Transcript of Heathrow Terminal 3 Integrated Baggage, APM Programme Management SIG Conference 2017, 02 March 17,...
March 2017
Terminal 3 Integrated Baggage
Darren Colderwood
Integrating Heathrow Baggage
• First of type baggage installation
• Delivered whilst Terminal 3 was operating (30k bags per day)
• Circa £600m programme of overall works
• 6 years to develop and build
• T3IB building - 200m long, 50m wide, 35m high
Wha
t’s insid
e T
3IB
T3IB and Multiple Associated Projects
First baggage facility to be connected
to the enterprise service bus
T3/T5
baggage tunnel
Traffic information
screensBaggage check-in
refurbishment
Container stores
Roads and blast
screens
Tug charging Baggage control
rooms and HBS
screening
Relocation of VIP
suite (T3 to T5)
Managing the Complexity of Change
New processesNew ways of
working
New and multiple
handlers
New technologies
and systems
New facilities &
environments
Integration with wider
airport programmes
Complex transition
over 16 months20+ airline partners
The Challenge of Complexity
T5
Te
ch
no
log
y
Infrastructure
No change
Some change
Change for most
Some new
New for most
Som
e ch
ange
Cha
nge
for m
ost
Som
e ne
w
New
for m
ost
T3IB
T2 PT5TBS
T5C
T1T
T3IB
T5
Stakeholder Communication and Engagement
Getting the Balance Right……
How we created a Large Multi-Faceted Team
Programme Team
FinanceProject
Management
Vanderlande
Mace
IT
Planning
Operations
Operational
Readiness
Risk
Management
Run as a Programme with funding agreed at board level, enabling
the team to manage the overall objective across the projects
Safety on Site
• Circa 5 million cumulative manhours
worked across 10 sites
• Only 2 reportable incidents since
construction began in 2011
• An outstanding safety performance
for a complex project in a constrained
location
Managing Construction Complexity
Jun 2016Check -in
move 5
(zone A)
T3IB Transition Plan
Fin
al co
nn
ectio
n f
rom
ch
eck-in
to
T3
IB
All
bag
s p
roce
sse
d th
rou
gh
new
fa
cili
ty
Transfer bags Checked –in bags
Mar 2015Check-in
moves 1 & 2
(zone G)
Apr 2015Check-in
moves 1 & 2
(zones E2,F,G)
Mar 2015Transfers
move 3
(Building 139)
May 2015Transfers
move 4
(Building 139)
Sep 2015Check-in
move 3
(zones C2,D,E1)
Feb 2016Check-in
move 4
(zones B, C1)
Mar 2015Transfers
move 2
(Lima 18)
Mar 2015Transfers
move 1
(Building 139)
*
Multi-layered Operational Readiness Solution
Final Drills: Live Trials
Show Me You Know: Rehearsals
Practice: Proving Participation
Training & Familiarisation
Employee
Engagement
Early Training & Familiarisation
Optimisation & Embedding
Go-Live
TimeIncreasing
Assurance
SME support
Making sure we were ready – integrated trials programme
Key Learning from the Programme
• T3IB was not initially recognised as a
technology programme.
• The programme was set up to be
managed in the standard way (risk
provision)
• T3IB was constrained by real estate
availability so had to be built
vertically
• The baggage system supplier had
not built a baggage system like this
before
• New technology meant new work
practices so new skills were required
Key Learning from the Programme
• The T3IB programme was not just a
construction programme but a major
business change programme too
• Effective stakeholder management and
collaboration between all teams was
absolutely pivotal to the success
• T3IB has brought people, processes,
infrastructure and technology together to
• keep baggage flowing smoothly
• improve baggage performance
• enhance the baggage experience for
passengers
Business Benefits
Our partners
March 2017
Terminal 3 Integrated Baggage
Thank you