder.

21. HEPC shall, together with HCIC, provide sufficient foreign exchange, as needed, according to the percentage of its commitment to making equity investment in ZPSC, to finance the project power plant construction, in case that the total foreign exchange cost of the project power plant exceeds $144 million.

Para. 14, schedule 6, LA; para. 5, schedule, PA

Not required as the foreign exchange cost did not exceed $144 million.

22. HEPC and ZPSC shall ensure that ADB is periodically updated on all proposals for the restructuring of ZPSC, including any change of ownership of ZPSC, and that, prior to finalization of any proposal for ZPSC restructuring, including any change of ownership of ZPSC, ADB shall be given adequate opportunity to provide prior commitment thereon.

Para. 15, schedule 6, LA; para. 23, schedule, PA

Complied with. ADB was informed of the change in shareholding structure of ZPSC.

23. HEPC shall achieve an annual return of not less than 6 % of the average net value of fixed assets in operation commencing from fiscal year 2008.

Section 2.17, PA Not applicable. HEPC was replaced by Xinyuan Company as the main shareholder of ZPSC. Financial statements of Xinyuan were not made available to ADB as this company was not required under the Legal documents.

Page 39: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

30 Appendix 7

Covenant Reference in Loan

Agreement

Status of Compliance

24. HEPC shall maintain a ratio of debt to equity not greater than 70 to 30 commencing from fiscal year 2008.

Section 2.19, PA Same as above

25. HEPC shall achieve a minimum debt service ratio of 1.2 times commencing from fiscal year 2008.

Section 2.18, PA Same as above

26. ZPSC shall achieve, for each of its fiscal years commencing from fiscal year 2009, an annual return of not less than 10% of the average current net value of ZPSC’s fixed assets in operation.

Section 2.20, PA Partially complied with. The return on assets has been 3%–4%; it is unrealistic to expect a 10% return on assets.

Others 27. ZPSC shall furnish ADB all relevant reports and

information concerning (i) the loan and the expenditure of the proceeds thereof; (ii) the goods and services and other items of expenditure financed out of such proceeds; (iii) the project; (iv) the administration, operations and financial condition of ZPSC; and (v) any other matters relating to the purposes of the loan.

Section 2.08 (a), PA

Complied with and all the necessary information on use of ADB loan proceeds have been provided.

28. ZPSC shall furnish ADB quarterly reports on the execution of the project and on the operation and management of project facilities.

Section 2.08 (c), PA

Partially complied with. The quarterly progress reports have been provided during the construction period of ZPSHPP. However, progress reports have not been submitted since 2009.

29. ZPSC shall submit within 3 months after the physical completion a report on the execution and initial operation of the project, including its cost, the performance by HEPC and ZPSC of their respective obligations under the Project Agreement and the accomplishment of the purposes of the Loan.

Section 2.08 (d), PA

Not complied with. ZPSC did not submit a project completion report to ADB.

ADB = Asian Development Bank, EIA = environmental impact assessment, EMP = environmental monitoring plan, ha = hectares, LARP = land acquisition and resettlement plan, HCIC = Hebei Construction & Investment Company, HEPC = Hebei Electric Power Corporation, MW = megawatt, HSPG = Hebei South Power Grid, kV = kilovolt, TRAP = Tariff Reform Action Plan, SGCC = State Grid Corporation of China, ZPSC = Zhanghewan Pumped Storage Company, Ltd. , PPSA = power purchase and sales agreement, SDPC = State Development Planning Commission, NDRC = National Development and Reform Council, PSH = pumped storage hydropower, ADMLR = Agreement on Dispatch and Management of Low Reservoir, ZPSHPP = Zhanghewan Pumped Storage Hydro Power Plant Source: ADB Staff Estimates

Page 40: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 8 31

ADB-FINANCED CONTRACT PACKAGES PCSS No.

Item

Mode of Procurement (ICB/IS/DP)

Date of

Contract

Contract Amount

($) A. Pumped Storage Power Plant

01 Civil Works 0003 Bituminous Concrete Lining of Upper Reservoir

ICB 15 Apr 2005 20,585,988

02 Equipment

0001 Turbine and Generator units and Computer Control System

ICB 06 Feb 2004 51,510,863

0004 Gas Insulated Transmission Lines ICB 21 Sep 2005 2,216,085 0005 Gas Insulated Metal-Enclosed Switchgear and

Auxiliaries ICB 21 Sep 2005 5,491,931

03 Materials

04 Institutional Strengthening

0006 Institutional Strengthening

ICB 21 Feb 2006 794,034

05 Consulting Services

0002 Implementation Consultant ICB 02 Feb 2004 902,852 DP = direct procurement, ICB = international competitive bidding, IS = international shopping. Source: Asian Development Bank.

Page 41: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

32 Appendix 9

ECONOMIC REEVALUATION 1. The Hebei Zhanghewan Pumped Storage Project comprised (i) the 1,000 megawatt (MW) Zhanghewan Pumped Storage Hydro Power Plant (ZPSHPP) and its interconnection to the 500 kilovolt (kV) grid substation; (ii) rural electrification in 23 counties; (iii) institutional strengthening of the implementing agency and the introduction of a competitive power market; (iv) the closure of seven small, old, inefficient coal-fired power plants with a total capacity of 505 MW in Hebei Province; (v) an increase in the irrigation capacity of water supply by 2.4 million cubic meters (m3) per year; and (vi) planting of 16,330 hectares (ha) of trees in Jingxing County. However, the economic analysis was conducted only for the 1,000 MW ZPSHPP, since the economic benefits of other parts of the project can be neither quantified nor assumed. The analysis was done in accordance with the Guidelines for the Economic Analysis of Projects1 of the Asian Development Bank (ADB). A. General Assumptions for Economic Analysis 2. The economic feasibility was evaluated by a comparison between the without- and with-project scenarios as follows:

(i) Under the without-project (baseline) scenario, the respective peaking power would be provided by existing small, old, inefficient coal-fired power plants.

(ii) Under the with-project scenario, the proposed project would replace the peak power generated by old and inefficient coal-fired power plants.

3. Economic analysis was conducted for the project lifespan of 27 years plus the project implementation period of 6.5 years. The residual value at the end of the project life is assumed to be zero. All prices and costs were expressed in 2014 prices and in the domestic currency using the world price numeraire. As the analysis was carried out using the world price numeraire, a standard conversion factor of 0.987 was used for non-tradables and 1.000 for tradables. B. Economic Costs 4. The financial capital costs were converted to economic values after deducting taxes and subsidies, then applying the conversion factors specified in the general assumptions. The capital costs of the project included actual costs related to civil works, materials, and equipment, and other associated costs. These costs occurred primarily during the construction period—within the first 6.5 years of the project. The operation and maintenance (O&M) costs, assumed to remain constant in real terms, comprised costs for maintenance, raw materials, salaries, overheads, utilities, and administration expenses. The O&M costs occurred throughout the project (27 years). It was assumed that the electricity for water pumping was provided by surplus wind power, which would have been curtailed in the absence of the project.2 Hence, the economic cost of electricity used in water pumping was assumed to be zero. C. Economic Benefits 5. Annually, the project has generated on average 2,639 gigawatt-hours (GWh) of clean electricity to serve peaking electricity demand. The economic benefits of the project included

1 ADB. 1997. Guidelines for the Economic Analysis of Projects. Manila.

2 Wind power curtailment in the northern People’s Republic of China (PRC) is estimated to be 22% of potential wind

generation, and the curtailed wind energy in the North China grid (Hebei South Power Grid is part of the North China Grid) amounted to 10,000 GWh in 2012.

Page 42: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 9 33

(i) coal savings (non-incremental) by replacing coal as a fuel for power generation; (ii) direct environmental benefits, reflected in the reduction in carbon dioxide emissions (CO2) resulting from the closure of old, inefficient coal-fired power plants; and (iii) grid stability and ancillary services (e.g., spinning reserve, frequency and voltage regulation, and black start capability). As the People’s Republic of China (PRC) does not have a market for ancillary services, the economic value of these benefits has been assumed based on recent studies that calculated them to be worth $5–$10 per megawatt-hour.3 Hence, the ancillary services have been valued at $10 per megawatt-hour as these services are more valuable in the PRC than in Europe and the United States because of the inflexible generation capacity mix in the PRC. 6. The project has resulted in considerable environmental benefits by reducing greenhouse gas emissions and other pollutants. On average, the project avoided 1,451,353 tons of coal equivalent (tce) per year, which translates to an annual emission reduction of 3,618,223 tons (t) of CO2; 8,128 t of sulfur dioxide; 4,865 t of nitrogen oxide; and 4,223 t of flue dust.4 The economic evaluation of the environmental impact is based on the benefits transfer method described in ADB’s Economic Evaluation of Environmental Impacts: A Workbook.5

D. Economic Internal Rate of Return 7. Table A9.1 compares the recalculated economic internal rate of return (EIRR) and economic net present value (ENPV) of the project with the appraisal estimates.

Table A9.1: Comparison of Economic Internal Rate of Return

Subproject

Appraisal Actual Without

Environmental Benefit

With Environmental

Benefit

Without Environmental

Benefit

With Environmental

Benefit

ENPV (CNY million) 1,867.0 2,604.0 992.0 1,237.0 EIRR (%) 19.1 21.7 16.1 17.4

CNY = yuan, EIRR = economic internal rate of return, ENPV = economic net present value. Source: Asian Development Bank estimates.

8. The recalculated EIRR is high but regarded as conservative, as it takes into account only the main benefits of different components and includes all project-related costs. The ENPV of the project without environment benefits is CNY992.2 million. The actual EIRR of the project without environment benefits is 16.1%, which is lower than the projected EIRR (19.1%) at appraisal but is still greater than the 12% economic cost of capital (discount rate). This variance is due to (i) exclusion of other parts of the overall project (rural electrification, irrigation, and afforestation, etc.); and (ii) the different methodology used to quantify the economic benefit of the pumped storage plant, particularly the ancillary services. The economic benefits and costs of the project with and without environment benefits are shown in Table A9.2.

3 CSP Alliance. 2012. The Economic and Reliability Benefits of CSP with Thermal Energy Storage: Recent Studies

and Research Needs. Washington, DC. The pump storage hydropower plants provide the same or even higher capability to enhance the grid stability.

4 The environmental benefits of CO2 emission reductions were estimated using the marginal abatement cost as a

proxy for the economic benefits of emission reductions. The CO2 price (CNY19/ton) in the PRC is based on the prevailing market price for Chinese Certified Emission Reduction (CCER) credits, which are traded in the domestic carbon market. The environmental benefits of the other emissions were estimated using the emission charges in the PRC issued by the National Development and Reform Commission.

5 ADB. 1996. Economic Evaluation of Environmental Impacts: A Workbook. Manila.

Page 43: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

34

A

pp

en

dix

9

Table A9.2: Economic Internal Rate of Return for the Project (CNY million)

Year Economic

Capital Cost

Economic Operating

Cost

Total Economic

Cost Direct Economic Benefits Total

Direct Economic

Benefit

Environment Benefit

Net Economic

w/o Environment

Benefit

Net Economic

with Environment

Benefit

Generation

(Coal Saving)

Consumption (Grid

Stability)

2002 (37.4) (37.4) (37.4) (37.4) 2003 (262.8) (262.8) (262.8) (262.8) 2004 (514.3) (514.3) (514.3) (514.3) 2005 (420.8) (420.8) (420.8) (420.8) 2006 (888.4) (888.4) (888.4) (888.4) 2007 (897.7) (897.7) (897.7) (897.7) 2008 (748.1) (4.4) (752.5) (752.5) (752.5) 2009 (129.9) (82.4) (212.4) 783.2 220.2 1,0003.4 92.0 791.1 883.1 2010 (69.7) (69.7) 765.1 213.4 978.4 89.9 908.7 998.6 2011 (85.4) (85.4) 779.9 218.8 998.7 91.6 913.4 1,005.0 2012 (83.2) (83.2) 719.8 201.7 921.5 84.6 838.2 922.8 2013 (83.2) (83.2) 698.3 196.3 894.6 82.1 811.3 893.4 2014 (80.9) (80.9) 749.2 210.1 959.3 88.0 878.5 966.5 2015 (80.9) (80.9) 742.4 208.1 950.5 87.2 869.7 956.9 2016 (80.9) (80.9) 737.9 207.0 944.9 86.7 864.1 950.8 2017 (80.9) (80.9) 729.5 204.6 934.2 85.7 853.3 939.0 2018 (80.9) (80.9) 731.5 205.2 936.7 86.0 855.8 941.8 2019 (80.9) (80.9) 738.1 207.0 945.1 86.7 864.3 951.0 2020 (80.9) (80.9) 735.9 206.4 942.3 86.5 861.4 947.9 2021 (80.9) (80.9) 734.6 206.0 940.6 86.3 859.8 946.1 2022 (80.9) (80.9) 733.9 205.9 939.8 86.2 858.9 945.2 2023 (80.9) (80.9) 734.8 206.1 940.9 86.4 860.1 946.4 2024 (80.9) (80.9) 735.5 206.3 941.8 86.4 860.9 947.3 2025 (80.9) (80.9) 734.9 206.1 941.1 86.4 860.2 946.6 2026 (80.9) (80.9) 734.8 206.1 940.8 86.3 860.0 946.3 2027 (80.9) (80.9) 734.8 206.1 940.9 86.3 860.0 946.4 2028 (80.9) (80.9) 735.0 206.1 941.1 86.4 860.3 946.6 2029 (80.9) (80.9) 735.0 206.1 941.1 86.4 860.3 946.6 2030 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.4

Page 44: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Ap

pe

ndix

9 35

Year Economic

Capital Cost

Economic Operating

Cost

Total Economic

Cost Direct Economic Benefits Total

Direct Economic

Benefit

Environment Benefit

Net Economic

w/o Environment

Benefit

Net Economic

with Environment

Benefit

Generation

(Coal Saving)

Consumption (Grid

Stability)

2031 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.3 2032 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.4 2033 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.4 2034 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.4 2035 (80.9) 734.9 206.1 941.0 86.4 941.0 1,027.4

Base Case

EIRR 16.1% 17.4%

ENPV 922.2 1,236.6

( ) = negative, CNY = yuan, EIRR = economic internal rate of return, ENPV = economic net present value, O&M = operation and maintenance. Source: Asian Development Bank estimates.

Page 45: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

36 Appendix 9

a. Sensitivity Analysis

9. Sensitivity analysis was performed to test the EIRR’s sensitivity to certain changes in parameters. This showed that the EIRR without environment benefits could fall to (i) 15.8% if all the economic benefits were reduced by 10%, (ii) 14.9% if the project experienced a cost overrun of 10%, (iii) 16.0% if the O&M costs rose by 10%, and (iv) 14.5% if all cases happen together (Table A9.3). Under the scenarios considered for sensitivity analysis, the EIRR values are greater than the economic discount rate of 12%.

Table A9.3: Sensitivity Analysis of the Economic Internal Rate of Return

Case Base Case without

Environmental Benefits

Case 1 Economic Benefits –10%

Case 2 Project Cost

+10%

Case 3 O&M Cost

+10%

Case 4 Combination of

All Cases

EIRR 16.1 15.8 14.9 16.0 14.5 EIRR = economic internal rate of return, O&M = operation and maintenance. Source: Asian Development Bank estimates.

Page 46: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 10 37

FINANCIAL REEVALUATION

1. The Hebei Zhanghewan Pumped Storage Project comprised (i) the 1,000 megawatt Zhanghewan Pumped Storage Hydro Power Plant (ZPSHPP) and its interconnection to the 500 kilovolt (kV) grid substation; (ii) rural electrification in 23 counties; (iii) institutional strengthening of the implementing agency and the introduction of a competitive power market; (iv) the closure of seven small, old, inefficient coal-fired power plants with a total capacity of 505 megawatt in Hebei Province; (v) an increase in the irrigation capacity of water supply by 2.4 million cubic meters per year; and (vi) planting of 16,330 hectares (ha) of trees in Jingxing County. This financial analysis assesses the project’s ability to generate sufficient revenues from operations to recover project costs, including operation and maintenance (O&M) costs, and to provide adequate cash flows for debt service and a reasonable return on investment. However, the financial analysis was conducted only for the ZPSHPP, since the financial benefits of other parts of the project can be neither quantified nor assumed. 2. The analysis was performed in accordance with the Financial Management and Analysis of Projects1 of the Asian Development Bank (ADB). All actual costs and prices are in constant 2014 currency values. In deriving the financial internal rate of return (FIRR), incremental annual cash flows were used throughout the 27-year lifespan of the ZPSHPP since commercial operations began in 2009 plus the project implementation period of 6.5 years. The residual value of physical assets was assumed to equal their depreciated book value at the end of the valuation period. The financial analysis model compared the FIRR with the weighted average cost of capital (WACC). Sensitivity analyses were conducted to assess the impact of various adverse conditions. A. Key Assumptions 3. The capital costs were based on actual costs incurred during construction. The capital costs included civil works, equipment and materials, consulting services, and other related expenses. Revenues were computed on the basis of the actual fixed lease fee paid to Zhanghewan Pumped Storage Company (ZPSC) by the State Grid Corporation of China.2 O&M costs included the purchase of raw materials and fuel, wages and benefits, maintenance and repair, and other sales and management expenses, which are assumed to remain consistent. Net cash flows from the project were determined after allowing for corporate income taxes at 25% of pretax profit, which is lower than the 33% income tax assumed at appraisal. 4. The WACC was recalculated after tax in real terms using the actual capital mix and costs of funds shown in Table A2.2 in Appendix 2. The real interest costs of loan funds, based on the actual interest rate of loan funds from ADB and other funding sources, were considered after adjusting for inflation (assumed to be 3.0%) and local income tax credit. The cost of equity is assumed to be 7.0% per annum.3 The recalculated WACC is 2.64 (Table A10.1).

1 ADB. (2005). Financial Management and Analysis of Projects. Manila

2 A new revenue setting methodology was adopted by the National Development and Reform Commission in 2007

for pumped storage hydropower (PSH) plants, whereby a fixed rent is paid irrespective of the actual amount of energy generated or consumed by these plants. This payment is expected to reward the PSH plant for supporting maintenance of the demand–supply balance and providing ancillary services to maintain grid stability. It greatly reduced the revenue risk of the project.

3 This is the commonly required return on investment for similar power generation projects in the People’s Republic

of China (PRC).

Page 47: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

38 Appendix 10

Table A10.1: Breakdown of Weighted Average Cost of Capital Calculation

Item ADB

China Development

Bank

State Grid Loan

Equity Total

Amount ($ million) 135.9 251.6 108.6 405.7 901.8

Weighting 15.1% 27.9% 12.0% 45.0% 100.0%

Nominal cost 3.0% 6.12% 5.5% 7.0% N.A.

Income tax rate 25% 25% 25% N.A N.A.

Tax-adjusted nominal cost 2.3% 4.6% 4.1% 7.0% N.A. Inflation adjustment to interest rate

N.A. 3.0% 3.0% 3.0% N.A.

Real cost 2.3% 1.5% 1.0% 3.9% N.A.

Weighted component of WACC 0.3% 0.4% 0.1% 1.6% 2.7

WACC 2.7% ADB = Asian Development Bank, N.A. = Not applicable, WACC = weighted average cost of capital. Source: ADB Staff Estimates

B. Financial Indicators 5. The results of the financial analysis for the project are in Table A10.2. The recalculated FIRR is still greater than the recalculated WACC. The recalculated WACC is used as the discount rate in calculating the financial net present value (FNPV) of the project and it is projected to generate a positive FNPV.

Table A10.2: Projected Financial Indicators

Project Appraised FIRR (%) Actual FIRR (%) FNPV (CNY million) on)

WACC(%)

HZPSP 7.3 5.9 1,620.5 2.7 CNY = yuan, FIRR = financial internal rate of return; FNPV = financial net present value, HZPSP = Zhanghewan Pumped Storage Project, WACC = weighted average cost of capital.

Source: Asian Development Bank staff estimates.

6. The recalculated FIRR for the project is 5.86%, compared with 7.30% during appraisal. The variance between the actual FIRR and the appraisal estimate is due to lower actual annual revenue (CNY415.1 million per year on average) than the appraised revenue of CNY1,048.6 million per year. Although the actual revenue is much lower (60%) than the appraisal estimate, the decrease in the FIRR was negligible because (i) the actual capital investment costs were 5% lower than expected; and (ii) actual O&M costs were lower than expected, since the electricity for water pumping was provided free of charge by the local grid company. Hence, the lower actual revenue is partially offset by lower capital and O&M costs. In addition, the fixed lease revenue significantly reduced financial uncertainty since the guaranteed annual fee will be paid regardless of actual dispatches. Cash flows for the project are shown in Table A10.3.

Page 48: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 10 39

Table A10.3: Cash Flows for the Project (HZPSP) (CNY million)

Year Capital Cost

Revenues Operating

Cost Income Tax

Net Cash Flow After Tax

2002 (36.9) 0.0 0.0 0.0 (36.9)

2003 (259.3) 0.0 0.0 0.0 (259.3)

2004 (461.4) 0.0 0.0 0.0 (461.4)

2005 (415.3) 0.0 0.0 0.0 (415.3)

2006 (876.7) 0.0 0.0 0.0 (876.7)

2007 (885.9) 0.0 0.0 0.0 (885.9)

2008 (738.3) 207.6 (4.9) 0.0 (535.6)

2009 (128.2) 406.5 (86.9) (7.5) 183.9

2010 0.0 414.5 (75.9) (17.3) 321.3

2011 0.0 413.9 (92.8) (12.8) 308.3

2012 0.0 415.2 (90.7) (3.5) 320.9

2013 0.0 415.1 (90.7) (23.8) 305.5

2014 0.0 415.1 (88.3) (21.5) 305.2

2015 0.0 415.1 (88.3) (22.4) 304.3

2016 0.0 415.1 (88.3) (23.4) 303.4

2017 0.0 415.1 (88.3) (24.3) 302.4

2018 0.0 415.1 (88.3) (25.3) 301.4

2019 0.0 415.1 (88.3) (26.3) 300.4

2020 0.0 415.1 (88.3) (27.4) 299.4

2021 0.0 415.1 (88.3) (28.4) 298.3

2022 0.0 415.1 (88.3) (29.6) 297.2

2023 0.0 415.1 (88.3) (30.7) 296.0

2024 0.0 415.1 (88.3) (31.9) 294.8

2025 0.0 415.1 (88.3) (33.2) 293.6

2026 0.0 415.1 (88.3) (34.5) 292.3

2027 0.0 415.1 (88.3) (35.9) 290.9

2028 0.0 415.1 (88.3) 36.9 289.8

2029 0.0 415.1 (88.3) 37.6 289.1

2030 0.0 415.1 (88.3) 37.6 289.1

2031 0.0 415.1 (88.3) 37.6 289.1

2032 0.0 415.1 (88.3) 37.6 289.1

2033 0.0 415.1 (88.3) 37.6 289.1

2034 0.0 415.1 (88.3) 37.6 289.1

2035 0.0 415.1 (88.3) 37.6 289.1

WACC 2.6% FIRR 5.9%

FNPV 1,620.5

( ) = negative, CNY = yuan, FIRR = financial internal rate of return, FNPV = financial net present value, WACC = weighted average cost of capital. Source: Asian Development Bank estimates.

Page 49: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

40 Appendix 10

C. Sensitivity Analysis 7. Sensitivity analysis was performed to test the FIRR’s sensitivity to certain changes in parameters. The sensitivity analysis focused on three variables: (i) O&M costs increase by 10%; (ii) project revenue decreases by 10%; and (iii) a combination of all variables. The analysis shows that the project will remain financially viable as the FIRRs are greater than the WACCs. The sensitivity analysis is shown in Table A10.4.

Table A10.4: Sensitivity Analysis of Financial Internal Rates of Return

Case WACC FIRR (Base Case) O&M Cost +10% Revenue

-10% All Variables Combined

ZPSP 2.6 5.9 5.1 4.6 3.8 CNY = yuan, FIRR = financial internal rate of return; FNPV = financial net present value, ZPSP = Zhanghewan Pumped Storage Project, WACC = weighted average cost of capital. Note: The sensitivity indicator is the ratio of percentage change in the financial internal rate of return divided by the percentage change in the given parameter. Source: Asian Development Bank estimates. D. Summary of Financial Statement: Implementing Agency 8. Table A10.5 shows a snapshot of the financial sustainability of the implementing agency, ZPSC, through the key financial indicators (both historical and projected) analysis. ZPSC uses less leverage and has a stronger equity position as it shows the low debt-equity ratio (less than 70:30) throughout the loan tenor. In terms of its profitability, ZPSC is expected to earn the sufficient revenue to (i) cover the upcoming debt service as DSCR is greater than 2.00x throughout the repayment period; and (ii) provide sufficient return on the equity investment (>7.00% from year 2017). The summary shows that ZPSC’s ability short term liabilities is expected to gradually improve from year 2022 as it shows the acceptable current ratio (greater than 1).

Page 50: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

A

pp

en

dix

10

41

Table A10.5: Financial Indicators Analysis of ZPSC

Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

Debt/ equity ratio

2.1 2.2 2.0 1.9 1.9 1.8 1.7 1.6 1.5 1.5 1.4 1.3 1.2 1.0 1.0 0.9 0.7 0.6

Return on equity (%)

5.0 3.7 2.3 6.8 6.1 6.3 6.6 6.9 7.2 7.4 7.7 8.0 8.4 8.7 9.0 9.4 9.7 10.1

Debt service coverage ratio

0.7 0.9 0.7 2.1 2.7 2.7 2.7 2.7 2.7 2.7 2.7 2.7 2.7 2.7 2.7 2.6 2.5 3.5

Current ratio 0.3 0.6 0.7 0.3 0.5 0.6 0.7 0.8 0.8 0.9 0.9 1.0 1.0 1.0 1.0 1.1 1.1 1.1

Page 51: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

42 Appendix 11

ENVIRONMENTAL IMPACT ASSESSMENT

A. Introduction

1. The Hebei Zhanghewan Pumped Storage Project was approved on 18 October 2002 and the loan was closed on 11 July 2013. The project is located in Hebei Province in the People’s Republic of China (PRC) and involves (i) construction of a 1,000 megawatt pumped storage power plant at Zhanghewan; (ii) construction of a 500 kilovolt (kV) transmission line to transfer electricity from the power plant to Hebei South Power Grid (HSPG); (iii) rehabilitation of the rural electricity distribution network; (iv) closure of old, inefficient coal-fired power generation units; and (v) support for reforms in the provincial power sector, irrigation improvement, and afforestation. The main objective of the project was to improve the efficiency of electricity generation and to reduce emissions in meeting the peaking power requirements of HSPG. Other objectives were (i) to rehabilitate distribution networks in the rural areas designated as poor; (ii) to expand the irrigation system and afforestation in Jingxing County; (iii) to close old, inefficient power plants; and to introduce competitive markets and use market forces to improve the efficiency of power utilities. 2. Construction of the Zhanghewan Pumped Storage Hydro Power Plant (ZPSHPP) commenced in December 2003. The dam construction was completed in July 2008. Construction of the upper reservoir was completed in April 2009 and civil works of the power house were completed in September 2009. The project was classified environmental category A. The domestic environmental impact assessment (EIA) was conducted in 1989 and approved by the state environmental protection agency in 1996. The EIA was updated in 2001 following modification to the project design suggested by ADB appointed project preparatory technical assistance consultants. The summary environmental impact assessment (SIEA) was prepared and circulated to the Asian Development Bank Board of Directors in April 2002. The SEIA included the environmental management plan to mitigate adverse environmental impacts of the project.

3. ADB project completion review (PCR) mission was conducted from 3 to 7 March 2014. Consultations were held with the project executing agency, Hebei Electric Power Corporation (HEPC); the implementing agency, Zhanghewan Pumped Storage Company (ZPSC); Hebei Energy Bureau; Shijiazhuang Planning Commission; Xingtai Planning Commission; Xingtai Coal-fired Power Plant; Jingxing Forest Bureau, Jingxing Water Resource Bureau; and Zhanghewan Reservoir Department. The mission team conducted project document review, site visits, and interviews with relevant authorities and institutes to review the effectiveness of environmental management and protection measures. This document presents the key findings. B. Environmental Protection and Management

4. HEPC was the executing agency for the project—responsible for overall project coordination, including the rural electrification program, closure of the old power plants, and construction and operation and maintenance of the 500 kV transmission facilities. ZPSC, the owner of the ZPSHPP, was the implementing agency and responsible for the design, construction, and operation of the ZPSHPP. 5. As part of the power sector reform process in 2005, HEPC was restructured as the provincial unit of the newly created State Grid Corporation of China, responsible for electricity transmission and distribution in Hebei Province. The generation assets of the former HEPC

Page 52: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 43

were transferred to five newly created national level power generation companies. A separate company (Xinyuan Company) was established as a subsidiary of State Grid Corporation of China to invest in and operate pumped storage hydropower plants. ZPSC became a subsidiary of Xinyuan Company. The role of HEPC is limited to implementing the construction of the 500 kV transmission line and the rural electrification components. The closure of the coal-fired power plant was coordinated by HPG, while the afforestation program and resettlement of households affected by the ZPSHPP were implemented by Jingxing County government in close coordination with ZPSC. 6. ZPSC set up a dedicated Environmental Management Department in 2003. The department was responsible for managing and supervising environmental protection works during construction, which included (i) planning and implementing specific environmental protection measures; (ii) ensuring that contractors followed the environmental management plan; (iii) hiring and ensuring qualified monitoring institutes to conduct air, water, noise, and other environmental monitoring regularly; (iv) ensuring the monitoring requirements were met; and (v) working closely with local environmental protection bureaus to ensure full compliance with PRC environmental regulations and requirements.

7. The work of the Project Environmental Management Department was supported by a third-party consortium consisting of two environmental consulting firms: (i) Hebei University of Science and Technology, and (ii) Hebei Tiandichaoyang Environmental Science and Technology Company. This consortium served as the environmental advisory agency for the ZPSHPP from 2004 to 2011. Hebei Keying Environment Testing Services was contracted to carry out environmental monitoring in 2012. For compliance with PRC environmental regulations and requirements, Hebei Environment Protection Bureau and Jingzing County Environment Protection Bureau conducted regular inspection of the ZPSHPP and supervised the environmental performance of the ZPSHPP construction. 8. For the ZPSHPP project component, institutional arrangements were established and environmental mitigation measures were adequately performed to reduce the direct impacts of the ZPSHPP construction. However, the ZPSHPP had limited authority to perform the agreed mitigation measures to promote aquaculture and control upstream water pollution control. The PCR mission noted that the environmental performance of all the project components, including the project components that did not receive ADB financing, followed EMP guidelines of the Project, PRC environmental regulations, standards, and requirements. Details of compliances with the environmental management plan (EMP) performance are in the Table A 11.1.

9. According to the agreed environmental monitoring and reporting requirements, environmental monitoring reports to be submitted to ADB were limited only to the ZPSHPP project component. Semiannual environmental monitoring reports were prepared from 2004 to 2006, and annual environmental monitoring reports were prepared from 2007 to 2012. Environmental monitoring reports between 2004 and 2008, and for 2012 were submitted to ADB. During the PCR mission, environmental monitoring reports from 2009 to 2011 were collected. All environmental monitoring reports from 2004 and 2012 were disclosed on the ADB website. 10. At project appraisal, the SEIA estimated the cost of implementing the EMP during project construction phase to be CNY10.68 million ($1.29 million equivalent). Environmental protection measures during construction phase included wastewater treatment, noise and dust control, solid waste treatment, soil treatment, vegetation protection, environmental monitoring during construction, public health monitoring and protection, and environmental protection and supervision. According to the ZPSC, the total cost for environmental protection during

Page 53: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

44 Appendix 11

construction phase was CNY15.7 million; the detailed cost breakdown by activity was not available. C. Environment Impacts and Mitigation Undertaken

11. The SEIA identified the likely environmental impacts of different project components; and proposed mitigation measures relevant to those impacts during the siting and design, construction, and operation phases. Table A11.1 presents the agreed EMP at project appraisal, including, possible negative impacts, measures to mitigate these impacts, and the implementation status of mitigation measures during project implementation. 12. ZPSC established an environmental emergency response plan in July 2007. The plan outlines (i) general principles; (ii) the definition of environmental emergencies; (iii) reporting and assessment of environmental emergencies; (iv) an early warning and response system; (v) command, organization, and roles and responsibilities; and (vi) assurances. According to the plan, environmental emergencies are defined as pollution accidents related to the release of waste gas, wastewater, solid wastes, and toxic and hazardous chemicals. The plan requires the reporting of an environmental emergency specialist/consultant to the project monitoring office within 1 hour and for the local environmental protection bureau within 2 hours from the time of occurrence. By the time of the PCR mission, no emergency event had occurred.

Table A11.1: Environmental Impacts, Mitigation Measures, and Implementation Status of Mitigation Measures

1,000 MW Zhanghewan Pumped Storage Hydro Power Plant

Phase Benefits Negative Impacts Proposed Mitigation Measures

Implementation of Mitigation Measures

Siting and Design

Rationalized base load versus peak plant operations; conversion of unused land at upper reservoir site to beneficial use

Inundation of 576 ha of land, including 225 ha of agricultural land, which cannot be readily replaced in immediate area

Inundated land will be offset by improved agricultural productivity in resettlement areas; combined with expanded irrigated area, greater unit and aggregated productivity will result.

Affected households have been provided with alternative farmlands and cash compensation. The increased capacity to hold water in the lower reservoir could expand irrigation capacity.

However, the irrigation canals for expanding irrigation coverage were not constructed at the time of PCR mission.

Creation of new upper reservoir and expansion of existing lower reservoir will allow expansion of fish and waterfowl populations, and provide capacity for expanded irrigation.

Relocation of total projected 3,254 residents in 905 households, of which 304 people in 95 households will move a short distance and remain in the reservoir area

“Land-for-Land” resettlement and rehabilitation program for displaced residents. Proposed resettlement areas have available agricultural land, currently producing below capacity.

Except 18 households, all the other affected people have been relocated and livelihood improvement assistance has been provided. The remaining households are expected to be resettled by September 2014.

Page 54: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 45

1,000 MW Zhanghewan Pumped Storage Hydro Power Plant Phase Benefits Negative Impacts Proposed

Mitigation Measures

Implementation of Mitigation Measures

Environmental rehabilitation of Laoyemiao Mountain upper reservoir area

Watershed management plan includes afforestation and revegetation, resulting in ecological restoration; Increase in variety and amount of fauna expected over long term

Ecological rehabilitation of upper reservoir area has been undertaken. At the time of the PCR mission, most revegetation in the project construction sites and landscaping works had been properly performed.

The PCR mission noted that Jingxing County completed afforestation activities in and around the lower reservoir and downstream of the river as part of the country afforestation program.

Construction Disturbance during construction; Temporary occupation of 86 ha of agricultural land

Appropriate construction mitigation (paving and spraying of roads for dust suppression) will maintain air quality within Grade II standards.

Multi-tube precipitators were installed at batch plants to reduce dust impacts. Personal protection devices like heavy-duty clothes and dust-proof masks were provided to workers.

Cement and other construction materials were transported by truck with proper covers. Water spraying on roads and construction sites was performed to suppress dust and associated impacts on workers and residences.

Operation Creation of new lake ecosystem will enhance watershed characteristics and support expanded aquaculture.

Future tourism development is a possibility.

Possible depletion of dissolved oxygen due to decaying plant material; possible fish mortality caused by depleted dissolved oxygen; possible algal blooms and eutrophication

Removal of structures and vegetation from reservoir areas to be inundated

Pumping/turbine operation will maintain dissolved oxygen levels.

Removal of structures and vegetation was undertaken prior to inundation. Water quality monitoring results show that dissolved oxygen is not an issue.

Page 55: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

46 Appendix 11

1,000 MW Zhanghewan Pumped Storage Hydro Power Plant Phase Benefits Negative Impacts Proposed

Mitigation Measures

Implementation of Mitigation Measures

Development of aquaculture (<0.5 ha) in lower reservoir expected to have positive financial and economic benefits

Possible loss of habitat for some fish species

Existing Zhanghewan and Huangbizhuang dams have permanently altered migratory fish habitat. New aquaculture will offset any incremental loss of habitat.

According to the domestic EIA prepared at project appraisal, migratory fish habitat does not exist because of the location and limited water flow. In addition, fish population has very low density.

Based on the information on fish habitat at and near the project areas, the ZPSHPP did not cause any serious adverse impact on fish habitat in the area.

Afforestation program will generate positive benefits from “economic” forests (apple, date, peach, and walnut trees) and sustainable timber harvesting.

Sedimentation in reservoirs causing backwater flooding and loss of storage capacity

Lower reservoir configuration includes sediment dam and sluice structure for sediment management. Watershed management plan will control excessive upstream erosion and sedimentation.

Sediment dam was installed to collect sediment and reduce the amount of sediment collected in the lower reservoir. ZPSP closely monitors the amount of sediment and cleans it up when needed.

Improve flood control

Loss of land area due to construction design requirements

Overall improvements in regional environment will offset land acquisition requirements.

There have been environmental benefits in terms of closure of coal-fired power plants and increased flood control capacity. However, there is insufficient data to state that environment benefit offset the land acquisition.

63 km Transmission Line Phase Benefits Negative Impacts Proposed

Mitigation Measures

Implementation of Mitigation Measures

Siting and Design

Expansion of electric supply capacity in southern Hebei Province

Permanent acquisition of 1.86 ha of land for construction of transmission lines; 0.73 ha will be permanently occupied for operation.

Minimal disturbance of agriculture land; no displacement or resettlement will be required; no sensitive or protected areas will be disturbed.

Transmission lines were installed on the hillside, where there is no residence or agriculture activity. Thus, it did not involve any displacement or resettlement of residents. In addition,

Page 56: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 47

63 km Transmission Line Phase Benefits Negative Impacts Proposed

Mitigation Measures

Implementation of Mitigation Measures

lines do not pass through any environmentally sensitive or protected areas.

Construction Possible creation of job opportunities for local residents

Air pollution from earthmoving and construction equipment; sanitary wastes from workers camp

Appropriate construction mitigation (paving and spraying of roads for dust suppression) will maintain air quality within Grade II Standards (GB3095-96). Provisions have been made for adequate sanitary facilities.

No resettlement was required.

Water spraying was performed during the construction of transmission lines to control fugitive dust. Ambient air quality results show that the project met Class II air quality standards. Adequate sanitary facilities that met workers’ health and safety requirements were installed and provided to construction workers. No resettlement was required.

Operation Could create feeding and nesting sites for birds, “edge effect” benefiting ecosystem adjacent to right-of-way

Disturbance associated with maintenance of lines (e.g., vegetation control); potential health hazards due to electromagnetic fields

Local government will control access to right-of-way, precluding health hazards. Vegetation control will favor mechanical maintenance over herbicide application.

Transmission towers are installed on steep mountain slopes with limited human activities. It seems that there is no issue that occurred due to human accessibility to the areas where the transmission lines are. No specific access control was performed.

Closure of Small, Old Power-Generating Units

Phase Benefits Negative Impacts Proposed Mitigation Measures

Implementation of Mitigation Measures

Coal consumption will be reduced by about 1.5 million tons per year. Air emissions and fly ash will be reduced proportionately.

Clean up of decommissioned sites; redeployment of power plant workers

Cleanup of power plant sites will follow national guidelines for redevelopment of industrial lands; reassignment, retaining, and reemployment will be conducted by Hebei Electric Power Company.

According to representatives from power companies, the closure of small power plants was performed following the relevant PRC regulations and requirements. No public complaints were received regarding the closure of small power plants.

Page 57: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

48 Appendix 11

Irrigation System Expansion

Phase Benefits Negative Impacts Proposed Mitigation Measures

Implementation of Mitigation Measures

Siting and Design

Achieve original design capacity to serve 8,167 ha irrigated area

Land required for construction/rehabilitation of canals has already been acquired.

Improved water supply and agricultural productivity will provide economic benefit, offsetting acquisition of land.

Irrigation system expansion was not implemented because of a delay in increasing water storage in the lower reservoir and reduced demand for irrigation water supply caused by a decline in farming activities.

Operations Improved productivity of agricultural land; improved supply of water for other uses

Possible increase of erosion due to tiling and harvesting; possible increased use of agricultural chemicals

Best management practices to be implemented for erosion control and agricultural chemical application

No effort was made to improve or adopt best management practices on erosion control, agricultural chemical use, and others as irrigation expansion was not carried out.

Expansion of Rural Electric System

Phase Benefits Negative Impacts Proposed Mitigation Measures

Implementation of Mitigation Measures

Siting and Design

Increased availability of grid-based electric power to rural and impoverished areas, with increased economic opportunities for rural residents

Right-of-way required for construction of transmission and distribution lines is 3.13 ha; an additional 8.56 ha will be occupied by substations.

Routing to minimize disruption of residents and agriculture activity; construction practices and schedules will be designed to reduce traffic and community disruptions.

The distribution lines were mostly laid along the roads, with no significant disruption to farming activities.

Operations Expanded electric supply will reduce residential coal consumption, improving indoor air quality and reducing health risks

Minor inconvenience of additional distribution poles and lines on right-of-way

Compensation for right-of-way access has been or will be made according to existing PRC laws and regulations.

As expansion of the rural electric system was initiated by HPG, these activities complied with PRC environmental regulations and requirements.

EIA = environment impact assessment, ha = hectares, HPG = Hebei Provincial Government, km = kilometer, MW = megawatt, PCR =project completion review, PRC = People’s Republic of China, ZPSC = Zhanghewan Pumped Storage Company, Ltd., ZPSHPP = Zhanghewan Pumped Storage Hydro Power Plant. Source: Asian Development Bank estimates.

D. Public Participation to Enhance Environmental Management Plan

13. A public participation program was implemented by the Project Environmental Management Department and the environmental monitoring and advisory agency from 2004 to 2012. The purpose of the program was to solicit the views of the affected people and to gain a better understanding of the project impacts and any improvement needed, to provide feedback to ZPSC for implementation of mitigation and corrective actions. Four different instruments were used for public engagement: (i) telephone hotlines, (ii) quarterly questionnaire surveys,

Page 58: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 49

(iii) interviews with people in the affected communities, and (iv) interviews with construction workers. Table A11.2 details how public participation was performed, concerns received through this process, and corrective actions taken by the ZPSHPP.

Table A11.2: Public Concerns and Corrective Actions Taken during Project Construction Year Details of Public Participation Concerns Received and Corrective Actions Taken

2004 Two telephone hotlines were in operation. Quarterly surveys were conducted. A total of 90 questionnaires were received (33% were completed by women). A total of 50 interviews with affected people were conducted through focus and random interviews over three periods. A total of 15 representatives from construction contractors were interviewed over three periods.

Dust control. Increased frequency of water spraying; 1.2 meter tall fences were erected around construction sites; digging more controlled; environmental inspection strengthened. Food waste dumping. Cleanup of food waste dumping; garbage bins added; training on waste management conducted. Exposed spoils. Restoration and rehabilitation of completed segments carried out; completed roads planted with trees; slope protection installed at spoil dumping sites. Explosion sound and vibration. Explosions limited to 11:30 am–12:00 noon.

2005 Two telephone hotlines were in operation. Quarterly surveys were conducted. A total of 267 interviews with affected people was conducted through focus and random interviews over three periods (49% of the participants were women). A total of 18 representatives from construction contractors were interviewed over three periods.

Dust control. Enhanced dust control measures by requesting construction trucks to cover cement, building materials; drivers were instructed to wash trucks and clean tires before they leave loading and unloading yards, and to slow down when passing villages and residential areas.

Positive feedback on the performance of environmental protection measures.

Positive feedback received due to better road access, improvement in transportation conditions, increased employment opportunities, and increased income generation by small businesses near the project.

2006 Two telephone hotlines were in operation. Surveys of 165 construction workers/managers and community members were conducted using random sampling methods, ad hoc visits, and face-to-face interviews.

Positive feedback on the performance of environmental protection measures.

Little concern on dust control—dust suppression measures like water spraying and vehicle control were enhanced.

2007 Two telephone hotlines were in operation. Two public opinion surveys were carried out; covering 161 participants (46% of them were female).

Positive feedback on the strengthened measures for environmental protection. Respondents were satisfied with greening, soil erosion control, spoil site rehabilitation, and dust and noise control.

A few negative comments on piling of construction garbage and exposed spoil sites in some spots.

2008 Two telephone hotlines were in operation. A questionnaire survey was carried out, covering 161 participants, of which 50% were female.

Positive feedback on the strengthened measures for environmental protection. Respondents were satisfied with greening, soil erosion control, spoil site rehabilitation, and dust and noise control. No complaints were received.

2009 Two telephone hotlines were in operation. A questionnaire survey of 75 participants was carried out, of which 50% were female.

Respondents are generally satisfied with environmental management works.

2010-2011

Two telephone hotlines were in operation. A questionnaire survey was conducted.

Respondents are generally satisfied with local environment, including water and air quality. Main concern was on ecological restoration of construction sites. Respondents believe that the project may bring employment opportunities for local residents.

2012 Two telephone hotlines were in operation. A survey was conducted in the last quarter of

Respondents generally thought the local environment quality is better or recovered to the level before

Page 59: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

50 Appendix 11

Year Details of Public Participation Concerns Received and Corrective Actions Taken

the year. ZPSHPP construction. Majority of respondents considered the water and soil conservation measures effective Some respondents mentioned that employment opportunities were created. Public thought the project may play a positive role in regional economy. Most respondents mentioned the project had some impact on ecological environment.

ZPSHPP = Zhanghewan Pumped Storage Hydro Power Plant. Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

E. Environmental Monitoring

14. The SEIA indicated the environmental monitoring program for the project. At project appraisal, the environmental monitoring program was developed focusing on the ZPSHPP. From 2004 to 2008, field sampling and laboratory tests were conducted by the subcontractors, Shijiazhuang City Environmental Monitoring Center and Jingxing County Environmental Monitoring Station. The environmental monitoring and advisory agency confirmed that (i) the monitoring exercises covering ambient environmental quality parameters are relevant to the environmental performance of the pumped storage project, (ii) sampling and analytical methods were credible, and (iii) monitoring results were all valid. Table A11.3 presents details of the environmental monitoring program and actual implementation activities under the program.

Table A11.3: Environmental Impacts, Mitigation Measures, and Implementation Status

Issue Major Impacts Mitigation Measures Monitoring Frequency Responsible Party and Compliance

Status Construction Period (2004–2009)

Air/ Noise Heavy equipment

operations and maintenance

Spray water for dust suppression

Equipment certified and maintained to meet national emission standard and noise standards

Daily/ongoing as needed

Continue operation of existing meteorological station

ZPSHPP EPO

Ambient air quality was monitored at different locations: office building area (2004–2012), construction camps (2004–2009), Ceyuzhen and adjacent villages (2004 and 2005), Yanzhuangcun Village (2006–2011). Daily average concentrations of TSP, SO2, NO2, and CO2 were measured.

Noise monitoring was conducted at different locations: office building area (2004–2012), construction camps (2004–2009), Ceyuzhen and adjacent villages (2004 and 2005), Yanzhuangcun Village (2006–2012).

The existing meteorological station is still running to monitor meteorological conditions in the project area.

Fully complied with

Water

Water-eroded sediment flux and construction waste run-off

Sediment barriers, runoff control dikes and ponds

Sanitary wastewater treatment for construction camps

Daily/ongoing as needed ZPSHPP EPO

Sediment barriers were constructed to reduce sediment in lower reservoir. Sediment was collected regularly.

As for surface water quality at lower reservoir, a total of 26 parameters, including pH, TSS, COD, BOD, DO, NH3 -N, nitrate N, Cr6, TP, TN, oil, chlorophyll, phenol, cyanide, arsenic, Pb, Zn, fluoride, chloride, Hg, Cd, coliform, sulphate were measured taking samples from different locations to monitoring water quality of

Fully complied with

Page 60: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 51

Issue Major Impacts Mitigation Measures Monitoring Frequency Responsible Party and Compliance

Status Construction Period (2004–2009)

headwater, center, and tail water of lower reservoir.

As for wastewater, concentrations of TSS, COD, BOD, NH3-N were collected. From 2004 to 2006, wastewater quality was monitored at discharge outlets of the treatment facilities of the upper reservoir, lower reservoir, and office building area; outlet of the engineering wastewater treatment for underground system. In 2007, wastewater quality was monitored at discharge outlets of the treatment facilities of the upper reservoir, lower reservoir, and office building area; lower dam construction camp wastewater treatment facility; and underground system wastewater treatment facility. In 2008, when most of the civil works were completed, wastewater was measured only at the upper reservoir site wastewater treatment facility; lower reservoir site wastewater treatment facility; project management office wastewater treatment facility. From 2009 to 2012, wastewater quality was measured at project management office wastewater treatment facility. Treated wastewater was recycled on-site for watering vegetation.

Land Land grubbing and clearing of reservoir; demolition of houses and removal of debris; clearing and preparation of transmission line right-of-way

Spray water for dust suppression as necessary Routing of transmission line to minimize tree loss

Daily/ongoing as needed ZPSHPP EPO

Land protection measures were carried out by construction contractors as part of contract requirements. Site grading was done on time; slope excavation strictly followed the construction design and was properly done to ensure stability of slope. Dust suppression measures were performed frequently to mitigate dust impact. Throughout construction, dust control measures were strengthened, reflecting the public concern on dust.

Transmission line was properly routed to minimize tree loss and impacts to local residences.

Fully complied with

Public Health

Public health sanitary wastes and infectious diseases

Pre-employment health screening/certification of workers Clinics established to support construction camps

Daily/ongoing as needed

ZPSHPP EPO and health specialists plus support from Jingxing County Public Health Department

A health examination system was established. Construction workers were required to pass a health examination covering influenza, malaria, diarrhea, and virus hepatitis prior to entry to the construction sites. Regular health examinations were conducted for workers from 2004 to 2008. No infectious, epidemic, contagious, or transmittable diseases, including HIV/AIDS, were discovered.

Health examinations were also conducted for residents in the relocation areas of upper and lower reservoirs from 2004 to 2006. In 2007 and 2008, the environmental advisory agency visited Yanzhuang Village and local clinics. No risk of major contagious diseases was found, including HIV/AIDS.

In 2004 and 2005, training on public health and safety was carried out for construction contractors, in accordance with Shijiazhuang regulations on public health emergency response.

During construction, two temporary clinics were built on-site in close cooperation with Ceyu town clinic. Each clinic had one doctor and two nurses to handle health issues for workers. Regular, periodic dialogue and exchange of information was carried out with Ceyu town clinic.

The management of water supply and waste disposal was strengthened.

Fully complied with

Page 61: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

52 Appendix 11

Operation Period (2010–2012)

Air and Water

Changes in local climate conditions Water sedimentation Accumulation of pollutants

Erosion control structures and revegetation Sanitary wastewater treatment systems

Cooperation with Shanxi EPB to limit upstream pollutant discharges

Continuous operation of existing meteorological station

Ambient air monitoring on quarterly basis

Quarterly for routine water quality

Monthly for human wastewater

ZPSHPP EPO and EPBs

Existing meteorological station is still operating.

During operation, the domestic wastewater is treated on-site using aeration treatment process, and then recycled on-site for watering vegetation.

The pumped storage power station has not been working with Shanxi EPB to limit upstream pollutant discharges. During operation, water quality monitoring was conducted once a year.

During operation, ambient air quality monitoring was conducted once a year.

Partially complied with. (Instead of the SEIA requirement, the project followed the PRC monitoring frequencies requirements).

Aquaculture

Fish population possible entrainment in pump/turbines

Active aquaculture limited to maintain desired dissolved oxygen content

Annual for first 5 years, then every 5 years if population thrives

Correction action to be developed if fish population does not expand

ZPSHPP EPO and EPBs

No action was taken to check fish population in and nearby the project site. According to the Zhanghewan Pumped Storage Project, no fish has been seen in lower reservoir or immediate upstream river.

Not complied with

Land

Land inundation and potential erosion

Buffer zone established

Revegetation and afforestation

Control of human access

Annual for first 5 years; every 5 years after that

ZPSHPP EPO, coordination with forestry and water resource agencies

The revegetation work was completed just before the PCR mission. ZPSHPP submitted and obtained approval for the soil conservation report in 2014.

Ongoing

Social impact mitigation and public health

Social impact mitigation and public health resettlement and worker redeployment.

Land acquisition plan, resettlement plan, and worker redeployment plans approved by the government and ADB

Monitored by ZPSHPP during project construction. ADB has been monitoring the social impacts of resettlement sites using staff consultants since then.

ZPSHPP EPO, health specialists with coordination/support from Jingxing County Public Health Department

The ZPSHPP affected a total of 2,878 persons in eight villages due to expansion of the surface area of the lower reservoir. In five out of eight villages, the affected people (total 446 persons) were resettled within the same village. Residents of

Beihaoting Village moved to newly established Beihaoting Village in December 2007 prior to commissioning of the ZPSHPP. The relocation of Shimen Village was completed in December 2010. As for affected people from Nanhaoting Village (780 persons), the relocation of 193 out of 211 affected households was completed in December 2013. By the time of the PCR mission, Jingxing County government expects the remaining 18 households will move to the new village within the next 6 months after they have reached agreement on their entitlement for compensation and livelihood support mechanisms. It is expected that this issue will be resolved by September 2014.

Ongoing

BOD = biochemical oxygen demand, CO2 = Carbon monoxide, COD = chemical oxygen demand, EPB = environmental protection bureau, EPO = environmental planning office, N = nitrate, NH3-N = ammonia nitrogen, NO2 = Nitrogen dioxide, Pb = Lead, SO2 = Sulfur dioxide, TN = total nitrogen, TP = total phosphorous, TSP = total

Page 62: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 53

suspended particulates, TSS = total suspended solids, Zinc = Zn, ZPSHPP = Zhanghewan Pumped Storage Hydro Power Plant.

Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

15. Table A11.4 presents the monitoring results of effluent discharged at various wastewater treatment facilities at the project site. The results show that wastewater quality met Class I comprehensive wastewater discharge standards (GB8978-1996) and wastewater treatment facilities have been working properly.

Table A11.4: Wastewater Quality Data

At Upper Reservoir Site Wastewater Treatment Facility (2004–2008)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

Class I

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

70 SS Below

standard Below

standard Below

standard 34–44 34–44 … … … …

100 COD Below

standard Below

standard Below

standard 53.1–70.1 53.1–76 … … … …

30 BOD Below

standard Below

standard Below

standard 20.4–24.3 24.0–27 … … … …

15 NH3-N Below

standard Below

standard Below

standard 2.4–9.7 9.0–9.7 … … … …

10 Petroleum Below

standard Below

standard Below

standard … … … … … …

At Lower Reservoir Site Wastewater Treatment Facility (2004–2008)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

Class I

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

70 SS Below

standard Below

standard Below

standard 23–45 19–30 … … … …

100 COD Below

standard Below

standard Below

standard 59.4–73.6 66.5–72.6 … … … …

30 BOD Below

standard Below

standard Below

standard 21.3–26.7 22.8–27.3 … … … …

15

NH3-N Below

standard Below

standard Below

standard 3.1–9.6 3.1–9.6 … … … …

At Lower Reservoir Site Wastewater Treatment Facility (2004–2008)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

10 Petroleum Below

standard Below

standard Below

standard … … … … … …

Page 63: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

54 Appendix 11

At Project Management Office Wastewater Treatment Facility (2004–2012)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

Class I

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

70 SS Below

standard Below

standard Below

standard 19–38.4 25–45 32–43 45 39–48 37–39

100 COD Below

standard Below

standard Below

standard 54.5–70 65.3–71 62.9–67 65 62–68 63–64

30 BOD Below

standard Below

standard Below

standard 22.8–27.3 21.3–26.7 24.2–27.2 23.7 20.3–22.6 24.3–24.8

15 NH3-N Below

standard Below

standard Below

standard 2.42–10.8 9.2–10.6 9.5–10.1 10.8 9.52–9.7 9.7–9.7

10 Petroleum Below

standard Below

standard Below

standard … … … … … 5.05–5.1

At Lower Dam Construction Camp Wastewater Treatment Facility (2004–2007)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

Class I

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

70 SS … … … 33–39 … … … … … 100 COD … … … 69.3–80 … … … … … 30 BOD … … … 23.7–27.9 … … … … … 15 NH3-N … … … 6.6–8.7 … … … … … 10 Petroleum … … … … … … … … …

At Underground System Wastewater Treatment Facility (2004–2007)

Comprehensive Wastewater Discharge Standards

(GB8978-1996)

Quality of effluent discharged after wastewater treatment

Class I

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

70 SS Below

standard Below

standard Below

standard 18–30 … … … … …

100 COD Below

standard Below

standard Below

standard 39–40.5 … … … … …

30 BOD Below

standard Below

standard Below

standard 5.4–6.0 … … … … …

15 NH3-N Below

standard Below

standard Below

standard 2.8–4.2 … … … … …

10 Petroleum Below

standard Below

standard Below

standard 0.0 … … … … …

(…) = data not available, BOD = biochemical oxygen demand, COD = chemical oxygen demand, NH3-N = ammonia nitrogen, SS = suspended solids. Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

16. Table A11.5 presents ambient air quality, which was measured at and around the project sites. The monitoring results show that ambient air quality met Class II air quality standards (GB 3095-1996).

Page 64: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 55

Table A11.5: Ambient Air Quality Data during Construction and Operation

Office Building of the Pumped Storage Power Station (2004–2012)

Air Quality Standards (GB3095-

1996)(Daily, mg/m

3)

Ambient air quality (daily average, mg/m3)

Class II

Year 2004 2005 2006 2007 2008 2009 2010-2011 2012

0.15 SO2

Below standard

0.0–0.1 0.0–0.1 0.0–0.1 0.0 0.0 0.0 0.0

0.12 NO2

Below standard

0.0 0.0–0.1 0.0 0.0 0.0 0.0 0.0

4.00 CO

Below standard

0.8–1.4 0.8–1.9 0.8–1.0 0.7–0.9 0.8–0.9 0.8 …

0.30 TSP

Below standard

0.1–0.3 0.1–0.3 0.1 0.1 0.1 0.1 0.1

Workers Camp (2004–2009)

Air Quality Standards (GB3095-

1996) (Daily,

mg/m3)

Ambient air quality (daily average, mg/m3)

Class II

Year 2004 2005 2006 2007 2008 2009 2010 2012

0.15 SO2

Below standard

0.0–0.1 0.0–0.1 0.0 0.0 0.0 … …

0.12 NO2

Below standard

0.0 0.0–0.1 0.0 0.0 0.0 … …

4.00 CO

Below standard

0.9–1.4 0.8–2.0 0.8–0.9 0.7–0.8 0.8–0.9 … …

0.30 TSP 0.352 0.1–0.3 0.1–0.3 0.1 –0.2 0.1–0.2 0.1–0.2 … …

Ceyuzhen Village (2004 and 2005) and Yanzhuang Village (2006–2011)

Air Quality Standards (GB3095-

1996) (Daily,

mg/m3)

Ambient air quality (daily average, mg/m3)

Class II

Year 2004 2005 2006 2007 2008 2009 2010-2011 2012

0.15 SO2

Below standard

0.0–0.1 0.0–0.1 0.0–0.1 0.0 0.0 0.0 …

0.12 NO2

Below standard

0.0 0.0–0.1 0.0 0.0 0.0 0.0 …

4.00 CO

Below standard

0.8–1.4 0.8–2.0 0.8–1.0 0.8–0.9 0.8–0.9 0.8 …

0.30 TSP

0.202–0.321

0.1–0.3 0.1–0.3 0.1–0.2 0.1–0.1 0.1 0.1 …

(…) = data not available, BOD = biochemical oxygen demand, CO2 = Carbon monoxide, COD = chemical oxygen demand, mg/m

3 = milligram per cubic meter, NO2 = Nitrogen dioxide, SO2 = Sulfur dioxide, SS = suspended solids,

TSP = total suspended particulates. Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

17. Table A11.6 shows water quality data at the lower reservoir during construction and operation. The monitoring results show that all the monitoring parameters, except for total nitrogen (TN) and total phosphorus (TP), met Class II surface water quality standards (GB3828-

Page 65: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

56 Appendix 11

2002) throughout the project construction and operation. According to the domestic EIA at project appraisal, other parameters except for TN and TP met the standards. Thus, an increase in TN and TP is unlikely to be caused by the project, as they are usually associated with agriculture.

Table A11.6: Surface Water Quality Data during Construction and Operation

Lower Reservoir Intake (headwater)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

Class II Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

6-9 pH

Below standard

Below standard

Below standard

7.9–8.5 8.0–8.5 8.1–8.4 7.8 8.1–8.4 7.7–7.73

≥ 6 mg/l DO

Below standard

Below standard

Below standard

8.6–10.1 9.4–10.8 10.1–10.5 9.7 10.1–10.5 …

≤ 4 mg/l COD(Mn)

Below standard

Below standard

Below standard

1.4–2.1 1.2–2.1 2.0–2.1 3.1 2.0–2.1 1.7–1.8

≤ 15 mg/l

BOD Below

standard Below

standard Below

standard 4.5–13.9 4.2–7.0 6.5–7.1 5.7 6.5–7.1 11–12

≤ 0.5 NH3-N Below Below Exceedance 0.1 0.4–0.7 0.4–0.6 0.2 0.4–0.6 0.0

Lower Reservoir Intake (headwater)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

≤ 0.025 mg/l

TP 0.1–0.2 Below

standard Exceedance 0.0–0.1 0.1 0.1 0.10 0.1–0.1 0.03

≤ 0.5 mg/l

TN 0.1–1.7

1.65–7.23

(average 4.44)

Exceedance 1.2–4.3 0.7–0.9 0.7–0.8 2.7 0.7–0.8 1.9

≤ 1.0 mg/l

Zn Below

standard Below

standard Below

standard 0.0–0.1 0.0 0.0 0.1 0.0 0.05

≤ 1.0 mg/l

Fluoride Below

standard Below

standard Below

standard 0.2–0.4 0.3–0.4 0.4 0.3 0.4 0.1

≤ 10 mg/l

Nitrate-N Below

standard Below

standard Below

standard 2.4–4.7 2.5–3.6 2.8–2.9 0.5 2.8–3.0 2.4–2.6

≤ 15 mg/l

SS Below

standard Below

standard Below

standard 5–10 <10 <10 8 <10 20–25

0.05 mg/l

Arsenic Below

standard Below

standard Below

standard 0.0 <0.0 <0.0 0.0 <0.0 0.0

≤ 0.00005

mg/l Hg

Below standard

Below standard

Below standard 0.0–0.1 <0.0 <0.0 0.0 <0.0 0.0–0.1

≤ 0.005 mg/l

Cd Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 <0.0

Not detected

≤ 0.05 mg/l

Cr+6

Below

standard Below

standard Below

standard 0.0 <0.0 <0.0 0.0 <0.0 0.0

≤ 0.01 mg/l

Pb Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 <0.0

Not Detected

≤ 0.05 mg/l

Cyanide Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 <0.0 0.0

≤ 0.002 mg/l

Phenol Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 <0.0 0.0

≤ 0.05 mg/l

Oils

Below standard

Below standard

Below standard 0.0 0.0 0.0 0.0 0.0 …

Page 66: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 57

Lower Reservoir Intake (headwater)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

≤ 0.1 mg/l

Sulfide Below

standard Below

standard Below

standard 0.0 0.0 0.0 0.0 0.0 0.0

≤ 250 mg/l

Chloride Below

standard Below

standard Below

standard 23.7–58.7 42.1–55.9 58–75 12.1 58–75 17

≤ 2000/l Coliform count

Below standard

Below standard

Below standard

690–1240 698–813 759–807 759 759–807 …

Lower Reservoir Center

Surface Water Quality Standards (GB3838-2002)

Surface water quality (annual average, mg/l)

Class II Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

6-9 pH

Below standard

Below standard

Below standard

7.8–8.5 7.9–8.2 8.1–8.2 8.1 8.0–8.1 7.9

≥ 6 mg/l DO

Below standard

Below standard

Below standard

8.0–9.2 9.2–9.23 9.3–9.4 9.7 9.3–9.4 …

≤ 4 mg/l COD (Mn)

Below standard

Below standard

Below standard

1.6–2.1 1.3–1.7 1.5–1.6 1.5 1.6–1.7 2.1–2.2

≤ 15 mg/l

BOD Below

standard Below

standard Below

standard 4.1–7.3 4.0–7.0 4.9–5.1 4.8 14.0–15 13

≤ 0.5 mg/l

NH3-N Below

standard Below

standard Exceedance 0.5–1.0 0.6–0.8 0.6 0.1 0.0–0.1 0.0

≤ 0.025 mg/l

TP

0.111–0.156

(average 0.133)

Below standard

Exceedance 0.0–0.1 0.1 0.1–0.7 0.1 0.1 0.0

≤ 0.5 TN

1.13–2.58

1.98–7.12

Exceedance 1.0–1.1 1.1–1.3 1.0–1.1 1.2 1.9–2.6 2.1–2.2

Lower Reservoir Center

Surface Water Quality Standards (GB3838-2002)

Surface water quality (annual average, mg/l)

≤ 1.0 mg/l

Zn Below

standard Below

standard Below

standard <0.0 <0.02 <0.0 0.1 0.1 0.1

≤ 1.0 mg/l

Fluoride Below

standard Below

standard Below

standard 0.2–0.3 0.3–0.4 0.2–0.3 0.2 0.1–0.3 0.2

≤ 10 mg/l

Nitrate-N Below

standard Below

standard Below

standard 2.5–4.7 2.3–4.5 3.9–4.4 4.4 0.1 2.6–2.7

≤ 15 mg/l

SS Below

standard Below

standard Below

standard <10 <10 <10 8 7–9 20–22

0.05 mg/l

Arsenic Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0 0.3

≤ 0.00005

mg/l Hg

Below standard

Below standard

Below standard <0.1 <0.0 <0.1 0.0 0.0 0.1

≤ 0.005 mg/l

Cd Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0

Not detected

≤ 0.05 mg/L

Cr

+6

Below standard

Below standard

Below standard <0.0 <0.0 <0.0 0.0 0.0 0.0

≤ 0.01 mg/l

Pb Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0

Not detected

≤ 0.05 mg/l

Cyanide Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0 0.0

≤ 0.002 mg/l

Phenol Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0 0.0

Page 67: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

58 Appendix 11

Lower Reservoir Center

Surface Water Quality Standards (GB3838-2002)

Surface water quality (annual average, mg/l)

≤ 0.05 mg/l

Oils Below

standard Below

standard Below

standard 0.0 0.0 0.0 0.0 0.0 …

≤ 0.1 mg/l

Sulfide Below

standard Below

standard Below

standard 0.0 0.0 0.0 0.0 0.0 0.0

≤ 250 mg/l

Chloride Below

standard Below

standard Below

standard 45.2–58.7 41.3–50.3 44.7–45.9 45.9 10.4–12.3 12–14

≤ 2000/l Coliform count

Below standard

Below standard

Below standard

870–1240 983–1240 929–987 910 870–935 …

Lower Reservoir Outlet (Tail water)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

Class II Year 2004 2005 2006 2007 2008 2009 2010 2011 2012

6-9 pH

Below standard

Below standard

Below standard

7.6–8.3 7.7–8.0 7.7–7.8 8.4 8.0–8.6 8.14–8.2

≥ 6 mg/l DO

Below standard

Below standard

Below standard

8.5–9.2 8.6–8.7 8.7–8.8 8.6 8.7–8.8 …

≤ 4 mg/l COD (Mn)

Below standard

Below standard

Below standard

1.2–1.7 1.9–2.1 1.9–2.1 2.6 1.7–1.8 2.3–2.4

≤ 15 mg/l

BOD Below

standard Below

standard Below

standard 3.9–11.6 3.9–4.7 4.1–4.2 6.2 14–14.2 12–13

≤ 0.5 mg/l

NH3-N Below

standard Below

standard Exceedance 0.1–0.8 0.5–0.7 0.5–0.6 0.3 0.1 0.0

≤ 0.025 mg/l

TP

0.106–0.150

(average 0.126)

0.01–0.263

(average 0.132)

Exceedance 0.1 0.1 0.1 0.5 0.1 0.1

≤ 0.5 mg/l

TN

1.12–1.88

(average 1.45)

1.98–8.36

(average 1.45)

Exceedance 0.1–1.8 1.0–1.3 1.1–1.2 3.2 1.9–2.5 2.0–2.01

≤ 1.0 mg/l

Zn Below

standard Below

standard Below

standard 0.0–0.1 <0.0 <0.0 0.1 0.1 0.1

Lower Reservoir Outlet (Tail water)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

≤ 1.0 mg/l

Fluoride Below

standard Below

standard Below

standard 0.2–0.4 0.2–0.3 0.1–0.2 0.3 0.1–0.3 0.2–0.3

≤ 10 mg/l

Nitrate-N Below

standard Below

standard Below

standard 1.7–2.8 1.8–2.1 1.9–2.1 0.1 0.1 2.2–2.6

≤ 15 mg/l

SS Below

standard Below

standard Below

standard 6–11 10–11 <10 8 6–7 14–16

0.05 mg/l

Arsenic Below

standard Below

standard Below

standard 0.0 <0.0 <0.0 0.0 0.0 0.2

≤ 0.00005

mg/l Hg

Below standard

Below standard

Below standard 0.0 <0.0 <0.0 0.0 0.0 0.1

≤ 0.005 mg/l

Cd Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0

Not detected

≤ 0.05 mg/l

Cr+6

Below

standard Below

standard Below

standard 0.0 <0.0 <0.0 0.0 0.0 0.0

≤ 0.01 mg/l

Pb

Below standard

Below standard

Below standard 0.0 <0.0 <0.0 0.0 0.0

Not detected

Page 68: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 11 59

Lower Reservoir Outlet (Tail water)

Surface Water Quality Standards (GB3838-2002)

Surface water quality (mg/l)

≤ 0.05 mg/l

Cyanide Below

standard Below

standard Below

standard 0.0 <0.0 <0.0 0.0 0.0 0.0

≤ 0.002 mg/l

Phenol Below

standard Below

standard Below

standard <0.0 <0.0 <0.0 0.0 0.0 0.0

≤ 0.05 mg/l

Oils Below

standard Below

standard Below

standard 0.0 0.0 0.0 0.0 0.0 …

≤ 0.1 mg/l

Sulfide Below

standard Below

standard Below

standard 0.0 0.0 0.0 0.0 0.0 0.0

≤ 250 mg/l

Chloride Below

standard Below

standard Below

standard 59–90 62–81 79–88 12.6 10.3–12.5 12

≤ 2000/l Coliform count

Below standard

Below standard

Below standard

861–954 869–954 891–940 891 918–940 …

(…) = data not available, BOD = biochemical oxygen demand, Cd = Cadmium, Cr = Chromium, COD Mn = chemical oxygen demand manganese, DO = dissolved oxygen, Hg = Mercury, mg/l = milligram per liter, N = nitrogen, NH3-N = ammonia nitrogen, Pb = Lead, pH = power of hydrogen, SS =suspended solids, TN = total nitrogen, TP = total phosphorous, Zinc = Zn. Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

18. Table A11.7 shows noise monitoring data at the lower reservoir during construction and operation. The results show that noise levels in and around the project area met Class I noise standards for urban areas (GB3096-1993).

Table A11.7: Noise Monitoring Data during Construction and Operation

Office Building of the Pumped Storage Power Station (2004–2012)

Noise standards for Urban Areas

(GB3096-1993) Noise [dB (A)]

Class I Year 2004 2005 2006 2007 2008 2009

2010-2011

2012

Day 55 52.3–56.4 48.6–54.5 42.8–51 42.3–53.6 42.3 42.3 40.9 49.5–49.9 Night 45 42.6–45.8 40.4–45.7 38–40.5 36.0–37.6 40.1 38.6 39.3 40.2–40.8

Workers Camp (2004–2009)

Noise standards for Urban Areas

(GB3096-1993) Noise [dB (A)]

Class I Year 2004 2005 2006 2007 2008 2009

2010-2011

2012

Day 55 52.3–56.4 47.1–54.5 48.7–51.5 43.4–53.2 41.9 40.2 … …

Workers Camp (2004–2009)

Noise standards for Urban Areas

(GB3096-1993) Noise [dB (A)]

Night 45 42.6–45.8 40.4–45.7 44.5–51.5 40.1–40.3 36.5 39.7 … …

Ceyuzhen Village (2004 and 2005) and anzhuang Village (2006–2012)

Noise standards for Urban Areas

(GB3096-1993)

Noise standards for Urban Areas (GB3096-1993)

Class I Year 2004 2005 2006 2007 2008 2009

2010-2011

2012

Day 55 52.3–56.4 47.8–54.5 42.7–49.1 39.6–54.7 39.1 38.9 39.3 49.2–49.4 Night 45 42.6–45.8 40.4–45.7 40.2–48.6 39.8–40.2 39.8 39.2 38.5 37.3–37.7

(…) = data not available, dB = decibel. Source: Zhanghewan Pumped Storage Hydro Power Plant environmental monitoring reports, 2004–2012.

Page 69: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

60 Appendix 11

19. Environmental monitoring was properly carried out throughout the project. The monitoring results show that the ZPSHPP did not cause any significant adverse impacts on air and water qualities in and around the project areas. Measures to mitigate noise and wastewater treatment were properly carried out. F. Environmental Benefits

20. The project saved an average of 1.45 million tons (t) of standard coal per annum as a result of the ZPSHPP. This translates into an average annual reduction of 4,233 t of total suspended particulates, 8,128 t of sulfur dioxide, 4,865 t of nitrogen oxide, and 3.62 million t of carbon monoxide (CO2). Table A11.8 presents details of coal savings and air pollutant reduction during operation.

Table A11.8: Calculated Coal Savings and Emissions Reduction during Operation (ton) Item 2009 2010 2011 2012 2013

Standard coal saving 1,517,186 1,481,984 1,510,729 1,394,219 1,352,647 CO2 emission reduction 3,782,344 3,694,586 3,766,247 3,475,789 3,372,149 SO2 emission reduction 8,496 8,299 8,460 7,808 7,575 NOX emission reduction 5,086 5,064 4,674 4,674 4,534 PM emission reduction 4,425 4,322 4,406 4,066 3,945 CO2 = carbon dioxide, NOX = nitrogen oxide, PM = particulate matter, SO2 = sulfur dioxide. Source: ADB Staff Estimates

21. ZPSHPP, which replaced old and inefficient small power plants and produces electricity to meet peak power demand in the region, contributes to the improvement of air quality through coal savings in the project area and to climate change mitigation. G. Conclusion, and Recommendation

22. The project design included several components and the responsibilities for implementing for implementing components are not closely coordinated. There were project components which were loosely linked to the core project component of the ZPSHPP and the implementing agency did not have the institutional mandate to ensure compliance with EMP for these components. In addition, environmental mitigation measures on rehabilitating the fish habitat and fish population and controlling upstream industrial water pollution was beyond the mandate of ZPSC and there should have been effective institutional arrangements for addressing these concerns. 23. The overall performance of ZPSHPP on EMP implementation, environmental monitoring, and reporting requirements is generally satisfactory. However, ADB recommends ZPSHPP to improve afforestation efforts to compensate ecological value loss caused by the upper reservoir construction.

Page 70: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 12 61

IMPLEMENTATION OF LAND ACQUISITION AND RESETTLEMENT PLAN AND OTHER SOCIAL BENEFITS

A. Project Description

1. The project is located in Hebei Province and involves (i) the construction of a 1,000 megawatt (MW) pumped storage power plant at Zhanghewan; (ii) a 500 kilovolt transmission line for transfer of electricity from the power plant to Hebei South Power Grid; (iii) rehabilitation of the rural electricity distribution network; (iv) closure of old and inefficient coal-fired power generation units; (v) support for reforms in the provincial power sector; (vi) irrigation improvement; and (vii) afforestation.

2. A land acquisition and resettlement plan (LARP) was prepared in 2002 for (i) the Zhanghewan pumped storage power plant and associated road construction, and (ii) transmission and distribution components. 3. According to the LARP, it was planned to (i) permanently acquire 576.0 hectares (ha) of land, of which 225.0 ha was farmland; (ii) temporarily occupy 86.0 ha of land; and (iii) demolish 81,800 square meters (m2) of houses, primarily because of reservoir inundation. In addition, some public infrastructure, facilities, and assets were to be affected, including irrigation canals, village roads, water towers, public wells, telecommunication and transmission lines, telephone lines, a school, and clinics. The affected people were estimated to include 854 households, with 2,907 people from six villages. The cost estimate for the LARP was CNY150.6 million in 2002. The planned resettlement and land acquisition impact by component is summarized in Table A12.1.

Table A12.1: Planned Land Acquisition and Resettlement

Land Acquisition (ha) Temporary Occupation

(ha)

Houses Demolished

(m2)

Estimated Affected

Component

Total Permanent

Of which, farmland

Households People

Reservoir Inundation 330.0 202.9 0.0 81,700 813 2,776

Construction Site 245.3 21.5 84.1 100 14 45

Transmission Line 0.7 0.6 1.9 0 27 86

Total 576.0 225.0 86.0 81,800 854 2,907

ha = hectare, m2 = square meter.

Source: Original land acquisition and resettlement plan, 2002.

B. Land Acquisition Planning, Impact, and Budget

4. The LARP was prepared by Beijing Hydroelectric Investigation Design and Research Institute for Zhanghewan Pumped Storage Company (ZPSC) in March 2002, in accordance with the Involuntary Resettlement Policy (1995) of the Asian Development Bank (ADB) and relevant laws and regulations of the People’s Republic of China (PRC).1 Table A12.2 presents the actual resettlement and land acquisition.

1 Preparation of the LARP was guided by the Regulation of Land Requisition and Resettlement for Large and

Medium Scale Water Conservancy and Hydroelectric Projects. The compensation rates followed the provision of the Land Administration Law, 1998.

Page 71: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

62 Appendix 12

Table A12.2: Actual Land Acquisition and Resettlement

Land Acquisition (ha) Temporary

Occupation (ha)

Houses Demolished

(m2)

Estimated Affected

Component

Total permanent

Of which, farmland

Households People

Reservoir Inundation 324.7 198.8 0.0 79,600 775 2,833

Construction Site 242.1 20.4 52.8 0 14 45

Transmission Line 0.6 0.3 1.3a 0 23 81

Total 567.4 219.5 54.1 79,600 812 2,959

ha = hectare, m2 = square meter.

a 1.33 ha of temporary land occupation is estimated by the project managers.

Source: Jingxing County Resettlement Office.

5. The actual permanent land acquisition was 567.4 ha, which was 8.67 ha less than the estimated 576.0 ha. The actual temporary land occupation was 54.1 ha, which was 31.8 ha lower than the estimated 86.0 ha. The actual housing demolition was 79,596 m2, down 1,584 m2

from the estimated 81,800 m2. The comparison of planned and actual resettlement and land acquisition is summarized in Table A12.3.

Table A12.3: Planned and Actual Land Acquisition and Housing Demolition

Component Permanent Land Acquisition

(ha) Temporary Land Occupation

(ha) Structure Demolition

(10,000 m2)

Planned Actual Difference Planned Actual Difference Planned Actual Difference

Reservoir Inundation

330.0 324.7 (5.3) 0.0 0.0 0.0 8.2 8.0 (0.2)

Construction Site

245.3 242.1 (3.3) 84.1 52.8 (31.3) 0.0 0.0 (0.0)

TransmissionLine

0.7 0.6 (0.1) 1.9 1.3 (0.5) 0.0 0.0 0.0

Total 576.0 567.4 (8.7) 86.0 54.1 (31.8) 8.2 8.0 (0.2)

( ) = negative, ha = hectare, m2 = square meter.

Source: Jingxing County Resettlement Office.

6. Permanent land acquisition actually affected 812 households, which was 42 households less than the estimated 854 households, and 2,959 people, which was 52 people more than the estimated 2,907 people. The comparison of planned and actual affected people is summarized in Table A12.4.

Table A12.4: Planned and Actual Affected People by Component and Village

Component/Village Household People

Planned Actual Difference Planned Actual Difference Reservoir Inundation 827 789 (38) 2,821 2,878 57 Nansi 85 85 0 291 291 0 Shimen 64 64 0 229 229 0 Beihaoting 113 98 (15) 417 343 (74) Nanhaoting 461 438 (23) 1,511 1,642 131 Zhanghewan 47 47 0 168 168 0 Yanzhuang 43 43 0 160 160 0 Ceyu 11 14 3 35 45 10 Zhuhui 3 0 (3) 10 0 (10) Transmission Line 27 23 (4) 86 81 (5) Construction Site 14 14 0 45 45 0

Total 868 826 (42) 2,952 3,004 52

( ) = negative. Source: Original resettlement plan in 2002 and various monitoring reports.

Page 72: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 12 63

7. The total cost of land acquisition was CNY289.8 million, which is CNY139.2 million more than the LARP estimates. This is mainly due to the significant increase in compensation rates for permanent land acquisition of the resettlement site for Nanhaoting Village (the largest affected village) because of long delayed relocation. The compensation rate for irrigated land, for instance, increased to CNY720,000/ha after 2009 from the planned CNY229,800/ha in 2002. The comparisons of planned and actual cost in total and in some key areas are summarized in Table A12.5 and comparison of planned and actual compensation rates are in Table A12.6.

Table A12.5: Planned and Actual Land Acquisition Cost (CNY million)

Item Cost

Planned Actual Difference

Compensation for land acquisition (used to restore livelihoods)

37.3 49.7 12.4

Infrastructure construction for resettlement area 19.8 32.9 13.1 Building new houses for relocated people 15.71 38.4 22.7 Other costs

a 77.8 168.8 91.0

Total 150.6 289.8 139.2 a Includes cost for the two bridges and roads in the old village, which have not yet been completed, and taxes and

fees. Source: Original resettlement plan, monitoring reports, and Jingxing County Resettlement Office.

Table A12.6: Planned and Actual Land Compensation Rates

Period Type of Land Planned (CNY/ha) Actual (CNY/ha)

Before 2009 Irrigation land 229,828.5 282,865.9

Dry land 93,284.1 114,811.2

After 2009 Irrigation land 229,828.5 720,000.0

Dry land 93,284.1 277,500.0

CNY = yuan, ha = hectare. Source: Monitoring reports and Jingxing County Resettlement Office.

C. Resettlement Management, Supervision, and Monitoring

8. Resettlement for the project was implemented in accordance with the Regulation of Land Requisition and Resettlement for Large and Medium Scale Water Conservancy and Hydroelectric Projects of 1991. Compensation rates followed the provision of the Land Administration Law, 1998. Jingxing County resettlement office was established upon project commencement, and has been operated by eight professional staff, including two staff from ZPSC. The office was responsible for undertaking the LARP, including project planning, implementation, supervision, monitoring, reporting, and financing. The office managed the land acquisition and resettlement activities well because they established a strong communication channel with affected people and implemented the land acquisition and resettlement activities accommodating the needs of affected people.

9. Four (Nasi, Zhanghewan, Yanzhuang, and Beihaoting) out of six villages completed the land acquisition and resettlement in 2006 or early 2007. The remaining two villages (Shimen and Nanhaoting) took much longer than planned since careful public consultation with affected people was needed to reach a consensus on resettlement arrangements. The delay in completing the resettlement of Nanhaoting village limited the maximum water level to 474 meters (m) in comparison to the designed water level of 480 m, but this did not affect the

Page 73: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

64 Appendix 12

operation of the power plant. This was feasible as the power plant is a pumped storage power plant and does not require a large amount of water storage for its operation. However, it reduced the flood control capability of the project, and provision of water for irrigation. Because of the reduction in agricultural activity, water demand for irrigation decreased. Hence, the economic cost caused by the delay in completing the resettlement was insignificant. The land acquisition completion dates by affected village are in Table A12.7.

Table A12.7: Village Resettlement Completion Dates

Village Planned Actual Difference (months)

Nansi April 2006 April 2006 0

Zhanghewan April 2006 April 2006 0

Yanzhuang April 2006 April 2006 0

Beihaoting April 2006 January 2007 9

Shimen April 2006 January 2010 43

Nanhaoting - original - revised

April 2006 December 2012

-- July 2014

75 19

Note: A supplementary resettlement plan made for Nanhaoting village in 2012 included a revised implementation schedule. Source: Monitoring reports and the project offices.

10. ZPSC engaged Xiamen University as the independent external monitor to undertake resettlement supervision, monitoring, and evaluation for the project on a quarterly basis from 2006 to 2008. This included information on the status of land acquisition and resettlement, survey results of affected persons, disbursement status of the resettlement budget, capacity building training for concerned officials, and public consultation. The independent monitoring was suspended because of the delay in finalizing the resettlement sites for Beihaoting and Nanhaoting Villages and the absence of progress on the ground from 2008 to 2010. Since 2006, ADB carried out monitoring on 12 occasions through the staff consultant and ADB missions to assess the progress of outstanding resettlement issues in two villages (Beihaoting and Nanhaoting). D. Information Disclosure, Consultation, and Participation

11. Jingxin County resettlement office applied a consultative and participatory process in the project planning, design, implementation, and monitoring. All affected persons received full information on the project, on resettlement and land acquisition policies, compensation measures, grievance procedures, and on legal rights. Jingxin County resettlement office held a series of consultation meetings with village leaders and affected households, including female representatives from affected villages, during preparation of the feasibility study and LARP, and implementation of land acquisition and resettlement. A land acquisition and resettlement booklet was distributed to the affected people. E. Grievance Redress Mechanisms 12. A grievance redress mechanism was established at every level of government, stipulating procedures in a transparent and efficient manner. The affected people could appeal through township land administration divisions and township governments, county land administration bureaus and governments, power transmission companies, and power supply companies, if they had problems or grievances regarding land acquisition, housing demolition

Page 74: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 12 65

and relocation, compensation, and resettlement. No complaint was formally reported from the affected people or nongovernment organizations during the project implementation period. However, through informal procedures and consultations, the resettlement concerns raised by villagers in Beihaoting and Nanhaoting were fully considered and addressed in a manner that satisfied all affected villagers. F. Income Restoration and Rehabilitation, and Job Creation by Village

13. Out of the six relocated villages, Nansi, New Zhanghewan, and Yanzhuang were resettled in 2006; New Beihaoting in 2007 and New Shimen in 2010; and Nanhaoting was substantially completed by April 2014. The first five villages were evaluated based on a sample household survey in 2012 and further information collected in March 2014 through key informant interviews. New Nanhaoting Village was evaluated using a sample household survey, group discussion, and key informant interview in March 2014. Impacts of land acquisition on the host villages were also briefly assessed.

14. New Nanhaoting Village. This village was affected by the construction of the lower reservoir of the power plant. It was the last one relocated quite recently, but still has some remaining issues. The new resettlement village for the affected households of Nanhaoting village was completed in December 2013 and 96% of the affected households relocated to the new village as of April 2014. However, 18 families have not moved as they have not yet reached agreement with the county government regarding their entitlement to new houses and compensation as well as uncertainty regarding livelihood options in the new village. The outstanding resettlement issues are expected to be resolved by September 2014.

15. The households were resettled from the old Nanhaoting Village to an area where the land was contributed by four villages and Xiulin township. The relocated households formed new Nanhaoting Village, which is next to a main road to the county center. The village is 12 kilometers (km) from Xiulin township center and 20 km from the county center.

16. Each household was granted a new single-story house of 133 square meters (m2) with a yard of 47 m2. The house has a separate kitchen and dining room, toilet and shower room, and three bedrooms. The houses can accommodate a second floor at their own cost, which the majority of households has done. The houses have access to basic infrastructure such as water, electricity, internet, and telecommunications. Many of the households have television, air conditioning, an electric washing machine, cooking stoves using natural gas, and a solar heater for hot water.

17. Affected assets were compensated at replacement cost. Each person received 513 m2

farmland in New Nanhaoting Village, and tenure status for forestland above the inundation line remains unchanged. In addition, (i) affected households will receive a subsidy of CNY75 per m2

for irrigation cost for 30 years, which will be paid to the households in three installments within the next 3 years; (ii) each affected person is supported by a government subsidy of CNY50 per month for 20 years; and (iii) a transitional subsidy of CNY600 per person per month for 6 months was paid in a single payment.

18. After villagers moved into the new area, two sessions of skills training were provided by the township and county governments. The villagers have been looking for employment opportunities in the factories through referral from their relatives and friends. As of now, 13.2% of laborers earn a salary in the nearby factories, 11.8% are doing business, 10.3% are engaged in transportation, 42.6% of laborers migrated outside, and 22.1% (mainly female) stay at home looking after children and the elderly, and doing housework. Figures A12.1 and A12.2 show a

Page 75: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

66 Appendix 12

comparison of the employment structure before and after resettlement. Most villagers relied on migrant work rather than farming in the old village, and more laborers are engaged in transport, factory, and self-employment, while fewer migrated outside after resettlement. Therefore, moving to the new village, which is closer to township and county centers, was beneficial to many of the affected people.

19. The major reasons for the changes in the employment structure (i) fewer laborers migrated outside because they need to decorate their new houses; (ii) more employment opportunities exist near the village in factories such as the textile mill, coal plants, and paper mill; and (iii) road conditions are better and demand is greater for transportation services.

Source: ADB Staff Estimates based on consultant’s report

Source: ADB Staff Estimates based on consultant’s report

Page 76: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 12 67

20. Salaries from nearby factories are more than CNY1,500 per month. Earnings from providing transportation services with own truck or tractor is about CNY3,000 per month on average. Net income from doing business ranges from CNY1,000 to CNY5,000. Average annual household income in New Nanhaoting Village was CNY10,285 in 2013, which is more than double the household income before relocation. The income is also higher than the average household income of CNY8,765 in 2012 in Jingxing County. 2

21. According to the sample survey, 100% of affected households are satisfied with housing conditions, income opportunities and salaries, access to school and hospital, transportation conditions, and access to utilities and public services.

22. New Beihaoting Village. This village was affected by the construction of the lower reservoir of the power plant. The land and all houses of the village were inundated by the lower reservoir. The whole village (343 persons, 98 households) was resettled to Zhongle and Dongzheng Villages of Beizheng township and formed New Beihaoting Village in 2007. The following resettlement and income restoration measures were taken: (i) a 143 m2 single-story house was granted to each affected household; (ii) affected assets were compensated at replacement cost; (iii) each affected person who had farmland prior to relocation obtained the same size of farmland of 533 m2 in the new village; (iv) each affected person is supported by a government subsidy of CNY50 per month for 20 years; and (v) tenure status for forestland above the inundation line remain unchanged.

23. Notable observations in its housing and social infrastructure of newly constructed Beihaoting Village are as follows: (i) each household has an individual heating system; (ii) about half the households opted for two-story house with attic storage with additional cost of house construction borne by the affected party; (iii) 12 households have computer and internet access; (iv) large water tanks with piped water supply; and (v) some households have air conditioning units and washing machines. The village is located close to a school and a township hospital.

24. New Beihaoting is a model village in Jingxing County under the New Countryside Construction Program, with a neat layout and advanced housing design. Jingxing County granted New Beihaoting Village over CNY300,000 for the construction of a village square with sports exercise equipment. In addition, Jingxing County government has been providing a subsidy of CNY14,000 to each household to upgrade their houses with a framed tin roof since September 2009.3

25. The living conditions and livelihoods of relocated households have greatly improved. New Beihaoting Village is located in a coal industry area where many construction activities are in progress. At present, the major source of livelihood comes from non-farming activities while non-farming activities prior to resettlement constituted only one-third of its overall source of income. The average annual household income in 2006 was CNY4,520 4 compared with CNY11,000 in 2013,5 with an annual increase of 16.1%. According to the survey, about 90% of household income came from nonagricultural activities which indicate that the permanent land acquisition of agricultural land had less impact on the household income. The project improved the public infrastructure of the affected villages such as (i) pavement of the road from Qinzhuang to Yinzhuang Village; and (ii) construction of a bridge connecting Liuzhuang Village

2 http://www.sjzjx.gov.cn/zwgk/ShowArticle.asp?ArticleID=17341.

3 The total cost is CNY17,000 and each household covers the gap of CNY3,000.

4 Monitoring report, October 2012.

5 Official internal data, which is lower than the data from interviews with village leaders.

Page 77: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

68 Appendix 12

to the main road, which were very much appreciated by the villagers. Overall, the people expressed contentment and satisfaction in their new location, and would not want to return to their old village because the new location has good access to the market and employment opportunities within 2 km from the village.

26. New Shimen village. Similar to Beihaoting Village, New Shimen farmland and the village site were affected by the lower reservoir. The whole village, with 229 persons in 64 households, was resettled to an area where the land was contributed by Jiangou Village in Beizheng township in December 2010. The new village is located within 10 km from Jingxing County center, and 2 km to the main road. 27. The following resettlement and income restoration measures were taken: (i) a single-story house (143 m2 of plot area and 128 m2 of floor area) was granted to each affected household, which can add another story at their own cost; (ii) affected assets were compensated at replacement cost; (iii) each affected person who had farmland prior to relocation obtained the same size of farmland of 600 m2 in the new village; (iv) each affected person is supported by a government subsidy of CNY50 per month for 20 years; and (v) tenure status for forestland above the inundation line remain unchanged. A single-story house has three bedrooms, and dining and living rooms, while a two-story house has three bedrooms and a porch. Electricity supply, piped water supply system, and a drainage system are connected in each household. A bus service is available from the village to the main road (2 km distance), providing easy access to the county’s hospital, schools, and market. Most of the households have a solar heater system installed at their own cost, a washing machine, and an electric stove. A clinic and a preschool have opened within the village.

28. The village is located in a coal industry area where many construction activities are in progress. The majority of household income (75%) comes from non-farming activities, including migration, compared to one-third of its overall source of income before resettlement according to a key informant interview in 2014. The average annual household income increased from CNY6,400 in 20106 (at the old village) to CNY11,000 in 2013,7 with an annual increase of 19.7%.

29. Nansi Village. The project affected 291 persons in 85 households. Out of the affected persons, 54 persons in 17 households moved to Baiwangzhuang Village in Shang’an township and formed a new village group in 2006. They received similar resettlement arrangements to Beihaoting Village. The remaining land was shared by the 237 persons who stayed in the village.

30. Zhanghewan Village. The project affected 168 persons in 47 households. Out of the affected persons, 115 persons joined their former villagers in New Zhanghewan Village in Beizheng township in 2006. 8 These 115 persons received similar resettlement arrangements to those of Beihaoting village. The remaining land was shared by the 53 persons who stayed in Zhanghewan village.

31. Yanzhuang Village. Only 9.08 ha of land, including 2 ha of farmland, without residential houses, was inundated and acquired by the project. This affected 160 persons in 43 households. Farmland compensation was used for the reclamation of 2 ha of unused village land into irrigated farmland for affected persons.

6 The data is from monitoring report of October 2012.

7 Official internal data, which is little lower than that from interview of the village leaders.

8 Majority of Zhangehewan villagers moved to current Beizheng township and formed New Zhangehewan village in late 1970s when constructing the original lower Zhanghewan reservoir.

Page 78: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

Appendix 12 69

32. On average, the villages’ income increase more than 10% per year. Table 8 below presents the income data of the three villages, the relocation people, and their host villages. As indicated, the relocated people from Nansi and Zhanghewan villages experienced the highest income growth since they resettled in the host villages and they are now better off than those who remained in the old villages. The high growth, according to key informant interviews, is due to location advantages of the host villages for easy access to nonfarm employment. 9

Table 8: Income Data of Nansi, Zhanghewan, and Yanzhuang Villages

Village Annual Per Capita Income (CNY) Annual

Growth 2006 2008 2010 2011 2012 2013

Nansi Resettlers 4,270 5,400 6,800 7,800 8,800 10,000 12.9%

Host village (Baiwangzhuang)

4,700 5,600 6,900 7,800 8,800 10,000 11.4%

Nansia

4,270 5,100 5,900 7,100 7,900 8,900 11.1%

Zhanghewan

Resettlers 4,300 5,300 7,200 8,500 9,600 11,000 14.4%

Host village (New Zhanghewan)

4,900 5,700 7,400 8,500 9,600 11,000 12.2%

Zhanghewana

4,300 5,100 6,700 7,100 7,800 8,600 10.4%

Yanzhuang 4,400 5,300 6,200 7,200 8,000 9,000 10.8% a Remaining population.

CNY = yuan. Sources: Monitoring report, October 2012; key informant interviews with township government.

33. Host villages. The county and township governments had high awareness to minimize the impacts of land acquisition, and acquired land from several host villages for resettling each relocated village. This resulted in less land loss for the host villages. Therefore, the land impact on the host villages is limited.

34. For example, farmland of 40 ha for new Nanhaoting Village was originally planned to be acquired from one village, but was finally acquired from four villages (Wangjiazhuang, Lijiazhuang, Xibaishan, and Meizhuang) and an area belonging to Xiulin township. Farmland of 20 ha for New Beihaoting Village was from Zhongle and Dongzheng Villages, while 16 ha of farmland for new Shimen Village was from a state nursery. G. Conclusions and Recommendations

35. Although resettlement activities in two villages took much longer than planned, the implementation of resettlement activities was satisfactory as it was carefully implemented by the country resettlement office in a highly participatory manner to accommodate the needs of affected people. Livelihoods of affected people were fully restored. The economic conditions of affected people were improved from before the land acquisition and resettlement because of the availability of income-generating opportunities in relocation sites. All affected people enjoy better housing and living conditions, more employment opportunities, and better access to public services such as schools and hospitals.

36. ADB closely monitored the most sensitive resettlement activities of three villages (Nanhaoting, Beihaoting, and Shimen) through the staff consultant and regular ADB missions

9 Township officials and village leaders.

Page 79: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

70 Appendix 12

since 2006. It was agreed to suspend the submission of independent resettlement monitoring reports as the resettlement activities were suspended from 2007 to 2010. Since 2010, resettlement was monitored through staff consultants. A combined monitoring method, with direct inspection through the ADB missions and periodic monitoring through staff consultants, was highly effective and was recommended to be used for sensitive resettlement cases.

37. A total of 18 households in Nanhaoting Village (4% of the total affected households from the village) have not yet moved to the new village as they have not reached agreement with the county government regarding their entitlement to new houses and compensation, as well as uncertainty regarding livelihood options in the new village. The county resettlement office has committed to maintain close dialogue with these households and provide the necessary assistance to satisfy their needs, while allowing them to stay in the original village until they satisfy the entitlements. Outstanding resettlement issues are expected to be resolved by September 2014. ZPSC agreed that ADB will field subsequent missions to monitor the resettlement activities beyond the project completion report period. ADB will monitor the outstanding issues until these issues are settled.

Page 80: Hebei Zhanghewan Pumped Storage Project: Project ... · Hebei Zhanghewan Pumped Storage Project People’s Republic of China Hebei Electric Power Corporation $144.0 million ($135.9

71 Appendix 13

QUANTITATIVE ASSESSMENT OF OVERALL PROJECT PERFORMANCE

Criterion Assessment Rating (0–3) Weight (%)

Weighted Rating

Relevance Highly Relevant 3 20 0.6 Effectiveness Effective 2 30 0.6 Efficiency Efficient 2 30 0.6 Sustainability Most Likely to be

Sustainable 3 20 0.6

Overall Rating Successful 2.4

Notes on the rating system:

Rating: 3 = Highly relevant/Highly effective/Highly efficient/Most likely to be sustainable

2 = Relevant/Effective/Efficient/Likely to be sustainable

1 = Partly relevant/Less effective/Less efficient/Less likely to be sustainable

0 = Irrelevant/Ineffective/Inefficient/Unlikely to be sustainable

Highly Successful: Overall weighted rating is equal to or greater than 2.7

Successful: Overall weighted rating is equal to or greater than 1.6 and less than 2.7

Partly Successful: Overall weighted rating is equal to or greater than 0.8 and less than 1.6

Unsuccessful: Overall weighted rating is less than 0.8

Source: Asian Development Bank estimates.