THE PROPOSED THAMES WATER UTILITIES LIMITED (THAMES TIDEWAY TUNNEL) DEVELOPMENT CONSENT ORDER
SECTIONS 91, 92 AND 93 PLANNINg ACT 2008 AND RULE 13(6) INRASTRUCTURE PLANNINg (ExAMINATION PROCEDURE) RULES 2010APPLICATION REERENCE: WW010001
Notice o issue-specic, open-foor and compulsoryacquisition hearinsNotice is hereby given that issue-specic, open-foor andcompulsory acquisition hearings will be held by the
Examining Authority (appointed by the Secretary o State)
or the examination o the application (the Application)
by Thames Water Utilities Limited or a developmentconsent order or the proposed Thames Tideway Tunnel
(the Project). The Application was made under section
37 o the Planning Act 2008 on 27 February 2013 and
accepted or examination by the Secretary o State
on 27 March 2013.
The Application relates to the construction and operation
o a wastewater storage and transer tunnel in London
which, together with shats, connection tunnels and
associated development, will enable the interception o
fows rom 34 existing combined sewer overfows (CSOs)and the transer o those fows or treatment in order to
tackle untreated sewage overfowing into the tidal River
Thames. The Project comprises the ollowing elements:
a) wastewater storage and transer tunnels between:
(i) Thames Waters existing operational sites at Acton
Storm Tanks in Ealing and Abbey Mills Pumping
Station in Newham (the main tunnel). The main
tunnel would run rom Acton Storm Tanks to theRiver Thames and then underneath the river as ar
as Rotherhithe, where it would divert to the north
east via the Limehouse Cut, terminating at Abbey
Mills Pumping Station;
(ii) King Georges Park in Wandsworth and theproposed main tunnel site at Carnwath Road
Riverside in Fulham (the Frogmore connection
tunnel);
(iii) Thames Waters existing operational site at
Greenwich Pumping Station and the proposedmain tunnel site at Chambers Whar in Southwark
(the Greenwich connection tunnel);
b) shats to be used or the construction, operation and
maintenance o the main tunnel and the Frogmore
and Greenwich connection tunnels;
c) CSO drop shats, short connection tunnels and
associated development or the interception o fowsrom existing CSOs and the diversion o those fows
into the main tunnel or the connection tunnels;
d) works to modiy Thames Waters existing Shad
Thames Pumping Station at Maguire Street in
Southwark, provision o a shat and modicationsto the existing sewer at Bekesbourne Street in Tower
Hamlets and works to drain the tunnels at Beckton
Sewage Treatment Works; and
e) Associated development to acilitate construction,
operation and maintenance o the tunnels and shatsdescribed above.
ADVERTISEMENT ADVERTISEMENT
Acton Storm Tanks, south o Canham Road and west
o Cobbold Road (London Borough o Ealing)
Hammersmith Pumping Station, east o Chancellors
Road and south o Distillery Road (London Borough oHammersmith and Fulham)
Barn Elms, on the south eastern perimeter o the Barn
Elms Playing Fields (London Borough o Richmond)
Putney Embankment Foreshore, on the oreshore north
o Lower Richmond Road and west o Putney Bridge
(London Borough o Wandsworth) including site otemporary slipway to the west o the CSO drop shat site
Carnwath Road Riverside, south o Carnwath Road
(London Borough o Hammersmith and Fulham)
Dormay Street, north o Dormay Street and west o The
Causeway (London Borough o Wandsworth)
King Georges Park, south o the intersection betweenBuckhold Road and Neville Gill Close (London Borough
o Wandsworth)
Falconbrook Pumping Station, east o York Road and
west o Lavender Road (London Borough o Wandsworth)
Cremorne Whar Depot, east o Lots Road between the
River Thames and the Lots Road Pumping Station (Royal
Borough o Kensington and Chelsea)
Chelsea Embankment Foreshore, on the oreshore southo the Royal Hospital Chelseas South Grounds and partly
within Chelsea Embankment and Ranelagh Gardens
(Royal Borough o Kensington and Chelsea)
Kirtling Street, either side o Cringle Street, (London
Borough o Wandsworth)
Heathwall Pumping Station, on the oreshore west oElm Quay and north o Nine Elms Lane (London Borough
o Wandsworth)
Albert Embankment Foreshore, on the oreshore to the
west o Albert Embankment between St Georges Whar
and Tintagel House (London Borough o Lambeth)
Victoria Embankment Foreshore, on the oreshore east
o Victoria Embankment between Northumberland
Avenue and Horse Guards Avenue (City o Westminster)
Blackriars Bridge Foreshore, on the oreshore south
o Victoria Embankment between Temple Avenue andBlackriars Bridge and adjacent to Paul's Walk, west o
Blackriars Station (City o London)
Chambers Whar, on the oreshore and north o
Chambers Street to the west o Lotie Street (London
Borough o Southwark)
Earl Pumping Station, east o Crot Street, south
o Chiltern Street and south o Yeoman Street (London
Borough o Lewisham)
Deptord Church Street, west o Deptord Church Street
and north o Crosseld Street and south o Coey Street
(London Borough o Lewisham)
Greenwich Pumping Station, west o Norman Road and
north o Greenwich High Road and including Phoenix
Whar to the north o the railway viaduct (Royal Borough
o Greenwich)
King Edward Memorial Park Foreshore , on the oreshoreand to the south o The Highway and east o Glamis
Road (London Borough o Tower Hamlets)
Abbey Mills Pumping Station , east o Prescott Channel
and west o Abbey Creek and Channelsea River and south
o The Greenway (London Borough o Newham)
Date Time Venue Issue
Monday 11 Friday 15
November 2013
Registration: 09.30
Hearing start: 10.30
America Square Conerence Centre, 1 America
Square, 17 Crosswall, London EC3N 2LBRationale or the selection o work sites and drive strategies matters
Tuesday 26 Wednesday 27November 2013
Registration: 09.30Hearing start: 10.30
America Square Conerence Centre, 1 AmericaSquare, 17 Crosswall, London EC3N 2LB
Development consent order, requirements, any s106 undertakingand local impact report matters.
Monday 20 Tuesday 21
January 2014
Registration: 09.30
Hearing start: 10.30
Glaziers' Hall, 9 Montague Close, London Bridge,
London SE1 9DD
Development consent order, requirements, any s106 undertaking
and local impact report matters.
Thursday 6 Friday 7
February 2014
Registration: 09.30
Hearing start: 10.30
Glaziers' Hall, 9 Montague Close, London Bridge,
London SE1 9DD
Development consent order, requirements, any s106 undertaking
and local impact report matters.
Issue Specic Hearings
Issue-specic hearings will be held at the ollowing dates, times and locations:
Date Time Venue
Thursday 28 Friday 29
November 2013
Registration: 09.30
Hearing start: 10.30America Square Conerence Centre, 1 America S
Tuesday 3 Friday 6
December 2013
Registration: 09.30
Hearing start: 10.30America Square Conerence Centre, 1 America S
Tuesday 10 Friday 13
December 2013
Registration: 09.30
Hearing start: 10.30Glaziers' Hall, 9 Montague Close, London Bridge
Tuesday 17 Friday 20
December 2013
Registration: 09.30
Hearing start: 10.30Glaziers' Hall, 9 Montague Close, London Bridge
Tuesday 14 Friday 17
January 2014
Registration: 09.30
Hearing start: 10.30Glaziers' Hall, 9 Montague Close, London Bridge
Compulsory Acquisition Hearings
Compulsory acquisition hearings will be held at the ollowing dates, times and locations:
Table 1 below identies the location o the sites where shats to be used or the construction and operation o the Project will be provided.
At each compulsory acquisition hearing, each aected
person is entitled (subject to the Examining Authority's
powers o control over the conduct o the hearing) to
make oral representations about the compulsory
acquisition proposals.
Further hearings may be held i the Examining Authority
decides, during the examination process, that they
are needed. The periods o Wednesday 22 January to
Tuesday 28 January 2014 and Monday 3 February to
Wednesday 5 February 2014 have been reserved orurther hearings. I urther hearings are required, then
they will be advertised by one or more urther notices.
In accordance with Rule 13(3) o the Inrastructure
Planning (Examination Procedure) Rules 2010, the
Planning Inspectorate will also notiy interested partiesand aected persons o the date, time and place xed
or each hearing.
It should be noted that agendas or each hearing will
only be published on the Planning Inspectorate, National
Inrastructure, Thames Tideway Tunnel project page (see
details below) o the Planning Portal website at least ve
calendar days beore the hearing is due to take place.
Detailed questions may also be published in the same
manner to support the agendas at these identiedhearings. Detailed times or the sessions will be identied
in the agendas or the hearings published on the Planning
Inspectorate, National Inrastructure, Thames Tideway
Tunnel project page:
http://inrastructure.planningportal.gov.uk/projects/
london/thames-tideway-tunnel.
A copy o the Application is available to view by
appointment at The Planning Inspectorates oces at
the ollowing address:
The Planning InspectorateTemple Quay House
Temple Quay
Bristol BS1 6PN
Email: [email protected]
Tel: 0303 444 5000
A copy o the App
o charge at the
Monday to Friday
Linden House,
The InstitutioStreet, SW1P
Glaziers Hall,
SE1 9DD.
A copy o the App
Inspectorate, NatTunnel project pa
http://inrastruct
london/thames-
regarding these h
in due course.
17 October 2013
Date Time Venue
Tuesday 19 November 2013Registration: 09.30
Hearing start: 10.30Grange Tower Bridge Hotel, 45 Prescot Square, L
Wednesday 20 November 2013Registration: 09.30
Hearing start: 10.30The Worx, 10 Heathmans Road, London SW6 4
Thursday 21 November 2013Registration: 09.30
Hearing start: 10.30Ahoy Centre, Borthwick Street, Deptord, Londo
Friday 22 November 2013Registration: 09.30
Hearing start: 10.30Glaziers' Hall, 9 Montague Close, London Bridge
Saturday 23 November 2013Registration: 09.30
Hearing start: 10.30QE2 Conerence Centre, Broad Sanctuary, West
Open Floor Hearings
Open-foor hearings will be held at the ollowing dates, times and locations:
At each open-foor hearing, each interested party is entitled (subject to the Examining Authoritys powers o control over the conduct o thehearing) to make oral representations about the application
At each issue-specic hearing, each interested party is entitled (subject to the Examining Authoritys powers o control over the conduct o the hearing) to make oral representations
about the particular issue to be considered.