Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in...

28
The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925. Heat4Cool – Task 8.3 Education and training. TRAINING MATERIAL In the framework of T8.3 of the Heat4Cool project, we are presenting you the training material dedicated to each of the four demo sites involved in the project, and the different technologies tested and installed in these facilities. This training material aims to present to external stakeholders the functioning of the Heat4Cool technologies installed in each demo, and present the systems developed within the project; thus, to allow a better comprehension, increase the interest of the audience and promote the use of the project solutions in the market. The training material is divided into four dossiers, each one dedicated to one demo site.

Transcript of Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in...

Page 1: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Heat4Cool – Task 8.3 Education and training.

TRAINING MATERIAL

In the framework of T8.3 of the Heat4Cool project, we are presenting you the training material dedicated to each of the four demo sites involved in the project, and the different technologies tested and installed in these facilities. This training material aims to present to external stakeholders the functioning of the Heat4Cool technologies installed in each demo, and present the systems developed within the project; thus, to allow a better comprehension, increase the interest of the audience and promote the use of the project solutions in the market. The training material is divided into four dossiers, each one dedicated to one demo site.

Page 2: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Demo site in Chorzow (Poland)

Demo manager: IZNAB

Page 3: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Table of Contents

1 HEAT4COOL PROJECT INTRODUCTION AND OBJECTIVES .......................................................... 4

1.1. INTRODUCTION ...................................................................................................................... 4 1.2 TESTING TECHNOLOGIES ............................................................................................................... 4 1.3 PROJECT OUTCOMES ................................................................................................................... 5 1.4 DEMO SITES INTRODUCTION .......................................................................................................... 6 1.5 CONSORTIUM ............................................................................................................................ 6

2 TECHNOLOGIES INTRODUCTION ............................................................................................. 8

2.1 PCM STORAGE BATTERIES (SUNAMP) ................................................................................... 8 2.1.1 BLUEPRINT ......................................................................................................................................8 2.1.2 COMPONENT DESCRIPTION ...............................................................................................................8 2.1.3 HOW IT WORKS: ..............................................................................................................................9 2.1.4 ENERGY AND MATERIAL FLOW: ...........................................................................................................9 2.1.5 PERFORMANCES: .............................................................................................................................9 2.2 SOLAR PV (AESOLAR) ......................................................................................................... 10 2.2.1 BLUEPRINT ................................................................................................................................... 10 2.2.2 COMPONENT DESCRIPTION: ........................................................................................................... 11 2.2.3 HOW IT WORKS: .......................................................................................................................... 12 2.2.4 ENERGY AND MATERIAL FLOW: ....................................................................................................... 12 2.3 SCI-BEMS (HYPERTECH) ..................................................................................................... 13 2.3.1 BLUEPRINT:.................................................................................................................................. 13 2.3.2 COMPONENT DESCRIPTION: ........................................................................................................... 14 2.3.3 HOW IT WORKS: .......................................................................................................................... 14

3 TECHNOLOGY SOLUTION ON SITE ......................................................................................... 15

3.1 CHORZOW DEMO SITE PRESENTATION: ....................................................................................... 15 3.2 INSTALLATION....................................................................................................................... 16 3.3 DEMONSTRATION OF THE BENEFITS IN THE REAL CASE AND HOW THE DIFFERENT TECHNOLOGIES ARE

INTEGRATED.................................................................................................................................. 24

4 FOLLOW US: ......................................................................................................................... 28

Page 4: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

1 HEAT4COOL PROJECT INTRODUCTION AND OBJECTIVES

1.1. Introduction The Heat4Cool project is an EU funded project, started in October 2016 and will run for four years. The project proposes innovative, efficient and cost-effective heating and cooling solutions to optimize the integration of six technologies:

• Adsorption heat pump,

• PCM storage batteries,

• SCI-BEMS, Solar PV,

• Solar thermal,

• Heat recovery from sewage water at building and district level, to meet net-zero energy standards.

The project will showcase four different retrofitting solutions, three of them will be focusing on residential buildings where the new innovative systems will be monitored and controlled through the SCI-BEMS (self-correcting intelligent building energy management system).

1.2 Testing technologies The technologies based on solar energy and heat pumps developed within the Heat4Cool project are being implemented in Tecnalia’s Kubik® facility, located in Bilbao (Spain).

Page 5: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

In the facility, Tecnalia tested the thermal storage system coupled with a reversible heat pump and the solar driven adsorption cooling system. The main aim of these tests is to carry out a proof of concept for two complete systems in order to assess the thermal performance of Heat4Cool solutions under realistic boundary conditions. These two systems are already connected to the centralized HVAC system to test the effective integration of the heating and cooling technologies. The thermal storage system coupled by a reversible heat pump is the concept solution developed by Sunamp. A total of 7 PCM (Phase change material) heat storages connected to an air to water electric heat pump have been installed. This is the first version of the system that will later evolve to a DC driven heat pump connected to a PV panel field, a solution that will be implemented in the pilot buildings of Sofia and Chorzow. The system to be tested in Kubik will allow improving the interaction between the heat pump and the heat storages while the contribution of the solar field will be post-processed. The solar-driven adsorption cooling system has Fahrenheit’s Zeolite prototype chiller as the main innovative component. Combined together with a solar thermal field composed of flat plate collectors, the heat pump will produce cold water that will be stored into an 800L tank connected to the cooling circuit. As a result of the adsorption process, waste heat will be produced at medium temperature (35-40 °C), which will be used for preheating of domestic hot water or dissipated to the atmosphere by means of a dry cooler unit. Preliminary tests have been performed for both sets and performance data of the components are being collected to evaluate the contribution and benefits of implementing both concepts.

1.3 Project Outcomes The integrated solutions developed and tested in Heat4Cool project will provide:

• Space heating, cooling and domestic hot water in one case by integrating the Adsorption heat pump to the natural gas boilers, and in the other case by coupling the DC heat pump powered by photovoltaic panels and PCM storage.

• Renewable energy solutions

• Smart control system which the “brain” of the heating and cooling energy system and will constantly monitor the environment conditions and the performances in order to identify the optimal option in terms of comfort and energy efficiency.

Heat4cool project aims to achieve:

• a reduction of 30% in energy consumption in a technically, socially, and financially feasible manner,

• a demonstrate a return on investment lower than ten years,

• and provide best practices examples for the construction sector.

Page 6: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

1.4 Demo sites introduction The Heat4Cool technologies has been installed and tested in four demo sites located in three different climate areas in Europe.

1. Chorzow, Poland

• The building is a multi-story house with three commercial premises and one residential apartment on the ground floor and 11 apartments on the other floors (12 residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted within the project.

2. Valencia, Spain

• Apartment housing composed by composed by 12 flats, 610m2 of total floor area.

3. Sofia, Bulgaria

• Residential building, 3 apartments, total floor area of 564m2.

4. Budapest, Hungary

• District H&C system supply three different buildings: two public buildings (a recently retrofitted over 100-year-old and a ~2-decade-old building) and one newly constructed mixed-purpose building (commercial and cultural institution).

1.5 Consortium The Heat4Cool project is composed by 13 partners from 7 associated European countries, more into details:

• 3 research organisations

• 9 SMEs

• 1 non- profit organisation

Page 7: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Project coordinator, Politecnico di Milano – Dr. Marcello Aprile ([email protected])

Page 8: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

2 TECHNOLOGIES INTRODUCTION In this section all the technologies installed in the demo site in Chorzow (Poland) have been presented.

2.1 PCM STORAGE BATTERIES (SUNAMP)

2.1.1 Blueprint

Figure 1 Scheme of the system Solar PV +DC Heat Pump + PCM storage

2.1.2 Component Description The system provided by Sunamp is composed by:

1) A DC air-to-water heat pump: this heat pump is able to provide thermal energy by efficiently upgrading the ambient heat to hot water and space heating or downgrading the ambient heat to space cooling. This heat pump can be run directly from DC electricity generated by the solar panels as well as from the AC electricity from the grid. In this project, two heat pumps are used with thermal loads of 10kW and 30kW, respectively;

2) PCM storage units: they are compact, high-power thermal storage based on phase change materials (PCMs). They are recharged directly from the heat pump when required and provide

Page 9: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

thermal energy to the building. The storage used in this project includes different PCMs with different operating temperatures.

2.1.3 How it works: Following multiple input from the building and environment and following a decision process in the controller developed by the partners in the project, the heat pump will operate to (i) recharge the PCM storage; (ii) provide space heating / cooling to the building or (iii) both. The PCM storage is then used to provide high flow rates of hot water on-demand. When the storage is not able to provide the hot water directly, it is used as a pre-heater to the backup system in the building e.g. a gas boiler. The capability to use DC or AC electricity and the usage maximise the flexibility of the system, allowing the building controller to optimize its operation for e.g. maximum amount of renewables or minimum cost or minimum CO2 emissions, while ensuring maximum comfort for the tenants.

2.1.4 Energy and material flow:

2.1.5 Performances: Performances are highly variables depending on:

1) Operating conditions; 2) Sizing of the components in this subsystem; 3) Integration into the buildings.

Page 10: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

A full description of real-operating conditions performance can be provided with the results collected on trial sites in the next months.

2.2 SOLAR PV (AES SOLAR)

2.2.1 Blueprint

Figure 2 Schematic Heat4Cool solar PV AC connected system

Page 11: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 3 schematic for Heat4Cool solution

2.2.2 Component Description: Solar PV generates DC (direct current) electricity from sunlight. Most loads in buildings use alternating current (AC). It is standard for Solar PV system on buildings to include an inverter to convert the DC electricity to usable AC electricity that can be used on site or exported to the grid. The inverter usually includes hardware and software to facilitate remote monitoring and other functionality.

Figure 4 Solar PV Module (LG Chem)

Page 12: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

HEAT4COOL aims to maximize the amount of electricity used by an air source heat pump that is supplied by on-site solar PV. Most air source heat pumps have an inverter built-in which converts AC electricity from the grid to DC electricity to run the internal systems. The HEAT4COOL solution utilizes a heat pump which ca be driven partly by DC electricity when available but also receive an AC input.

2.2.3 How It Works: The Solar PV system is configured based on available space, possible orientation, inclination, geographic location and normal heat loads of the heat pump to maximize the solar electricity provided in relation to the heat pump load. Whenever electricity is generated by the solar PV system it will flow first to any loads on site (including the heat pump when calling for power) and then will export to grid to benefit from an export tariff or other mechanism of reward. The heat pump used by HEAT4COOL is equipped with both AC and DC inputs because the DC input would not be able to provide the required start-up power alone. The Solar PV system includes an inverter because otherwise there would be times when potential PV production would be curtailed if the heat pump requirement was lower.

2.2.4 Energy and Material Flow:

Building Demand

• Electrical

Page 13: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

2.3 SCI-BEMS (HYPERTECH and WATT & VOLT)

2.3.1 Blueprint: The SCI-BEMS system concentrates on the monitoring and control, from one side of the centralized heating/cooling energy generation system, and on the other side on the comfort-based energy efficient automation of the end-user demand. The monitoring and principles of optimal use for the central system were defined and setup through rigorous testing and simulations by the technical partners, taking into account the different conditions and setups of the various pilot sites. On the demand side, the system consists of a smart home installation that allows real-time recording and control of the emission system. The basic workflow for the optimization is shown in the figure below.

Figure 5 Graphical representation of the demand side SCI-BEMS system.

Page 14: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

2.3.2 Component Description: The main objective when designing the system is to enable the detailed monitoring of the heating/cooling system in its entirety, as well as its constituent components, as well as the ability to apply certain control strategies in a remote and automated manner. To that extent, a plethora of metering and monitoring devices, along with communication servers are deployed in the pilot sites. Due to the specificities of each one, the solution was tailored according to each pilot site’s needs. More details on this are reported in the installation section below. When it comes to the in-apartment infrastructure, a common approach was adopted, based on a solution comprising a gateway device and various z-wave enables sensors and thermostats. The figure below depicts the main components of such an installation. What is now shown in the figure is the non-hardware part of the installation, which comprises of cloud-based services for the recording and processing of the data.

Figure 6 SCI-BEMS components.

2.3.3 How It Works: The critical part of the SCI-BEMS automation algorithm focuses on the efficient management of the apartments’ demand for heating and cooling. The approach consists of a number of steps, which can be seen in the following figure.

SCI-BEMS

Wi-Fi

Ethernet

Raspberry Pi+

RaZberry gateway

AeotecMultisensor 6

SensoairCO2 Sensor

Fan Coil ThermostatMH8-FC4

Page 15: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 7 SCI-BEMS automation workflow.

In essence, through the real-time monitoring of environmental conditions and HVAC data, we are able to extract in an automated and consistent manner the comfort preferences of the occupants. These are used as constraints in a model predictive optimization of the system’s emission setpoints. The optimal control signals are then applied to the fan coil or radiator units remotely.

3 TECHNOLOGY SOLUTION ON SITE

3.1 Chorzow demo site Presentation: The polish demo building is located in the city center of Chorzow, Poland. The climatic zone is classified as III class, according to Polish regulation, with design temperature as low as -20°C on average during winter time, and the median annual temperature +8.6°C. That is why, it is important to design energy

Page 16: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

efficient installation, to overcome the building thermal losses. The building front facades is oriented to the North with an angle 15° W.

Figure 8 Demo side façade

The building was constructed in 1902, with a total surface of parcel 514 m2, from which the constructed part constituted around 325 m2. Since then, several improvements were introduced, from which one of the most important are: renovation of external façade, shafts and natural ventilation system. The building is a multi-family house with three commercial zones. The total number of residential apartments is 12, each with different size. In total there are six storeys, including basement and attic. Works performed in the building within the Heat4Cool project are: Modernization of the electrical system in the staircase, basement and one apartment Modernization of the space heating system in 11 apartments Modernization of the hot water supply system in 11 apartments Installation of the photovoltaic system on the roof of the building. The following technologies were implemented: 30 kW air to water heat pump for central space heating system and hot water preparation; Heat batteries based on phase change materials technology for hot water preparation installed between the heat pump and hot water system of the building – 8 heat batteries, each of 12 kWh capacity, 96 kWh in total; PV system on the roof of the building – 43 LG 340N1K-V5 modules with total generation of 14.62 kWp.

3.2 Installation In the Polish demo building located in Chorzow (South Poland), the space heating and hot water systems have been retrofitted using solutions developed in Heat4Cool project.

Page 17: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

The scheme below presents the layout of the system.

Figure 9. Layout of the implemented system

The main source of the heating power for space heating and domestic hot water are gas boilers, individual for each residential apartment. In a few apartments the boilers have been replaced for the new ones due to the old age of the previous ones. The radiators of some apartments were exchanged with bigger ones to meet the heat demand of the apartments with lower water temperatures. In 2 apartments new heating installations have been implemented as previously the apartments were heated with coal stoves. In the basement 8 heat batteries each of 12 kWh capacity have been installed to preheat the hot water for the residential apartments. They are connected in 4 couples where cold water from water mains is heated by the PCM material inside of the heat batteries. The PCM is charged with heat by the heat pump installed outside of the building.

Page 18: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 10. 8 units of heat batteries with PCM installed in the basement.

The air to water heat pump is one-unit external device installed next to the building. It has two separate circuits for heating and for hot water and it is connected with building’s installation through pre-insulated PEX pipes running in the ground. The heat pump was placed using crane on prepared concrete foundation. Some pictures from the installation available below:

Page 19: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 11. The heat pump transported to the foundation.

Page 20: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 12. The heat pump placed on the foundation.

The heating circuit can achieve max. 80°C. In the Polish system it was set for 55-60°C as a supply for the heating system what was calculated as the most efficient temperature. The heating circuit is running directly to each residential apartment to small plate heat exchangers located next to the gas boilers. They are connected in the apartments’ heating systems in the part where water returns from radiators. It takes the heat from the heat exchangers and runs to boilers where is further heated, if

needed.

Page 21: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 13 The heat pump installed in the back yard. On the right side twin PEX pre-insulated pipes from the building are connected.

To prevent heat transfer from the apartment’s installation 3-way valves with on/off actuator has been installed. Till the moment when the temperature of water provided from the heat pump the heat exchanger is higher, then the temperature of water on the other side of the heat exchanger (apartment) the valve is closed for the heat exchanger and the water is running in by-pass till it achieves required temperature. If the temperature is higher the valve opens, and water is flowing through the heat exchanger. Using Tech i2 controllers in apartments modification in circulators control was implemented. The circulation pump in an apartment’s heating system works independently from the gas boiler. If the heating water temperature in the space heating system is higher than the boiler’s set point the boiler does not turn on, resulting in no usage of gas. At the same time the circulation pump works and runs the water through the installation. If the temperature provided to the apartment from the central heating system will be lower than boiler’s set point, than boiler will turn on to provide required temperature to the heating circuit. This solution allows to maximize use of heat provided form the heat pump and minimize the use of natural gas by boilers.

Page 22: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 14. Heat exchanger installed in each apartment separating the heat pump heating circuit and apartment’s heating

circuit. 3-way valve on the right of the heat exchanger.

The second circuit of the heat pump charging the heat batteries works with maximal temperature 55°C. The controller reads the temperatures inside the heat batteries and where the temperatures are below minimum set points, it turns on the circulation pump in the charging circuit. The pump will run till the temperature achieves the maximum set points. The heat batteries are discharged by the cold water from water mains. They heat it and it goes to the apartments and flows through each boiler where is heated to the temperature set by tenants in the boilers. The average temperature of hot water flowing out of the heat batteries to the apartments is between 41-42°C.

Figure 15. Sunamp’s controller for managing of the charging of the heat batteries.

Page 23: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 16. Heat batteries charging circulation pump controlled by Sunamp’s controller.

The temperature in all apartments is controlled by Fibaro thermostatic heads installed on Danfoss thermostatic valves on each radiator. They regulate the flow in heating system of each apartment and decide about its heat demand. On the building’s roof 43 LG photovoltaic modules have been installed to generate electrical power for the new system. They are connected to SolarEdge 15kW inverter installed at the attic. The peak power generated by the panels is 14.62 kWp. The PV installation is connected to the grid to maximize the benefits. Energy supplier installed 2-way electricity meter measuring imported power from the grid and exported to the grid when the building’s demand is lower than generation. As prosumer the owner of the building can take from the grid for free 80% of the provided electrical power.

Figure 17. PV modules installed on the roof.

Page 24: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 18. The PV modules seen from the rear side of the building.

The system is monitored and controlled by BMS created for the building. It collects data from meters and send it to the data base. It also allows to control the system, i.e. to change the set points of the thermostatic heads, turn on or turn off the heat pump and circulation pumps.

3.3 Demonstration of the benefits in the real case and how the different technologies are integrated

According to the simulations developed for choosing the best solutions to implement in Polish demo site, annual energy needs for the building are 137 kWh/m2year, where 20% is preparation of hot water and 80% is space heating. The chart below presents comparison between simulation results and gas usage resulting from existing invoices.

Page 25: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Figure 19. Use of energy comparison bills – simulation. SH_bills – Space Heating bills, DHW_bills – Domestic Hot Water bills, SH_Sim – Space Heating Simulation, DHW_Sim – Domestic Hot Water Simulation

Figure 20. Comparison of different PCM material and its impact on efficiency of the system.

In the Polish demo site heat batteries with PCM43 material are used. According to the simulations such solution together with the air source 30 kW heat pump will provide 62% of energy needed for hot water distribution for apartments and 40% of energy needed for space heating. The electricity consumption by the new system will be not fully covered by the photovoltaic system. Overall considering also the photovoltaic energy sold to the grid all the simulation achieves the target of 30% primary energy saving and avoided CO2 emissions. The graphs below present example of

Page 26: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

weekly production of the PV system from 26th of March till 8th of April 2020. The daily production reached up to around 69 kWh.

Page 27: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

Page 28: Heat4Cool Task 8.3 Education and training. TRAINING MATERIAL€¦ · residential apartments in total) with a total floors area of 998 m2. Only 11 apartments have been retrofitted

The Project has received funding from the European Union’s Horizon 2020 programme for energy efficiency and innovation action under agreement No. 723925.

4 FOLLOW US: